Professional Documents
Culture Documents
1
Contents
Chapter 01 Introduction
Chapter 04 Organization
Chapter 05 Duties
2
Chapter 01
Introduction
have compiled and implemented Project Quality Management Handbook for Sri Lanka
with the contract and the technical rules by all the staff for Sri Lanka Puttalam 3×300MW
3×300MW Coal-Fired power plant Project, thus providing for the owners satisfactory power
The project manager requires all the staff in the project department to carefully study,
understand and implement the handbook. The project manager invites someone from the
operation management department of the corporation to review the internal quality system of
the project department and to correct anything not conforming to the rules, so as to
continually improve and enhance project management and try to set an example for CMEC
project management.
1.2.2 Quality System Procedure of China National Machinery & Equipment Import & Export
Corporation
1.2.3 Quality Management Handbook of China National Machinery & Equipment Import &
Export Corporation
3
Chapter 02
Project Overview
Puttalam Coal-Fired Power Plant is located in Kalpitya Peninsula around Ranalyadi village, about
12km away from Putnamsi, capital of Puttalam along the western coast of Sri Lanka.
The planned capacity of Puttalam Coal-Fired Power Plant is 900MW. The project is divided into
two phases. The phase Ⅰ covers a 300MW steam turbine generator group, associated power
transmission system, coal supply facility, coal storage and ash treatment system as well as site
infrastructure and its associated system. the phase Ⅱ includes 2×300MW steam turbine
generator group and associated power transmission system and part of the coal supply system.
Puttalam Coal-Fired Power Project is undertaken by China National Machinery & Equipment
Import & Export Corporation who is in charge of the whole project’s design, procurement, supply,
installation, experiment and testing. Finally the corporation hands over the whole power plant to
4
Chapter 03
Project Objectives
Boiler
Turbine
Temperature 538℃
Engine
5
Rated speed 3000r/min
Frequency 50Hz
Efficiency ≥98.9%
3.2 Objectives
1) the project management level aims to be the model of CMEC and tries to reach the top
2) there will be no big quality problems with the design, equipment and construction,
4) the project will strictly comply with the contract to satisfy the owners and their
consulting engineers.
6
Chapter 04
Organization
Project manager
2 Deputy project manager Zong Guoqing Shi Jiantao Bai Yugang Beijing
Wang Ludong Li Ning
7
4 Deputy site manager Li Rong On-site
8
Chapter 05
Duties
To successfully complete various tasks required by the contract and strictly comply with the
contract, it is necessary to have a complete and proper organization to bring all the staff’s
capabilities into full play, that is, to make sure that everyone is well-positioned and
5.2 Scope
This rule applies to all the staff in the project department of Sri Lanka Putnam Coal Power
Plant Project.
5.3 Duties
As the general contractor, CMEC has the follwing responsibilities in project management: to
subcontractor the quality requirements of the corporation in the legal form of contract, verify
if the subcontractors has effectively implement all the relevant rules of the contract.
The project manager is responsible for all the work relevant to the project as well as the
following:
2) control the scheduled progress, project quality and total cost of the project;
9
1) manage all the specific work in the department;
1) manage the quality of the project in compliance with the requirements of external
contract;
3) be responsible for supervising the manufacturing process and managing the supervisory;
1) be responsible for managing the contract technology and procuring the equipment as
2) be responsible for technical contacting and coordinating with the designing institute,
reports;
10
2) be responsible for bond proceedings;
2) be responsible for numbering, distributing and filing of letters, plans and manufacturer
data.
2) prepare the capital distribution plan and properly arrange the capital;
2) be responsible for all lawsuits, arbitration and non-lawsuit legal disputes concerning
11
the project;
12
Chapter 06
Site Management
1.Organization
13
Site Manager
Commercial Department HSE Department Construction Department Equipment & Technique Department
QA/QC
Planning
Design Management
Equipment & materials procurement at site
Coal Jetty
Document Management
3.Duties
b) communicate and negotiate with the owners and contractors about various work of the project;
c) study and formulate quality objectives of the project; establish, improve and implement the quality
d) make decisions concerning major technical and quality activities (such as use of new technology, new
equipment, new techniques and new materials and rework of the project), deal with serious quality
e) be responsible for directing and coordinating deputy site manager and general engineer, and directly
leading the work in security environment protection department and business department, solve major
interface issues, review and approve the project progress plan and the capital distribution plan.
a) be responsible for all the site work under the leadership of site manager;
b) be responsible for fulfilling the obligations in the contract;
d) preside over the engineering meeting on major equipment quality problems and be responsible for
a) be responsible for management of the site engineering department and equipment technology
department;
b) be responsible for formulating the overall construction organization plan, reviewing the professional
construction organization plan of various construction parties as well as the construction plans and
c) fulfill the project quality objectives and undertake the project division and implementation work based
on the specific conditions of the project, and ensure the fulfillment of the project objectives;
d) be responsible for formulating and adjusting milestones of the project progress and the progress plan of
e) organize and participate in the designing technique sharing and collective reviewing of the construction
plan;
f) participate in the reviewing of major changes in the design of equipment and systems as well as verify
g) preside over meetings on the construction plans of major projects and on major quality issues, and
h) organize the testing of the machine and the whole starting work, and participate in the hand-over of the
a) be responsible for handling quality and security issues, carefully analyze the reasons and take certain
b) supervise the construction environment of the construction site, create a clean construction site and
c) eradicate the insecure state of all the matters on the construction site and the unsafe deeds of the staff;
d) check the security of various instruments and equipment to ensure that the construction proceeds in a
1
secure state;
e) formulate relevant construction management rules and guarantee measures in compliance with national
a) be responsible for reviewing construction techniques and construction plans and submit them to the
b) be responsible for managing records of changes in project technical specifications, documents and
c) participate in the design sharing and plan reviewing, and be responsible for reviewing, delivering and
d) participate in formulating the project network progress plan and review the progress plans of all parties;
e) partipate in reviewing of conditions for commencing the project, signing the commencement (completion)
report, stopping (resuming) report and be responsible for managing the construction plan and adjusting
f) be responsible for project verification, preside over the on-site hand-over and coordinate the disputes;
h) participate in the testing of part of the machine and the starting work of the project;
i) supervise and participate in the quality inspection of the contractor’s materials, finished products and
semi-finished products;
j) be responsible for verifying deficiencies in the equipment before marketing, reviewing the default plan
k) participate in the analysis and survey of non-standard products, major construction quality accidents and
l) be responsible for formulating the project quality guarantee plan to ensure the implementation of quality
guarantees;
m) exercise the veto right in the face of any actions breaching the project procedures and affecting the
project quality;
n) inspect and examine the contractor’s quality guarantee system and provide comments or
2
3.6 Business management department/plan management
b) be responsible for controlling and coordinating the project’s capital and expenses, and controlling the
project’s cost;
c) be responsible for formulating or auditing the construction budget and formulating the final accounting
report;
c) be responsible for accounting management, contract management and plan management of the project
department;
e) be responsible for managing documents and data of the project department as well as receiving and
f) be responsible for filing of plans, documents, data, procedures, specifications and standards;
a) strictly comply with the quality standards and procedures of the project;
c) be responsible for verifying and receiving the equipment and materials, unpacking, storage and
delivering.
