Professional Documents
Culture Documents
Document ID SP-2269
Security Restricted
Version 1
This document is the property of Petroleum Development Oman LLC. Neither the whole nor any part
of this document may be disclosed to others or reproduced, stored in a retrieval system, or transmitted
in any form by any means (electronic, mechanical, reprographic recording or otherwise) without prior
written consent of the owner
Version: 1
Petroleum Development Oman LLC Effective: Feb. 2018
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 2
Document authorization
Document authorization
Document authority Document custodian Document controller
( CFDH)
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 3
Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: Feb. 2018
i Revision History
The following is a brief summary of the most recent revisions to this document. Details of all
revisions prior to these are held on file by the issuing department.
Version
Date Author Checked Scope / Remarks
No.
PR-1984: 08/06/2011 UEQ/131 UEQ Originally issued for use as a Procedure
Version 1.0
PR-1984: 20/01/2013 UEQ/11 UEQ Minor correction / addition in sub-sections
Version 1.1 1.1, 1.2, 2.3, 2.4, 2.5 and Appendix C.
PR-1984: 21/12/2015 UEQ1 UEQ Revised entirely
Version 1.2
PR-1984 01/03/2018 UEQ1 UEQ Major changes:
Version 4 Section 1.2
The inclusion of pre-defined CR for
Pipeline materials (see Appendix F);
detailed the inspection requirements for
like to like replacements.
Appendixes
Appendix C.1 (PIM’s are not mandatory,
the Assessment Team will justify for CR2
items if specific QC stages attendance is
required)
Appendix C.2 (avoid duplication of
inspection - PDO/EPC Contractor)
Appendix D (Lowering of inspection
requirements for some categories,
established what entity is going to approve
the ITP when applicable)
Appendix E (Lowering of inspection
requirements for some categories,
established what entity is going to approve
the ITP when applicable, elimination of
TPI for in-process inspection)
SP-2269 28 Jan 2016 UEQ13 UEQ1 Comprehensively revised to include
Version 1 Stockist procurement QA requirements,
ITRs, Approved TPI agencies list as per
Annexure G to J and changed document
from procedure to specification with a new
document number.
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 4
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 5
Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: Feb. 2018
TABLE OF CONTENTS
i Revision History ...................................................................................................................... 4
ii Related Corporate Management Framework (CMF) Document ............................................ 5
iii Related International Standards ............................................................................................. 5
1 Introduction ............................................................................................................................. 8
1.1 Purpose ............................................................................................................................. 8
1.2 Scope ................................................................................................................................ 8
1.3 Distribution / Target audience ........................................................................................... 9
1.4 Changes to the Specification ............................................................................................ 9
1.5 Effective period .................................................................................................................. 9
1.6 Review and Improvement ................................................................................................. 9
1.7 Definitions .......................................................................................................................... 9
1.8 Abbreviations ................................................................................................................... 10
2 Criticality Rating Process ...................................................................................................... 12
2.1 General ............................................................................................................................ 12
2.2 Roles and Responsibilities .............................................................................................. 12
2.3 Criticality Rating Criteria .................................................................................................. 13
2.3.1 Operations failure of the item ........................................................................ 13
2.3.2 Design maturity/reliability .............................................................................. 14
2.3.3 Manufacturing complexity .............................................................................. 14
2.3.4 Cost implications of failure ............................................................................ 15
2.3.5 Service characteristics (toxicity, temperature, pressure) .............................. 15
2.3.6 Location ......................................................................................................... 16
2.3.7 Personnel safety ............................................................................................ 16
2.3.8 Special considerations .................................................................................. 17
2.4 Quality Intervention Levels for Prospective Vendors ...................................................... 17
2.4.1 ITP Review .................................................................................................... 18
2.4.2 Pre-Inspection Meeting ................................................................................. 18
2.4.3 Review of design calculations / drawings ...................................................... 18
2.4.4 Review of manufacturing & testing procedures ............................................ 18
2.4.5 Resident/Visiting Inspector ............................................................................ 18
2.4.6 Quality Audit(s) .............................................................................................. 18
2.4.7 Staged Inspections / Surveillance/Final Inspection ....................................... 18
2.5 Guidelines on QA/QC Interventions (for off-shelf items or during manufacturing) ......... 19
3 Appendixes ........................................................................................................................... 20
Appendix A Criticality Rating Data Sheet ......................................................................... 20
Appendix B Example typical Criticality Rating Data Sheet ............................................... 21
Appendix C Quality Intervention Levels ............................................................................ 22
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 6
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 7
Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: Feb. 2018
1 Introduction
Procurement right material / equipment /packages are one of the high risk activities of PDO
project delivery. One of the key mitigation for this risk is application of fit for purpose quality
interventions commensurate with its risk level.
