You are on page 1of 3

Engineering and Construction Fuel Depot and Hydrant Network -UTP Project

MECHANICAL DATA SHEET


EXPANSION JOINTS
DS-PP-0015 (Rev. 0)

Brightstar Asia Co., Ltd. Alana Engineering Co., Ltd. Index International Group Pub Co., Ltd.
(Consultant) (Design & Contractor)

Rev. Date By Check Approved Remark


A 09/10/2023 Teerachai T. Atthaphan Y. Suchart K. Issue for Approval
0 19/10/2023 Teerachai T. Atthaphan Y. Suchart K. Issue for construction
MECHANICAL DATASHEET
EXPANSION JOINTS
PROJECT NAME U-TAPAO AIRPORT PROJECT DOC NO. DS-PP-0015
CLIENT GLOBAL AERO ASSOCIATES CO., LTD. DATE OF ISSUED 19/10/2023 REVISION 0
LOCATION U-TAPAO AIRPORT, BANCHANG, RAYONG CONTRACTOR INDEX
PLANT AREA / UNIT GAA PHASE 1 PREPARED BY JVCM
1 SPECIALTY TAG NO. SP-1101, SP-1201, SP-1301 SP-1102, SP-1202, SP-1302
2 QUANTITY 3 3
3 LOCATION P&ID DWG. NO. PC-01-10-0001, PC-01-10-0002, PC-01-10-0003 PC-01-10-0001, PC-01-10-0002, PC-01-10-0003

4 FLUID Jet A-1

5 INSTALLATION LOCATION Tank Inlet and Outlet Nozzles


DESIGN CONDITION

6 DESIGN PRESS. barg 16

7 OPERATING PRESS. barg 10

8 DESIGN TEMP. °C 70

9 OPERATING TEMP. °C 40

10 DENSITY : kg/m³ 840 at 15 °C

11 VISCOSITY cSt 2.2

12 EQUIPMENT TYPE (DETAIL) Universal Expansion Joint

13 DESIGN As per EJMA Standard

14 FUNCTION SERVICE Abosrb soil differential settlement and thermal expansion from piping system
15 SIZE 16" 24"

16 OVERALL LENGTH mm. 600 (VTA) 700 (VTA)

17 CONNECTION ANSI 150# RF Flange

18 TYPE OF FLANGE Fixed Flange x Loose Flange


19 BELLOW TYPE Double

20 MAX. AXIAL MOVEMENT mm. 25 (TBC, Note 4)

21 MAX. LATERAL MOVEMENT mm. 25 (TBC, Note 4)


2 1452 (VTA) 3230 (VTA)
22 EFFECTIVE AREA cm
SPECIFICATION

23 AXIAL SPRING RATE N/mm 138 (VTA) 221 (VTA)

24 LATERAL SPRING RATE N/mm 137 (VTA) 316 (VTA)

25 BELLOWS MATERIAL SS316L

26 FLANGE MATERIAL SS400

27 SHORT PIPE MATERIAL Carbon Steel (Note 6)


28 MIDDLE MATERIAL Carbon Steel (Note 6)
29 MIDDLE HOLDER MATERIAL SS400

30 LIMIT RODS MATERIAL SS400

31 THICK HOLDER MATERIAL SS400

32 CONICAL SEAT MATERIAL SS400

33 LIMIT / CONTROL ROD GAP VTA (Note 5)

34 EXTERNAL PAINTING As per Specification for Field Painting; SP-ME-0101

35 MATERIAL CERTIFICATE Required


DOC.

