Procedures
Compiled by Rod Berry
1. On hearing the first stage warning (intermittent air horns, sirens, bells
and orange flashing light) the following personnel will proceed as
follows:
Don 30 min SCBA, pick up monitor and proceed to rig floor, and await
results of H2S monitoring. Drilling Supt to carry a radio, switched
on to locked channel # 9
3. On Duty Toolpusher:
4. On Duty Driller
On drill floor don 10 min SABA. Raise pipe off bottom to the flow
check position.( If required)
Not on drill floor, proceed to his roof deck muster station, don 30 min
SCBA and await instruction to return to drill floor.
1
5. On duty Asst. Driller
On drill floor, don 30 min SCBA, and standby for instruction from
Driller or Toolpusher.
Not on drill floor, proceed to his assigned muster station, don 30min
SCBA and await instruction to return to drill floor.
6. On Duty Derrickman
7. On Duty Floormen
On drill floor , don 10 min SABA and standby on rig floor to assist
Driller.
Not on drill floor, proceed to their assigned muster station, don
30min SCBA and await instruction to return to drill floor.
8. Rescue Team
On duty Crane driver, and 5-roustabout crew standby by at their roof
deck under the direction of the Barge Engineer.
1. All off duty crews and non-essential personnel will proceed to their
assigned muster stations, don their 30minute SCBAs, plug into the air
loop system and standby.
2. If persons fail to show up at muster point then Barge Engineer will
appoint two men from the rescue team to proceed together to search
all areas for missing personnel with first starting their search in the
area in which the H2S alarm first detected H2S. The Barge Engineer will
also keep a constant check on the H2S concentration in the assembly
area, using a portable H2S Gas Detector.
3. If gas cannot be detected in the area where the sensor (or sensors)
have been activated or the alarm proves to be only minor gas shows in
circulation, with otherwise normal well conditions, the Drilling
Supervisor (in consultation with the rig Drilling Supt.) will remain in
2
charge until H2S concentration is within acceptable operating limits
(below 10 ppm), after which he declares the alert over.
3
B. Stage two alarm - Above 20ppm.
Don 30 min SCBA, Mask up, proceed to rig floor with their H2S
monitor, and await results of H2S monitoring. Drilling Supt to carry a
radio, switched on to locked channel # 9
3. On Duty Toolpusher:
4. On Duty Driller
If on drill floor, Mask up and wait for further instructions from Drilling
Supervisor or Rig Drilling Supt.
Not on drill floor, proceeds to assigned muster station, don 30min
SCBA and await instruction to return to drill floor.
4
If on drill floor, Mask up and standby for further instructions from Rig
Drilling Supt.
Not on drill floor, proceed to assigned muster station, don 30min
SCBA and await instruction to return to drill floor.
6. On Duty Derrickman
If on drill floor, Mask up and standby for further instructions from Rig
Drilling Supt.
If in derrick, mask up connect to air line and await instruction. If
instructed to leave derrick, disconnect airline, open escape cylinder,
climb down ladder to drill floor and proceed to assigned muster point.
7. On Duty Floormen
If on drill floor, Mask up and standby for further instructions from Rig
Drilling Supt.
Not on drill floor, proceed to their assigned muster station, don
30min SCBA and await instruction to return to drill floor.
2. All other personnel mustered at their assigned roof deck muster area
are under the direct supervision of the Barge Engineer and Muster
checkers. The Barge Engineer will monitor for H2S gas on the roof deck
muster area. If the concentration of H2S exceeds 20ppm he will instruct
all personnel to mask up.
5
4. If in the judgment of the Drilling Supervisor in consultation with the Rig
Drilling Supt., he considers the H2S concentration and general well
conditions warrant further precautions, he will have the rig abandoned.
6
C. On receiving the abandon rig signal
2. Drilling Supt.
Secure well, muster together for head count, then proceed to the
designated lifeboat station, board lifeboat and launch it. Make way to
standby work vessel up wind from rig.