ALUR DOKUMENTASI PROYEK FASE PERENCANAAN / DESAIN

Umum (Arsitektur, Struktur, MEP dll)

D.E.D /
K.A.K & E.R For Con dwg
DE

B.A. Aanwijzing Schematic dwg D.D dwg


DE DE

B.A. Klarifikasi / Nego


(Konfirmasi Material)
RKS /
Specification
DE

VK-BK Construction Management Responsibility :


DE = Design & Engineering Personnel
CM = Construction Inspector Personnel
HSE = HSE Personnel

LEGEND :
ABBREVIATIONS :
Owner’s Basic Design deliverables KAK = Kerangka Acuan Kerja
ER = Employer’s Requirements
Contractor’s Design Section deliverables BA = Berita Acara
DD = Design Development
ALUR DOKUMENTASI PROYEK FASE PELAKSANAAN / KONSTRUKSI
Umum (Struktur, Finishing dll)

D.E.D /
For Con dwg
SD MS
DE DE DE
HSE
RFI MA WP
DE DE CM
HSE
MDS
RKS / RFIT CM
Specification DE
DE RFIT
RFIT
TR CM
CM DE
DE
TR
CM
DE
VK-BK Construction Management Responsibility :
DE = Design & Engineering Personnel
ABBREVIATIONS :
CM = Construction Inspector Personnel
MA = Material Approval
HSE = HSE Personnel SD = Shopdrawing
MS = Method Statement
MDS = Material Delivered to Site
LEGEND : WP = Work Permit
RFI = Request For Information
Contractor’s Design Section deliverables RFIT = Request For Inspection & Test
TR = Test Report
Contractor’s Construction Section deliverables
ALUR DOKUMENTASI PROYEK FASE PELAKSANAAN / KONSTRUKSI
Instalasi Peralatan Utama MEP

D.E.D /
For Con dwg
SD MS
DE DE DE
HSE
RFI MA WP
DE DE CM
HSE
MDS
RKS / RFFT CM
Specification DE
DE RFST
TR CM
DE
DE

VK-BK Construction Management Responsibility :


DE = Design & Engineering Personnel
ABBREVIATIONS :
CM = Construction Inspector Personnel
MA = Material Approval
HSE = HSE Personnel SD = Shopdrawing
MS = Method Statement
MDS = Material Delivered to Site
LEGEND : WP = Work Permit
RFI = Request For Information
Contractor’s Design Section deliverables RFFT = Request For Factory Acceptance Test
RFST = Request For Site Acceptance Test
Contractor’s Construction Section deliverables TR = Test Report