d) be responsible for procuring, storing and quality-controlling the major materials for the project;
f) be responsible for organizing the procurement check of materials, equipment and semi-finished products;
3
施工组织设计报审表
Review/ Approval Request for Construction Execution Plan (Method Statement)
表号:DJH-A-06
编号:
工程名称 合同编号
致 项目经理部:
施工组织设计已经我单位审定,现报上,请予审批。
附:《施工组织设计》及说明书
承包商(章)
负责人: 年 月 日
工程部意见:
工程部(章) 专业工程师: 年 月 日
部门负责人: 年 月 日
项目经理部审定意见:
项目经理部(章)
总(副总)工程师: 年 月 日
本表一式六份,由承包商填报,项目经理部存四份、承包商存二份。
专业施工组织设计/重大施工技术方案报审表
4
Review/approval request for specialized construction organization plan/Significant construction
technology plan
表号:DJH-A-07
编号:
工程名称 合同编号
致 项目经理部:
现提出 专业施工组织设计/重大施工技术方案,请予
审批。
附件:
承包商(章)
技术负责人: 年 月 日
工程部审查意见:
工程部(章)
部门负责人:
专业工程师: 年 月 日
项目经理部审定意见:
项目经理部(章)
总(副总)工程师: 年 月 日
本表一式六份,由承包商填报,项目经理部存四份、承包商存二份。
调试方案报审表
Review/approval request for Commissioning plan
5
表号:DJH-A-08
编号:
工程名称 合同编号
致 项目经理部:
现报上 调试方案,请审核。
附件:
承包商(章) 负责人: 年 月 日
工程部审核意见:
工程部(章): 部门负责人: 年 月 日
专业工程师: 年 月 日
项目经理部审定意见:
项目经理部(章) 总(副总)工程师: 年 月 日
项目经理: 年 月 日
本表一式六份,由承包商填报,项目经理部存四份、承包商存二份。
重要工程开工报审表
Review/approval request for main works commencement
表号:DJH-A-09
编号:
6
工程名称 合同编号
致 项目经理部:
我单位承建的 项目的施工准备工作
已完成,具备开工条件,计划与 年 月 日开工,请予审批。
1.施工组织设计,专业施工组织设计、施工技术方案已批准;
2.劳动力已按计划进场;
3.机械设备已进场,并布置就绪;
4.管理人员已全部到位;
5.开工所需的施工图纸已到,并已会审、交底;
6.开工所需的材料、设备已进场;
7.开工前的各种手续已办妥(见附件)。
根据以上条件,可以满足连续施工要求。
附件:(复印件)
承包商(章)
项目负责人: 年 月 日
工程部核查意见:
工程部(章): 部门负责人: 年 月 日
专业工程师: 年 月 日
项目经理部审定意见:
项目经理部(章)
项目经理: 年 月 日
本表一式六份,由承包商填报,项目经理部存四份、承包商存二份。
保温工程施工申请单
Insulation Work Construction Application Form
表号:DJH-A-10
编号:
工程名称 合同编号
7
致 项目经理部:
我单位负责施工的 设备(管道)已
安装完毕,经检验,质量符合规定要求,具备保温施工条件,请查验。
附:质量检验记录、保温材料质量保证资料和抽检试验报告。
承包商(章)
项目负责人: 年 月 日
工程部审查意见:
专业工程师: 年 月 日
本表一式三份,由承包商填报,项目经理部存二份、承包商存一份。
施工/调试进度计划报审表
Review/Approval request for construction & commissioning schedule
表号:DJH-A-11
编号:
工程名称 合同编号
8
致 项目经理部:
根据本工程的一级网络进度计划,我单位已编制完成 项目的
施工进度/调试进度计划,特此上报,请予审批。
附件:1.进度计划表;
2.编制说明
承包商(章)
项目负责人: 年 月 日
工程部审查意见:
工程部(章): 部门负责人: 年 月 日
专业工程师: 年 月 日
项目经理部审定意见:
项目经理部(章)
项目经理: 年 月 日
本表一式三份,由承包商填报,项目经理部存二份、承包商存一份。
施工进度计划报审表
Review/approval request for construction schedule
表号:DJH-A-12
编号:
致 项目经理部:
9
现将 工程施工进度计划报请审查。
附:月施工进度计划及编制说明
施工单位(章) 负责人(签字)
年 月 日
工程部审核见:
专业工程师: 年 月 日
工程部(章) 部门负责人: 年 月 日
项目经理部审批意见:
商务部:
分管领导:
主管领导:
项目经理部(章)
注:本表由施工单位填报,项目经理部存四份、承包商存一份。
变更工期申报表
Review /approval request for work period change
表号:DJH-A-13
编号:
工程名称 合同编号
10
致 项目经理部:
工程根据合同规定应于 年 月 日
竣工,由于 原因,要求变更工期(延
长或缩短),竣工期(包括已指令变更工期在内)从原来的 年 月 日变更
至 年 月 日,请予批准。
附件: 变更工期详细原因。
承包商(章) 项目负责人: 年 月 日
工程部审核意见:
工程部(章): 部门负责人: 年 月 日
专业工程师: 年 月 日
项目经理部审定意见:
项目经理部(章)
项目经理: 年 月 日
本表一式三份,由承包商填报,项目经理部存二份、承包商存一份。
复工申请表
Resumption work application form
表号:DJH-A-14
编号:
工程名称 合同编号
11
致 项目经理部:
鉴于 项目的停工因素(见停工通知单 号)
已经消除,特报请审查,批准复工。
附件:具备复工条件的详细说明。
承包商(章)
项目负责人: 年 月 日
工程部复查意见:
工程部(章): 部门负责人: 年 月 日
专业工程师: 年 月 日
项目经理部审定意见:
项目经理部(章)
项目经理: 年 月 日
本表一式三份,由承包商填报,项目经理部存二份、承包商存一份。
主要工程材料报审表
Request for Review/ Approval of Main work materials
表号:DJH-A-16
编号:
工程名称 合同编号
12
致 项目经理部:
经过我公司自检,下列材料符合国家标准和技术规范以及本工程设计的要求,
拟在本工程中采用。现报请审查,请予批准。
附件:
承包商(章)
技术负责人: 年 月 日
工程部审查意见:
工程部(章)
专业工程师: 年 月 日
本表一式四份,由承包商填报,项目经理部存二份、承包商存二份。
主要设备开箱申请表
Request for main equipment opening package inspection
表号:DJH-A-17
编号:
工程名称 合同编号
13
致 项目经理部:
现计划与 年 月 日 时,在 地
方,对 设备进行开箱检验,请予审批。
附件:设备保管措施要点。
承包商(章)
负责人: 年 月 日
工程部意见:
工程部(章)
专业工程师: 年 月 日
储运部意见
负责人: 年 月 日
本表由承包商填写一式三份,项目经理部存二份、承包商存一份。
设备缺陷通知单
Equipment defects requisition
表号:DJH-A-18
编号:
工程名称 合同编号
14
致 项目经理部:
在 过程中,发现 号机组 设备 部
位存在 问题(见 设备
图),请协调处理。
附件:1.缺陷情况; 2.简图和测量数据。
承包商(章)
技术负责人: 年 月 日
工程部意见:
专业工程师: 年 月 日
供货商意见:
代表: 年 月 日
设计意见:
代表: 年 月 日
项目经理部意见:
总(副总)工程师: 年 月 日
1.本表一式四份,由承包商填报,项目经理部存二份、承包商、供货商(制造厂)各存一份。
2.涉及设计变更时,本表抄送设计单位一份,并由设计单位提出相应的设计变更通知书。
设备缺陷处理报验表
Request for review & disposal of equipment defects
表号:DJH-A-19
编号:
工程名称 合同编号
15
致 项目经理部:
年 月 日我单位对 号机组 设备
部位的缺陷发出“设备缺陷通知单”(通知单编号 ),
并按 要求(标准),已消缺完毕,特此报验。
附件:
承包商(章)
负责人: 年 月 日
供货商(制造厂)核验意见:
代 表: 年 月 日
工程部核验意见:
工程部(章):
专业工程师: 年 月 日
本表一式四份,由承包商填报,项目经理部存二份、承包商、供货商(制造厂)各存一份。涉
及设计变更时,抄送设计单位一份。
工程控制网测量报验单
Inspection sheet for engineering control network survey
表号:DJH-A-20
编号:
工程名称 合同编号
16
致 项目经理部:
我单位已完成 工程控制网测量工作,请查验。
附件: 施工测量记录、质量检验评定表
承包商(章)
项目技术负责人: 年 月 日
工程部查验意见:
工程部(章): 工程部负责人: 年 月 日
专业工程师: 年 月 日
本表一式四份,由承包商填报,项目经理部存二份、承包商存二份。
特殊工种证件报验单
Request for review of certificate for special type of work
表号:DJH-A-21
编号:
工程名称 合同编号
17
致 项目经理部:
现报上进驻本工程的特殊工种人员名单,请查验。今后,有人员中途调动,我
单位将及时重新统计,并上报。
附:证件(复印件)
承包商(章)
技术负责人: 年 月 日
本表一式三份,由承包商填报,项目经理部存二份、承包商各存一份。
特殊工种人员证件统计报表
Statistical returns for certificates of special type of work staff
表号:DJH-A-21 续
编号:
18
工程部查验意见:
专业工程师: 年 月 日
本表一式三份,由承包商填报,项目经理部存二份、承包商存一份。
主要施工计量器具、检测仪表检验统计表
Statistical table of Main construction metering appliance & instrument examination
表号:DJH-A-22
编号:
工程名称 合同编号
19
致 项目经理部:
现报上本工程使用的主要施工计量器具、检测仪表检验结果统计表,以供查对。
附件:检验合格证(复印件)
承包商(章)
负责人: 年 月 日
本表一式三份,由承包商填报,项目经理部存二份、承包商存一份。
主要施工计量器具、检测仪表检验统计表
Statistical table of Main construction metering appliance & instrument examination
表号:DJH-A-22 续
编号:
20
工程部查验意见:
工程部(章)
专业工程师: 年 月 日
本表一式三份,由承包商填报,项目经理部存二份、承包商存一份。
施工质量检验项目划分报审表
Review/approval request for construction quality inspection items division
表号:DJH-A-23
编号:
工程名称 合同编号
21
致 项目经理部:
我单位依据 质量检验评定标准
篇和本工程的设计,已完成 专业
工程项目的施工质量检验项目划分表,现报上,请审定。审定后,我单位即予正式
出版。
附件:《施工质量检验项目划分表》
承包商(章) 项目负责人: 年 月 日
工程部审核意见:
工程部(章): 工程部负责人: 年 月 日
专业工程师: 年 月 日
项目经理部审定意见:
项目经理部(章)
总(副总)工程师: 年 月 日
本表一式三份,由承包商填报,项目经理部存二份、承包商存一份。附件在承包商修改
出版后,分发有关单位。
土建工程报验检验单
Request for review Inspection sheet of civil wor
表号:DJH-A-24-1
编号:
单位工程名称 日 期
致 项目经理部
现我方已完成 (分部、子分部)
(分项、检验批)
。
22
经我方检验符合设计、规范要求,请予以验收。
附件: 名 称 页 数 编 号
1、 质量控制资料汇总表 页
2、 隐蔽工程检查记录 页
3、 预检记录 页
4、 施工记录 页
5、 施工试验记录 页
6、 分部工程质量检验评定记录 页
7、 分项工程质量检验评定记录 页
8、 检验批质量验收记录 页
9、 页
10、 页
质量检查员(签字)
:
施工单位(章)
: 技术负责人(签字)
:
审查意见:
(1)所报附件材料真实、齐全、有效;
符合 不符合
(2)所报检验批实体工程质量符合规范和设计要求:
符合 不符合
审查结论: 合格 不合格
工程部(章): 专业工程师: 日期:
注:本表由施工单位填报,项目经理部存四份、承包商存二份。分部工程应由工程部负责人签字。
安装工程报验检验单
Request for review inspection sheet of installation work
表号:DJH-A-24-2
编号:
报验工程名称 报送日期
致 项目经理部:
报验的工程施工已完成,并自检合格,现报请检验。
23
附:自检记录资料 份
施工单位(盖章) 报验人(签字) 年 月 日
工程部检验意见:
经查验该项工程:
1、《施工质量检验及评定标准》中, 标准规定
符合 不符合
2、施工图纸(含工程变更)
符合 不符合
质量评定 合格 不合格
工程部(章): 专业工程师 年 月 日
注:本表由施工单位填报,项目经理部存四份、承包商存二份。分部工程应由工程部负责人签字。
土建中间验收交接表
Civil work Intermediate turnover form
表号:DJH-A-25
编号:
工程名称 合同编号
24
致 项目经理部:
我单位负责施工的 土建工程,经检查,质量符合交付
下道工序施工条件,请组织查验。
附:自检记录和测量记录
交付单位(章) 负责人: 年 月 日
接受单位查验意见:
接受单位(章) 负责人: 年 月 日
工程部意见:
工程部(章) 专业工程师: 年 月 日
本表一式三份,由交付单位填报,查验后,交付、接受单位及项目经理部各存一份。
25
安装交付土建中间验收交接表
Installation work Intermediate Turn over Form
表号:DJH-A-26
编号:
工程名称 合同编号
致 项目经理部:
我单位负责施工的 安装工程,经检查,质量符合交付
下道工序施工条件,请组织查验。
附:自检记录和测量记录
交付单位(章) 负责人: 年 月 日
质量部门查验意见:
接受单位(章) 负责人: 年 月 日
CMEC 工程部意见:
工程部(章) 专业工程师: 年 月 日
本表一式三份,由交付单位填报,查验后,交付、接受单位及项目经理部各存一份。
土建交付安装中间验收交接表
Civil work delivery to Installation Intermediate Turn over Form
表号:DJH-A-27
编号:
工程名称 合同编号
致 项目经理部:
我单位负责施工的 土建工程,经检查,质量符合交付
安装条件,请组织查验。
附:自检记录和测量记录
交付单位(章) 负责人: 年 月 日
接受单位查验意见:
接受单位(章) 负责人: 年 月 日
工程部意见:
工程部(章) 专业工程师: 年 月 日
本表一式三份,由交付单位填报,查验后,交付、接受单位及项目经理部各存一份。
安装交付调试中间验收交接表
Installation delivery to commissioning Intermediate Turn over Form
表号:DJH-A-28
1
编号:
工程名称 合同编号
致 项目经理部:
我单位负责施工的 安装工程,经检查,质量符合安装
工程施工及验收规范、设计图纸,具备调试条件,请组织查验。
交付单位(章) 负责人: 年 月 日
接受单位查验意见:
接受单位(章) 负责人: 年 月 日
工程部意见:
工程部(章) 专业工程师: 年 月 日
本表一式三份,由交付单位填报,查验后,交付、接受单位及项目经理部各存一份。
工程质量事故报告单
Construction quality accident report
表号:DJH-A-29
编号:
工程名称 合同编号
2
致 项目经理部:
年 月 日 时在 (工程
部位)发生 工程质量事故,现报告如下:
事故概况:
事故原因(初步调查结果或现场报告情况):
造成损失:损失金额(估算) 万元
应急措施:
初步处理意见:
(详情待现场调查后另报)
承包商(章)
项目负责人: 年 月 日
本表一式四份,由承包商填报,项目经理部存二份、设计单位、承包商各存一份。
凡属于重大质量事故,应按政府有关规定报告。
质量事故处理方案报审表
Review/approval request for quality accident disposal scheme
表号:DJH-A-30
编号:
工程名称 合同编号
3
致 项目经理部:
年 月 日 时 (工程部位)发生
工程质量事故,已于 月 日 号质量事故报告单报告你处,经
组织对该事故详细调查和研究,现将详情及处理方案报上,请审查。
附:事故调查报告及处理方案
承包商(章) 项目负责人: 年 月 日
设计核查意见:
设计代表: 年 月 日
工程部审查意见:
工程部(章): 工程部负责人: 年 月 日
专业工程师: 年 月 日
项目经理部意见:
项目经理部(章) 总(副总)工程师: 年 月 日
本表一式四份,由承包商填报,项目经理部存四份、设计单位、承包商各存一份。
质量事故处理结果报验表
Review/approval request for accident disposal results
表号:DJH-A-31
编号:
工程名称 合同编号
4
致 项目经理部:
年 月 日发生的 (工程部位)的质量事故,
我单位已按批准的 号质量事故处理方案处理完毕,请予查验。
附件:自查记录和试验记录。
承包商(章) 项目负责人: 年 月 日
工程部查验意见:
工程部(章): 工程部负责人: 年 月 日
专业工程师: 年 月 日
项目经理部核查意见:
项目经理部(章)
总(副总)工程师: 年 月 日
本表一式三份,由承包商填报,项目经理部存二份、承包商存一份。
工程联系单
Engineering Liaison Sheet
表号:DJH-A-35
编号:
工程名称 合同编号
主送单位 抄送单位
5
致 项目经理部 :
事由及内容:
附件 份
承包商(章)
项目负责人: 年 月 日
答复意见:
单位(章)
代 表: 年 月 日
本表属通用性质的表格,凡需引起注意或请求协助解决的事项,可填写本表进行联
系。本表由承包商填写,份数视内容而定。代表:随主送单位变。
整改报验单
Review/approval request for change
表号:DJH-A-36
编号:
工程名称 合同编号
6
致 项目经理部:
我单位在收到 号整改通知单后,已按要求整改完毕,请予复查。
附件:整改情况
承包商(章) 项目负责人: 年 月 日
工程部复查意见:
工程部(章): 工程部负责人: 年 月 日
专业工程师: 年 月 日
本表一式三份,由承包商填报,项目经理部存二份、承包商存一份。
工程量签证单
Engineering quantity visa
表号:DJH-A-37
编号:
工程名称 合同编号
7
内容:
承包商(章)
负责人: 年 月 日
工程部查验意见:
工程部(章): 工程部负责人: 年 月 日
专业工程师: 年 月 日
项目经理部审核意见:
项目经理部(章)
项目经理: 年 月 日
本表一式三份,由承包商填报,查验后,连同附件,项目经理部存二份、承包商存一份。
施工图会审纪要
Minutes of Checkup for Construction Drawings
表号:DJH-A-38
8
编号:
卷册号
名称
相关卷册和图纸
施工承包商:
出席单
位和人 设备制造商:
员 设计承包商:
CMEC 工程部:
会审纪要:
序号 提出问题 审定意见
会 签 栏
施工承包商 设备承包商 设计承包商 CMEC 工程部
工作联系单
working Liaison Sheet
表号:DJH-B-01
编号:
9
工程名称 合同编号
致 :
内容:
工程部(章):
工程部负责人/专业工程师: 年 月 日
本表一式三份,由工程部填写,项目经理部存二份、承包商存一份。
整 改 通 知 单
Change notice
表号:DJH-B-02
编号:
工程名称 合同编号
10
致 (承包商):
整改内容:
工程部(章)
工程部负责人/专业工程师: 年 月 日
承包商签收:
承包商(章):
签收人: 年 月 日
本表用于管理事项的整改通知,由工程部填写一式三份,项目经理部存二份、承包
商存一份。
11
停 工 通 知 单
Shutdown Notice
表号:DJH-B-03
编号:
工程名称 合同编号
致 (承包商):
工程 部位,由于
原因,现通知你自 年 月 日时起暂停施
工。
工程部(章)
部门负责人: 年 月 日
承包商签收(章):
负责人: 年 月 日
项目经理部意见:
项目经理部(章):
项目经理: 年 月 日
本表一式三份,由工程部填写,项目经理部存二份、承包商存一份。
Chapter 07
12
Contract Management
7.1 Duties
The business management department is in charge of the centralized management of the business
part of the contract and organizing the technology management department to take charge of the
7.2 Procedures
1) the deputy project manager organizes the business management department to be responsible for
2) the deputy project manager organizes the technology management department to be responsible
3) the general contract should be submitted to the document management department with its
original copy for filing and then be printed and delivered to relevant staff by the general
management department;
4) for the amendment to the business contract, the business management department should submit
the reviewing record or the meeting minutes. The deputy project manager, after reviewing them,
should submit them to the project manager for written approval, and the original file should be
submitted to the document management department for archiving and be printed and delivered to
5) for the amendment to the technical contract, the technology management department should
submit the reviewing record or the meeting minutes. The deputy project manager, after reviewing
them, should submit them to the project manager for written approval, and the original file should
be submitted to the document management department for archiving and be printed and delivered
6) the business management department should, in compliance with the owner payment plan
required by the contract, assist the deputy project manager in organizing the collection of project
payment and report the collection situation to the project manager on a regular basis;
7) the general contract should be used within the project department only; those not belonging to the
project department but wishing to borrow the general contract should be approved by the project
13
manager/deputy project manager.
1) this project subcontract and procurement contract determine the supplier by tender-invitation or
price-inquiry;
2) the business management department is responsible for formulating the general business rules for
charge of reviewing the technical specification and technical amendments formulated by the
designing institute and the above two departments review the procurement contract, and the
contract evaluation report should be approved by the project manager after being reviewed by the
3) the subcontract management department should number the subcontract and equipment and
4) the subcontract and equipment procurement contract originals should have four copies, with two
for the supplier and two for the document management department for archiving, and then be
5) the business management department formulates the payment plan and the deputy project
manager reviews it. After being approved by the project manager, the business management
department should pay the subcontractor according to the contract and report the payment
situation to the deputy project manager and the project manager on a regular basis;
6) for the amendment to the business contract, the business management department should submit
the reviewing record or the meeting minutes. The deputy project manager, after reviewing them,
should submit them to the project manager for written approval, and the original file should be
submitted to the document management department for archiving and be printed and delivered to
7) for the amendment to the technical contract, the technology management department should
submit the reviewing record or the meeting minutes. The deputy project manager, after reviewing
them, should submit them to the project manager for written approval, and the original file should
be submitted to the document management department for archiving and be printed and delivered
8) the subcontract should be used within the project department only; those not belonging to the
14
project department but wishing to borrow the subcontract should be approved by the project
Chapter 08
Design Management
15
8.1 Duties
1) The design management department should comply with “Design Development Control
Program” in the 2010 revised edition of CMEC’s Quality Management Handbook to undertake
the centralized management of Sri Lanka Putnam Coal Power Project executed by the designing
institute.
2) The general engineer organizes tender-invitation of project design supervision, organizes and
coordinates the initial design to the construction plan design supervised by the supervising unit,
and be responsible for the contact and technical coordination between the supervisory and the
design institute.
8.2 Procedures
1) the project manager and the general engineer organize the technology management department to
2) the site manager organizes the site inspection to collect hydrological and meteorological field
data about the plant, conduct the geological survey and submit the survey report;
3) when the project contract comes into effect, it is time to organize the design coordination
meeting, implement the initial design and formulate the progress plan of the construction plan
design;
4) organize the design briefing: review the interface between various professions, discuss and
implement the design supervisor’s comments, determine the major and minor machines’ types
and parameters so as to provide correct references for signing the equipment subcontract. The
review comments should be recorded in the “Design reviewing comment form” (see Appendix 1)
5) organize reviewing at the stage of construction plan design (mainly design supervision review)
6) the technology management department organizes the comprehensive review before completing
and publishing the construction plan and confirms the required sequences according to the
owner’s plan, thus reviewing and publishing it one after another and delivering it to the owner
7) the technology management department organizes the treatment of the owner’s confirmation
comments, including oral defense, revision until the final edition of the construction plan.
