Petroleum Development Oman L.L.C.

Plant Lifecycle Information Plan


(Handover and As-Built Documentation)

Document ID SP-1131

Document Type Specification

Security Unrestricted

Discipline Project Engineering

Owner Julian Masters UEP

Issue Date August 2015

Revision 5.0

This document is the property of Petroleum Development Oman, LLC. Neither the whole nor any part of this document
may be disclosed to others or reproduced, stored in a retrieval system, or transmitted in any form by any means
(electronic, mechanical, reprographic recording or otherwise) without prior written consent of the owner.
Revision: 5.0
Petroleum Development Oman LLC
Effective: Aug-15

I Authorized For Issue – August 2015

Page 2 of 21 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 5.0
Petroleum Development Oman LLC
Effective: Aug-15

II Revision History
The following are brief revision summary of this document. Details of all revisions prior to
these are held on file by the issuing department.

Revision Date Originator Checker Reviewers Scope /


No. Remarks
Revision 5.0 Aug-15 Kingsley Chime Spence, Jaqueline Julian Masters Updated to:
UEOI41 UEOI51 UEP (Project incorporate rev 4
Maulana, Andre CTP34 Delivery) feedback;
Chukwuma, Chinonso Harthy, manage PCAP
UEOI12 Mohammed overlap;
Morowei, Ebikpogba UEOI2; Bulushi, harmonize doc.
UEOI23 Yousuf UEOI1; classes; Critical
Shahaibi, Farid UEOI22 Lawati, Sadiq Documentation
Khusaibi, Abdullah UEOI4; Kharousi, and field
UEOI21 Fadya UEOI5; hardcopy
Singh, Vinay UEOI431 Elharras, requirements
Parthasarathy, Mohamed CTPI;
Veeraraghavan UEOI14 Mullappally,
Vezhaparamban, Rappai Joseph UEQ11;
UEOI411 Harding, David
Mistry, Daxesh UEOI13 UOP4
Paramasivan, Suresh
Kumar UEOI15
Patel, Amitkumar
UEOI46; Bhayani,
Kaushikkumar UEOI43;
Lawatia, Ali UEOI11

Revision Date Originator Checker Reviewers Scope /


No. Remarks
Revision Oct-13 Kingsley Chime Yousuf Bulushi Julian Masters UEP Revised
4.0 UEOI/12A UEOI/1 (Project Delivery) deliverables
Mohamed Elharras requirement to
Sultan Owaisi
CTPS3 introduce PLIP
(Pipelines CFDH)
Zykov, Aleksandr concept
CTPS34 Mohammed Aghbari
Raule, Ramoncito (Electrical CFDH)
Gary Briston
CTPS32
(QA/QC CFDH)
Thane Dewalker, Salim Hinai (C&A)
Umashankar CTPS33; Nasser Behlany
Panayotova, Veronika (MCI CFDH)
UEOI12X
Anthony Sipkema
(Tech Safety CFDH)

Page 3 of 21 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 5.0
Petroleum Development Oman LLC
Effective: Aug-15

Hilal Aghbari (Civil


Lead CFDH)
Harrasy Saaid
(Mechanical CFDH)
Tor Bjerkestrand
(UOM CFDH)
Ali Harrasi (UOP
CFDH)
Version May-06 UEV11 Revised and
3.0 reformatted
Version Aug-99 Ohi Aikhoje Revised
2.0 OTE/4
Version July - ETH/11 Initial issue
1.0 88

Page 4 of 21 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 5.0
Petroleum Development Oman LLC
Effective: Aug-15

