Document ID SP-2329
Security Unrestricted
Revision 6.3
This document is the property of Petroleum Development Oman, LLC. Neither the whole nor any part of this
document may be disclosed to others or reproduced, stored in a retrieval system, or transmitted in any form
by any means (electronic, mechanical, reprographic recording or otherwise) without prior written consent of
the owner.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
i Revision History
The following is a brief summary of the most recent revisions to this document. Details of all revisions
prior to these are held on file by the issuing department.
Revision
Date Author Scope / Remarks
No.
Adding:
- Two R&R in part 5.1.3
Agreement of affected
custodian.
Mahmood Khayari - And adding in Part 4.1 Permit
6.3 Sept-22 Applicant shall review PDO LFIs
UOP63
(Learning from Incidents);
attach any LFIs that are relevant
to the permit and add additional
controls as required.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
TABLE OF CONTENTS
i Revision History ................................................................................................................3
ii Related Business Processes ............................................................................................4
iii Related Corporate Management System (CMS) Documents ...........................................4
Executive summary ...........................................................................................................9
1.1 Scope .......................................................................................................................... 9
1.2 Objectives ................................................................................................................... 9
1.3 Changes to the document........................................................................................... 9
1.4 Step-out approval ....................................................................................................... 9
1.5 System custodian and focal points ............................................................................. 9
The PTW system ............................................................................................................ 10
2.1 What is a PTW system? ........................................................................................... 10
2.2 PTW Facility Requirements ...................................................................................... 10
2.3 Who is involved in the PTW system? ....................................................................... 11
2.4 Who decides on whether a PTW is necessary and which type?.............................. 11
2.5 What types of PTW are there? ................................................................................. 11
2.6 The type of work that needs a PTW ......................................................................... 18
Contractor’s Own PTW System Use .............................................................................. 20
Applying for a PTW ........................................................................................................ 21
4.1 PTW process flow ..................................................................................................... 21
4.2 How to complete a PTW form ................................................................................... 22
4.3 Gas testing ................................................................................................................ 27
4.4 Level 2 Job Health Safety and Environment Plan (JHSEP) ..................................... 29
4.5 Applying for Task SOP PTW .................................................................................... 30
Permit to Work Meeting .................................................................................................. 31
Briefing of the Permit Holder by the Permit Applicant .................................................... 33
Issuing a PTW ................................................................................................................ 34
7.1 Pre Issue by Responsible Supervisor....................................................................... 34
7.2 Mechanical isolations ................................................................................................ 34
7.3 Electrical isolations ................................................................................................... 34
7.4 Daily Validation by the Area Authority ...................................................................... 35
The Permit Holders role in managing the PTW ............................................................. 36
8.1 Before work starts ..................................................................................................... 36
8.2 During the work ......................................................................................................... 37
8.3 Recording gas tests .................................................................................................. 37
Page 5 SP-2329 – PTW System Printed 03/11/22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Executive summary
A Permit to Work (PTW) system determines how a job can be carried out safely and is a control to
ensure all risks have been minimised. Compliance with a suitable and sufficient PTW will ensure
safety. It is a legal requirement under Omani Law - Ministerial Decision 286/ (2008).
This specification describes the requirements of PDO’s PTW system.
1.1 Scope
This PTW specification shall be used in all PDO operations and contracts, unless a contractor
has opted out by using his own PDO approved system. Any contractor PTW system in use
in PDO shall be approved and shall comply with all the requirements as detailed in section
titled ‘Contractor’s Own PTW System Use’. This specification explains the PDO PTW system,
defines when a PTW is required and the PTW approval and control process.
1.2 Objectives
The PTW system is an essential PDO HSE management process ensuring awareness of the
work hazards and the controls required to work safely in hazardous areas or activities. It
provides a process ensuring non-routine, hazardous or potentially hazardous activities can
be conducted safely.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
A Class A PTW has a maximum authorisation period of 14 days with a 7 day extension
allowance subject to the Responsible Supervisor approval.
It is used for controlling high risk work with a major incident risk e.g. fire, explosion.
It requires:
72 hours notice (except for unplanned but essential work.)
Production Coordinator approval.
A site visit and examination on the first day before work starts by the Responsible
Supervisor and Permit Applicant before the Responsible Supervisor initially authorises the
PTW in a process facility. The Responsible Supervisor can delegate site visits to an
alternative licensed Responsible Supervisor.
A Job HSE Plan is mandatory when creating a Class A PTW.
Thereafter for work in a process facility a daily visit and examination to revalidate the PTW
by the Area Authority
A site visit and examination by the Area Authority on the first day of work in hydrocarbon
areas unless the Responsible Supervisor has authorised the delegation of this
requirement to an Authorised Gas Tester.
Daily revalidation by the Area Authority
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
A Class B PTW has a maximum authorisation period of 28 days with a 7 day extension
allowance subject to the Responsible Supervisor approval.
It is used to control medium risk work. It requires:
48 hours notice (except for unplanned but essential work)
Production Coordinator approval (where PTW is associated with a full isolation)
Authorisation by the Responsible Supervisor.
A Job HSE Plan is mandatory when creating a Class B PTW.
A site visit and examination by the Area Authority for him to authorise the PTW in a
process facility on the first day before work starts.
Daily revalidation of the PTW by the Area Authority.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
permits” at a time however these should be close to each other in a way that all worksites
are visible to the holder and logically can be controlled by him.
Refer Appendix 3 for assurance task.
Original - - - - - - - - - - - - - - - - - - - - - - in Worksite
1st page Information Copy- - - - - - - - Responsible Supervisor’s
Archive after close out with- - - - - - - - Discipline supervisor
A Task SOP PTW has a maximum authorisation period of 7 days, the normal working hours
is day time from 6:00AM to 19:00PM unless other additional hours have be considered and
included in the risk assessed in creation stage of “Task SOP permit”.
It is used to control certain low risk routine activities. It requires:
The activity to be included in the 14 day plan prior to authorizing the Task SOP permit to
commence.
A specific risk assessment to be attached to the Task SOP PTW document which shall
be used to communicate hazards and controls to the work crew.
Authorisation by the Responsible Supervisor.
A work site check and examination by the permit holder for before work starts for each
location.
Daily revalidation of the Task SOP PTW by the permit holder.
Communicating to discipline supervisor in daily basis in moving to work and back to the
base safely, for tracking purpose.
The Task SOP shall be identified in the ePTW system by positioning a Notification of Work
(NoW) icon at the worksite. This shall be done on a daily basis by the permit holder, permit
applicant or supervisor of the holder. Prior to signing any PTW in his area the Area
Authority shall check the ePTW system for any Notification of Work (NoW) in the
surrounding area and manage any conflicts accordingly ensuring that all parties are
informed or stopping work as appropriate.
The Task SOP Permit process shall have its own procedure.
Task SOP PTW forms contain 6 steps; Role and Responsibilities, Filling guide, Reporting
Guide/sheet & Task SOP life cycle in Appendix 3.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Note:
Permit applicant should write RA code in the description/Title box. Also the Task SOP hard copy and
RA should be attached in ‘’NOW’’.
The details of each Task SOP activity are transferred to the NoW and submitted to the Responsible
Supervisor for authorization. Once the NoW has been issued by the RS, the document is suspended
and re-issued by the Permit Holder or his Supervisor without further input from the operations team.
This cycle is continued until the NoW reaches its end date at which point the Permit Holder shall
close out the NoW and update the remarks.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The activities, specific PTW type and controls that are required for any type of work in each
area are communicated in the table in Appendix 1.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
2.6.5 PTW type and controls for activities in PDO electrical installations
The table for the type of PTW required and the controls for activities in a Zone 1 or 2
hazardous area or a non-hazardous area are classified in Appendix 1.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
LINK to List of Contractor Systems (To update the list please contact UOP6)
Contractor’s PTW System application SOP can be found by following the LINK
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
A Permit Applicant is the only person licensed to apply for a new PTW and is normally the supervisor
of the crew who will conduct the work. He/she must have passed the ‘Permit Signatories’ course and
be licensed as a ‘Permit Applicant,’ ‘Area Authority’, or ‘Responsible Supervisor’ for the area in which
the work is being carried out.