16
8.3 Duties of site design management
the site manager organizes engineers of various professions to coordinate the site design service.
1) the site manager organizes various labor unions to inspect the system, equipment and
construction installation by the professionals to ensure that the designed functions meet the
contractual requirements;
responsible for the technical coordination between design, owners, construction, installation and
3) deal with the alteration in system, equipment and materials according to the sequence of design
revision and fill the “design revision notice” which should then be submitted to the document
management department for numbering and archiving by category. The design revision
procedures are:
a) the installation unit or the owner or CMEC or the design institute itself propose the revision
requirements (written);
b) the site manager and the design manager reviews it and organizes the exclusive meeting to
c) professional designers in the design institute prepare the revision notice and deliver it after
4) the design institute is responsible for revising the construction plan and publishing the completion
plan, and then submitting it to the owner for signing and to CMEC for archiving;
5) the site manager organizes various professionals to facilitate the project design summary by the
design institute and then submits it to the document management department for archiving.
Chapter 09
Quality Management
17
9.1 Objectives
To fulfill CMEC’s quality guidelines, this program controls the manufacturing and testing of the
equipment for Sri Lanka 3X300MW Coal Power Project to ensure that the equipment procured
9.2 Scope
This program applies to the products and equipment procured for Sri Lanka 3X300MW Coal
Power Project.
9.3 Duties
1) the technology management department assists the quality management department in centralized
management of the equipment’s manufacturing quality, progress, examination and factory testing
2) the site project department is responsible for centralized management of the quality professionals’
9.4 Procedures
1) the technology management department is responsible for managing the detailed information of
major and minor equipment (including their names, numbers, types, major property parameters,
prices, progress requirements, addresses, contactors and phone numbers) and formulating the
2) the quality management department formulates the outline for factory supervision and testing
verification on the basis of the equipment list and the testing plans provided by various
equipment contractor:
b) determine the witnessing points for equipment inspection and plant-resident supervision, and
according to the function of equipment and components in the power plant, divide them into:
stop to be test (point H), on-site (plant) witness (point W) and document witness (point R).
assists the quality management in drafting the equipment manufacturing quality inspection and
witness points “H”, “W”, and “R” which will be reviewed by the deputy project manager before
being implemented;
4) the quality management department, according to the requirements in “Witness Points (Point H)
18
for Owner’s Participation in the Project”, drafts the witness plan and submits it to the owner after
5) the quality management department organizes the owners to participate in the witness testing of
various plants:
a) within 30 days before the witness testing, send notices to the owners (including witness date,
testing content and procedures) and at the same time, send to the site project department and
equipment manufacturing factory. The site project department is responsible for checking the
foreign partners’ agenda and the number of participants and reporting to the corporation;
b) check the testing preparation and document preparation of the manufacturing factory,
including: testing objectives, procedures, testing content, recording form and relevant
technical data;
d) submit the witness documents according to the owner’s requirements and submit one to the
6) Delivery verification
Verification before packing includes product specification, type, number, standard certificate
and random data (product description and installation, delivery and maintenance manual) and
the appropriateness and consistence of the packing list. The packer should sign or seal on the
packing list.
7) The quality management department and the technology management department should, in
compliance with the storage management procedures and requirements, assist the transportation
1) according to the contractual requirements, the site project department organizes the testing unit to
formulate the site system and equipment testing witness projects list, reviewed by the site project
department and the construction and installation unit and submitted to the owner for confirmation
and implementation;
2) the testing unit will comply with the project progress and draft the site testing witness plan with
19
the installation unit, approved by the site project department and the installation unit and then
3) the professionals responsible for quality from the site project department organizes the site testing
witness:
7 days before the testing witness, notify the owners and require them to reply within 2 days;
the day before the testing witness, hold a pre-testing-witness meeting (CMEC and the owner);
the site project department will organize witness with the installation unit and arrange
the witness report approved and signed by the owner witness should be submitted to the owner
for confirmation and be returned within 7 days. Then distribute the copies and archive the
original CMEC.
Continuous reliability testing is a comprehensive examination of the security and reliability of the
major and minor equipment and various systems. If within the days specified in the contract, the
major and minor machines do not have any problems, it is necessary to undertake continuous
the site project department organizes the testing unit to formulate the pilot running plan and the
outline which will be implemented after being reviewed by the operation, installation and other
parties;
the testing unit is in charge of machine running, operation, inspection, parameter recording and
the site project department is responsible for pre-testing preparation, including treatment of any
issues in the pilot starting of the whole machine; the testing unit and the installation unit transfer
the post; the equipment and the system are in the to-be-launched state, the witness documents
should be confirmed by the owner; during the testing, after all posts have been staffed, it is time
during the operation, the site project department is responsible for coordinating with the owner
witnesses. When the operation meets the required objectives, arrange the owner to sign reception
and confirmation; when the continuous operation ends, it is time to start the commercial
20
c) Testing witness of machine group performance
Performance testing is the final verification of the performance guarantee value of the machine
the general engineer is responsible for organizing tender-invitation, reviewing and determining
the performance testing outline is formulated by the testing subcontractors and confirmed by the
owner;
the site project department and the testing subcontractors study and determine the appropriate
time for implementation and seek approval from the owner (arrange stop and prepare for the
testing);
the testing proof about the equipment and components should be submitted to the owner for
confirmation;
with the help of installation, install the testing components, place and adjust the testing
share the technology with operation and installation and other parties;
the operation subcontractors are responsible for the operation, inspection and maintenance of the
machine group, and the testing subcontractors guide the operation adjustment, testing and
recording;
the site project department is responsible for coordination between the owners during the testing;
when the testing is completed, the testing subcontractors are responsible for managing the data
and submitting the testing report. The site project department is in charge of organizing the
owners to submit the testing report and associated data for confirmation.
Chapter 10
Supervision Rules
21
10.1 Introduction
1) to fulfill CMEC’s quality guidelines and comply with the rules in CMEC’s Quality Management
manufacturing, eradicating common, frequent and repetitive quality issues to eliminate product
deficiencies before marketing and prevent non-standard products from entering the construction
site;
3) equipment supervision is to supervise the quality of standard products within the manufacturing
factory under the contractual circumstances (including external cooperative and purchased
components), but it does not substitute for quality supervision by any state or industrial
management and quality guarantee system to help the manufacturing factory detect problems and
make timely correction, but the supervision does not substitute for the responsibility of the
manufacturing factory to check for itself, nor does it replace the final check of contractual
products. The quality and performance of the equipment is up to the manufacturing factory.
according to the contract/technical agreement signed with the equipment subcontractor, which is
to supervise in the course of manufacturing if the contractual products meet the requirements;
2) adopt different ways of supervision for different types of products. Equipment supervisors should
formulate an equipment quality testing plan and implement it according to the plan, and establish
3) the supervision means are: stop to be checked (point H), on-site witness (point W) and document
witness (point R). the program of stop-to-be-checked (point H) requires that representatives of
the project department (including the owner/engineer) to participate in the site check and sign
approval before going into the next stage; the program of on-site witness (point W) requires the
representatives of the project department to participate in the witness the program of document
witness (point R) is to review the manufacturing factory’s check and testing report;
22
4) when signing the equipment contract with the manufacturing factory, both parties should agree on
the supervised program and means of supervision (point H, W and R). After the supply contract
comes into effect, the manufacturing factory should provide for the project department/quality
management department a manufacturing plan and a quality check plan; before the scheduled day
(30 days for point H, 90 days for programs in which the owners participate and 21days for point
5) when receiving the notice, the project department/quality management department should send
representatives in time to participate in the witness in the manufacturing factory. If they can not
participate as scheduled, point W will change into point R automatically. But if point H changes
into point R without written notice from the project department, the manufacturing factory should
not automatically go into the next stage; instead, it should negotiate with the project
department/quality manufacturing department about change of the witness date. If it can not
make it after the date change, it is deemed to have abandoned the witness;
6) if the manufacturing factory does not notify the project department/quality management
department can not participate in the witness as scheduled, the project department/quality
7) after the quality witness, representatives of both parties should sign on “Equipment
Manufacturing Quality Witness Comment” (see Appendix 1). Then the project department and
the manufacturing factory should have one copy for each, and two copies shall be added if the
3) the technical rules stipulated by the machinery department and the electric power department;
5) by introducing the equipment standard for technical manufacturing, the enterprise standard is
approved by relevant authorities on the basis of introducing technical standard, take in according
to the national standard of the introducer country or the international standard or the introduced
technology.
23
1) when signing the contract with the manufacturing factory, it is necessary to include the equipment
3) important equipment should be supervised jointly by external supervising unit and the staff from
the quality management department, but the equipment supervision commission contract must be
4) before the supervision, the supervisors should formulate a plan for the contractual equipment,
including the technical data, plans, standard and testing record as well as site witness certificate
format provided by the manufacturing factory, and then the plan should be submitted to the
5) before the supervision, the project department/quality management department should notify the
manufacturing factory of the supervisor name roll and associated power. The supervisors should
supervise on the site according to the negotiated supervised projects and the equipment
manufacturing progress. They should report the existing problems and the treatment results to the
1) the supervisors should strictly comply with relevant rules and labor discipline of the
2) supervisors should first get to know and understand the contractual clauses, supervision
agreement, the quality guarantee system of the manufacturing factory and the rules in “general
standards”; and then understand the equipment manufacturing standards and the manufacturing
progress;
3) participate in or understand the raw material of important components required in the outline, the
chemical testing of cast steel components and the screening testing of parts;
4) be acquainted with the quality assurance measures and implementation of major components, the
5) participate in and understand the part-whole testing, linkage testing and assembly and testing
before marketing specified in the contract or the agreement, and undertake the site witness and
visa proceedings, but the visa can not replace the verification after the contractual products arrive
24
at the site or the verification testing after the delivery;
6) understand the design alteration of the contractual equipment and the manufacturing
improvement;
7) understand the protection, maintenance, indoor storage and packed delivery of the contractual
equipment;
contact the manufacturing factory in the form of “Project Contact List for Equipment
Supervision” (see Appendix 2), and then report to the project department/quality management
department any major problems that breach the contractual requirements or concern the design,
9) the supervisors should establish the “Equipment Supervision Log” (see Appendix 3) and
“Equipment Supervision Report” (see Appendix 4) to keep record of the supervision and then
10) after the equipment supervision, the supervisors should sign on the equipment verification
Appendix 1
见证内容(Witness content):
见证地点(Witness site)
:
不合格项内容(Unqualified item):
见证结论(Witness Conclusion)
:
收件单位处理意见:
Receiver’s comments:
签字: 年 月 日
signature: year month date
注:本通知单一式两份,一份发件者存,一份交收件单位,待收件单位作出处理意见后返
回发件单位存档, “一般”文件在两日内回复, “急”文件应立即回复。
Note: this notice is in duplicate, one for the sender storage and the other for the receiver which
will be sent back to the sender for archiving after being commented by the receiver. “ordinary”
file should be replied within two days and “urgent” file should be replied immediately.
