TABLE OF CONTENT
BOOK II
4.3.6.1 GENERAL
4.3.6.2 SCOPE
Bidder shall conduct performance tests, bonafide test and individual test
which shall include all individual items of equipment, complete systems
and subsystems covered under this Contract.
At the end of warranty period of the plant or part thereof for which a taking
over certificate has been issued, the Bidder shall conduct full inspections
on the plant or part thereof to ensure the Owner that the equipment is in a
good condition prior issuance of Final Acceptance Certificates.
Preliminary test procedures for all equipment shall be submitted one year
after the Contract Award.
The Bidder shall submit detailed test procedures and criteria for all
individual items of equipment, complete systems and subsystems
specified in this Contract.
The Bidder shall submit these procedures to the Owner at least six
months before the scheduled test date. These test procedures shall
include but not be limited to:
Table 4.3.6.1. List of Codes and Standards for Equipment Performance Test in Site
PERFORMANCE TEST
EQUIPMENT
TEST CODE LOCATION
Forced Draft Fans (i.e. : Primary Air Fans, AMCA 203 Site
Secondary Air Fans, External Heat
Exchanger Air Fans and Gas Recirculation
Fans if required).
Induced Draft Fans AMCA 203 Site
ASME PTC 6 Site
Steam Turbine Units
PTC 12.1 Site
Closed Feedwater Heater
ASME PTC 12.3 Site
Deaerators
ASME PTC 12.2 Site
Condensers
ASME PTC 12.1 Site
Heat Exchangers
The Bidder shall conduct Plant Performance tests at Site and shall be
conducted as required by Part 3.13 and Part 4 Section 4.6, on all
equipment in the Bidder's supply in order to verify that the equipment
satisfies all the designs requirement and to demonstrate that the
performance and guarantee specified in the Contract have been met.
The Bidder shall provide and install all necessary test points, instruments,
fittings and other equipment and consumables except fuel required for
conducting the performance tests.
MAIN STEAM
b. Net Power Output means electricity output available to the grid which
equal to gross power output subtracting auxiliary power and
transformer losses.
Means,
d. Gross Plant Heat Rate means the amount of fuel energy or Boiler heat
input to generate a unit of gross electric energy output (power output
at the generator terminal)
e. Net Plant Heat Rate means the amount of fuel energy or Boiler heat
input to generate a unit of net electric energy output (power output at
the generator transformer secondary terminal)
a. Guarantee Conditions
Ambient air
0
Temperature 27.4 C
Relative Humidity 81.1 %
Barometric pressure 1015.7 mbar
0
The worst sea water temperature 33 C
*) : Bidder to specify
b. Guarantee Items
The Bidder shall guarantee the Net Plant Heat Rate (NPHR) at
the corresponding MCR when the boiler firing specified typical
coal.
The Bidder shall identify each power user included in the above
guarantee for each unit and common ancillary plants.
b.4. Environmental
1. Emission
The Bidder shall guarantee that each parameter of
emission resulted from operated power plant comply with
Decree of Minister of Environment, Republic of Indonesia
No. 21 year 2008. Furthermore, time and location of
monitoring also observation method of emission must be
comply with the Decree of BAPEDAL Principal, Republic of
Indonesia, No. 205 year 1996.
2. Noise
The Bidder shall guarantee that noise resulted from
operated power plant shall comply with the regulation
requirement of the noise level for the local area surrounding
the power plant. The method of measurement, calculation
and evaluation of noise level, will be ruled by Decree of
Minister of Environment, Republic of Indonesia, No. 48 year
1996.
a. General
a.1. Test schedule will be prepared by the Bidder and the test shall
be conducted in accordance with the “PERFORMANCE TEST
PROCEDURE” submitted by the Bidder and approved by the
Owner and complying with the specified guarantee conditions.
a.2. The Bidder shall make the detailed test procedure which
covers all guarantee items based on the outline in this
specification, and shall submit it to the Owner for approval.
a.3. The detailed test procedure shall include the following items.
a.4. The Bidder shall provide sufficient and skilled supervisory staff
and service engineers to perform all tests.
a.6. The Bidder shall provide all necessary instruments work for
the tests, such as calibration of instrument, recording,
calculation, and other related works.
a.7. The Bidder has to repeat any test, if in the opinion the Owner,
the test was not performed properly.