TABLE OF CONTENT
I Authorized For Issue – August 2015 .................................................................................. 2
II Revision History ................................................................................................................... 3
1 INTRODUCTION ........................................................................................................................... 6
1.1 Purpose ................................................................................................................................... 6
1.2 Changes to this Specification ......................................................................................... 6
1.3 Step-out Approval ............................................................................................................... 6
1.4 Scope ....................................................................................................................................... 6
2 PROCESS DESCRIPTION ........................................................................................................ 7
2.1 General Description ........................................................................................................... 7
2.2 Information Deliverables Management ....................................................................... 7
2.3 Definitions .............................................................................................................................. 8
2.4 Abbreviations ........................................................................................................................ 8
2.5 Related CMF Business Control Documents ............................................................. 9
3 PROJECT HANDOVER DELIVERABLES REQUIREMENT ......................................10
3.1 General Requirements ....................................................................................................10
3.2 Master Information Deliverables .................................................................................10
3.3 Critical Documents & Data ............................................................................................10
3.4 Manufacturers (Vendor) Record Book (MRB) ........................................................10
3.5 Plant Operating Manual ..................................................................................................11
3.6 Commissioning Work Packs .........................................................................................11
3.7 Project Change Control ..................................................................................................12
3.8 Document Classification .................................................................................................12
3.9 Storage of Information.....................................................................................................12
3.10 Master Information Retrieval and Control ................................................................12
3.11 Pre-Start-up Audit (PSUA) Documentation .............................................................12
3.12 As-Building and TA Approval........................................................................................12
3.13 Quality Assurance .............................................................................................................13
3.14 IM Kick-off Form ................................................................................................................13
4 ROLES AND RESPONSIBILITIES .......................................................................................14
4.1 Project Engineer/Manager .............................................................................................14
4.2 Project Discipline Engineer ...........................................................................................14
4.3 Design Integrity (Project) IM Lead ..............................................................................14
4.4 Contractor ............................................................................................................................14
4.5 PLIP Template Description of Fields and Review Guidelines .........................16
4.6 Names of Discipline Engineer ......................................................................................18
Appendix 1: Plant Lifecycle Information Plan (Template) ............................................21
Appendix 2 MRB Content Structure .....................................................................................21
Appendix 3 IM Kick-off Form ...................................................................................................21
Appendix 4 User Feedback Form ..........................................................................................21

Page 5 of 21 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 5.0
Petroleum Development Oman LLC
Effective: Aug-15

1 INTRODUCTION
Project records, documents, drawings and business process data are critical to safe Operations and
Maintenance of PDO’s Assets. This document brings the deliverable requirements and Lifecycle
Information Management into one place. It is applicable for all PDO assets and projects no matter
which contracting strategy is pursued.
The Plant Lifecycle Information Plan (PLIP) is a Discipline Control and Assurance Framework
(DCAF) Control deliverable (control number 253). It describes ‘What’ information shall be developed
from the beginning of a project. It contains generic listing of Information deliverables requirements
(drawing, data, records and documents) to be developed during project, and what is to be handed
over to support Operations, ensuring complete delivery of all Critical Documentation that are
essential for Asset lifecycle Operations.
1.1 Purpose
Every new or modified Asset will either produce new information deliverables or modify existing
ones. The purpose of this specification is to specify information requirements (records, drawings,
business process data and documents), that may be developed or modified and delivered at the end
of a project.
It will be used to set project deliverable expectation in SELECT (Basis for Design), DEFINE (FEED),
EXECUTE (Detailed Design and Execute) and OPERATE (modifications) phases.
The PCAP (DCAF) deliverables requirement is mapped in the PLIP so that it serves as the primary
source of information deliverables that shall be scaled by the project delivery team to produce a
project specific PLIP.
1.2 Changes to this Specification
The Owner of this document is the CFDH, Engineering Project Delivery and the custodian is the
manager Engineering and Operations Information Management (UEOI). Users of this Document who
identify inaccuracy or ambiguity should utilize the “User Feedback Page” provided in the Appendix 4
to notify the Custodian or his/her delegate, and request changes be initiated.
1.3 Step-out Approval
Should compliance be considered inappropriate, then step out approval must be obtained from the
Document Custodian in accordance with approved Change Control system prior to any changes or
activities associated with the specification being carried out.
1.4 Scope
The Information set contained in appendix 1 is a generic list of Information requirements from which
a project specific PLIP shall be developed. The PLIP template readily filters into: project review
requirement, final handover deliverables, and Critical Documentation requirement (required for
Operating Integrity).
All Operations activities that change the plant shall also modify corresponding Information to reflect
the change. The "default values" in the template came originally from 3 sources:
 Reference tables in DEP 82.00.10.30-Gen Engineering Information Specifications,
 Data from previous projects
 Existing discipline documents
These have been validated by the respective discipline CFDHs.