The Criticality Rating (CR) process establishes the importance of an item (equipment,
material, package) with respect to design, procurement, fabrication, operation and the
consequences of its failure. The CR will be used to optimize inspection, quality and
engineering resources by increasing attention on critical items, and reducing review of non-
critical items.
From experience, PDO has pre-determined inspection / intervention requirements for many
items thereby use of CR process is limited to certain packages and other items.
1.1 Purpose
The purpose of this specification is to describe the application of quality intervention for
provision of products either following a process to determine the Criticality Rating of the
items or following pre-determined inspection requirements.
Where applicable, Quality Intervention Level shall be assigned based on the Criticality
Rating.
1.2 Scope
1.2.1 This specification applies to all procured items which are sourced for PDO’s
assets/projects (in alignment with approved PDO PGSC list).
Where a contract specifies requirement for a Criticality Rating procedure, Contractor shall
adopt this document.
1.2.2 For pipeline materials the Criticality Rating has been pre-defined (see Appendix F)
1.2.3 Criticality Rating is not applicable for the following:
a) Existing Frame Agreements where ITP/inspection requirements are part of the
agreement. (Note: For new Frame agreements this procedure shall apply).
b) Pressure vessels (for pressure vessels the criticality rating shall be performed in
accordance with DEP 31.22.00.30 Equipment Criticality in Pressure Vessel
Design)
c) C&A Equipment/materials – the requirements related to ITP
submission/inspection activities are stated in Appendix D; only when respective
item is not listed in Appendix D, SP-2269 shall apply.
d) Electrical Equipment/materials – the requirements related to ITP
submission/inspection activities are stated in Appendix E; only when respective
item is not listed in Appendix E, SP-2269 shall apply.
e) For MESC items (Ball, gate, globe and check valves, fittings, flanges, pipes) PDO
intervention points (e.g. R - Review, W - Witness, H - Hold Point) and sampling
frequency shall be stated in the Technical/Inspection Requirements prepared by
Mechanical Static/Quality disciplines; only in the absence of the
Technical/Inspection Requirements, SP-2269 shall apply). Refer to Appendix J for
Technical/ inspection requirements for MESC products.
f) Like to like replacements (maintenance related items). The item can fall in 1.2.2 or
1.2.3 a) to e) or g) categories. Where Frame Agreements are not in place for
equipment e.g. pumps, the Project/Discipline Engineer will follow specification
requirements.
g) Off-shelf items. The project team should review the Final Documentation/MTC’s
before purchasing to ensure the item is in accordance with specification’s
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 8
1.7 Definitions
Terminology Definition (for the purpose of this document)
Bulk Order A large quantity of items mostly loose materials (assorted types of
materials, rating/sizes) in various lengths and quantity (e.g. Pipes,
Fittings, Flanges, Valves)
Company Petroleum Development Oman L.L.C.
Contractor The party which carries out all or part of the design, engineering,
procurement, construction, commissioning or management of a
project, operation or maintenance of a facility.
Criticality Rating A rating applied against consequence of failure; an indication of the
level of importance to be attached to items, commensurate with the
effect that failure may have on a sub-system/system, or in
compromising safety of personnel, the environment or Company
economics. Based upon this indication, the appropriate quality
intervention level will be established.
Item Equipment, material, package
Manufacturer The party, which fabricates and manufactures items and provide
services to perform duties specified by PDO and/or Contractor.
Principal In this context is the foreign service provider which the local agent
represents, the manufacturer of the product which the local agent
represents, or the foreign stockist of the product which the local agent
represents, and, normally, not a regional office or a distributor
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 9
Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: Feb. 2018
1.8 Abbreviations
Abbreviation Description (for the purpose of this document)
CFDH Corporate Functional Discipline Head
CMF Corporate Management Framework
CP Code of Practice
CR Criticality Rating
CRA Corrosion Resistant Alloy
CS Carbon Steel
DE Discipline Engineer
DEP Design Engineering Practice
EMC Engineering Maintenance Contract
EP Engineering & Procurement
EPC Engineering, Procurement and Construction
EPCC Engineering, Procurement and Construction Contract
FAT Factory Acceptance Test
GU Guidelines
HSE Health, Safety and Environment
ICV In Country Value
IMC Integrated Management Contract
IRN Inspection Release Note
ISO International Organisation for Standardization
ITP Inspection and Test Plan
LTCS Low Temperature Carbon Steel
MESC Material and Equipment Standards and Codes
NCR Non Conformance Report
ODC Off-plot Delivery Contract
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 10
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 11
Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: Feb. 2018
2.1 General
The Criticality Rating of items is evaluated during two different phases:
Initial CR assessment shall be performed during Define phase; only when not possible
during Define phase and for any new item identified later the CR assessment shall be
performed during Execute phase.