Each test shall be carried out for a maximum four (4) hours. The
test period shall be selected at a time when the power system is
Test conditions
- The steam generator is operated automatically and maintains
main steam pressure and temperature at the specified value.
Other main factors such as excess air ratio, number of
burners, etc., shall be retained at the specified conditions.
- Blow off from steam generator and other parts are entirely
closed.
d. Instrumentation accuracy
d.1 The high heating values of the fuels shall be determined in the
owner's laboratory and two other laboratories to be chosen
respectively one by the Owner, the other by the Bidder. In
order to determine the specific consumptions of the Plant, the
arithmetical mean value of the high heating values shall be
adopted.
d.2 The Net Plant Heat Rate shall be corrected according to the
deviation of the following items to the specified conditions, by
approved correction curves:
Condenser pressure
Make up water flow
Ambient temperature
Generator power factor
Coal analyses
System Frequency
Ambient temperature
Ambient humidity
Where as:
e. Environmental Guarantees
General
The Bidder have to guarantees that emissions (of air emission, and
noise) from the power plant equipment supplied under this Contract
will not exceed the following emission limit during normal plant
operation i.e. when operating continuously at the nominal operating
conditions after successful construction, erection and commissioning.
Emission
The Bidder shall conduct Emission Performance Test on
75 % MCR
Noise
e.2 Standards
Notes:
1. Gas volume in standard conditions (25 °C and 1 atm)
2. Opacity is used as practical indicator for monitoring.
3. All parameters are corrected as 7% O2 for Coal in dry
condition except the opacity.
4. All parameters are corrected as 5% O2 for Oil Fuel in
dry condition except the opacity.
5. This emission standard shall be applied on 95 % of
normal operation within three months.
6. Nitrogen Oxide is defined as NO2
Emissions Calculation
1. Amount of Coal
2. Output ( MWh)
3. Sulphur Content (%)
4. Caloric Value (TJ/kton of Coal)
5. Operation hours ( Hour)
6. Heat Input (Btu/Jam or MMBTU/ Jam )
EMS Report
1. Name of chimney
2. Coordinate
3. Chimney Dimension
Diameter
Length x Wide
High
4. Air Emission Parameter
Sulphur dioxide (SO2)
Nitrogen Oxide (NO2)
Total Particle
Note :
Test conditions
The result of item above bonafide test shall be used to verify the Bidders
proposed Heat Balances for the specified fuels.
The Bidder shall also conduct all tests in accordance with requirement of
Technical Requirement such as Desalination Plant, Waste Water
Treatment Plant, Coal Handling System, etc.
Any deficiency brought out by these tests shall be promptly corrected by
Contractor at no cost to Owner.
Three (3) copies of mill and test certificates shall be supplied to the
Owner.
The Bidder shall supply at the ex-works stage three (3) bound copies of
all certification, suitably indexed, to cover all performance tests of
equipment.
During all tests a complete and detailed log of observations and readings
shall be made and certified copies submitted to the Owner.
The detailed test procedures, lists, logic diagrams and flow diagrams
together with test results shall be correlated and presented as a single
bound final test report to form a comprehensive set of test procedures
and records of the tests conducted on the plant.
Three (3) bound copies of Final Test Reports shall be supplied by the
Bidder to the Owner.
The time period for repair will be decided by the Owner if it is beyond the
specified completion date
If the Bidder fail to repair and/or replace within the time period mentioned
above, then the Owner has a right either to reject or to apply the
liquidated damage for performance, refer to Part 3 clause 3.4.
At the end of warranty period for each item or equipment, the Bidder shall
perform first inspection of the equipment as a condition for the Owner
issuance of the final acceptance certificate.
- Dismantling of equipment
- Open and inspect internal equipment