Page 6 of 21 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 5.0
Petroleum Development Oman LLC
Effective: Aug-15

2 PROCESS DESCRIPTION
2.1 General Description
I. Projects shall follow this sequence of activities to produce project specific PLIP:
1. Select information deliverable that will be generated or modified by the project, as part of
project initiation and kick-off, utilizing appendix1 of this document.
2. For modification work, confirm dependency of each data type selected on other data sets:
e.g. change in PEFS might affect POM, HAZOP, Operation HSSE Case, SAP, Variable
Table, etc.
3. For those deliverables that require PDO review or approval, confirm which PDO focal point
will provide the review/approval
4. Populate “REQUIRE_PDO_REVIEW/APPROVAL” with focal point information received to
produce project specific PLIP, and obtain TA approval in line with DCAF.
5. Utilize project specific PLIP and produce project master deliverables register (MDR) with
tentative information deliverable milestone dates (Issued for Review, Approved for Design,
Approved for Construction and As-Built).
6. Develop/modify deliverables in line with PR-1666 - Engineering and Operations Document,
Drawing and Data Control Procedure, and on completion of project, handover IM deliverables
electronically to the project IM Lead.
II. IM deliverables handover assurance review shall be undertaken by Operating Integrity IM team,
to confirm readiness to deliver specified information deliverables.
III. Project IM Lead or delegate shall check attributes of information being delivered, and confirm
completeness before handover to Asset Information Center (AIC). He will notify the contractor to
proceed and deliver hardcopy of Tier 1 Critical Documentation to the field as identified in PLIP.
IV. AIC IM Lead or delegate will receive IM deliverables (documents and drawings), publish and
notify all stakeholders, and sign the Project Completion Certificate (PCC).
V. Business process data shall be delivered to application system owners for publishing as required
by SP-2142: Engineering Project Data Specification.
VI. Refer to PR-1150: Project Close-out Procedure for the project activities required for the formal
transfer of ownership of a constructed and commissioned facility from the project delivery team to
the Asset owner.
2.2 Information Deliverables Management
Follow PR-1666: Engineering and Operations Document, Drawing and Data Control procedure
during Information development, modification or field hardcopy management.
When a project modifies existing asset documentation like PEFS, etc, the impact on the following
information deliverables: HAZOP Report, Operation HSSE Case, Safeguarding Memorandum, MRB,
POM, Variable Table, etc, shall be evaluated and confirmed on the IM Kick-off form. The master
revision of these deliverables shall be retrieved and updated as part of the project delivery activities,
rather than creating addendum.

Page 7 of 21 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 5.0
Petroleum Development Oman LLC
Effective: Aug-15

2.3 Definitions

Deliverable(s) Product(s) of an activity (ies) or undertaking(s). The product can be a


document, data, drawing, record or just an activity.
DCAF Discipline Control and Assurance Framework: specifies the TA level
required to review and approve discipline control deliverables.
Electronic Electronic file created by scanning or direct rendition through software.
Image
Document Manuals, drawing, reports, datasheet, etc
Information Documents, 3D Model, Engineering Data and Business process data
deliverables (E-SPIR; SAP-PM, CIMS, EDW, etc)
IM Kickoff Form Template populated to request existing data to be issued for a project
work. It contains concurrent modification and dependency declaration
by the PE.
Livelink PDO corporate EDMS.
Compound Multiple files (maybe containing independent files), which are delivered
Document as a single document, e.g. MRBs
Contractor A party to a Contract with PDO.

2.4 Abbreviations

AFC Approved for Construction


AFD Approved for Design
AIC Asset Information Center
AI-PSM Asset Integrity – Process Safety Management
CCMS Certification and Completion Management System
CMMS Computerized Maintenance Management System
EDS Engineering Design System
EDMS Electronic Document Management System
EIS Engineering Information Specification
EOIM Engineering and Operations Information Management
FCP Facility Change Proposal
IFR Issued for Review
IM Information Management
IOM Installation, Operation and Maintenance Manual
ITT Invitation To Tender
MRB Manufacturers Record Book
PCAP Project Control and Assurance Plan
PCC Project Close-out Certificate
PE Project Engineer
PLIP Plant Lifecycle Information Plan
SoF Statement of Fitness
PIN Project Initiation Note
POM Plant Operating Manual

Page 8 of 21 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 5.0
Petroleum Development Oman LLC
Effective: Aug-15

PDMS Plant Design Management System


PSUA Pre-Start-up Audit
RLMU Redline Mark-up Drawings
TA Technical Authority
VDRL Vendor Document Requirements Listing: listing showing specific
Document requirement relating to the equipment being supplied or
manufactured.
WP Work Package; a group of activities that are considered as one unit from
the planning perspective.

