Sub-Section 4.3.3 Schedule

TABLE OF CONTENT

BOOK II

PART 4 TECHNICAL REQUIREMENT


SECTION 4.3 GENERAL TECHNICAL REQUIREMENTS

SUB-SECTION 4.3.3 SCHEDULE

4.3.3 SCHEDULE................................................................................................................... 1
4.3.3.1 BID PROPOSAL SCHEDULE...................................................................1
4.3.3.2 CONTRACT SCHEDULE............................................................................2

Revision 0 Sub-Section 4.3.3 - i Lontar Extension CFSPP (1 x 315 MW)


BOOK II
PART 4 TECHNICAL REQUIREMENT
Section 4.3 General Technical Requirements
Sub-Section 4.3.3 Schedule

4.3.3 SCHEDULE

4.3.3.1 BID PROPOSAL SCHEDULE

The Bidder shall provide with his Bid Proposal as required in Part 5 Schedule
4, a Schedule in network form based on the dates given in Part 5, Schedule 4
and the Project Outline Schedule. The network shall be based on Bid
Proposal information and include:

- Dates for ordering of special and/or long delivery items.

- Dates for issue of drawings and documents for planning purposes.

- Dates for issue of all drawings and documents for manufacture and
construction purposes requiring Owner's review.

- Dates for the placing of orders for material, receipt of material, fabrication
and manufacture, factory testing and shipment.

- Dates for site investigation.

- Dates showing start and completion of site construction of each section of


the permanent works including but not limited to piling works and piling
testing.

- Dates for periods when equipment is available for work by the Bidders.

- Dates for start and completion of design engineering for all disciplines.

- Dates for submittal to and return after final review by the Owner of all
drawings and documents listed in Part 4, clause 4.3.2.3, of the
specification.

- Dates for submittal of design, operation and maintenance manuals for


approval.

- Dates for submittal of commissioning checklists and detailed schedules for


approval.

- Dates for submittal of complete schedules for all manufactured items.

Activities shall be timed in week units except for commissioning or similar


detailed program which have activities specified in days.

Activities for which it is intended to operate multiple shift working shall be


clearly defined.

Each system as itemized in Part 5, Schedule 1 shall be included.

4.3.3.2 CONTRACT SCHEDULE

Revision 0 Sub-Section 4.3.3 - 1 Lontar Extension CFSPP (1 x 315 MW)


BOOK II
PART 4 TECHNICAL REQUIREMENT
Section 4.3 General Technical Requirements
Sub-Section 4.3.3 Schedule

The Schedule provided in accordance with clause above shall be revised in


detail by Bidder to reflect any changes in scope of Work or scheduled dates
agreed during Contract discussion and to a format acceptable to the Owner
suitable for computer application.

The Bidder shall utilize a precedence method scheduling system which shall
be compatible with the Microsoft Project program. The details of the input
format and the input required to the Bidder will be provided during the
Contract discussion.

The revised schedule shall be submitted to the Owner as part of the Contract
Document to be signed and will become the Contract Schedule.

The Contract Schedule shall be revised by the Bidder to incorporate any


variations in the scope of work and in the schedule agreed during the
Contract. The revised schedule shall be submitted promptly to the Owner for
review and approval.

The Bidder shall submit 5 (five) copies all programs (original or revised issues)
to the Owner for approval. After approval, copies shall be supplied in
accordance with the procedures specified in Part 4, Sub-section 4.3.2 of the
Specification.

Following approval of the Contract Schedule, detailed programs for all Work to
be executed during the first twenty-four (24) weeks of the Contract shall be
submitted.

These programs, which shall embrace design, procurement, manufacture,


testing, shipping and erection on Site, shall be based on the Contract
Schedule and shall be used as target programs possibly subject to revision.

The detailed programs shall be submitted to the Owner at twelve (12) week
intervals, updated to reflect the changes that have occurred in the previous
twelve (12) weeks and to show the detailed program of Work for the next
twenty four (24) weeks.