36 TEST CERTIFICATE Required

37 Warranty 1 Year after installation


38 REMARK : SKETCH :

39
40 1. REQUIRED INSTALLATIN & MAINTENACE MAUAL

41 2. REQUIRED GA DRAWING INCLUDED FULL PARTS LIST

42 3. VTA=VENDOR TO ADVISE, VTC=VENDOR TO CONFIRM,

43 TBC = TO BE CONFIRMED BY EPC CONTRACTOR

44 4. TO BE CONFIRMED BY EPC CONTRACTOR PER FINAL PIPE STRESS

45 ANALYSIS.

46 5. GAP FOR EACH NUT ON LIMIT ROD SHALL BE ADVISED BY VENDOR

47 TO SUIT WITH APPLICATION.

48 6. VENDOR TO CONFIRM THAT THESE PIPES CAN BE SUPPLIED WITH

49 CS EPOXY LINED OR SS MATEIRAL.


MECHANICAL DATASHEET
EXPANSION JOINTS
PROJECT NAME U-TAPAO AIRPORT PROJECT DOC NO. DS-PP-0015
CLIENT GLOBAL AERO ASSOCIATES CO., LTD. DATE OF ISSUED 18/10/2023 REVISION B
LOCATION U-TAPAO AIRPORT, BANCHANG, RAYONG CONTRACTOR INDEX
PLANT AREA / UNIT GAA PHASE 1 PREPARED BY JVCM
1 SPECIALTY TAG NO. SP-1101 SP-1501 SP-1102 to SP-1105
2 QUANTITY 1 1 4
3 LOCATION P&ID DWG. NO. PC-01-07-0006 PC-01-07-0005 PC-01-07-0007, PC-01-07-0008

4 FLUID Jet A-1


Tank-to-Tank Transfer
5 INSTALLATION POSITION Jockey Pump Suction Hydrant Pumps Suction
Pump Suction
DESIGN CONDITION

6 DESIGN PRESS. barg 16


7 OPERATING PRESS. barg 10
8 DESIGN TEMP. °C 70
9 OPERATING TEMP. °C 40
10 DENSITY : kg/m³ 840 at 15 °C
11 VISCOSITY cSt 2.2
12 EQUIPMENT TYPE (DETAIL) Pump Expansion Joint
13 DESIGN As per EJMA Standard
14 FUNCTION SERVICE Vibration Isolation, Absorb Misalignment & Thermal expansion from piping
15 SIZE 4" (TBC) 6" (TBC) 8" (TBC)
16 OVERALL LENGTH mm. 200 (VTA) 200 (VTA) 200 (VTA)
17 CONNECTION ANSI 150# RF Flange
18 TYPE OF FLANGE Fixed Flange x Loose Flange
19 BELLOW TYPE Single
20 MAX. AXIAL MOVEMENT mm. 25 (TBC, Note 4)
SPECIFICATION

21 EFFECTIVE AREA cm2 131 (VTA) 440 (VTA)


22 AXIAL SPRING RATE N/mm 105 (VTA) 166 (VTA)
23 BELLOWS MATERIAL SS316L
24 FLANGE MATERIAL SS400
25 SHORT PIPE MATERIAL Carbon Steel
26 INTERNAL SLEEVE MATERIAL SS316L
27 TIED RODS MATERIAL SS400
28 THICK HOLDER MATERIAL SS400
29 CONICAL SEAT MATERIAL SS400
30 LIMIT / CONTROL ROD GAP VTA (Note 5)
31 EXTERNAL PAINTING As per Specification for Field Painting; SP-ME-0101
32 MATERIAL CERTIFICATE Required
DOC.

33 TEST CERTIFICATE Required


34 Warranty 1 Year after installation
35 REMARK : SKETCH :

36
37 1. REQUIRED INSTALLATIN & MAINTENACE MAUAL

38 2. REQUIRED GA DRAWING INCLUDED FULL PARTS LIST

39 3. VTA=VENDOR TO ADVISE, VTC=VENDOR TO CONFIRM,

40 TBC = TO BE CONFIRMED BY EPC CONTRACTOR

41 4. TO BE CONFIRMED BY EPC CONTRACTOR PER FINAL PIPE STRESS

42 ANALYSIS.

43 5. GAP FOR EACH NUT ON LIMIT ROD SHALL BE ADVISED BY VENDOR

44 TO SUIT WITH APPLICATION.

You might also like