Appendix 3
27
斯里兰卡普塔拉姆燃 煤电站项目
Sri Lanka Puttalam Coal Power Project
设备监造日记
中国机械设备进出口总公司
斯里兰卡普塔拉姆燃煤电站项目部
28
Appendix 3
备注
Notes
29
Appendix 4
备注
Notes
30
Chapter 11
Document Management
11.1 Duties
The deputy project manager is responsible for organizing the centralized management of all the
documents and data concerning this project by the document management department.
11.2 Principles
1) all the documents, upon reception, should be reviewed by the deputy project manager and then be
2) all legitimate original documents concerning the contract, business, technology and bank
3) establish the submittal and borrowing rules, that is: register when submitting and borrowing the
4) the communication should be mainly verbal so that there is verbal proof for check;
5) external documents should be reviewed and signed by the deputy project manager. When the
deputy project manager is out on business or not in the headquarters, the officer assigned by him
is responsible for reviewing and signing and then submitting to the deputy project manager for
6) internal documents should be submitted to the project manager/deputy manager for reviewing
and signing.
The documents to be sent should be of uniform format. Before sending it, it is necessary to
register according to the number on the “Registry of Documents to Be Sent” of the document
management department and then submit to the deputy project manager for reviewing and
signing. After sending the documents, it is necessary to submit to the document management
After receiving the documents, the document management department should register and submit
it with the “Letter Treatment List” to the deputy project manager for reviewing and then to the
officer to handle according to the comments of the deputy project manager and sign on the
31
“Registry of Documents Received”. Finally, the original documents should be submitted to the
11.4 Document communication between the internal project department and the site project
department
1) the correspondence between the internal project department and the owners should be copied
and sent to the site project department through fax, e-mail or letters;
2) the correspondence between the site project department and the owners should be copied and
sent to the internal project department for archiving through fax, e-mail or letters.
Archiving the documents and data should be undertaken by the document management
department according to the categories such as contract, agreement, meeting minutes and design
institute.
All the documents and data of the project department (especially the business contracts and the
equipment booking contracts) should be used within the project department only and shall not be
32
Chapter 12
33
2.4Technical inspection of heat treatment √
2.5 Heterogeneous steel joint inspection
①
(Typical sample is permitted)
1.Technology assessment √
2.Mechanical property √
3.Metallurgical structure √
4.Inspection of rupture plane √
① For inspection and witness of heterogeneous steel joint, the sample is taken just according to the steel
type, such as for steel 102+TP304H welding joint, whether it is used at superheater or reheater, or the
pipe specification, it is representative.
2.6 Bend tube inspection (bend tube overall √
dimension, ellipticity, exterior thickness
reducing)
2.7 Tube bending degree √
2.8Hot calibration technology and surface √
inspection after hot calibration
2.9 Random inspection by through ball test √
2.10 Hydrostatic test √
2.11Assembling quality inspection of pipe √
clipand related accessories (material,
appearance, expansion clearance)
2.12 Inspection of each stage of superheater and
reheater panel
1. Geometric dimension √
2.Flatness √
3 Economizer (include 3.1 Steel tube
suspension tube) 1. Incoming inspection of steel tube
( 1 ) Steel tube material quality assurance √
certificate
(2)Recheck report of incoming steel tube √
( 3 ) Recheck report of inside quality of √
incoming steel tube (NDT)
2.Inspection of steel tube surface quality √
3.Measurement of steel tube dimension (OD, √
wall thickness, ellipticity)
3.2 But welding weld
1.Appearance inspection of weld (appearance, √
dimension and surface quality)
2.Inside quality of weld (NDT report) √
3.3Welding technology and welder qualification √
inspection
3.4Bend tube inspection (overall dimension of √
bend tube, ellipticity, exterior thickness
reducing)
3.5 Random inspection by through ball test √
3.6hydrostatic test √
4 Steam drum (drum) 4.1Steel (include body, head and downcomer
socket, etc)
1.Steel incoming inspection
(1)Steel material quality assurance certificate √
(2)Recheck report of incoming steel √
( 3 ) Recheck report of inside quality of √
incoming steel (NDT)
2.Quality inspection of steel surface √
34
4.2 Weld inspection (include ring weld,
longitudinal weld, fillet weld of various header,
reinforcing ring of hole and door, etc weld)
1.Appearance inspection of weld (appearance, √
dimension and surface quality)
2. Inside quality of weld (NDT report) √
3.Weld repair report √
4.NDT report √
4.3Welding technology check
1.Technology assessment and quality assurance √
measures
2.Welder qualification and welding materials √
certificate
4.4Inspection of heat treatment
1. Check of parameters and specification for √
heat treatment
2. Mechanical property inspection after heat √
treatment
4.5Check of drum appearance and dimension
1.Length, diameter, wall thickness √
2.Drum roundness √
3.Head roundness √
4.Deflection along total length of drum √
5.Deviation of drum ID √
6.Unfitness of each butt weld for drum √
7.Tube joint pitch and its deviation √
8.Longitudinal displacement √
9.Circumferential displacement √
4.6 Hydrostatic test √
4.7 Various steel seal check (include steel grade, √
manufacturing month and year, welder, tester,
heat treatment, etc)
5 Header (include 5.1Material of header and tube socket
waterwall, 1.Imcoming inspection of steel tube
economizer, ( 1 ) Steel tube material quality assurance √
superheater, reheater, certificate
etc header) (2)Recheck report of incoming steel tube √
( 3 ) Recheck report of inside quality of √
incoming steel tube (NDT)
2.Inspection of steel tube surface quality √
3.Measurement of steel tube dimension (OD, √
wall thickness, ellipticity)
5.2Inspection of header butt weld
1.Appearance inspection √
2.Inside quality of weld (NDT report) √
3.Repair report √
5.3Inspection of fillet weld for tube socket
1 . Appearance inspection (Weld height, √
appearance and surface)
2.Inside quality of weld (NDT report) √
3.Repair report √
5.4 Physical dimension check of header and
tube socket
1.Appearance inspection √
35
2.Length, diameter, wall thickness √
3.Deflection along total length of drum √
4.Deviation of socket pitch √
5.Deviation of socket height √
6 . Longitudinal and circumferential √
displacement of socket
5.5Check of welding and heat treatment
technology
1 . Welding technology assessment, welder √
qualification
2.Specification and parameter of heat treatment √
5.6Inspection of baffle weld inside the header √
5.7Inspection of cleanliness inside the header √
5.8Hydrostatic test √
6 Regenerative air 6.1Quality assurance and recheck report of raw √
heater material (include forging)
6.2 Appearance inspection of weld √
6.3Dimension, appearance, assembling quality √
6.4NDT report of central cylinder, guiding end √
shaft, etc.
6.5Trial assembly of heat exchange sheet √
7 Boiler steel structure 7.1Steel (Plate, section bar, high strength bolt,
(girder, column, beam, etc.)