Revision of previously assigned Criticality Rating may be performed prior to the award
of the Purchase Order based on Lessons Learnt, reduced confidence level of selected
Vendors (the reason for changing the CR shall be stated in Appendix A Criticality
Rating Data Sheet, Remarks column).
Criticality Rating of items shall be defined during CR discipline workshops facilitated by
PDO and/or Contractor Discipline Engineer from the originating discipline. The
Assessment Team shall consist of the following:
Discipline Engineers (from the originating discipline)
Project Engineer
Quality Engineer
Discipline Engineers from other disciplines (if required)
Technical Safety Engineer (if required)
Welding Engineer (if required)
NDT Engineer (if required),
Maintenance and Integrity Engineer (if required), etc
Notes:
1. PDO (Project team, FEED Office)/EMC/EPCC/IMC/ODC Discipline Engineers shall
be TA2/TA3 in their discipline.
The Criticality Rating Data Sheet (see Appendix A) details the criteria to be considered by
the Assessment Team when determining Criticality Rating.
Each criticality element is subdivided into four levels of severity, with appropriate rating
allocation ranges from 1 to 4. All elements will be completed by the Assessment Team as
identified in section 2.2 below.
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 12
Note: The Criticality Rating will be developed with facility efficiency, reliability and safety
aspects in mind at all stages of work.
The Criticality Rating for items will be derived by determining and assessing the critical
activities (see Appendix A) against the total score as follows:
Total Score
from
Criticality
Appendix A Description Nomenclature
Rating
of this
document
The Quality and Performance reliability of
Extremely
25 - 32 manufacturing is vital and must not be 1
critical
compromised.
The Quality and Performance reliability of
17 - 24 2 Very critical
manufacturing is of significant importance.
The Quality and performance reliability of
11 - 16 3 Critical
manufacturing is of moderate importance.
The Vendor’s Quality Assurance of the items is
Below 11 4 Non-critical
acceptable.
Note:
1. The CR will be included in the Purchase Requisition, Purchase Order, ITP and MTO (as
applicable)
4 Jeopardise facility operation and have serious consequences i.e. facility shutdown
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 13
Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: Feb. 2018
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 14
2 Small total cost, both as direct result and as a consequence 100K – 500K
2.3.5
Service characteristics (toxicity, temperature, pressure)
Service characteristic factors of process item that may escalate the criticality due to health
and safety consequences are pressure class rating, design temperature, flammability and
toxicity of the fluid etc. Similar factors are taken for items such as electrical and instrument
items.
Design Short
Pressure Service Rating /
Temp. Voltage Circuit
rating conditions/Fluid Certification
(deg C) Withstand
Innocuous
Sequential /
Non-flammable, batch (non-
1 critical)
150 # < 250 e.g. nitrogen, air, <=33kV < = 40kA NA
control and
water
bulk
materials
Low hazard
Base-layer
Motors
and
Generators
2 250 - Flammable, EOR >33kV advanced
300 # VSD’s >
400 chemicals, steam <=132kV >40kA process
50MW
control,
Transformers
Offline
> 100MVA
instruments
Medium hazard
Services such as
400 - 500 high toxic, high
3 corrosion rates, Exception to Online /
600 # or >132kV NA standard Ex inline
hydrogen, wet H2S
certification instruments
-50 to 0 or sour, acid, cyclic
or vacuum
4 High hazard
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 15
Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: Feb. 2018
Note: The highest category from each of the columns becomes the category for above
table (Example – 150 #, - 50 C° the score is 3).
2.3.6 Location
The location of the facility where the item is in use is an important factor that may escalate
the criticality since the impact on environment, health and safety differs based on the
location.
Score Location
No perceived risk
1 No injury or damage to health
to personnel
Minor injury or health effects (Lost Time Injury)
Minor health effects, which are reversible, e.g. skin irritation, food
poisoning.
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 16
1 N/A
2 N/A
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 17
Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: Feb. 2018
A copy of Appendix C.1/C.2 (when applicable) for the items assessed will be appended to
the Purchase Requisition.
PDO may wish to attend the pre-inspection meetings. Contractor will provide at least 15
working days notice of such meetings.
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 18
DE/ QE will pay attention to the special processes as defined in SP-1171 (e.g. welding,
painting, PWHT, NDE, etc) and such processes will be carried out under supervision of a
competent person as defined by the respective specification. All special processes will be
executed in accordance with documented and qualified procedures that ensure work is
complying with PDO technical specifications.
