CONSTRUCTION SCHEDULE PLAN ( Scaffolding Work )

Site Preparation
2019
ESTIMATION NOVEMBER DECEMBER
NO. DESCRIPTION DATE REMARKS
WEEK 2 WEEK3 WEEK 4 WEEK 5 WEEK 6 WEEK 7 WEEK 8 WEEK 9

FROM TO 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

A Material Arrival 28/10/19


B Shop Fabrication 04/11/19
C Field Erection 22/11/19
1 Preparation Work
1.1 Manpower Scaffolding 14/11/19
( with Certificate )
1.2 Manpower Induction 18/11/19 18/11/19
1.3 Material Scaffolding 18/11/19
( Cerificate )
1.4 Inspection & Delivery to Field 20/11/19

2 Work Setting Area


2.1 PIPERACK Area C1 22/11/19
2.2 PIPERACK Area B1-B6 4 GROUP
2.3 PIPERACK Area A1- A5
2.4 PIPERACK Area F1
2.5 PIPERACK Area E1
2.6 PIPERACK Area H3
2.7 PIPERACK Area PR. O - PR.5
2.8 PIPERACK Area SOUTH NEW
2.9 PIPERACK Area D1A NEW
2.10 PIPERACK Area NORTH NEW
2.11 PIPERACK Area C5 NEW
2.12 PIPERACK Area F3 NEW
3 Dismantling & Demob.