Only PTWs for jobs that are in the ‘Frozen Plan’ can be submitted for approval unless the job is
classified as an urgent job and the normal lead times do not apply.
He/she shall:
Complete the PTW form.
Complete the Application section of any certificates required with the PTW.
Identify the tag numbers for all equipment that requires to be isolated. The specific
isolation details shall only be provided by a competent isolating authority for that system.
Produce a suitable and sufficient Job HSE Plan
Ensure that the PTW is presented at the meeting by himself or someone who is fully
conversant with the activity and location of work.
Examine the worksite with the Responsible Supervisor where required to check that all
necessary controls have been identified and included in the Job HSE Plan.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Confirm whether any other custodian could be impacted by the work and if so jointly
review the PTW with them to ensure the controls manage the risk to the other custodian.
When satisfied the other custodian shall sign the "Other Affected Custodian”.
Permit Applicant shall review PDO LFIs (Learning from Incidents); attach any LFIs that
are relevant to the permit and add additional controls as required.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Any requirement for “Remote Suspension” shall be highlighted in the work description of
the associated PTW and be agreed by the Responsible Supervisor. Remote Suspension is
where the Permit Applicant may suspend the PTW in the system on conformation from the
Permit Holder that work has stopped for the day and is used where the worksite is at a
significant distance from a PDO network and driving to the networked location would add
additional travel exposure.
Start/End Date
Select the planned start and end dates from the calendar
The maximum standard authorisation period is:
14 days for Class A
28 days for Class B
28 days for a No Permit Job
7 days for a Task SOP
The authorisation period shall take account of the planned work schedule to avoid PTWs
being authorised for periods longer than required but also to prevent a further PTW being
required if the job over runs slightly (no longer than 7 days).
Site
Select the site location
Work location
Mark the work location on the GIS map
For repetitive routine tasks (subject of a planned routine) across different stations, where the intrinsic
hazard is the same, (i.e. NDT work, Beam Pump maintenance) and the site conditions are also similar
(e.g. No change in H2S classification,) the Responsible Supervisor may allow a number of stations or
worksites to be identified on a single permit. This shall be done by selecting an area on the GIS map
rather than placing a pin.
Equipment Tag Number
Select equipment tags associated with the work.
Number in Work Party
Detail the number of people involved in the activity
The maximum number in the work party should be agreed at the time of PTW authorisation by the
Responsible Supervisor, Area Authority, and Permit Applicant, and consideration should be given to
worksite location and visibility of work party. An ePTW Level 2 Risk Assessment shall be created when
the work party strength exceeds 20.
Work Order Number
Provide related SAP Work Order number
Tools to be used
List any tools required to be used during the activity
Vehicles/Equipment to be used
List any vehicles or other equipment required to be used during the activity
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Where vehicle access to a Process Facility, Restricted Area or any other location may constitute a
hazard then the vehicle details and reason for requirement shall be written in this section.
An associated route plan for the vehicle shall be attached to the PTW. The route plan shall be a plot
plan of the station with the vehicle route and final position marked clearly on it.
The Vehicle Access Checklist shall be attached.
Lead Discipline
Select discipline from pick list
Isolation Requirement
Select Isolation Type required
Hazardous Area
Select Area Zoning
The hazardous area classification of the worksite (shown on the Hazardous Area drawings for the
station).
H2S Facility
Select H2S area classification
Whether the work is in an H2S facility (shown on the H2S facility listing in the Area Safety Case) and
the station classification / designation.
SP-1190-4 details the requirements for working in H2S areas in line with the area classification.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Include a worksite examination to identify and assess the hazards (except for Class B PTWs at remote
locations where it is known that no other facilities, such as overhead or underground services could
create a hazard to the work party)
Groups Effected/Consequence
Provide details
Hazard(s)
Select all applicable Hazards from the dropdown list
Control(s)
Select all applicable Controls from the dropdown list
Enter additional specific controls
Select any Pre Requisite Controls (Controls that need to be in-place before the PTW can
be issued)
Sign JHSEP
Sign that JHSEP is complete
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The reason for isolation shall provide sufficient description to allow the isolating authority to create
the correct level of isolation. Routine/Breakdown maintenance is not an acceptable reason.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
For Class B PTWs, the Responsible Supervisor shall decide whether or not a site visit
and examination is required by him and it is normally delegated to the Area Authority.
NOTE*: Worksite visits by Responsible Supervisor and Permit Applicant can be relaxed at the discretion
of the Production Coordinator following a documented risk assessment being completed. A Responsible
Supervisor may delegate the worksite inspection to another person licensed as a Responsible Supervisor
for that area.
NOTE ** - For certain ongoing Class A activities inside a Process Area where the risks are clearly
understood and controlled, the daily gas test (not the first gas test of the activity) may be delegated to a
competent Authorised Gas Tester (AGT). This should be agreed and approved by the Responsible
Supervisor following a review of any potential activity conflicts. The Area Authority however, must continue
to carry out regular worksite visits during the ongoing activity.
NOTE *** - Except where a gas test is required, as the Area Authority may wish to do the first Gas Test
each day for Class A PTWs, otherwise he may delegate to an AGT
NOTE **** - All new excavation work requires a site visit by the Responsible Supervisor or Delegate and
the Permit Applicant. See PR-1002 Operations Excavation Procedure
An exception to the requirement for an Area Authority to carry out the first gas test of an activity
relates to well cellar entry, where the inherent risk has been deemed “low” the gas test can be
done by an Approved Gas Tester.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The Area Authority shall conduct the first gas test each day for a Class A PTW, however it can
be delegated to another AGT for certain jobs at the discretion of the Responsible Supervisor.
Where this is the case the PTW declaration shall be ticked to state that the gas test results will
be entered at site.
AGTs may conduct further gas tests on a Class A PTW as required during the day and can
also conduct gas tests for work under any Class B PTW.
In all cases, the AGT must:
Gas test at the frequency stated on the PTW or the Confined Space Entry Certificate.
Fill in the result of the gas test on the gas test record and sign it.
When the gas test indicates that it is NOT safe to work, the AGT must:
Tell the Permit Holder to immediately stop all work.
Inform the Permit Holder and Area Authority why it is unsafe to work and ensure the problem
is resolved.
The Area Authority must be a licensed AGT and must ensure he immediately stops the work
and moves everyone to a safe location if the site conditions become hazardous or the controls
become inadequate.
In addition to gas testing, continuous gas monitoring may be required if specified on the PTW.
A Permit Holder trained in the use of the gas monitor may supervise work for which continuous
gas monitoring is required without being licensed as a Gas Tester. Continuous gas monitoring
results do not need to be recorded on the PTW.
Hot work
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Gas test each day before starting work and then continuously for work or operating
equipment that may cause flames or sparks in process facilities where significant quantities
of gas are present.
Hot work includes all open flame work or where sparks could generated such as grinding,
electrical work or vehicle entry.
Responsible Supervisors and Area Authorities can increase the test frequency.
When a gas test is required, the Permit Applicant shall:
Tick the gases to be tested.
Indicate how often the test shall be repeated.
State if continuous monitoring for gas is required during the work.
Further guidance on gas testing can be found in PR-1154 Gas Testing Procedure
Groups Effected/Consequence
Provide details
Team Members
The team members shall be selected from the drop down list.
Risk Assessment Task
Update the field with ‘To assess the risk associated with…..’
Hazard(s)
Select all applicable Hazards from the dropdown list.
If required add additional hazard as new.
Initial Risk
Select all the initial risk from the matrix as detailed in PR-2271.
Control(s)
Select all applicable Controls from the dropdown list
If required add additional measures ensuring that the Action Party is named.
Select any Pre Requisite Controls (Controls that need to be in-place before the PTW can
be issued)
Appropriate recovery measures shall be detailed
Residual Risk
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Select all the residual risk from the matrix as detailed in PR-2271.
Risk Assessment Approval
The Level 2 JHSEP shall be approved as per the level of residual risk. This is detailed in
PR-2271 Operational Risk Assessment.