2.5 Related CMF Business Control Documents


The related CMF Documents can be retrieved from the CMF Business Control Portal.
1 CP-102: Data and Document Management Code of Practice
2 CP-115: Operation of Surface Product Flow Assets
3 CP-117: Project Engineering Code of Practice
4 SP-1074: Preparation of Plant Operation Manuals
5 SP-1122: Specification for Project Quality Plan
6 SP-1131: Handover & As-Built Documentation (Plant Lifecycle Information Plan)
7 SP-1134: General Specification for Detailed Engineering of Oil & Gas Facilities
8 SP-2065: Document Management In Engineering Projects and Operations
9 SP-2113: Specification for Commissioning and Start-Up
10 SP-2142: Engineering Project Data Specification
11 SP-2144: Engineering Project IM SoW
12 PR-1052: Preparation and Updating of Station Plant Operating Manuals
13 PR-1150: Project Close-out Procedure
14 PR-1159: Commissioning Procedure
15 PR-1169: Initial Start-Up Procedure
16 PR-1247: Project Management of Change Procedure
17 PR-1666: E & O Document, Drawing and Data Management Procedure
18 PR-1692: PDO Document Retention Procedure
19 PR-2066: Deviation from Standard and Procedure
20 PR-2117: Engineering Project Data Control Procedure
21 PR-2160: Pre Start-up Audit Procedure
22 DEP 82.00.10.30-GEN (Engineering Information Specification) February 2012

Page 9 of 21 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 5.0
Petroleum Development Oman LLC
Effective: Aug-15

3 PROJECT HANDOVER DELIVERABLES REQUIREMENT


3.1 General Requirements
When a project is completed, it is the responsibility of the Project delivery team to ensure delivery of
both completed Physical Asset as well as the Information Asset to Operations in line with PR-1150:
Project Close-Out Procedure.
Master Information shall be delivered to PDO as specified in the project specific PLIP:
 The Contractor shall deliver to PDO, complete final handover package electronically as
specified
 Contractor shall receive notification from project IM Lead to produce Tier 1 Critical
Documentation hardcopy and deliver the documentation to the field
 The Master Hardcopy delivered to the field shall be received by the OI Coordinator
(OXO16x) who will sign the transmittal, stamp/sign the deliverables received and deliver
them to the station
 Information retention shall be in line with CP-102: Corporate Document Management –
CoP and PR-1692: PDO Document Retention Procedure
3.2 Master Information Deliverables
Master information comprises of: As-Built drawings like PEFS, Certified Final Document like POM,
3D model files and Business Process data for systems (SAP-PM, CCMS, CIMS, EDW, etc). They
shall be delivered to data system custodian in line with SP-2142 and SP-1131.
These information deliverables are developed or modified during projects or operations as a result of
new Asset development or modification of existing Assets (no matter how small the modification
work may be).
3.3 Critical Documents & Data
Tier 1 and 2 Critical Documentation: As-Built drawing, Certified Final document, and Data (business
process data like SAP-PM, etc), are as defined in CP-115 - Operation of Surface Product Flow
Assets - CoP, as the minimum Information deliverable that shall be delivered to Operations at the
end of an Engineering project.
Only Tier 1 Critical Documentation shall be produced in hardcopy format, and delivered to the station
to support Asset operation, refer to PR-1666 for detailed lifecycle management procedure.
3.4 Manufacturers (Vendor) Record Book (MRB)
The MRB is compound document containing distinct document types and identification number. As
shown in the table below, the electronic version of these document types shall be delivered as
individual files to the parent MRB, while general assembly and presentation of electronic and
hardcopy shall follow the structure shown in appendix 2.

Page 10 of 21 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 5.0
Petroleum Development Oman LLC
Effective: Aug-15