Vendor surveillance visits should be undertaken by PDO/Contractor Quality team /
Discipline Engineers for critical items or when required by contractual obligations.
All Inspection Reports shall be made available to PDO for review/information. The
Inspection Reports will also be accessible by PDO electronically.
The IRN shall be issued by the responsible Inspector once the item is ready for delivery
and all key documents, procedures, drawings reached Code A (approved with no
comments), NCR’s/deviations approved or closed; where possible, Vendor Data Book shall
be reviewed by TPI (for CR1, CR2, CR3) for content, technical compliance and
completeness.
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 19
Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: Feb. 2018
3 Appendixes
Appendix A Criticality Rating Data Sheet
Equipment/Package Tag No./Materials:
Description:
Contract No.: Project:
Criticality Categories Score
Operations failure of the item:
Allow use of installed bypass or change without difficulty 1
Cause problems but not loss of production 2
Allow bypass or change out but with some loss of production 3
Jeopardise facility operation and have serious consequences i.e. facility shutdown 4
Design maturity/reliability:
Proven design, used frequently 1
Modification to proven design 2
Extrapolation to proven design 3
New innovative design 4
Manufacturing complexity:
Simple manufacturing processes, common construction materials 1
More complicated manufacturing processes, common construction materials 2
At least one complex manufacturing process or special construction material 3
A large number of complex or new manufacturing processes or special construction 4
Costmaterials
implications of failure:
Negligible 1
Small total cost, both as direct result and as a consequence 2
Moderate total cost, both as direct result and as a consequence 3
High and excessive total cost, both as direct result and as a consequence 4
Service characteristics (toxicity, temperature, pressure):
Innocuous 1
Low hazard 2
Medium hazard 3
High hazard 4
Location:
Isolated, operating personnel only 1
Remote, low population only 2
Public boundary, sensitive environment 3
High population, high sensitivity environment 4
Personnel safety:
No perceived risk to personnel 1
Moderate risk to personnel mitigated by systems and equipment 2
Significant risk to personnel 3
High risk to personnel 4
Special considerations*:
a) Schedule Delivery (Shutdowns / Emergency) 1
b) Purchase Order Quantity 2
3
4
Remarks: Total Score:
Criticality Rating:
CR 1: Extremely critical (Importance - Vital CR 2: Very critical (Importance – Significant)
&
CRNo
3:Compromise)
Critical (Importance - Moderate) CR 4: Non-critical (Less important based on Vendor quality controls)
Assessment team (Lead) Discipline Engineer Process Owner
(names)
Name: Name:
Signature: Signature:
Date: Date:
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 20
Name:XX Name:
Description:
Contract No.: Project:
Quality
S. Intervention Level
Quality Activities (QIL)
No
1 2 3 4
1 Vendor to submit the Quality Plan for packages to EMC/EPCC/IMC/ODC/EP Contractors R - - -
(as applicable) and PDO for review/approval within 30 calendar days after PO placement.
Vendor to submit Quality Control Plan (Inspection & Test Plan) prior to start of production
for review, approval and mark-up of any hold/witness/review/etc points by R R R -
2
EMC/EPCC/IMC/ODC/EP Contractors (as applicable) and PDO. PDO shall review only the
ITP’s for CR1 and CR2 items.
3 Pre-Inspection Meetings – clarify PDO/Contractor quality requirements D D D -
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 22
Description:
Contract No.: Purchase Order No.:
Quality
S. Intervention Level
Quality Activities (QIL)
No
1 2 3 4
Vendor to submit the Quality Plan for packages to EPC Contractor and PDO for R - - -
1
review/approval within 30 calendar days after PO placement
Vendor to submit Quality Control Plan (Inspection & Test Plan) prior to start of production
2 for review, approval and mark-up of any hold/witness/review/etc points by EPC Contractor R R R -
and PDO. PDO shall review only the ITP’s with CR1 and CR2.
Pre-Inspection Meetings – clarify EPC Contractor quality requirements. PDO R D D -
3
Project/Discipline Engineer will decide only for CR1 items if PDO presence is required.
Review of design documentation, drawings, calculations or procedures as listed in VDRL R R R R
4
after award and before manufacturing activities by EPC Contractor.
Resident inspection by EPC Contractor or EPC Contractor appointed Third Party Inspector
5 during all stages of manufacturing activities. The Assessment Team will justify if Resident D - - -
Inspector is required (to be stated in Remarks column).