Detailed Task SOP requirements shall be set out in its own procedure.
A Task SOP developed for a specific activity which is mentioned at the top of the form with
associated risk assessment number for the specific task.
The Task SOP PTW consists of two parts:
The first part is the Task SOP PTW.
The second part is the reference risk assessment for specific activity associated with
structured work flow steps which shall be followed (Step.A to Step.D), however there
may have an extra forms or associated certificates like confined space, mechanical or
electrical certificates...etc.
Only the work detailed in the Task SOP PTW shall be conducted. Work shall stop
immediately if work goes outside this boundary and a class “A” or “B” PTW for the remainder
of the work shall be raised.
There is no requirement of standalone JHSEP as it is covered under the specific risk
assessment and TRIC incorporated in Task SOP PTW.
The Task SOP shall clearly detail where the work is to be conducted (fields and location)
Task SOP permit allows to work in number of worksites to be identified on a single permit
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The team shall determine if the PTW is for emergency work and if not ensure the PTW work is
in the frozen plan and reject if it is not.
Determine if the 72 hour and 48 hour rules have been complied with and ask for justification
from the Permit Applicant where there are shorter time scales. PTW Applicants with insufficient
justification shall have their permits rejected.
A review shall take place of the PTW to ensure the following:
The correct type of permit been used
The work scope and location are clear
All hazards have been identified, including those arising from the location of work
Controls have been identified to mitigate the hazards
Additional controls have been added where required.
Any SIMOPS issues have been addressed, include a check of other work ongoing or
scheduled in the area.
Work is in line with any MOPO requirements
Gas testing requirements have been identified
Any isolations have been pre-planned, their details updated on the Isolation Certificate.
Isolations have been agreed by production operations for mechanical and by
Electrical/Instrument for other isolations.
Additional documentation has been added where required.
If agreed then minor changes, agreed and understood by all PTW team meeting
members as well as the Permit Applicant, can be made at the time of the permit
meeting prior to authorization. Significant changes shall mean that the permit is
rejected and will need to be resubmitted at a later date.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Issuing a PTW
7.1 Pre Issue by Responsible Supervisor
Before work is scheduled to start the PTW needs to be Pre-Issued by the Responsible
Supervisor. Prior to Pre-Issuing the PTW he shall ensure the following:
The work is in the current frozen plan or that a SAP MoC step in to the plan has
been raised for the activity.
There are no conflicts.
SIMOPS controls are clearly identified and understood, if required.
Any Other Affected Custodians have been informed.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Before work starts under a PTW the Permit Holder shall ensure:
He reviews any concurrent activities that may affect his worksite, in which case he shall
stop the job immediately and hold a “Pause & Check” discussion with the other PTW Holder
and both work crews. Together the two PTW Holders shall agree which PTW Holder will
adopt overall supervision of the critical concurrent phase of the activity.
Any Pre-Requisite controls have been implemented.
He understands the work content and the Job HSE Plan.
He holds a TRIC discussion with his work crew to discuss the requirements of the work
and the Job HSE Plan.
All members of the work crew have understood what is required, and the role they play
from the TRIC, and they sign the TRIC to acknowledge this.
The Dynamic Risk Assessment plan has been recorded on the TRIC.
That the PTW is validated by the appropriate Area Authority before starting work every
subsequent day.
When he is satisfied that the worksite is safe shall the Permit Holder accept and sign the PTW.
By signing the PTW the Permit Holder is agreeing to the following:
He fully understands the work and precautions.
All members of the work crew are fully briefed.
The Job HSE Plan is understood and will be complied with.
The PTW will be displayed at all times of the work at the worksite in a plastic wallet.
No work will be done unless the Area Authority has validated the PTW.
The worksite will be left in a safe condition on completion or suspension of work.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
A TRIC card shall not be used to allow the work to continue regardless of the change.
Work shall stop immediately if it goes out with the boundary of the permit.
IT IS THE RESPONSIBILITY OF THE PERMIT HOLDER TO STOP THE WORK IF IT GOES
OUTWITH THE BOUNDARY OF THE PTW.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The Area Authority shall assure himself of the work status for all PTW under his control
prior to signing off shift.
The Area Authority shall follow up on any overdue PTW showing in the system at the end
of the shift as this may be an indication that something has gone wrong with the work.
8.5.3 Stopping and re-starting work in the event of an alarm in the station
Stopping work
All work shall stop immediately following the facility evacuation alarm sounding. The Permit
Holder shall ensure that all his worksites have been left in a safe condition and then he shall
evacuate as soon as possible.
If the unplanned stoppage of work could cause a dangerous situation the work crew shall take
emergency action as stated for the scenario in the Job HSE Plan.
When the alarm condition has cleared, the Worksite Copy of the PTW is to be taken to the
Permit Issue Point or Area Authority for reauthorisation in the ePTW system.
Re-Starting work
Alarms caused by a real situation may require the Area Authority to suspend and re-validate
the PTWs. In this instance the Area Authority shall suspend all permits on behalf of the Permit
Holder and then as Area Authority, he shall ‘Suspend for Emergency’. The normal re-validation
procedure shall be followed and a further worksite examination is required to check if the
problem which caused the alarm may have impacted on conditions at the worksite.
If the alarm was a false alarm, the Area Authority may verbally re-authorise each Permit Holder
to re-start work once the ‘all clear’ signal has been is given.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Restrictions though apply on the number of roles that a person may carry out on single PTW
as shown in Table 10.2.
For normal activities, it is expected that the Responsible Supervisor, Permit Applicant, Area
Authority and Permit Holder will be four different individuals.
In emergency or breakdown situations or for work involving specialists3 it can be difficult to
arrange four different individuals and in such cases a person licensed for one role can fulfil an
additional role. There are restrictions to ensure that an independent review of the safety of the
work is carried out.
Table 10.2 - Roles that can be filled by any one person on a single PTW
May act as Responsible Area Authority Permit Permit Holder
Supervisor Applicant
Responsible Yes Yes No No
Supervisor (See Note 1)
Area Authority No Yes Yes No
(See Note 2)
Permit Applicant No No Yes Yes
(See Note 3)
Permit Holder No No Yes Yes
(See Note 3)
NOTE:
1. In urgent cases or during night time breakdown situations, a licensed Responsible Supervisor may sign
as a Responsible Supervisor and an Area Authority.
Some Area Authorities have been licensed as Responsible Supervisors to allow work to proceed without
calling up the daytime Responsible Supervisor. This will allow two-man PTW operation if the Permit Holder
has also been licensed as a Permit Applicant. This option is acceptable only in urgent cases or the night
time breakdowns when there are no other active PTWs operating. Normal daytime roles of the
Responsible Supervisor shall not be delegated to the Operators at the remote stations.
2. If the Area Authority has not been licensed as Responsible Supervisor, or if the Permit Holder has not
been licensed as a Permit Applicant, it will be necessary to call up the daytime Responsible Supervisor.
In this case the Area Authority will be the Permit Applicant.
3 Specialist work can be (but is not limited to) any work that is not normal maintenance or engineering
work. For such work, a licensed Permit Applicant can act as a Permit Holder.
Page 48 SP-2329 – PTW System Printed 03/11/22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Isolation Process
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
NOTE: It is not the responsibility of the PTW Applicant to provide the isolation details, this is
the role of the Isolating Authority.
Where the isolation is required for operational reasons, with no associated PTW or operations
are creating the permit then the same Area Authority can raise the isolation and provide
isolation details if he is also a competent Isolating Authority.
The PTW Applicant or Isolating Authority shall place the marker at the work location on the
base map. The equipment to be isolated shall be selected from the drop down list, only if the
equipment to be isolated is not available in the master data should it be added as ‘New
Equipment’. The isolation title shall then be given. Endorsing Authority shall be added if one or
more of the isolation points takes place in another asset, area or falls under the authority of
another equipment owner. A clear reason for isolation shall be provided, this is important as it
will guide the isolating authority to which level of isolation is required. For example breaking
containment would require an additional level of isolation above that required for a non-
intrusive inspection.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The first part of the tag with the attachment loop shall attach to the isolation point. The
second part shall be attached to the PTW & the Isolation Certificate. The third part (smallest
part) is kept at the Issue Point until the isolation is removed.