The procurer (PDO or Contractor) shall customize the VDRL template in SP-2065 - Document
Management in Engineering Projects - Appendix 3 for relevant documentation required to support
operations and maintenance of the equipment. The MRB shall be supplied in electronic format with
only one clean copy produced in hardcopy and delivered to the field.
3.5 Plant Operating Manual
The Plant Operating Manual (POM) contains or refers to document types like PEFS (a distinct
document with identification number). These document types shall not be added or inserted (as
picture or object) directly on the POM but shall be referenced, indexed and hyperlinked from POM to
the original location of the master drawing. This will maintain single master location of information,
and allow modification to take place independently on the referenced information.
For each project, an assessment of the impact on the existing POM shall be undertaken, and
updates (when required), shall be made directly to the master POM held by AIC, rather than creating
an addendum file, refer to section 2.2. The Contractor shall update the POM in accordance with the
following Specifications and Procedures:
 SP-1074: Preparation of Plant Operation Manuals Specification
 PR-1052: Preparation and Updating of Station Plant Operating Manuals.
 PR-1666: Engineering and Operations Document, Drawing and Data Control Procedure.
3.6 Commissioning Work Packs
On completion of the construction, pre-commissioning / commissioning and handover of the project,
all Construction, Fabrication and Commissioning deliverables (CCMS punch lists, check sheets, test
sheets, quality dossier, handover certificates, etc), associated with works on the facilities shall be
assembled, delivered, retained and archived electronically in AIC in the appropriate work parks. The
work packs shall be signed off by all parties as detailed on the individual sheets and certificates. For
more details refer to:
 SP-2113: Specification for Commissioning and Start-Up (Key Principles)

Page 11 of 21 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 5.0
Petroleum Development Oman LLC
Effective: Aug-15

 GU-623: Project Completion Management System CMS Guideline


3.7 Project Change Control
Notification and approval documents relating to: changes / variances in Basis for Design, Front End
Design Deliverables, Project Specification, Budget Proposals / RFAs, Detailed Design (AFC
drawings and documentation) and selected Standards shall be held in the project workspace and
form part of the handover to AIC.
Reference should be made to PR-1247: Project Management of Change Procedure and PR-1153:
Field Trouble Reporting Procedure for more information.
3.8 Document Classification
This standard defines document types and assigns numeric codes (refer appendix 1) to each type, to
aid their reference and retrieval from IM system.
3.9 Storage of Information
Electronic version of Information delivered at the end of a project shall be stored and maintained in
AIC while hardcopies of Tier 1 Critical Documentation and MRBs shall be delivered to the respective
field. Project hardcopy information required shall be delivered to AIC (central archive). Similarly, the
EDMS workspace shall be handed over to Design Integrity IM Team in UEOI; refer to PR-1666.

3.10 Master Information Retrieval and Control


Master Information required for Operating, Maintenance and Design Integrity is controlled
electronically, and becomes uncontrolled when printed unless stamped with “Controlled Hardcopy”
and wet signed, or printed with watermark, etc.
During a project, construction deliverables in hardcopy shall be printed from the project IM system
and signed by the IM focal point of the party that made the print to confirm the source of printing. Any
other printed hardcopy or electronic version residing elsewhere is uncontrolled.
Information required for reference or to support activities (PIN, Integrity and FCP of existing asset)
shall be retrieved from AIC master IM system.

3.11 Pre-Start-up Audit (PSUA) Documentation


Documents identified in the project PLIP as “REQUIRED_FOR_FINAL_HANDOVER” shall be
available in their final form prior to the PSUA. This requirement recognizes that certain drawings may
still be in RLMU state; As-Built drawings may still be outstanding.
The project IM Lead shall demonstrate that an information handover assurance review has been
undertaken on a project before progressing with PSUA activities.
Refer to PR-2160: Pre Start-up Audit Procedure for general requirement and guidance for PSUA.

3.12 As-Building and TA Approval


TA review/approvals are required during detailed design and engineering leading to AFC
deliverables. Any change to the AFC package requires appropriate TA approval before being
implemented.

Page 12 of 21 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 5.0
Petroleum Development Oman LLC
Effective: Aug-15

At the end of commissioning, the RLMU drawings shall be signed by both the contractor and the
PDO commissioning engineer (or representative at site), to confirm consistency of RLMU with the
actual constructed work, refer to PR-1666.

3.13 Quality Assurance


The contractor shall have an approved checking and approval process in place (as a part of its
ISO9000 system), which is implemented and supported by regular assurance /quality checks.
This will ensure that the information deliverables are reviewed and checked internally before they are
delivered to PDO.

