BT Cocoa
BT Cocoa
A PERPERTAION WORK
1 Survey & Measurement ls
2 Design Drawing ls
3 Shop Drawing & As-Built Drawing ls
4 Mobilitation Tool & Man Power ls
5 Temporary Platform ls
6 Temporary Isolation Chamber ls
7 Temporary Power Outlet Panel ls
8 Portable Exhaust Fan & Support Installation ls
9 Tool & Supporting Material ls
B CIVIL WORK
B.1 Concrete Dismantling Work
1 Marking & Cutting Concrete Floor ls
2 Floor Concrete Dismantling and Finishing ls
3 Pipe Casing and Support Installation Ea
4 Concrete Dismantling Disposal ls
C MODIFICATION WORK
1 Reducer Fitting Magnetic Rotary
- Flange Up Machine Plate t.3x400x660 Ea
- Plate Roll Reducer Plate t.3 ( Cone ) Ea
No Uraian Pekerjaan Satuan
D FINISING
1 Temporary Partition Chamber Dismantling ls
2 Temporary Platform Dismantling ls
3 Final Clearing Area ls
4 Mobilitation Tool & Man Power ls
TOTAL :
PPN 10% :
GRAND TOTAL (RP) :
(BT COCOA)
101,075,000.00
10,107,500.00
111,182,500.00