etc.) (1)Steel material quality assurance certificate √
(2)Recheck report of incoming steel √
3 . Inspection of steel surface quality and √
dimension
7.2 Appearance inspection of girder, column and √
main beam
7.3Weld suface quality (Appearance, dimension) √
7.4 NDT report of weld √
7.5 Check of main dimension and dimension √
check of high strength bolt
7.6Inspection of connection pair for high √
strength bolt
7.7Check of pre-assembly √
7.8 Number of random inspection for girder and
column
7.9 Inspection of anti-corrosion paint √ √
8 Burner 8.1Steel
1.Steel quality assurance certificate (include √
welding material)
2.Recheck report of incoming steel √
8.2 Appearance inspection of weld √
8.3Check of dimension for main installation √
connection
8.4Inspection of nozzle oscillating angle and √
flexibility of actuator action
8.5 Number of random inspection for single and
grouping burner
9 Safety valve 9.1Steel (include valve body, valve seat, valve
stem, spring, etc material)
1.Material quality assurance certificate √
2.Incoming recheck report √
36
9.2Appearance inspection (include dimension √
inspection)
9.3 Valve body NDT report √
9.4 Hydrostatic test √
9.5Tightness inspection √
9.6Hot test of openning and reseating √
37
supervised H W R
12.1.5 FD fan
No. Components Item supervised Witness mode
38
supervised H W R
3. NDT report √
39
supervised H W R
4No-load test √
5Vibration test √
6Locked test √
7Efficiency test √
12.1.7 PA fan
No. Witness mode
Components
Item supervised H W R
supervised
40
1 Raw material 1.Chemical composition, mechanical property √
and heat treatment results report of main parts
2.Recheck report √
3.NDT report √
41
2Incoming recheck report √
4No-load test √
5Vibration test √
6Locked test √
7Efficiency test √
12.1.9 ID fan
No. Witness mode
Components
Item supervised H W R
supervised
42
√
3.NDT report
2 Main shaft 1Chemical composition report of material √
2Test report of mechanical property √
3NDT report √
3 Vane 1Vane frequency test (axial flow fan) √
2Dye penetration test (include flange) √
4 Impeller 1Raw material quality assurance certificate √
2. Test report of mechanical property for material √
3NDT report of weld √
4Certificate of heat treatment √
5Dynamic balance test √
5 Bearing housing Leakage test √
6 Regulating system 1Interlock test of regulating component √
2Assembling record of regulating vane (axial flow √
fan)
7 Oil system (adopt 1.Cleanliness inspection
bearing with 2.Leakage inspection of oil tank
forced-circulation 3.Tightness test of oil cooler
oil lubrication 4.Trial run test of oil pump
8 Complete machine 1 10% overspeed test of impeller √
2 Mechanical trial run √
3Operation performance test within full range √
4Shaft vibration and idling √
5Noise status √
6Appearance and installation dimension √
7 Inspection of anti-corrosion paint and inspection of √
packing
43
2 Silicon chip 1Quality certificate √
inspection
2Incoming recheck report √
4No-load test √
5Vibration test √
6Locked test √
7Efficiency test √
12.1.11 ESP
No. Witness mode
Components
Item supervised H W R
supervised
44
smoke-box, ash plate and polar
hopper, pole
plate and polar
5 Rapping Rapping test record
6 Lower of Inspection of anti-corrosion paint and inspection of √
supporting packing
beam for ash
hopper,
platform, stair
Hydrostatic test √
Hydrostatic test √
material √
Heating
3 √
(1)Chemical composition and mechanical property
surface
√
(2)Surface quality inspection of steel tube
45
Waterwall panel test
Superheater inspection
(1)Physical dimension √
(2)Flatness √
Completion Appearance √
7
inspection Packing and shipment √
46
axle 2)Dimension check √
47
12.1.14 Gantry type reclaimer
No. Witness mode
Components
Item supervised
supervised W R
H
48
1) Electric system test
√
2) Hydraulic and pneumatic system test
Complete √
3)No-load trial run
12 machine √
4)Load trial run
property test* √
5)Test of dust collector
√
12.2.1Turbine proper
49
4 Bearing, 1.Casting defect of pad alloy and bodiless inspection √
Bearing 2. Thickness difference of bearing alloy √
pedestal
3. Thickness difference between thrust pads √
sole plate
4.Inspection of bearing contact surface and tension √
5.Split clearance √
6.Bearing pedestal kerosene test and its hydraulic test √
of pressure chamber and inject tube
7.Diameter of bearing working surface and contact √
accuracy
8.Geometic accuracy and contact accuracy between √
sole plat and bearing pedestal
9.Bearing pedestal cleanliness inspection √
5 Bolt for 1. 1.Chemical composition of material √
cylinder and 2.Mechanical property of material √
coupling
3.Spectrum hardness recheck √
4.Thread accuracy √
6 Coupling 1.Chemical composition of material √
2.Mechanical property of material √
3.Ultrasonic test √
4. Radial beat at outer circle and lock √
5.Beat of two end faces (slanting) √
6.Central distance of screw √
7. Screw finish √
8.Verticality between bolt hole and its end face √
7 Impeller 1.Chemical composition of material √
and main 2.Mechanical property of material (include FATT √
shaft property)
3.NDT √
4.Heat stability test √
5.Residual stress test √
6.NDT and roughness inspection of inner hole √
7.Surface roughness and roundness of journal √
8. Radial beat of journal and rim √
9. Beat at end face of thrust disk collar √
8 Steam seal 1. Clearance of steam seal split √
50
2.Spring material and elasticity curve √
3.Machining tolerance and roughness of seal block √
tooth tip
9 Moving 1.Physical and chemical composition of material √
blade 2.Mechanical property of material √
3.Test results √
4. Appearance inspection of hard alloy sheet welding √
quality or surface hardening part
10 Guide vane 1.Physical and chemical composition of material √
2.Mechanical property of material √
3.Test results √
4.Surface roughness √
11 Turbine 1. Impeller rim end face and radial beat after shrunk on √
rotor 2.Coupling end face and radial beat after shrunk on √
assembling
3.Record of weight of blade with root √
4.Appearance inspection of lacing wire after riveting of √
blade
5.Clearance between blade top face and inside of √
shroud ring after riveting of blade
6.Clearance between shroud ring arc √
7.Maximum deflection at middle of rotor √
8.Results of static balance √
9. Record report and phase curve of dynamic balance √
10. Frequency measurement of frequency-modulating √
blade (group frequency and dispersion rat of moving
blade, all frequency-modulating blades whose
frequency is under300Hz)
11.Dynamic vibration characteristic test of last stage √
blade and penultimate stage blade for new blade
12.Rotor overspeed test √
13.Rotor packing test √
12 Final 1.Sole plate clearance √
assembly 2. Guiding key clearance for sliding pin system √
3. Concentricity between cylinder and casing √
51
4.Diaphragm, diaphragm sleeve, steam seal, etc lower √
positioning key clearance and guiding key clearance
(applicable to unit with whole assembly ex-factory)
5. Concentricity between various stage diaphragm √
6.Concentricity between rotor and cylinder √
7.Dynamic and static clearance of flow path √
8.Rebound elasticity and expansion clearance of steam √
seal ring
9.Pad clearance and pad cover tension √
10.Coupling alignment inspection √
11.Rotor uprising √
12.Cylinder load distribution √
13. Casing split clearance after closing √
14. Radial and axial clearance of steam seal √
15.Rotor axial shift and thrust clearance √
16.Spheric pad contact with bearing pillow √
13 Turning 1.Turning gear function √
after final 2.Turning test √
assembly
14 Front Anti-corrosion paint inspection √
housing,
Bearing
pedestal
52
5.Assembly check √
3 Test and 1. Cleanliness inspection of governing and safeguard √
inspection system
2. Static interlock test of governing system √
3.Measurement of natural parameters √
(1)Closing time of main steam valve
(2)Closing time of governing valve
(3)Speed droop
(4)Delay rate
(5)System stability
(6)Relationship between start valve stroke or EHC
drive current and stroke of main steam valve, governing
valve
4.Emergency governor √
(1)Overspeed test
(2)Oiling test
53
7.Anti-rust treatment again (only applicable after √
hydrostatic test)
8. Paint brand number and painting technology √ √
9. Sealing measures √
3 Shrink fit 1.Appearance inspection √
oil pipe 2.Cleanliness inspection √
3.Acid cleaning results √
4.Paint brand number and painting technology √ √
5.Welding quality and weld position √
6.Ray test of weld for bearing oil tube in oil discharge √
pipe
7. Internal hanger and support √
8.Protection oil quality √
9.Sealing measures √
4 Oil ejector 1.Property test √
54
3 Cylinder 1.Test report of raw material
(1)Quality assurance certificate of steel works √
(2)Imcoming chemical composition and mechanical √
property test
2.Welding inspection
( 1 ) Technology assessment of longitudinal and √
circumferential weld
(2)Welder qualification and welder seal √
(3)Welding sample report √
(4)Surface quality of welding √
(5)Inspection of welding raw material √
3.NDT
(1)X ray detect √
(2)Ultrasonic detect √
4 Heat transfer 1.Test report of raw material
tube (1)Quality assurance certificate of steel works √
(2)Imcoming chemical composition and mechanical √
property test
2.Eddy current test report √
3.Inspection of bend tube thickness reduction √
4.Through ball test √
5 Assembly 1.Assembly quality of tube bundle √
2. Conduit cleanliness inspection √
3.Weld inspection √
4. Inspection of explosion tube expansion √ √
5.Leakage test √
6 Hydrostatic 1.Hydrostatic test of water side √
test 2.Hydrostatic test of steam side √
7 Heat 1. Integral heat treatment √
treatment
8 Painting and 1.Check of main installation dimension √
packing 2. Inspection of paint, oil seal √ √
3. Inspection of nitrogen filling protection √
4. Inspection of packing and shipment marking √
9 Bought-in 1.Check of quality assurance document for bought-in √
equipment equipment
55
12.2.3 feedwater pump
No. Witness mode
Components
Item supervised H W R
supervised
56
12.2.4feedwater pump motor
No. Witness mode
Components
Item supervised H W R
supervised
57
7.impeller static balance √
8.rotor dynamic balance √
2 Guide blade, wearing 1. chemical ingredient of material √
ring suction section and
delivery section, shell 2.mechanical property of material √
and pump cover, internal
cover and middle
3.NDT of material √
section, connection tube, 4.pressure component static hydraulic test √
sealing gasket, cross bar
and double head bolt and 5.NDT of connection tube welding with cover √
nut, sealing member of
head cover, tail cover 6. guide blade gate roughness ( polish √
and end cover, bearing
process)
etc. static parts.