3.14 IM Kick-off Form


The project shall utilize the IM Kick-off Form (appendix 3):
 To request for existing information required for project execution
 To confirm the impact of project on concurrent project or FCP
 To request for allocation of Tags

Page 13 of 21 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 5.0
Petroleum Development Oman LLC
Effective: Aug-15

4 ROLES AND RESPONSIBILITIES


4.1 Project Engineer/Manager
The overall Accountability of ensuring that PLIP activity is completed at the beginning of the project
(FEED/Detail Design/Execution). He shall:
 Identify IM resource to cover the project scope.
 Confirm impact of a data type (e.g PEFS) modification on other data system like SAP & POM
 Convene an integrated session to customize PLIP for the project scope when required.
 Endorse the project specific PLIP for implementation

4.2 Project Discipline Engineer


 Utilize the generic PLIP (appendix 1) and filter into discipline deliverables scope.
 Work with project IM Lead to customize and validate existing data entries as it affect work
scope, ensuring that all PCAP deliverables are incorporated.
 Endorse the project specific PLIP (as required by DCAF).
 When required, participate in joint discipline customization of PLIP
 Review and approve discipline Information generated in project as required in PLIP

4.3 Design Integrity (Project) IM Lead


 Ensure contractor understands the information requirement in order to generate the project
PLIP.
 Provides electronic copy of the master information, including identification of any other
project using the same master.
 As part of project initiation, ensure PE confirms the impact of modification of PEFS for
example, on other data system like SAP, POM, etc
 Ensure compliance with IM procedures and specifications.
 Work with PDO partners developing or modifying information to ensure adequate internal
review and approval.
 Ensure that information specified in a project PLIP is effectively developed and delivered
ensuring that it meets this specification for handover AIC.
 Conduct contractor information handover assurance review in line with functional assurance
plan.
 At the end of project, archive the EDMS workspace of project information deliverables.

4.4 Contractor
 Propose an IM resource for project and agree resource capability with Design Integrity IM
Lead before assigning responsibility for all or part of information management activities.
 Produce a project PLIP as part of project initiation and kick-off, (see section 2.1).
 Develop the MDR and associated plan showing key information development milestone
dates (Issued for Review, Approved for Design and Approved for Construction, etc). These
milestones shall be measured and reported as agreed with the Design Integrity IM Lead as
one of the project KPIs.

Page 14 of 21 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 5.0
Petroleum Development Oman LLC
Effective: Aug-15

 Ensure adequate internal review, checking and approval of information before delivering to
PDO.
 Handover electronic information to Design Integrity IM Lead as contained in MDR.
 Receive notification from project IM Lead and produce master hardcopy of Tier 1 Critical
Documentation.

Page 15 of 21 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 5.0
Petroleum Development Oman LLC
Effective: Aug-15

4.5 PLIP Template Description of Fields and Review Guidelines

COLUMN NAME DESCRIPTION / CLARIFICATION ACTIONS REQUIRED


The party who will produce the document --- either a PDO entity
ORIGINATOR Discipline Lead to specify
or 3rd party or Contractor or Supplier.
The name of the PDO team member who is responsible for the
PROJECT FOCAL POINT Discipline Lead to specify
SOURCE document (prepares or reviews or approves).
Discipline Lead to verify what
Standard "Discipline Code - Discipline name" as defined in is selected by IM team and to
DISCIPLINE_CODE
DEP82.00.10.30-Gen Engineering Information Specifications. consult with IM team if it
should be changed.
Discipline Lead to verify the
INFORMATION REQUIRED A typical titles, type or category of documents and data to be
default value (listed by IM
(DOCUMENT & DATA) delivered at various stages through the project lifecycle.
team).

Standard "Discipline-Document Type Code + Name" and


DOCUMENT_TYPE_NAME "Descriptions" defined in DEP82.00.10.30-Gen Engineering
Discipline Lead to verify the
Information Specifications. Standard classification on document
default value (specified by IM
types facilitates document repository in EDMS (standard folder
team).
DOCUMENT_TYPE_ structure in Livelink) and to make cross reference to the Record
CODE Management requirements (e.g. retention).

INFORMATION
DESCRIPTION POSSIBLE TITLES_
Additional description of document types No action
AND_TYPE_DESCRIPTION

Discipline Lead to specify or


verify the default values.
Preferably to refer to a DEP or
Reference to DEP or other samples/examples which define
a Project Specification. As the
REFERENCES minimum requirements or level of details regarding the technical
minimum, the Discipline Lead
contents of the Document.
should be able of providing a
sample/example from previous
projects.
Notes to describe specific project requirements or clarifications Discipline Lead to add specific
PROJECT SPECIFIC NOTES
on the information (document or data) listed. special notes

Page 16 of 21 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 5.0
Petroleum Development Oman LLC
Effective: Aug-15

