steps to success
welder will be able to weld
across that! gap!
This is a Required
ASME Code Verification
1
Employee Training
Good fit up of the joint is crucial for high quality welding. Poor fit up can make it
difficult for the welder to fuse both sides of the weld root. An unfused root can be a
stress riser for fatigue cracking and/or a site for deposit formation and corrosion.
Large diameter vessel shells, pipe and fittings are often out of round and require
adjustment during fit-up. Joint alignment can be done with mechanical devices and
should be free of depressions, hammer marks, and arc strikes. Heat is not used in
the alignment of joints where it has been determined that the corrosion resistance
of the alloy is reduced.
Misalignment tolerances are specified as a percentage of the wall thicknesses
involved, and determined by the service requirements.
2
Employee Training
Backing
Definitions
A material or device placed against the back-side of the joint to support and retain molten weld metal.
Base metal The metal to be welded.
Bevel angle The angle on one side or surface of the member.
Groove angle The total included angle of the groove that makes up the weld joint.
Crack A fracture in the weld or base metal.
Complete When the weld metal or tack weld metal extends through to the bottom of the weld joint.
penetration
Filler metal The metal or alloy to be added in making a welded joint.
Lack of fusion A non-standard term indicating a weld defect in which fusion did not occur between weld metal and fusion
faces or adjoining weld beads.
Overlap: The protrusion of unfused weld metal beyond the weld toe or weld root.
Root face The portion of the groove face within the weld joint on the underside of the weld.
Root gap A separation or gap at the joint root between the work pieces.
Subweldement An incomplete vessel, or part, that is joined by welding
t The thickness of the thinner material or part being joined.
Tack weld A weld made to hold the parts of a weldment in proper alignment until the final welds are made.
3
Employee Training
★ Dimensional Check
★ Orientation Check
5
Employee Training
6
Employee Training
7
Employee Training
9
Employee Training
Documentation Completion
● Head Fit-Up Documentation
★ Liquid Container Head Log
★ Documentation on Head subweldment
● Girth Fit-Up Documentation
★ Container Assembly Verification
★ Special Container Assembly
★ Documentation on Vessel Shell subweldment
● Drain and Vent Nozzle Fit-Up Documentation
★ Documentation on Vessel Shell subweldment
● Piping Fit-Up Documentation
★ B 31.3 Piping Verification Record For Tanks
★ Piping Verification Sheet
10