11.13 De-Isolation
The Permit Holder shall request de-isolation. If testing is required before de-isolation then 9.14
De-Isolation for Test shall be followed. Once the Isolating Authority in consultation with the
Area Authority (if they are different people) have assured themselves that the system integrity
has been restored, for breaking containment this will be with the successful completion of the
relevant reinstatement test as per SP-2290, they shall sign to authorise de-isolation.
The de-isolation shall be carried out as per the approved de-isolation plan on the Isolation
Certificate
Once approval to remove the isolation has been given the isolation can be removed.
The Isolating Authority or Electrical Person shall:
Check the ePTW overview and Process Isolation Wall (if available) to ensure there is no
conflict with other work or isolation and the system is safe to de-isolate.
Inform the CRO before de-isolating the equipment.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Vehicle access
Vehicles are not permitted to enter or to drive within 50m of a process facility so if a vehicle is
required to enter a PTW is required. Exceptions to this rule are:
Vehicle access to a pig trap area for pipeline pigging operations covered by a Class B
PTW, pigging authorisation certificate and listed in the approved programme. The same
requirements for entry and gas testing will apply and continuous gas testing is required if
the vehicle engine remains running.
Travel to and from the facility in crew vehicles via the normal marked route to the facility
parking area.
Use of delivery trucks, as covered in 13.6.10.
If vehicle access to a Restricted Area is required it will have been recorded on the PTW in the
“Vehicle Access Section”.
The Permit Applicant shall ensure that a vehicle access checklist (Appendix 6) is
presented with the PTW, and the Permit Holder shall ensure that all conditions therein
are complied with.
The Area Authority shall only authorise entry of the vehicle after verifying the conditions
have been met.
NOTE: Vehicle access should only be granted for delivering essential materials or equipment
and shall not be granted for general access or transport of personnel. The vehicle shall be
removed immediately on the completion of the delivery.
NOTE: A gas test is required before each vehicle access or movement. Details and results of
the gas test shall be entered on the PTW and the station gates shall be closed after each entry
or exit.
Continuous gas monitoring is required wherever a crane is used.
NOTE: The Permit Holder shall verify the vehicle is free of mobile phones and any other sources
of ignition e.g. matches and lighters.
NOTE: This approval is not to be used to authorise the passage of high vehicles beneath
overhead power line as this requires a separate Overhead Line Clearance Certificate.
The Permit Holder shall brief the Responsible Supervisor and/or the Area Authority on the
scope of the work and the Area Authority shall ensure that the Permit Holder fully understands
the scope of the work, hazards and controls before validating and allowing work to commence.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Laying sleepers, connecting up spools, hydrostatic test, removal of spades at the Xmas tree
and manifold for final handover to production, (using documented handover procedures) all
require a Class B PTW.
The disconnection and re-hook up of existing wells requires a Class B PTW unless flowline
cutting is required which requires a Class A PTW.
Seismic operating procedures clearly defining access limitations close to facilities are
acceptable as an adequate control mechanism for vehicle access provided the vehicles are
outside of Hazardous Areas and not close to Overhead Lines (defined in ESOP).
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
of a rapid rise in fluid level within the pit. If escape cannot be assured then the work
should not be allowed to proceed.
Where no breaking containment is to take place it is not required to have a Confined Space
Entry Certificate to accompany the Class B PTW, but shall require that a gas test to be carried
out by an AGT with the results recorded on the PTW, and the following checks carried out:
Visually inspect the cellar for reptiles and signs of poisonous insects.
In cases where the cellar is partially filled with sand, try poking the sand surface with a
long stick to check for reptiles.
A defined and tested escape route
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Visually inspect the cellar for reptiles and signs of poisonous insects.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
In cases where the cellar is partially filled with sand, try poking the sand surface with a
long stick to check for reptiles.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Note: Where stations have a connection from an oil-saver pit to a point external to the
fence, as the area is effectively a Zone 1 area and the tanker discharges into an open
funnel with a pit underneath the funnel then a Class B PTW for activity 6 is required and
an initial gas test needs to be performed before the vehicle enters the area and
continuous gas monitoring during the discharge.
If a non-drip connection is used and the tanker remains outside the hazardous area then the
work does not require a PTW, however the AA must be kept informed.
Use of a suction tanker
A vehicle entering an operating facility to empty a pit of hydrocarbons requires a Class B
PTW under activity 6. If the tanker is collecting hazardous chemicals/substances then a Class
B PTW under activity 4 is required.
Delivery of liquid or solid stores by vehicle to a station
Vehicle entry to an operating facility requires a Class B PTW under activity 6 with an
exception being where the vehicle is only for the delivery of operational stores and is under
the Area Authority's direction throughout its visit. For this exception to be a No Permit Job
the following conditions shall be required:
The delivery of goods should be planned and known beforehand to the Area Authority.
Offloading is in a safe, non-hazardous, area away from hydrocarbon and electrical
facilities.
The Operator/Area Authority shall directly control the access and movement of the
vehicle.
13.6.12 Radiography
All radiography (x-ray and gamma sources) performed outside engineer enclosures requires
a Class B PTW for activity 4, a completed radiography certificate, a Job HSE Plan and sketch
of the Controlled Area (7.5 us/h) boundary distances.
In addition where radiography is to be carried out in a process area or close to process
facilities the safety systems and any nucleonic level measurement should be inhibited
through the approved route.
An example of a radiography certificate can be found in SP-1237 and is the only
supplementary certificate that can used without being part of a PDO PTW (see below).
A PDO Class B PTW is required for radiography inside existing production facilities and all
pipeline activities however on occasion where radiography is performed in a controlled open
area or fabrication yard it will require an in-house contractor PTW control. All radiography
performed outside of the engineered enclosures shall have a valid PDO or contractor PTW
to facilitate discussion and planning of the work.
The PTW Applicant in conjunction with the radiography Site in Charge (Radiation Protection
Supervisor) is responsible for completing the Radiography Certificate prior to commencing
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
radiography activities which can be used with a non PDO PTW provided the contractor self
manages radiography activities and ensures valid documentation.
Operational, maintenance and emergency procedures for handling, storing and transporting
radioactive sources or generators shall meet HSE Specification SP-1327 and the NDT
contractors shall have their own approved Radiation Safety Management System signed off
by their Radiation Protection Advisor.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Permit Applicant Pigging Contractor Apply for PTW as per SP-2329. (A separate PTW is needed
for launching and receiving)
Add other affected custodian(s)
Attach pigging authorization certificate
Provide details of launching or receiving set up as per PR-
1082
Attach up to date Drawing and Method Statement for
launching or receiving activity from PR-1082
Area Authority UIPT AA / PDO Station Carry out AA duties as per SP-2329, Daily Validation of PTW
Operator / 3rd Party AA
Responsible UIPT RS / PDO Station Carry out RS duties as per SP-2329. Sign PTW as other affected
Supervisor RS / 3rd Party RS custodian on launching/receiving permit if issued from another
facility.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
2. A Class A PTW is required of hot work is planned to free shackles and this requires a
worksite examination.
3. Routine non-invasive maintenance work on offshore SBMs does not require a PTW.
4. Other repair work shall use a PTW appropriate to the activity in Appendix 1. A worksite
examination is required if the Responsible Supervisor considers the risk warrants it.
5. The area within 50 meters of a flow line associated with an SBM shall be classified as a
Hydrocarbon Area
Fault finding for low hazard work to find the cause of a defect (and possibly repair) does not
require a PTW if the following conditions are met:
a. The work is done or supervised by a competent person;
b. The hazards have been identified on a Job HSE Plan, it is authorised by the
Responsible Supervisor and a TRIC is in place.
c. The work required to repair the fault is minor, does not fall into a PTW activity and it
can be completed under the initial authorisation without raising a PTW.
NOTE: An appropriate PTW shall be raised if the repair work is more complex or includes
activities requiring a PTW.
Emergency breakdown work does not require a PTW. The work is similar to those for fault
finding i.e. make the plant safe and find the cause of the breakdown.