Document Security Classification per PDO guidelines Discipline Lead to verify the
SECURITY_CLASSIFICATION (Unrestricted, Restricted, Confidential, Most Confidential) --- default value (specified by IM
various handling procedures are required team).
Related objects of the Document to facilitate navigation from the
Discipline Lead to verify the
object to the documents. An object can be an Asset type (in
RELATED_OBJECTS default value (specified by IM
Plant Asset Hierarchy --- Site, Plant, Process_Unit, Equipment,
team).
Tag, Model_Parts) or other Document such as a Purchase Order.
Format of the Information (Document or Data) to be delivered Discipline Lead to verify the
BASIC DURING_PROJECT_FORMAT during the project for eview/approval/information (Paper, MS default value (specified by IM
DOCUMENT Word, MS Excel, MS Access, Adobe Acrobat, AutoCAD, etc.) team).
PROPERTIES Format of the Information (Document or Data) to be delivered Discipline Lead to verify the
AFTER_PROJECT_FORMAT during handover to Operation (Paper, MS Word, MS Excel, MS default value (specified by IM
Access, Adobe Acrobat, AutoCAD, etc.) team).
With respect to project scope, identify from the Critical
REQUIRE_FIELD_CONTROLLE PE verifies from Operations,
Documentation list of CP-115, which Information is required to be
D_HARDCOPY default values (Yes or No).
physically available in the field for Operations of the facility.
Categorization/value of the Information (Document or Data) for Discipline Lead to verify the
AFTER_PROJECT_CATEGORY PDO after handover from project to operation (Essential, Legal, default value (specified by IM
Desirable) --- different requirements on repository and retention team).
Discipline Lead to verify the
Based on PDO document group retention guidelines (asset life, 2
RETENTION_PERIOD default value (specified by IM
yrs, etc).
team).
Critical Information (document and data) deliverables as defined Discipline Lead to verify the
CRITICAL_ DOCUMENTATION in CP-115: Operation of Surface Product Flow Asset. This is default value (specified by IM
the minimum deliverables that is required for Operating Integrity. Team).
Discipline Lead to verify the
Document is a deliverable of PCAP (Project Control and
DCAF Control (Identification default value (specified by IM
Assurance Plan). Those "Yes" deliverables subject to PCAP
Number) team) against the latest signed
DOCUMENT requirement.
PCAP-discipline list.
DELIVERY
(SELECT) REQ_FOR_ Will the Information (documents & data) be delivered as part of Discipline Lead to verify the
REQUIRED CONCEPT SELECTION the concept selection? default values (Yes or No).
PER PROJECT
(DEFINE)REQ_FOR_PROJECT Will the Information (documents & data) be delivered as part of Discipline Lead to verify the
PHASE SPECIFICATION/FEED the project specification package (FEED)? default values (Yes or No).
(DEFINE) REQ_FOR_ Will the Information (documents & data) be delivered as part of Discipline Lead to verify the
DETAILED_ DESIGN the detailed design package? default values (Yes or No).
(EXECUTE) REQ_FOR_ PSUA Will the Information (documents & data) be required to support Discipline Lead to verify the
AND PRE- COMMISSIONING PSUA, Pre-commissioning and Commissioning/Start-up default values (Yes or No).

Page 17 of 21 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 5.0
Petroleum Development Oman LLC
Effective: Aug-15

/ COMMISIONING (Flawless start-up initiative)?


REQUIRED_FOR_FINAL_HAND Will the Information (documents & data) be required as part of the Discipline Lead to verify the
OVER handover package to PDO? default values (Yes or No).
Will the Information (documents & data) deliver as As-built (ASB) Discipline Lead to verify the
REQUIRED_HANDOVER_
or Certified FINAL (revision of information not requiring As- default values (ASB, FINAL or
STATUS (ASB or FINAL)
Building)? If value is no, then information not required. No).
This field was left blank to allow project customization in line with
project strategy. It should be populated as part of MDR
REQUIRE_PDO_REVIEW/APPR development, to capture PDO's review requirements on Discipline Lead to specify or
OVAL documents produced by others (contractor / suppliers) per the verify the default values.
Document Type: IFR=Issue For Review; IFA=Issue For
Approval; IFI=Issue For Information; No=No review required.
Resource typically a
Highlights document types in which RLMUs may be generated. At
commissioning Engineer but
the end of project, PDO focal point shall check As-Built produced
OTHERS FINAL RED-LINE CHECKING the Project Engineer to agree
against “RLMU”, to confirm that As-Built produced is a true
resource with Operations if
reflection of constructed works.
different
Who is the final owner/status of the deliverable after handover?
Typically, ownership of Critical Documentations is with the Asset Discipline Lead to specify or
FINAL OWNER/STATUS
Manager, while other deliverables are stored electronically in a verify the default values.
secured EDMS location for future reference.
COMMENT General comments from IM team or Discipline Lead

