You are on page 1of 2

Enter Your House Built up Area in Sq ft R

S. Percentage For a 1000 sq ft Enter Your House Area


Item of work
No. of total work house in Sq ft

Construction
Rate per Sq ft
1100 1,000 700

Excavation in ordinary soil


1 3% 33,000 23,100
and concrete
2 Foundation 5% 55,000 38,500
3
Construction upto plinth 5% 55,000 38,500

Superstructure in
4 25% 275,000 192,500
brickwork
Roofing including
5 17% 187,000 130,900
waterproofing
6 Flooring 6% 66,000 46,200
Wood work i.e. Joinery,
7 13% 143,000 100,100
doors and windows
8 Internal finishes 6% 66,000 46,200
9 External finishes 3% 33,000 23,100
10 Water supply 4% 44,000 30,800
11 Sanitary work 8% 88,000 61,600
12 Electrification 5% 55,000 38,500
13 Total 100% 1,100,000 770,000
ea in Sq ft Red Color Area
S.No.
Requirement Unit of Approx Approx
of Materia measurement Quantity Qyt for Qyt for
cu. ft cu. ft

Area of Construction in Sq ft 1000 700

1 Cement Bags/sqft 0.4 400 280

2 Sand (cu ft) Cut/sqft 1.81 1,810 1,267


Aggregate (cu
3 Cut/sqft 1.14 1140 798
ft)

4 Bricks Nos/Sqft 34 34000 23800

5 Size Stone Nos/Sq ft 11 11000 7700

6 Steel Kg/Sqft 2.1 2100 1470

7 Wood CuF/Sqft 0.077 77 53.9