Once the plant is safe the correct type of document to manage the repair will be agreed
between the Responsible Supervisor and Area Authority and a PTW issued.
Multi discipline work. If one trade is required to support another trade then the work can be
done on the same PTW provided that the Permit Applicant and Permit Holder have been
licensed to cover multi-discipline work.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
For work involving diving operations at the Mina Al-Fahal Marine Terminal, an In-house PTW
will be applied utilizing the diving contractors, International Maritime Contractors (IMCA) and
International Association of Oil & Gas Producers (OGP) compliant dive permit system.
Each contractors dive permit is to be authorised by the PDO Responsible Supervisor for every
diving permit/activity.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The following steps shall be adhered to for all ESPs, ESPCPs & PCPs activities:
1. The Responsible Supervisor requests the CSR to attend job.
2. The CSR instructs the vendor engineer to carry out the work (this does not have to be
face to face) and to refer to relevant Job HSE Plan for the activity and verify all controls
are in place.
3. Vendor engineer informs CCR when the job is started.
4. The CCR Operator logs the work details and start time in the “Station Log Book” and
reports the status to the Responsible Supervisor.
5. Vendor engineer informs CCR when the job is completed.
6. The CCR Operator logs the work details in the “Station Log Book” including the
completion time and reports the status to the Responsible Supervisor.
7. Vendor engineer submits Job HSE Plans for all completed jobs to the CSR for
documentation and assurance on return to the base.
*Note: The Electrical Supervisor shall sign as the Affected Custodian with direct liaison with
the ESP-CSR and the Production Supervisor to sign as the Responsible Supervisor.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
See Appendix 10 for Roles, Responsibilities, and detailed drone activity list.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
14.2 Activities requiring signature from the PDO Drilling Supervisor when the
contractor PTW system is adopted.
The PDO Drilling Supervisor shall counter sign the contractor’s in-house PTW forms for the
following works:
Hot work except when done in the approved rig workshop.
Isolation of any rig safety systems.
The signature of the PDO Drilling Supervisor makes him responsible for:
Agreeing that the work shall be conducted on the equipment at the proposed time.
Ensuring that all hazards have been adequately identified and assessed.
Reviewing the Job HSE Plan to ensure that it is suitable and sufficient.
Deciding on necessary worksite preparations and safety precautions.
The Toolpusher responsibilities are listed within the contractor’s PTW system.
14.4 Work done on or near drilling rigs by departments other than Well
Engineering
Some work on the drilling location can be performed by or for departments other than Well
Engineering. e.g. welding and testing flowlines, digging pits etc. This work shall take place
within the PDO PTW system and meet the following requirements:
Work On the drilling location
The PTW shall be raised by the appropriate Permit Applicant.
The PTW shall be authorised and validated by the PDO Drilling Supervisor who will act
as both the Responsible Supervisor and the Area Authority.
Page 72 SP-2329 – PTW System Printed 03/11/22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Well Engineering can isolate the flowline to carry out work where the requirements described
in section 11.1 have been met.
15.3 Flaring operations in Well Engineering shall comply with the following:
1. Well Engineering Completion and Well Intervention (CWI) team will raise a PDO class B
PTW for flaring operations accompanied by the PDO Earth map showing the ‘Total
Exclusion Zone’ (TEZ). The PTW shall comply with PR-1172 and be presented to the PDO
Operations Responsible Supervisor (ORS) who once satisfied with the content and
implication of the PTW will authorise the PTW for 14 days.
2. Each day before flaring the CWI team will submit their “intent to flare” request to the ORS,
who shall examine the request for potential conflicts with other work requests within the
TEZ.
3. Where no conflicts are identified (or other conflicting work activities have been prohibited)
the ORS will instruct the appropriate Area Authority to validate the flaring PTW in 12 hour
periods up to a maximum of 24 hours.
4. If the well site is near to an associated production station the daily validation should take
place ‘face to face’. Where the well site is a large distance from the production station,
then on a case by case basis, remote validation may be considered subject to the
requirements below:
5. The Operations Area Authority shall visit the well site for the activities first validation and
thereafter at least once per week where activities are ongoing to check the task and risks
have not changed.
6. The authorisation period can start from either 06.00/07.00 or 18.00/19.00 depending on
work cycles.
7. The PTW requirement only applies to flaring. Non-flaring activities such as bleeding down
lubricators do not require a PTW as they are captured under the existing CWI procedures.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The PTW Holder at a remote site shall communicate progress and worksite conditions to the
Area Authority before he leaves the permit validation point at the end his normal day shift and
also communicate completion of the activity to the Area CCR or appointed 24 hour monitoring
contact.
Where impracticable for the Permit Holder to return the PTW to the Permit Issue Point when the
work is stopped the worksite supervisor shall agree with the Area Authority that the work has
been suspended for the day and the Area Authority shall suspend the permit in the ePTW system
on his behalf. Before this the Permit Holder must phone the Area Authority/CRO to advise on
work progress and site conditions prior to leaving the worksite
The Area Authority shall not leave the station until he has made himself aware of the status of all
ePTWs in his area. The Permit Holder shall not leave the worksite he has updated the AA or
CRO.
After the “Permit Cancellation” has been signed, no further work shall take place under that PTW.
When the work is complete it may not be practicable to immediately return the wet ink copies of
the ePTW to the Permit Issue Point. In these cases the Worksite Supervisor should agree with
the Area Authority that the Worksite PTW be taken to an agreed collection point (e.g. PDO camp
offices).
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
TRAINING LICENSING
Gas Testers Permit Permit Holders Licensed
POST Course Signatories Course
Course
Responsible
Supervisor
Area Authority
Permit Applicant (Optional)
Permit Holder
(Optional)
Licensing after the PTW training is essential to ensure that Permit signatories understand how to
apply the PTW system in their area.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Other Specific Areas UIE, UIB, RAH, Marine etc These shall remain as stand-
alone areas. NFF is required to
move to any other main or
stand-alone area (Critical
Sour/YK/EPZ Area)*
*Re-licencing by the local panel will be required for a move to Critical Sour/Yibal Khuff or any other
area with EPZ. During this session the panel shall focus on EPZ ER Management.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
NOTE: Providing all the above criteria are met then there is no requirement for a PTW Licensing
Panel to sit.
Licensing Note for File (NFF) Link
The persons involved in the assessment should be familiar with the work area of the candidate, the
particular hazards associated with that discipline and PDO's Operating and Emergency Procedures
applicable to the work area.
It is recommended that the selection of suitable persons to form the Assessment Team is based on
knowledge and experience of the PTW system. The number of persons in the assessment team
should be sufficient to provide a collaborative decision on a candidate. The team should comprise
of a cross section of all departments.
*Well Engineering FBOM, Engineering Lead, IM&T Interior Operations Lead or Maintenance
Coordinator Pipeline may run a Licensing panel for their own area if they have been approved to do
so by a PDO Production Coordinator. To obtain approval, the holder of the equivalent role, shall
observe 2 licensing panels held by a Production Coordinator and chair 2 licensing panels whilst
being observed by the Production Coordinator. If the Production Coordinator is satisfied with the
performance of the equivalent role holder then he can issue a Note for File stating that XXX person
in the XXX role (equivalent to the Production Coordinator) has been authorised to chair a PTW
licensing panel for XXX area. This shall be signed, dated, and kept as a reference by both parties.
If the equivalent role moves to another area then he shall obtain a new NFF from the new area to
continue his licensing duties.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The Production Coordinator shall not issue the NFF if he has any concerns regarding the equivalent
roles capability or if the equivalent role has not demonstrated their ability to successfully chair a
panel.
Random checks by the asset shall be carried out to ensure continued quality of the licensing panel
assessment.
Table 1:
License Assessment Teams
Role Licensed By
Production/Maintenance Coordinator (or Delivery Team Leader (or equivalent)
equivalent) (following PTW training, interview & issue of
appointment letter)
Responsible Supervisor (or equivalent) Area Licensing Panel
Area Authority Area Licensing Panel
Permit Applicant Area Licensing Panel
Permit Holder Area Licensing Panel
Questioning, which may be verbal or written, should cover the following topics:
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Their knowledge of the hazards associated with the technical content of the work that they
will be supervising.