Audit(s) against PO requirements during manufacturing activities to be performed by
6 Contractor. Audit schedule to be developed based on the manufacturing plan for one or D D - -
more audits.
Attendance of specific QC stages (witness and hold points) by EPC Contractor or EPC
7 Contractor appointed TPI/ specialist engineer as identified in the QC Plan. PDO R R D -
involvement is not required.
Surveillance visits by EPC Contractor at Vendor/Sub-Vendor’s premises to review ongoing
8 D D - -
inspection and test activities. Review of verifying records.
Witnessing of functional testing (Factory Acceptance Test) by EPC Contractor or EPC
9 Contractor appointed TPI/specialist engineer as identified in the QC Plan. PDO R R R -
Project/Discipline Engineer decides only for CR1 items if PDO will witness the FAT.
Final inspection release by EPC Contractor appointed TPI including review of material
10 R R R -
certification, manufacturing, inspection and test records.
R = Requirement
D = Requirement dependent upon:
a) Any specific requirement included in the item specification
b) Confidence in capability of Vendor
Note: If deemed not required, justification shall be provided in Remarks column
Corresponding Criticality Rating (CR) to Quality Intervention Level (QIL):
CR1-QIL1, CR2-QIL2, CR3-QIL3, CR4-QIL4
The Criticality Rating for this item* is: The Quality Intervention Level is:
Remarks:
Notes:
*Certification requirements shall be determined as per specification requirements and other applicable
standards. The Inspection documents shall be in accordance with ISO 10474 or EN 10204; if the standard
is not specified, then consider ISO 10474.
QIL4: Inspection document 3.1 or 2.2
QIL3: Inspection document 3.1
QIL2: Inspection document 3.1
QIL1: Inspection document 3.2
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 23
Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: Feb. 2018
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 24
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 25
Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: Feb. 2018
Note: 1. For CR2 items the Discipline Engineer will decide the in-process inspection
activities to be witnessed by TPI (if any)
2. The remaining quality activities are as per Appendix C.1/C.2
3. FI - Final Inspection, PIM - Pre-inspection Meeting
FAT - Factory Acceptance Test
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 26
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 27
Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: Feb. 2018
http://cms.portal.corp.pdo.om/_layouts/15/WopiFrame.aspx?sourcedoc=/CMSAttachments/UED
/UEQ/Appendix%20H%20Approved%20Inspection%20Agencies.pdf&action=default
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 28
http://cms.portal.corp.pdo.om/_layouts/15/WopiFrame.aspx?sourcedoc=/CMSAttachments/UED
/UEQ/Appendix%20I%20Policy%20for%20Procurement%20of%20Small%20Quantity%20CS%
20Pipeline%20items.pdf&action=default
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 29
Printed copies are UNCONTROLLED.
Version: 1
Petroleum Development Oman LLC Effective: Feb. 2018
Piping Bulk:
http://sww.pdo.shell.om/sites/UEOD/UEQ/Inspection%20and%20Testing%20Requirements%20
%20Bulk%20Piping/Forms/AllItems.aspx
Valves:
Ball Valves
http://cms.portal.corp.pdo.om/_layouts/15/WopiFrame.aspx?sourcedoc=/CMSAttachments/UED/U
EQ/Appendix%20J%20Inspection%20Requirements%20for%20Ball%20Valves.xlsx&action=defau
lt
Check Valves
http://cms.portal.corp.pdo.om/_layouts/15/WopiFrame.aspx?sourcedoc=/CMSAttachments/UED/U
EQ/Appendix%20J%20Inspection%20Requirements%20for%20Check%20Valves.xlsx&action=def
ault
Gate Valves
http://cms.portal.corp.pdo.om/_layouts/15/WopiFrame.aspx?sourcedoc=/CMSAttachments/UED/U
EQ/Appendix%20J%20Inspection%20Requirements%20for%20Gate%20Valves.xlsx&action=defa
ult
Globe Valves
http://cms.portal.corp.pdo.om/_layouts/15/WopiFrame.aspx?sourcedoc=/CMSAttachments/UED/U
EQ/Appendix%20J%20Inspection%20Requirements%20for%20Globe%20Valves.xlsx&action=def
ault
DBB-SBB Valves
http://cms.portal.corp.pdo.om/_layouts/15/WopiFrame.aspx?sourcedoc=/CMSAttachments/UED/U
EQ/Appendix%20J%20Inspection%20Requirements%20for%20DBB-
SBB%20Valves.xlsx&action=default
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 30
Page Ref: Brief Description of Improvement and/or Change Required and Reasons
Printed 14/10/2018 SP-2269 Specification for Quality Intervention for Provision of Products Page 31
Printed copies are UNCONTROLLED.