3 Sleeve, coupler 1surface hardness inspection √
2precision machining surface quality and size √
inspection
4 Assembly 1. each part of pump radial and axial √
clearance
2. rotor axial displacement and radial rising √
5 Test 1.type approval test √
2. Property test √
3.ex-factory test(hydraulic and efficiency) √
4.vibration test √
5. noise test √
6 Completion inspection 1appearance installation size inspection √
2package and delivery mark inspection √
58
7 Total Insulation condition, stator, rotor cleanness, main √
assembly installation size
8 Ex-factory Test will be completed as internal standard GB755-87 √
test
9 Equipment Painting anti-corrosion inspection, appearance, package √ √
completion and delivery mark inspection
inspection
59
7 Assembly 1. blade, impeller and guide blade polish quality √ √
2.rotor lifting height √ √
3. clearance between impeller and impeller room, √ √
clearance between guide bearing and sleeve
8 Ex-factory 1. operating and performance test √
test 2. vibration and noise measure √
9 Completion 1. Painting anti-corrosion inspection, appearance, and √
inspection installation size inspection
2. package and delivery mark inspection √
12.2.9 deaerator
No. Witness mode
Components
Item supervised H W R
supervised
60
5.appearance size inspection √
6. Welding NDT report √
7.hydraulic test √
8. deaeration head cleanliness inspection √
2 Steel pipe 1. chemical ingredient of material √
2.mechanical property of material √
3 Nozzle, spray 1. machining quality inspection √
disc 2. nozzle atomization characteristic industry test √
12.2.10 condenser
No. Witness mode
Components
Item supervised H W R
supervised
61
3. pump shell material certificate, chemical ingredient, √
mechanical performance, precision machining surface
quality and size inspection
2 Rotor Static balance test √
3 Pump shell Welding joint kerosene test √
4 Steam and water 1.welding quality inspection √
separator
2.leakage inspection √
5 Base Appearance and size inspection √
6 Vacuum pump Each part fitting clearance and size inspection √
assembly
7 Completed set 1. vacuum pump motor installation Alignment √
Equipment
assembly 2. Completed set equipment connection quality √
inspection
3. piping system sealing inspection √
8 Ex-factory test 1.single pump total performance test √
2.completed set operation test √
3. vibration and noise measure √
9 External 1.motor certificate √
purchase 2.import equipment Quality assurance document √
equipment inspection
10 Painting, 1. painting quality inspection √
package 2. packing and delivery mark inspection √
62
10.after rotating and rotor finishing, size precision, √
surface roughness and Position Tolerance inspection of
key part
including:at the both sides of turbine and excitor,
bearing retainer,Shaft-Extension retainer,rotor slot
width,ring key slot width,ring key slot to outside circle
finishing,coupler flange,round finishing in the end
axial flange and coupler flange,end finish turning,lead
wire key slot
2 Guard ring 1.guard ring quality guaranty √
2.mechanical property test report √
3.detection report √
4.stress test report √
5.chemical ingredient analysis report √
6. guard ring machining size precision and surface √
roughness inspection, including matching surface of
guard ring and proper, internal conicity, guard ring
length, ring key slot width, size from slot to end surface
and slot depth
3 Centre ring 1.raw material quality guaranty √
2.chemical ingredient analysis report √
3.mechanical property test report √
4.detection report √
5.machining size precision and surface roughness √
inspection of guard ring matching surface and axial
matching surface
6.stress test report √
4 Blower Fan 1.raw material quality guaranty √
2. physicochemical performance test report √
3.surface roughness grade √
4. Shank diameter, size precision and surface roughness √
inspection
5.frequency measuring test report √
6.detection report √
5 Rotor slot 1.raw material quality guaranty √
wedge 2.mechanical property test report √
3.chemical ingredient analysis report √
4.detection report √
6 Rotor 1.raw material quality guaranty √
copper wire 2.mechanical property test report √
3.chemical ingredient analysis report √
63
4. magnetic inductivity measure report √
5.tube conductor detection result √
6.appearance inspection √
7 Collector 1.raw material quality guaranty √
ring 2.mechanical property test report √
3.chemical ingredient analysis report √
4.internal diameter and collector ring jacket assembly √
size precision and surface roughness inspection
8 Silicon 1.raw material quality guaranty √
sheet 2.single consumption measure report √
3.lamination painting film and burr test check √
9 Stator 1.raw material quality guaranty √
copper wire 2.mechanical property test report √
3.chemical ingredient analysis report √
4.conductivity measure report √
5.tube conductor detection result √
10 Rotor 1.rotor lead wire assembly process inspection √
2.slot liner size and assembly size inspection √
3.copper wire welding quality inspection √
4. both end different of extended the slot after each √
coil assembling
5. bush guard ring front slot wedge tightness √
6.slot wedge contact surface √
7. slot wedge air vent and rotor skew tooth eccentric √
different
8.collecting ring assembly and test √
9. end cushion block √
10.excitation winding insulation resistance measure √
11. excitation winding AC withstand voltage test √
12. excitation winding DC resistance measure under √
actual cooling state
13. excitation winding AC impedance measure √
14. bearing vibration value in three aspect when √
dynamic balance
15 overspeed test √
64
16.internal hydrogen cooling generator rotor air vent √
inspection test
17.excitation winding hydraulic and flow test(only for √
water cooling generator)
18.rotor air tightness test √
19.appearance √
20. insulation water pipe assembly connection and √
appearance inspection
11 Stator coil 1.coil size and shape √
2. coil insulation integrity and surface condition √
3. coil insulation dielectric performance √
4.hydraulic and flow test(only for stator water cooling √
generator)
12 Stator 1.core internal diameter, length and segment length √
2.core slot shape √
3.core compacting √
4.core axial geometric centre deviation √
5. temperature measuring element √
6.holding ring and support assembly √
7. pressure plate √
8. wedge tightness after heating √
9. coil welding √
10. insulation box or upper, under joint insulation √
11. lead wire copper wire size √
12.stator core loss heating test √
13. DC resistance measure when winding under actual √
cooling state
14. winding for cover and phase insulation measure √
15.stator winding DC withstand voltage and current √
leakage measure
16.stator winding AC withstand voltage test √
17.air tightness test √
18. clean and appearance √
19.insulated water pipe assembly and connection √
13 Integral and 1.internal water cooling turbine generator rotor winding √
product hydraulic and flow test
65
performance 2.double internal water cooling turbine generator rotor √
inspection winding hydraulic and flow test
3.sealing pad internal diameter, width and matching √
surface size precision and surface roughness
inspection
4.sealing state inspection and hydrogen leakage test √
5.cooler hydraulic test √
△6.no load character test √
△7.stable short circuit characteristic test √
8.stator winding vibration √
9.vibration test √
△10.noise test √
△11. voltage deviation √
△12. frequency deviation √
△13.sine distortion degree √
△14. telephone harmonic factor √
△15.non-balance load capacity √
△16. short circuit ratio √
△17.subtransient reactance xd(PUV) √
△18.stator, rotor winding temperature rising test √
△19. efficiency √
△20.bearing oil outlet temperature and bearing bush √
temperature
21.stator end cover assembly precision inspection √
22.hydrogen cooler end cover assembly precision √
inspection
Note::in the table“△”mark witness base on factory report,generator with type approval test change into
site witness and document witness
66
system system
ex-factory 2)automatic voltage regulator and additional unit static
characteristic test
test And whole static characteristic test
3) operation control circuit action test
4) use analog method to inspect protection and monitor
device
5) measure of automatic voltage regulator voltage setting
scope
6) measure of excitation manual unit scope
7) automatic manual changeover test
8) excitation transformer test
9) monitor each additional unit setting and action
correction
10) other project user required type approval test
4 Completion package and delivery mark
inspection
12.3.2main transformer(220kv/20kv)
No. Witness mode
Components
Item supervised H W R
supervised
67
9 Cooler 1.quality guaranty √
2.ex-factory or type approval test report √
10 Submerged 1.quality guaranty √
pump 2.ex-factory or type approval test report √
11 Voltage performance test report √
regulation
switch
12 Total 1.whether abnormal matter for integral assembly √
assembly 2.insulation distance to oil tank √
13 Whole 1.sealing leakage test √
equipment 2.ex-factory routine test √
test
3.type approval test
(1)temperature rising test √
(2)lightning attack test √
4. special test
(1)circuit capacity test √
(2)sound level measure √
(3)zero-sequence impedance measure √
(4)no load current harmonic measure √
14 Transformer painting anti-corrosion inspection and appearance √
integral package inspection
68
5. body dry inspection √
6.semi finished product test inspection √
4 Total √
assembly
inspection
5 Finished 1.voltage ratio, vector relationship inspection √
product test
inspection 2.insulation resistance, absorption ratio, medium loss √
inspection
3.withstand voltage test inspection √
4.induction withstand voltage test inspection √
5.no load test inspection √
6.load test inspection √
6 Equipment disassemble inspection √
completion
inspection
12.3.4start/stanby transformer(220kv/6.3kv)
No. Witness mode
Components
Item supervised H W R
supervised
69
3.withstand voltage test inspection √
4.induction withstand voltage test inspection √
5.no load test inspection √
6.load test inspection √
7.partial measure inspection √
8.impact test inspection √
6 Equipment disassemble inspection √
completion
inspection
7 Transformer Painting anti-corrosion, appearance and packing size √
integral
inspection
70
6load test √
8 Type approval execute as contract and related standard √
test
9 Transformer painting anti-corrosion, appearance and package √
integral
inspection
71
2. after total assembly, CT winding volt-ampere √
character repetition measure
3. measure switch on, off time √
4. measure switch on, off speed √
5. measure Closing Resistance running time √
6. measure switch on, off synchronization √
7.operation mechanism pressure characteristic test √
8. circuit resistance measure √
9.SF6 leak detection test √
10.power frequency withstand voltage test √
11 Package 1.comply with requirement of factory package √
transportation specification
2. good, reliable anti-collision, anti-vibration √
measure
12 Switch integral Painting anti-corrosion, appearance and packing size √
inspection
12.3.7 GIS
No. Witness mode
Components
Item supervised H W R
supervised
72
terminal, 2.joint size match inspection √
transformer
connection
pipe(if have)
9 Partial unit 1.primary wiring inspection √
assembly test 2.main circuit insulation test √
3. auxiliary circuit insulation test √
4.main circuit resistance measure √
5.mechnical and interlock test √
6.gas sealing test √
7.auxiliary device test √
8.SF6 moisture content measure √
10 Integral 1.power frequency withstand voltage test √
assembly test
2.partial electric discharge test √
11 Equipment Painting anti-corrosion, appearance and packing size √
integral inspection
73
12.3.9 6KV switch cabinet
No. Witness mode
Components
Item supervised H W R
supervised
74
4 Electric 1withstand voltage test of main circuit √
performance
test 2withstand voltage test of secondary circuit √
3insulation detection √
5 Operating 1secondary distribution correction test √
performance
test 2swirch on, off flexibility test √
6 Type execute as contract and related standard √
approval
test
7 Completion package and delivery mark √
inspection
12.3.12 battery
No. Witness mode
Components
Item supervised H W R
supervised
75
4 electrolyte material quality certificate document √
3 Main Safety valve quality certificate document √
completed
set element
4 Equipment nameplate, main size √
appearance
check
5 Battery 1battery sealing performance test √
performance
test 2voltage measure test √
6 Type execute as contract and related standard √
approval
test
7 Completion package and delivery mark √
inspection
76
2 Equipment nameplate, painting, main size √
appearance
check
3 Commission 1. system hardware, function and application software √
test of each
acceptance test
control
system 2. application software logic design configuration √
DAS, FSSS, function acceptance test
MCS, SCS,
ECS
4 Completion package and delivery mark √
inspection
78
12.4.2drain water tank
No. Witness mode
Components
Item supervised H W R
supervised
79
component inspection
material
2 Main Quality assurance document inspection √
completed
set parts
3 Assembly 1 geometric size correct inspection √
2 welding quality inspection √
4 Ex-factory Whole equipment performance test √
test
5 Completion 1appearance, painting anti-corrosion inspection √
inspection
2package, delivery mark inspection √
1 Drawing √
Drawing design
2 Material √
Qualification certificate
3 Production √
Process chart
process
4 Upper rack Construction acceptance will be executed as √
GB205-83 steel structure project, appearance size
acceptance as drawing
80
5 Safeguard system √
Shear pin reliable, action reliability
6 Drive system Equipped with outdoor motor and speed reducer √
with chain wheel drive
7 Flushing system √
Equipped with 316 SS nozzle(include water pipe)
8 Guide rail √
Working surface linearity, length and deviation
9 Screen and Chain Screen outline size, frame angle scale, clearance of √
Board screen and rail sealing strip, chain board pitch
10 Chain Board √
extension alarm Adopt spring alarm device
device
11 Locating slot and √ √
connecting bolt,
Accept as pre GB1184-80 standard
nut and washer
etc.