Knowledge of the potential hazards that could arise in the locations where they will be
working.
Emergency procedures
Ability to communicate with their workforce in order to carry out TRIC/Toolbox Talks"
NOTE: EPZ areas shall include an element(s) covering EPZ and Emergency Response
NOTE: Assessment for Licensing may take place before an individual is sent on a PTW Course, to
ensure that the candidate is suitable for the proposed role.
For consistency, the license should be authorised by the Chairperson of the Licensing Panel
(Production Coordinator or equivalent or delegate).
NOTE: For UIT, UIP,UWI and UIB personnel this should be a senior line representative
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
For Responsible Supervisors and Area Authorities, where the focus is on knowledge of the Plant &
processes under their responsibility, the Licenses are intended to be issued with Specific Area
coverage, or restrictions. After successful questioning, Responsible Supervisors and Area
Authorities may be issued with a License card for the area(s) in which they will work.
For Applicants and Holders, where the focus is on knowledge of the Hazards in 'their own work
discipline, the Licenses are intended to be issued with Specific coverage or restrictions on Types of
Work. After successful questioning, Applicants and Permit Holders may be issued with a licence
card for the type(s) of work under their control. It should be noted that a person holding a license for
a PTW Applicant should also be allowed to operate as a PTW Holder.
If an individual has a “roving” role (e.g. Metering Specialist, Well Services, NDT Specialist, and
Geomatics survey) this should be identified on the license for the individual.
If an individual changes employer, this should not affect his license qualifications, or require any
further licensing. The individual should be able to offer his existing license for immediate
replacement.
18.6 Re-licensing
Refresher training for PTW shall be undertaken as per PR-2234 for Process Safety Competency.
Since Licensing is an initial assessment of a person’s knowledge before he takes an active part in
the PTW System, re-licensing following refresher training is a much simpler process. The
assessment of a person’s continued ability to work adequately with the PTW System shall involve a
conversation with the Production Coordinator (or delegate) which is recorded on the Refresher
NFF.
Personnel must attend the appropriate PTW training course and be re-licensed by the Licensing
panel if:
A person who has attended the Permit Course is required to become an Area Authority,
Permit Applicant, Holder or Responsible Supervisor.
A person’s Line Manager believes that the individual would benefit from re-training in order
to become re-familiarised with the system.
If they cannot meet the requirements of PR-2234 for PTW Refresher
If the persons licence has been revoked and it is felt the person needs to undergo further
training and re-assessment.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The audit shall review the PDO PTW system in addition to a representative sample from
contractors with their own approved PTW systems. For example, the audit should review the
PDO PTW system, a PTW system from a well engineering contractor and one from the EMC.
The audit shall take place annually using the PTW Effectiveness Tool Appendix 9. The
assessment methodology/instructions can be found in the tool.
Any PTW system scoring 2 or less against any criteria in the effectiveness tool will constitute a
non-compliance. To ensure gap closure a PIM action shall be raised for any non-compliance to
one of the audited PTW systems. UOP6 shall be the post action approver for all PIM actions
raised during the PSBR 4 audit.
UOP6 shall issue a quarterly PSBR 4 audit report to share learning across all directorates using
a standard reporting template.
UOP6 shall incorporate lessons learned into the L2 PSBR 4 and AIPSM PTW audits as required.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
* NOTE: A non compliance is a deviation of unacceptable magnitude from the defined standard
which, unless corrected, may lead to a breakdown of the system.”
Corrective actions
An isolated minor non-compliance not repeated by the individual involved or in the area audited
should be raised as an observation but should not constitute non-compliance in the audit.
Non-compliances shall be categorised as follows:
PTW System Operation.
PTW System Requirements.
PTW System Documentation and Hardware.
PTW Training.
HSE Awareness.
Competency.
Motivation.
Information and Communication.
Management and Supervision.
Management of Contractors.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The Audit Authority shall ensure that all corrective actions are actioned, evidences and are
subject to regular monitoring.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Operational experience has shown that some of the Permit Type Certificates and Supplementary
Documents contained within the eVision ePTW system do not meet PDO’s current requirements, as
such the electronic version of the documents listed in the table below shall not be used.
The relevant procedure shall be followed for all documents listed above. Where associated with a
Class A or Class B ePTW the document type shall be mentioned in the job description, completed as
required, and kept at the work site with the printed copy of the ePTW. A copy of each completed
document shall be scanned and attached to the ePTW. On completion of the task the Permit Holder
shall ensure that the latest update to the documents has been scanned and attached to the ePTW
prior to job completing in the system.
Where an Electrical Safety Document is needed then this requirement shall be mentioned in the work
description of the associated Class A/B ePTW. The ePTW shall be issued as required and the
Electrical Safety Document shall be completed as per the Electrical Safety Rules. The Overhead Line
Clearance, Sanction for Test, Electrical Permit To Work and Limitation of Access check boxes on the
Class A/B ePTW shall not be used. On completion of the task the Permit Holder shall ensure that the
latest update to the documents has been scanned and attached to the ePTW prior to job completing
in the system.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Location of Work
Activity
Process Facility Hydrocarbon Area
1. Hot Work
Welding (Gas) / Oxy-Acetylene cutting (Hot Work) (1.1) (1.2)
+ CM
©PR-1146 ©PR-1146
Welding (Arc) (Hot Work) (See 13.6.1) (1.3) (1.4)
+ CM +
©PR-1146 ©PR-1146
Grinding (Hot Work) (1.5) (1.6)
+ CM + +
©PR-1146 ©PR-1146
2. Confined Space Work
Confined Space Entry, except for Well Cellars and Casasco pits. (2.1) (2.1)
Note-Gas testing in accordance with PDO policy is required. (See + CM + + CM+
4.3) ©PR-1148 ©PR-1148
Entry into Well Cellars (See 13.6.7) and Casasco Pits (See 13.5.2) (2.2) (2.2)
and excavations below 1.5m.
