Added Tasks

Task Duration (Days) Reason


Negotiations with sponsors and 3 Funding from external stakeholders
investors is needed to conduct the project.
Finalise and approve budget 1 This is done to ensure that the
budget is sufficient for the prosed
scope of work.
Risk identification 3 Risk evaluated to determine their
impact on the project’s success.
Risk prevention plan 1 An effective means of dealing with
the risk is required if they do occur.
Follow up with Executive Team 1 This ensures objectives are being
monitored during the project’s
progression.
Contract agreement with 0 Milestone
Contractors
Approval of Plan 1 The plan should be agreed upon by
relevant management members
before the project can proceed.
Annual mechanical maintenance 10 A regulatory requirement to inspect
and maintain the mechanical
integrity of the equipment.
Evaluate design and 4 Ensures that all designs are approved
constructability and inspected before construction
can occur.
Approve work flow drawings and 2 Regulatory requirement.
documentation
Pre-construction Phase 4 Task performed to gather the
material (and equipment) to
commence construction.
Get quote for purchases 1 Accounting purposes and to ensure
the prices will be within the budget.
Purchase material and equipment 1 Construction can commence.
Notice to proceed 2 To alert the construction team that
all measures are in place for the
commencement of building.
Project Close out 6 Preparation of project end.

Project presentation 1 Discussing whether the project


objectives were met or not to
management.
Final report and sign-off 1 Final record of project for book-
keeping purposes.
Auditing and objectives review 3 Verifying the project objectives and
audit as per required by law.
Building occupation certificates 1 Regulatory requirement.
and environmental permission
Office site functional 0 Milestone