12 Integral assembly √
Integral assembly
13 Whole equipment Painting anti-corrosion, appearance and packing √
size inspection
81
Chapter 13
Inspected by
Serial Description Subsection Inspection Item HPC CM CEB/P
C EC E
Final inspection H H
Clag chamber and ash hopper
1.1.6
installation
Ash hopper assembly WR R
Final inspection H H
82
1.1.7 Combustion eqipmwnt installation Burners installation HR H H
Downcomer erection WR WR
Desuperheater erection WR W WR
83
Boiler accessory pipelines and
1.3
equipment installation
Feed water pipeline installation WR WR
Final inspection H H
LP drainage installation WR WR
Final inspection H H
Feed Water, drainage, air vent
1.3.3 Water feeding pipeline installation WR WR
pipeline installation
Final inspection H H
Final inspection H H
Final inspection H H
Steam escape pipe installation for safety
WR WR
valves
Final inspection H H
Final inspection H H
1.3.4 Steam escape pipeline installation
Sootblowing steam escape pipeline
WR WR
installation
Final inspection H H
Flashtank steam escape pipeline
WR WR
installation
Final inspection H H
Sootblower installation WR W W
Sootblowing steam (water) pipeline
1.3.5 Sootblower installation WR WR
installation
Pressure test and final inspection H H
84
Dosing pipeline installation WR WR
Dosing pipeline and equipment
1.3.7
installation
Pressure test +final inspection H H
Internal & external flushing and dust Internal & external flushing and dust
1.3.9 removal water pipeline installation removal water pipeline installation inside WR WR
inside Boiler Island Boiler Island
85
Secondary grouting for the foundations of
WR R
the Static precipitator
The roof covering and side board
WR R
installation for the Static precipitator
Inlet and outlet horn installation for the
WR R
Static precipitator
Ash hopper installation for the Static
WR R
precipitator
Staires and platforms installation for the
WR R
Static precipitator
Electrodes assembly and installation for
WR W W
the Static precipitator
Distribution plate installation for the
WR W W
Static precipitator
Vibration and gear assembly installation
WR W W
for the Static precipitator
The partial test run for the vibration and
HR H H
gear assembly of the Static precipitator
Wind pressure test for the whole
3 HR H H
Boiler
Boiler fuel oil equipment and pipeline
4
installation
4.1 Oil tank and accessories installation Oil tank and accessories installation WR W
final inspection H H
86
Pratial test run for the coal feeders HR H W
87
Stacker and reclaimer erection WR W W
Sootblowing pipelines WR W
Blowdown pipelines WR W
Accessory pipelines and equipment
7.2 final inspection + pressure test H H
installation for the Start-up Boiler
Sampling pipelines WR W
Dosing pipelines WR W
final inspection H H
Pressure gauges WR W
88
Blower installation HR H W
Inspected by
Serial
Description Subsection Inspection Item HPC CM CEB/P
No.
C EC E
89
Installation of accumulator battery WR W I
Charging/discharging and capacity test WR W H
4.2 GIS inspection and installation GIS proper inspection and installation WR W I
4.3 Installation of GIS auxiliaries Installation of flexible busbar WR W I
4.10 On-line test run of 220KV GIS HR H H
Installation of control and DC system
5
and equipment
Inspection of transformer HR H I
Inspection of transformer HR H I
90
Installation of electrical equipment for
9
the coal handling system
91
Installation of lighting facility for
15.5 Circuit energization inspection HR H I
outdoor power distribution equipment
Installation of desulphurization
18
equipment
Inspected by
Serial
Description Subsection Inspection Item HPC CM CEB/P
No.
C EC E
Erection Project for Turbine and
1
Generator
1.1 Turbine proper erection
Inspection and verification of the
HR H R
geometric dimension of foundation
Foundation load-bearing surface
R
roughening
1.1.1 Foundation preparation
Installation of the inner baffle plate for
R
the secondary grouting
Inspection of anchor bolts HR H R
92
Installation of the shims WR W R
Inspection and installation of the sole
1.1.3 WR W R
plate
Inspection and cleaning of the bearing
WR W R
pedestal(box)
Inspection of the bearing busing WR W R
1.1.4 Inspection of the bearing pedestal(box)
Inspection of the pads of the bearing
R
bushing
Coupling connection HR H H
93
Installation of HP steam inlet dummy
WR W W
piston ring
Installation of HP diaphragm sleeve R
94
Installation of IP oil servo WR W R
Rotor inspection R W
1.3.2 Generator rotor inspection
Air pressure test for the rotor HR H H
95
1.3.11 Installation of seal pad R
Installation of equipment R R
Installation of equipment and pipes of
1.3.19 Installation of gas pipe R R
the gas system
Air pressure test of the gas supply pipe HR H H
tube expansion WR W WR
Installation of Condenser titanium
WR W W
tube
2.1 Condenser assembly and installation connection to cylinder R R R
96
Test run of the condenser scavenging
WR W W
pump
Installation of the ball collecting net R R
97
Grouting of the electric feed water
WR W R
pump
Installation of the oil system for the
WR W W
electric feed water pump
Oil system flushing for the electric feed
WR W W
water pump
Installation of the cooling water system
R
for the electric feed water pump
Test run for the motor-driven feed water
HR H H
pump
Inspection of the booster pump R R
Installation of the booster pumpand
R
coupling alignment
Installation of the booster pump for the
4.4 coupling alignment of train R W
feedwater pump
final inspection of FWP train HR H H
98
Installation of the circulating water pump
WR W W
motor
coupling alignment WR W
Installation of the other pumps for the
circulating water pump house coupling R W
alignment
Installation of the lifting equipment of the
R H
circulating water pump
Equipment test run for the circulating
6.4 final inspection before test run HR H H
water pump house
Installation of the circulating water trash
R R
Installation of the trash remover of the remover
6.5
circulating water pump Test run of the circulating water trash
R W
remover
Inspection of the blowdown pump R R
Installation of the blowdown pump
6.8
equipment Installation of the blowdown pump R R
Test run of the blowdown pump R W
R- Review W- Witness H- Hold Point
Inspected by
Serial
Description Subsection Inspection Item HPC CM CEB/P
No
C EC E
Installation of the I&C in the
1
main building
1.1 Installation of the common control
99
Installation of the (support) frames and
R
protective pipes of the cable bridge
1.2.4 Installation of the electric wirings
Cable laying WR W
Manufacture and wiring of the cable head WR W
I&C installation of the turbine
1.3
generator set
Manufacture and installation of the base
Installation of the on-siteI&Cplate R
1.3.1 plate
(cabinet)
Installation of the plate (cabinet) R
Installation of the on-site manometer and
Installation of the measuring and control R R
1.3.3 differential pressure instrument
instruments
Installation of the transducer R R R
Installation of the (support) frames and
R R
protective pipes of the cable bridge
1.3.4 Installation of the electric wirings
Cable laying WR W
Manufacture and wiring of the cable head WR W
I&C installation of the deaerating
1.4
feeding
Manufacture and installation of the base
Installation of the on-site I&C plate R
1.4.1 plate
(cabinet)
Installation of the plate (cabinet) R R
Installation of the on-site manometer and R
R
Installation of the measuring and control differential pressure instrument
1.4.3
instruments Installation of the switching value
R R
instruments
Installation of the (support) frames and
R R
protective pipes of the cable bridge
1.4.4 Installation of the electric wirings
Cable laying WR W R
Manufacture and wiring of the cable head WR W R
Inspected by
Serial
Description Subsection Inspection Item HPC CM CEB/P
No
C EC E
100
Reheat hot section bypass pipeline
WR W WR
installation
2 IP and LP pipelines
101
Hydrostatic test for IP and LP water
HR H H
supply pipelines
2.5 LT heater drainage pipeline installation LT heater drainage pipeline supports and
WR R R
hangers installation
2.10 Shaft gland and door rod steam leakage Shaft steam pipeline installation WR R RW
102
pipeline installation
Shaft gland and door rod steam leakage
WR R R
pipeline supports and hangers installation
Inspected by
Serial
Description Subsection Inspection Item HPC CME CEB/P
No
C C E
103
Simulation test of the system HR H H
2 Desalination system
Stuffing WR R W
FRP pipes WR R RW
2.2 Installation of pipelines
Stainless steel pipes WR R RW
Leak test of the system HR H H
2.3 Trial run of the system
Simulation test of the system HR H H
3 Condensate water treatment system
High speed mixed ion exchanger WR R RW
Installation of the regeneration separating
WR R RW
plant
Installation of the resin trappers WR R RW
Installation of the air receivers WR R W
3.1 Installation of equipment Installation of the recirculating water
WR W W
pumps
104
Installation of the acid metering pumps WR R W
105
Seawater prefilters WR R RW
Sea water pumps WR W W
Automatic backwash filters WR R RW
Electrolytic tanks WR R RW
6.1 Installation of equipment Sodium hypochlorite storage tank WR R RW
Sodium hypochlorite dosing pumps WR R W
Blowers WR R RW
Closed type cooling device WR R RW
Acid cleaning device WR R RW
FRP pipes WR R RW
Installation of the stainless steel pipe WR R RW
6.2 Installation of pipelines
Installation of the low pressure
WR R RW
carbon-steel pipe
Leak test of the system WR W H
6.3 Trial run of the system
Simulation test of the system HR H H
R- Review W- Witness H- Hold Point
13.7 Quality Inspection & test plan - Civil Works of Water Supply and Drainage systems
Inspected by
Serial
Description Items to be inspected HPC CM
No CEB/PE
C EC
106
Water-filling test for Domestic Sewage
WR H H
pipeline & cellar well
107