Entry into Well Cellars or Casasco pits by Area Authority to carry NPJ NPJ
out Operational Tasks to an approved procedure. + CM + CM
3. Electrical Work and Work in Electrical Areas (Section 13.9)
Work requiring an electrical safety document as specified in (3.1) (3.1)
Electrical Safety Rules (ESRs) ©PR-2331 ©PR-2331
The opening of live electrical junction boxes by Electrical (3.2) (3.2)
Authorised Persons
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Location of Work
Activity
Process Facility Hydrocarbon Area
4. Handling Hazardous Substances
Handling substances hazardous to health, e.g. toxic chemicals or
(4.1) (4.1)
asbestos
Use of Radioactive sources (See 13.6.12) (4.2) (4.2)
Contamination with Naturally Occurring Radiation Material (NORM) (4.3) (4.3)
Working with Pyrophoric Scale (except for scale encountered during (4.4) (4.5)
pigging operations) +
5. Work on Safety Systems (See 13.6.1)
Work that affects the availability of ESD & F&G Systems (5.1)
Work that affects the availability of Process and Machinery control N/A
(5.2)
systems
6. Mechanical Maintenance Activities (See Section 13 + 16)
Work that involves cold cutting pipe on systems containing (6.1) (6.1)
hydrocarbons or hazardous fluids + CM+ + CM+
©PR-1146 ©PR-1146
Work that involves unbolting flanges on systems containing
(6.2) (6.2)
hydrocarbons or hazardous fluids
Grit Blasting (Hot Work) (6.3)
(6.3)
+
Power/hand tools (except grinders) that may create a spark (6.4) (6.4)
between surface and tool + CM
High Pressure (HP) water jetting (6.5) (6.5)
Painting (hand and spray) (See 13.6.19) (6.6) (6.6)
Engineering and routine/corrective maintenance work which does
not involve unbolting flanges or cutting into systems which have (6.7) (6.7)
contained hydrocarbons or hazardous fluids
Work in authorised workshops located in non-hazardous areas. NPJ NPJ
Leak clamping of oil/gas flowlines (6.8) (6.8)
Beam pump/PCP maintenance activities (See 13.6.5) (6.9) (6.9)
Polyethylene lining of pipelines and flowlines (6.10) (6.11)
+
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Location of Work
Activity
Process Facility Hydrocarbon Area
6. Mechanical Maintenance Activities (See Section 13 + 16)
Vacuum tanker discharge inside a process area. (6.12)
NPJ
(See 13.6.10) + CM
Suction tanker operations inside a process area. (6.13)
NPJ
(See 13.6.10) + CM
Engineering and routine/corrective maintenance work which involves
(6.14) (6.14)
the use of lifting equipment
7. Work at Height
Working where a person may fall more than 2 meters, except on
(7.1) (7.1)
approved walkways and scaffolds
8. Scaffolding Activities
Erection or dismantling of scaffolding (8.1) (8.1)
9. Operations using Cranes and other Heavy Machinery
Operations where heavy machinery e.g. cranes/crane loads,
mechanical excavators, trucks etc. could pass over, or come into
contact with, live hydrocarbon, high pressure steam or chemical (9.1) (9.2)
systems or overhead power lines Gas testing requirements for any
diesel engine used is as per Activity Number (11.1)
10. Systems and Equipment Testing and Commissioning / Decommissioning
Pressure testing of plant and equipment (10.1) (10.1)
Commissioning Systems and Equipment (10.2) (10.2)
Decommissioning (10.3) (10.3)
11. Use of non-certified equipment in Hazardous Areas
Use of Temporary Diesel Engines in hazardous areas (including (11.1)
(11.1)
vehicle access, and the use of a mobile crane) (Including refuel + CM
operations) ©PR-1960
Use of non-Intrinsically Safe equipment (11.2) (11.2)
+ CM
Use of Intrinsically Safe test / portable equipment (11.3) NPJ
Use of cameras. Providing a gas detector is carried by an individual
who has been briefed in its use, and is able to demonstrate an
NPJ NPJ
understanding of the detector operation and actions to be taken on
CM CM
alarm activation. Flash requirements to be included on the access
authorization form
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Location of Work
Activity
Process Facility Hydrocarbon Area
11. Use of non-certified equipment in Hazardous Areas
Mobile diesel powered cleaning units used only by Area Authority NPJ NPJ
for external cleaning of water injection plant and equipment. + CM + CM
Use of GPS equipment that is Non I.S. on a well pad. Providing a
gas detector is carried by an individual who has been briefed in its NPJ NPJ
use, and is able to demonstrate an understanding of the detector + CM + CM
operation and actions to be taken on alarm activation
When GPS equipment used in a fenced Process area, 11.2 applies (11.2)
N/A
+ CM
12. Civil Works
Excavation. (Hand excavation to 300 mm depth is required in (12.1) (12.1)
areas where pipes or cables may be present) (See 13.6.11 +
©PR-1002 ©PR-1002
13.8.2)
Rebar cutting, bending and shuttering (form work) and concrete
(12.2) (12.2)
pouring
Engineering construction activities, not involving welding, burning
(12.3) (12.3)
or grinding (See Section 13.2)
Roadway Work for Levelling and grading using machinery (12.4) (12.4)
13. Operational Activities
Production operations including routine checks and visual
inspections by the Area Authority which require blowing down or NPJ NPJ
sampling of hydrocarbons (providing an approved Operating
Procedure is being followed)
Routine, documented drilling activities. (See Section 14) ©PR-1098
Well Services operations at locations where well site
custodianship has not been transferred to the Well Services (13.1) (13.1)
department. (See Section 15)
Drilling Water Services activities listed in Procedure DWSOP No
P033 (13.2) (13.2)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Location of Work
Activity
Process Facility Hydrocarbon Area
13. Operational Activities
Marine Operations. See Section 13.7
Government Gas Operations. See Section 13.8
Geomatic Survey (See Section 13.4) (13.5)
NPJ
Sampling of Process fluids where the fluids are classed as low,
high, or very high risk sour service, or are not yet classified and (13.6)
NPJ
the sampling is carried out using approved Production + CM
Chemistry procedures
Sampling of Process fluids where the fluids are classed as
sweet, and the sampling is carried out using approved (13.8) NPJ
Production Chemistry procedures. + CM
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Location of Work
Activity Hazardous Area Non Hazardous Area
(Zone 1 or 2)
15. ESP Activities
Meggar Testing HV – See Activity Number (16.1) No PTW Required.
Controlled by ESR’s
Fluid Shot (15.2) N/A
Electrical Isolation - HV No PTW Required. No PTW Required.
Controlled by ESR’s Controlled by ESR’s
Commissioning ESP, ESPCP & PCP (Will require gas test if breaking
(15.3) (15.3)
hydrocarbon envelope)
Trouble shooting ESP, ESPCP, & PCP (Controlled under ESRs. See No PTW Required. No PTW Required.
activity 16.1 No Permit Job to be signed by Electrical Supervisor) Controlled by ESR’s Controlled by ESR’s
ESP Powered by Generator (Controlled by ESRs See Activity No PTW Required.
(15.4)
Number (16.1)) Controlled by ESR’s
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Appendix 1.1 Notification of Work Activities (Not for use in Gas or EPZ Area)
02. Electrical
OHL HV Cable termination N/A
NoW
RA Code 18
0.3 Wells
ESP Troubleshooting. NoW
N/A
(Without electrical intervention) RA Code 2.0
Well static survey running gauge cutter NoW
N/A
RA Code 14
Sub-surface integrity test (SIT) NoW
N/A
RA Code 5.0
Well integrity test (WIT) NoW
N/A
RA Code 3.0
Beam Pump Maintenance NoW
N/A
RA Code 16
PCP Maintenance NoW
N/A
RA Code 17
Belt Replacement Activity for Rod Pumping NoW
N/A
Wells RA Code 24
Stuffing Box Packing Replacement Activity for NoW
N/A
Rod Pumping Wells RA Code 26
Horse Head Removal, Horse Head Installation NoW
N/A
and Horse Head Alignment RA Code 27
Pump Pressure Test "PPT"+ Troubleshooting NoW
N/A
trips for Rod Pumping Wells RA Code 28
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
04. Instrument
CP monitoring in Flow line and pipeline NoW
N/A
RA Code 10a
Cathodic protection Transformer monitoring NoW
N/A
and adjustment Functions RA Code 10b
05. Mechanical
Existing field flow line construction NoW
N/A
RA Code 7.0
New flow line construction in green field NoW
N/A
RA Code 8.0
06. SCADA
SCADA Maintenance NoW NoW
RA Code 1.0 RA Code 1.0
WIMAX Maintenance NoW NoW
RA Code 9.0 RA Code 9.0
WIMAX PM NoW NoW
RA Code 12a RA Code 12a
07. Scaffolding
Scaffolding for well pad non sour facility NoW NoW
RA Code 15.0 RA Code 15.0
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
daily permit and interface meetings. Activities, risk factors, interface concerns shall be
identified and resolved at the meeting.
When moving location e.g. Rig or Hoist, the contractor PTW system shall state that current
and known potential SIMOPS issues have been reviewed with the asset owner (normally
production operations) and actions agreed before any work is undertaken.
The SIMOPS document shall describe the audit and worksite visit framework that the
contractor will put in place as part of the assurance process.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The Contractor PTW system shall display their PTW activity matrix in the following table.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The Contractor PTW system shall meet the following requirements to be approved by the
PDO production function for operating an in-house PTW system use in PDO concession
areas. Checklist can be downloaded from LINK.
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Comments
Comments
Comments
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Appendix 4 - Daily log, Gas test record and E-PTW user guide
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Question Answer
1. What eye protection would be Wrap around one piece safety goggles
suitable for use during grinding or with mesh or perforated side
chipping operations? ventilation
2. What eye protection would be Optical filter goggles or face shields to
suitable for use during welding or reduce radiation to a safe level.
burning operations?
3. What eye protection would be Visors which fit to a head harness or
suitable for use during chemical safety helmet to protect face from
handling operations? splashes
4. What type of hearing defenders Ear muffs
offer the best protection against all
general noise attenuation?
