Construction Daily Site Report Assis. Dir. PD Contractor Assistant Dir.. Contractor RE
Stage Inspection Record Assis. Dir. PD Contractor PD Contractor The Engineer
Monthly Progress
PD Chief Eng. PD Chief. Eng. Contractor The Engineer
Report
Interim Payment Certificate - - PD Chief. Eng. The Engineer PMU
Variation Order PD Chief. Eng. The Engineer PMU
Report of Test on
Completion (Final PD Chief Eng. Contractor PD Contractor The Engineer
Inspection)
Taking Over
Taking Over Certificate - PD - The Engineer (PMU)
Completion Report and
PD Chief Eng. Contractor PD Contractor (PMU)
As-built Drawing
Defect Final Inspection - - Contactor PD Contractor The Engineer
Liability Performance Certificate
Period - - Chief Eng.- - The Engineer (PMU)
(Letter of Acceptance)
CHAPTER 2 OUTLINE OF THE GUIDELINE
2.1 Construction Management System
Efficient Construction Management System need to be developed to ensure the quality and safety in
road and bridge construction work. The practical construction management system is introduced by
this Guideline which is operational under the current organization. However, it shall be modified and
amended in accordance with organization reforms as needed. In addition, construction project under
international organization, it is recommended to establish the Project Management Unit to manage
the
project in corroboration with the Consultant selected by proper procurement
process.
Work by MOC
Cost Management Cost Control
Environmental Management