4.6 Names of Discipline Engineer


The names of respective discipline engineer assigned to support the project scope (full time or part time) are as follows:
Page 18 of 21 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 5.0
Petroleum Development Oman LLC
Effective: Aug-15

DISCIPLINE LEAD (Focal Point


Remark
DISCIPLINE in PDO Project Team)
DISCIPLINE DESCRIPTION
_CODE Define Detailed
Execute
-FEED Design
Management and Project execution plan, basis of design, organization, authorities.
AA
Project Engineering Integrated plans such as those for Pre-Commissioning.
BA Construction Construction- and fabrication-related information. Also, installation and
transportation specifications.
CB Architectural All buildings: including interior design and structure.
CG Geotechnical / Soil properties, shallow hazards, piles, suction piles, anchors, mud
Foundation mats.
CI Infrastructure Onshore: Roads, drainage, sewering, fences, etc.
CS Structures All major structures (steel and concrete) also vessels, ships, jackets,
topside modules, floating production systems.
EA Electrical Design and application of circuitry and equipment for power generation
and distribution, machine control.
FA Cost and Planning Integrated project cost, schedule, budget estimating and tracking.
HE Environmental Environment-related topics.
HH Health Human and animal health.
HP Security Prevention of espionage, sabotage, intellectual property leakage, attack
or unauthorized handling.
HS Safety Technical Safety-related topics.
HX HSE&S General To use if Health, Safety, Environment and Security document cannot be
assigned to one of the other HSE&S document types (i.e. not
Environmental, Health, Safety, Security. Also for Hazard Management).
IC IC Process control For Process Control and Optimization discipline related deliverables.
& Optimization. Distributed control systems, PLCs, process control logic
IN Instrumentation Instruments and instrument systems
JA Information Content management, Data, Document and Knowledge management,
Management Procedures, Specifications, Standards.
KA Information IT Infrastructure, hardware, software, applications
Technology

Page 19 of 21 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 5.0
Petroleum Development Oman LLC
Effective: Aug-15

LA Pipelines Line pipe, stability, hydraulics, installation, commissioning.


MP Piping Pipe, flanges, fittings, valves, pipe supports, stress analysis.
MH HVAC Heating, Ventilation and Air-conditioning.
MR Rotating Equipment Compressors, pumps turbines, etc.
MS Mechanical - Static Vessels, furnaces, boilers, tanks, etc.
MX Mechanical Other Use only when the other Mechanical disciplines cannot be used (i.e. not
HVAC, Mechanical - Static, Piping, Rotating Equipment)
NA Engineering The branch of engineering that deals with equipment reliability.
Maintenance
OA Operations Readiness for production, marine, subsea, logistics, supply base,
shutdown, etc.
PF Fluid Flow Includes all issues important to maintaining the flow of oil and gas from
Assurance reservoir to receiving facilities.
PX Process Other Use only when the other Process disciplines cannot be used (i.e. not
Fluid Flow and Assurance, Process Operational Turnaround Support,
Process Technology)
QA Quality Assurance Includes formal review of designs, problem identification, corrective
actions to remedy any deficiencies and evaluation of actions taken.
RA Materials and Materials, corrosion and coating issues across multiple disciplines.
Corrosion
TA Telecommunication Radio communication, satellite and Cable communication, etc.
ZT Production Everything related to Production Technology
Technology
ZP Petrophysics. Everything related to Petrophysics
ZR Reservoir Everything related to Reservoir Engineering
Engineering
ZV Vendor All equipment deliverables
ZW Well Engineering Everything related to oil and gas wells.

Page 20 of 21 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision: 5.0
Petroleum Development Oman LLC
Effective: Aug-15

Appendix 1: Plant Lifecycle Information Plan (Template)

Project Lifecycle
Information Plan (PLIP) Template v5.1.xlsx

Appendix 2 MRB Content Structure

Compound Document
Structure.xlsx

Appendix 3 IM Kick-off Form

IM Kick off
Form_Final Version.xls

Appendix 4 User Feedback Form

Feedback Form.docx

Page 21 of 21 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)