Price Determination Days Procurement Days Layout Plan Days Implementation Days

PDN001: Price Determination 7 PCT001: procurement of 30 LNP001: Get 7 IMP001: Appoint workers 3
of multiple purpose vending multiple purpose vending documentation done
machine machine
PCT002: Price Determination 7 PCT002: procurement of 30 LNP002: Get a 5 IMP002: Installation of 7
of cash to coin convertor cash to coin converter Layout Plan done multiple purpose vending
machine
PDN003: Price Determination 4 PCT003: Procurement of 10 LNP003: Get 20 IMP003: Installation of cash 2
of shipments shipments approval to coin converter
PDN004: Price Determination 7 PCT004: Procurement of 7 IMP004: Commencement of 3
of transportation from Karachi transportation from shipments
to Islamabad Karachi to Islamabad
PDN005: Price Determination 8 PCT005: Procurement of 7 IMP005: Commencement of 4
of FMCG products supply FMCG product supply transportation from Karachi
channel channel to Islamabad
PDN006: Price Determination 7 PCT006: procurement of 8 IMP006: Installation of 5
of installation location installation locations FMCG product supply
channel
PDN007: Price Determination 7 PCT007: Procurement of 9 IMP007: Implementation of 7
of electrical wiring electrical wiring installation locations
PDN008: Price Determination 7 PCT008: Procurement of 8 IMP008: Implementation of 7
of solar UPS/ generators solar UPS/ generators electrical wiring
PDN009: Price Determination 9 PCT009: procurement of 10 IMP009: Implementation of 8
of security cameras security cameras solar UPS/ generators
IMP010: Installation of 10
security cameras
IMP011: Handover to 20
Sponsors
NETWORK DIAGRAM