COST CENTERCOST

PRODUCT ACCOUNTING
CONTROLLING
END USER TRAINING DOCUMENTS

KKS1 -

Functionality

This transaction code is used to calculate variance on production order collectively.


The system compares the control costs (actual costs) with the target costs and assigns the
variances to variance categories. The variances are assigned to variance categories in the
following sequence:
 Input price variance
 Resource-usage variance
 Input quantity variance
 Remaining input variance
 Mixed-price variance
 Output price variance
 Lot size variance
 Remaining variance

Variances are 0 if only partial Goods Receipts has been performed.


Variances are posted if only complete Goods Receipts has been performed.

Scenario

We want to calculate variances on all the production order in all the plant.

Requirements

WIP has been calculated at the previous step.

Menu Path Accounting  Controlling  Product Cost Controlling 


Cost Object Controlling  Product Cost by Order 
Period-End Closing  Single Functions  Variances 
KKS1 - Collective Processing
Transaction Code KKS1

1. Double click on KKS1 - Collective Processing.

SAPTOPJOBS Page 1 of 7
COST CENTERCOST
PRODUCT ACCOUNTING
CONTROLLING
END USER TRAINING DOCUMENTS

Variance Calculation: Initial Screen

2. Update the following fields:

Field Name Field Description Values


Plant Code identifying the operational 1001
unit of the company where the
material is manufactured and
stored.
Period Number identifying a fiscal 11
month.
Fiscal year Fiscal year for which you 2002
calculate variance.

3. Click the Detail list checkbox to select

4. Click the Execute button.

SAPTOPJOBS Page 2 of 7
COST CENTERCOST
PRODUCT ACCOUNTING
CONTROLLING
END USER TRAINING DOCUMENTS

Variance Calculation: List

5. Double click on the Variance .

SAPTOPJOBS Page 3 of 7
COST CENTERCOST
PRODUCT ACCOUNTING
CONTROLLING
END USER TRAINING DOCUMENTS
Variance Calculation: List

6. Click the Cost Elements button.

SAPTOPJOBS Page 4 of 7
COST CENTERCOST
PRODUCT ACCOUNTING
CONTROLLING
END USER TRAINING DOCUMENTS
Variance Calculation: List

7. Click the Basic List button.

SAPTOPJOBS Page 5 of 7
COST CENTERCOST
PRODUCT ACCOUNTING
CONTROLLING
END USER TRAINING DOCUMENTS
Variance Calculation: Basic List

8. Click the Back button.

SAPTOPJOBS Page 6 of 7
COST CENTERCOST
PRODUCT ACCOUNTING
CONTROLLING
END USER TRAINING DOCUMENTS

Variance Calculation: List

9. Click the Back button.

10. If you are satisfied with the results, repeat the same process in Production mode by
deselecting the Test run checkbox.