Method of Construction
Method of Construction
Getting rights of the land – The Municipal Commission in the area plays its role and there are
many laws pertaining to this.
Plan and Sanction of Plan – The built up area and the plans are generated (Vastu is a very
important part along with the National Building Codes along with Indian Standards)and they
have to be sanctioned by the Municipal Engineer.
Passing of Soil tests from Municipal boy and commencement of construction -The
commencement of construction is marked by setting out gridlines at the site by a surveyor with
the help of coordinate control points.This is very important so as to mimic the plan drawing at
the plan. The footing locations are also marked with lime powder.
Excavation-Footings locations are excavated till the required depth of the foundation and the
bottom bars of the footing are set in place after the formwork has been set.
Column casting – After the footings has initial set (after a period of a day) the column formwork
is put in place starting from the column starter and the column is pored with concrete till the
level of the ground beams.
Ground/Tie Beams – After a period of a day the column is stripped of the form-work and form-
work is also removed from the footing and the ground is back filled till the level of the ground
beams.
The ground beam reinforcements re arranged and in the same way casting is done and vibrated.
Damp proof Course- after the ground beam has been cast damp proof courses are
provided(Bituminous) and then the ground slab is put in place consisting of rubbles and then the
ground slab is cast after the reinforcement has been place.
The columns are constructed till the first floor level and the staircase reinforcement are placed
and the stairs constructed till the first floor
The Primary and the Secondary beams are then put into place along with the slab reinforcements
as in monolithic construction.
The stairs reinforcements for the second floor are then arranged and concreting is done.
Meanwhile brick masonry for the walls are done along with placing of lintel beams and door and
window frames are put in place.
after the roof slab has been constructed screed concreting is done so that rainwater doesn’t cause
efflorescence as the process of screed concreting (1:450)is essentially sloping so that the roof
water flows in desired direction.