5. What footwear should be used to Industrial class safety boots with steel
protect the wearer from the impact toe cap protection.
of heavy objects?
6. What footwear should be used to Plastic and synthetic rubber. Integral
protect the wearer from contact tongue construction to prevent liquids
with chemicals? going through laceholes
7. What gloves should be used to High Insulated as per BS 647
protect the wearer from electricity?
8. When using a hand held power drill Safety glasses or goggles
in a workshop, what protective
equipment should be worn?
9. Panel to include area specific
questions
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
FIRST AID
Question Answer
1. How often should the water in eye Every 3 months
baths be replaced?
2. What is meant by First Aid? Immediate treatment at the scene of
accident only
3. What is the aim of resuscitation? To prevent damage to the brain and
other vital organs caused by lack of
oxygen.
4. If battery acid is spilled on the skin, Wash affected area with copious
what first aid action should be amounts of fresh water then seek
taken? medical advice.
5. What first aid treatment should be Wash under cold running water to
carried out on a skin burn if the skin remove heat for at least 10 min.
is not broken?
6. Give the four ways by which a Inhalation; Ingestion; Injection;
chemical/harmful substance may Absorption
enter the body?
7. What four factors influence the Duration of exposure; nature of
harmful effects of chemical chemical; amount entering the body;
poisoning? susceptibility of individual
8. If you see someone has been Ensure your own safety first
injured what steps should you
Raise the alarm
take?
Apply first aid
Inform supervisor/doctor
9. Panel to include area specific
questions
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Question Answer
1. Do explosimeters measure gas Gas concentration as a percentage of
volume or gas concentration? LEL (Lower explosive Limit).
2. Why doesn't a gas sample above Not enough oxygen to support
its UEL burn? combustion/Too much fuel (too rich to
burn)
3. What kind of extinguisher should BCF/CO2/DCP
be used to combat a small fire in a
vehicle engine compartment?
4. A BCF fire extinguisher could be True
used on a car engine fire; True or
False?
5. What should you do in the event
you see a fire in a PDO facility?
6. Smoking may take place in an area False
where Hot Work (welding, burning
etc.) is being conducted. True or
False?
7. What should you do in the event
that an alarm sounds on your gas
monitor?
8. Panel to include area specific
questions
Question Answer
1. When stepping from a ladder onto Down
a working platform, should you step
up or down?
2. One hand may be used for carrying False: both hands must be free to hold
tools when climbing a ladder; True the ladder
or False?
3. Why should each limb be on a In case of rung-breaks
different rung when climbing a
ladder?
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Question Answer
4. What work may be done from a Light work; with one hand; no over
ladder (3)? reaching
5. Should ladders be used as a Never: can fall through or off, or ladder
bridge? may slip
6. What footwear is suitable for Safety footwear
climbing ladders?
7. How would you turn round when You must not! Obtain other means of
working on a ladder? access
8. Is it safe to reach through the rungs No
of a ladder?
9. Name 4 precautions you should Secure; no side overhang; rear
take when transporting a ladder in overhang minimum and flagged; no
a pick-up? articles on top of ladder
10. What colour is a container for Red
carrying additional petrol on
vehicles?
11. What colour is- a container far Green
carrying additional lube oil on
vehicles?
12. What is a first aid accident? Work-related incident resulting in
medical treatment for an employee
who is able to resume his work within
24 Hours
13. What precautions are to be taken Secured near top or ensure it is footed.
when setting up a ladder for use?
14. When wearing a harness, where Always above, and to a piece of
would you attach it? permanent structure
15. Panel to include area specific
questions
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
PROCESS SAFETY
Question Answer
1. When is single" or double valve When it is relied upon as a means of
isolation not considered to be an isolation for the purpose of entry by
adequate form of isolation? personnel into tanks or vessels
2. What preparations must be carried Isolate at Wellhead, depressurise,
out before cold cutting into drain and purge
flowline?
3. When emptying a tanker into a Ensure tanker is connected to earthing
'saver pit' what precautions must bond to prevent sparking
be taken?
4. What should be the first move to Close isolating valves at the wellhead
combat a leaking flowline? and manifold
5. When is a tank/vessel considered When it contains greater than 96%
to be inert? Inert gas (Nitrogen)
6. What is the first step when Prepare a venting procedure
instructed to vent a vessel or
process equipment?
7. What 2 precautions should be Adjust flow rates to prevent freezing of
taken during venting a vessel or control valves; avoid skin contact with
process equipment? vent lines
8. What is the first step when Prepare a venting/draining procedure
instructed to vent or drain
condensate?
9. Why do we report all Actual, To learn and put measures in place to
Potential, and Near Miss incident prevent it happening again
10. What type of gas meter would you One that measure Hydrocarbon in inert
use on a system where Nitrogen is atmosphere not a normal multi gas
present meter
11. Panel to include area specific
questions
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Required
Activity Brief Description Location
Certificates/ Permits
Gas leak detection Detect gas leaks by a UAS mounted with On-plot & Off-plot NSA, CAA, PDO
OGI sensor
Oil Leak Detection Detect and locate the oil leaks locations Off-plot NSA, CAA, PDO
Flare Tip Inspection Flare inspection for any damages and On-plot NSA, CAA, PDO
anomalies in the tip
Internal Tank Using special caged drone to inspect the On-plot PDO
Inspection tank from inside for any damages or
anomalies
External Tank Tank inspection from outside using visual On-plot NSA, CAA, PDO
Inspection & thermal payload to detect and damages
or anomalies in the tank
Power Overhead line Inspection for any anomalies such as Off-plot NSA, CAA, PDO,
Inspection cracks, hotspots, and bird nest along the Overhead Line
powerline Clearance
Ground Penetrating Using GPR to detect objects and mapping On-plot & Off-plot NSA, CAA, PDO
Rader Survey underground infrastructures
Vent Stack Inspection Using Visual & Thermal payload to detect Off-plot NSA, CAA, PDO
anomalies and damages in the vent stack
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Revision 6.3
Petroleum Development Oman LLC Effective: Sept-22
Chimney Inspection Using Visual & Thermal payload to detect On-plot & Off-plot NSA, CAA, PDO
any damages or anomalies in the Chimney
Block valve station Using Visual & Thermal payload to detect Off-plot NSA, CAA, PDO
and damages or anomalies in the BVS
Internal Pipe Using special caged drone to inspect the On-plot & Off-plot PDO
Inspection pipeline from inside for any damages or
anomalies
Solar Panel Inspection Using Visual & Thermal payload to detect On-plot & Off-plot NSA, CAA, PDO
and hotspots or dust accumulation in the
solar panels
Telecom Tower Using Visual & Thermal payload to detect On-plot & Off-plot NSA, CAA, PDO
Inspection any damages or anomalies in the tower
Rig Mast Inspection Using Visual & Thermal payload to detect Off-plot NSA, CAA, PDO
any damages or anomalies in the Rig
Right of way Using fixed wing UAS to inspect the Off-plot NSA, CAA, PDO
Inspection pipelines and surrounding area for any
defects or unauthorized activates
Flow Line Inspection Using Visual payload to detect any Off-plot NSA, CAA, PDO
damages or anomalies or leaks along the
flow lines
Route survey Using Fixed wing UAS integrated with PPK Off-plot NSA, CAA, PDO
to survey the wanted route survey
Topographic survey Using Fixed wing UAS integrated with PPK On-plot & Off-plot NSA, CAA, PDO
along with control points to survey the
area and produce Ortho -DSM -DTM
As built survey Using Fixed wing UAS integrated with PPK On-plot & Off-plot NSA, CAA, PDO
along with control points to survey the
area and produce Ortho -DSM -DTM
Aerial shooting Using HD camera payload to capture On-plot & Off-plot NSA, CAA, PDO
videos - Photos and panoramic view
LaiDAr Survey Using high accuracy LaiDAr sensor On-plot & Off-plot NSA, CAA, PDO
integrated with UAS to survey the area
Sludge Measurement Using Thermal payload to detect the tank On-plot & Off-plot NSA, CAA, PDO
sludge level from outside and measure the
volume using sophisticated algorithm
accordingly
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.