You are on page 1of 1

992 CHEMICAL ENGINEERING

Equipment No. (Tag)


Column Tray data sheet ,,,, ,,,, Descript. (Func.)
•J (PROCEED)
Sheet No.
1
Operating Data TOP BOTTOM
OR TOP
2
AND BOTTOM
TOWER INSIDE DIAMETER (Inches) (mm) 3
TRAY SPACE (Inches) (mm) 4
TOTAL TRAYS IN SECTION 5
6
7
Internal Conditions at Tray Number
VAPOUR TO TRAY 8
RATE (lb/hr) (kg/hr) 9
3
DENSITY (lb/ft3) (kg/m ) 10
PRESSURE (psi) (kg/cm2) (Bar g) (Bar a) 11
TEMPERATURE (°F) (°C) 12
LIQUID FROM TRAY 13
RATE (lb/hr) (kg/m3) 14
DENSITY (lb/ft3) (kg/m3) 15
TEMPERATURE (°F) (°C) 16
VISCOSITY cP 17
NUMBER OF LIQUID FLOW PATHS 18
19
Technical/Mechanical Data 20

TOWER MANHOLE INSIDE DIAMETER (Inches) (mm) 21


TRAY MATERIAL 22
TRAY THICKNESS 23
CAP MATERIAL 24
HOLDDOWN MATERIAL 25
NUTS and BOLTS MATERIAL 26
SUPPORT RING MATERIAL 27
SUPPORT RING SIZE (Inches) (mm) 28
DOWNCOMER BOLT BAR THICKNESS (Inches) (mm) 29
30
CORROSION ALLOWANCE 31
TRAYS (Inches) (mm) 32
TOWER ATTACHMENTS (Inches) (mm) 33
TRAYS NUMBERED FROM TOP TO BOTTOM 34
TRAY MANWAY REMOVAL FROM 35
36
37
DATE OF ENQUIRY DATE OF ORDER 38
ORDER No. DRG. No. 39
MANUFACTURER 40
41

NOTES 42

(1) INTERNAL VAPOUR AND LIQUID LOADINGS AT THE LIMITING SECTIONS ARE REQUIRED TO ENSURE PROPER TRAY DESIGN. 43
DENSITIES ARE REQUIRED AT ACTUAL INSIDE TOWER CONDITIONS OF TEMPERATURE and PRESSURE. VISCOSITY IS NOT 44
REQUIRED UNLESS GREATER THAN 0.7 cp 45
46
(2) CROSS OUT DIMENSION UNITS WHICH DO NOT APPLY. TRAY SUPPLIER TO ADVISE. 47

REMARKS 48

49
50
51
52
53
54
55
56
57

Prepared 3 6 58

Checked 2 5 59

Approved 1 4 60
Date Engineering Process REV By Appr. Date REV By Appr. Date 61

Service Company Address 62

Equipment No. 63

Project No. 64

You might also like