Professional Documents
Culture Documents
SKAA 3022
WATER RETICULATION
SYSTEM DESIGN
Prepared By:
Page 1
INTEGRATED DESIGN PROJECT 2 SKAA 3022
3.0 CONCLUSION
LIST OF TABLES
Page 2
INTEGRATED DESIGN PROJECT 2 SKAA 3022
LIST OF FIGURES
Page 3
INTEGRATED DESIGN PROJECT 2 SKAA 3022
LIST OF ABBREVIATIONS
Page 4
INTEGRATED DESIGN PROJECT 2 SKAA 3022
LIST OF APPENDICES
4.0 APPENDIX
4.1 List Of Appendix
4.1.1 Appendix 1 – Layout Plan Of Peak Flow & Fire
Flow 1
4.1.2 Appendix 2 – Layout Plan Of Peak Flow & Fire
Flow 2
4.1.3 Appendix 3– Layout Plan Of Peak Flow
4.1.4 Appendix 4– Layout Plan Of Fire Flow 2
4.1.5 Appendix 5–Table A1 Minimum Residual
Pressure Head Requirement
4.1.6 Appendix 6–Table A2 Average Domestic Flow
Page 5
INTEGRATED DESIGN PROJECT 2 SKAA 3022
Page 6
INTEGRATED DESIGN PROJECT 2 SKAA 3022
CHAPTER 1
Water affects the life of every human on Earth. The daily water demand and
water distribution system is needed to transport water from a source to a consumer.
Therefore, the system has to be designed to consistently provide water in sufficient
quantity to users at an acceptable pressure as economically as possible. This
dissertation is about the design of the system for the “Permohonan Kebenaran
Merancang Mengikut Seksyen 21, Akta Perancangan Bandar Dan Desa 1976 (Akta
172)”. The design is based on Malaysia Jabatan Kerja Raya (JKR) Standards, which
was adapter to MWA Design Guidelines for Water Supply Systems. The size and type
of pipes were determined to meet the requirement of the standards. Several demand
scenarios were analyzed for the system such as average daily demand, peak hour
demand and critical demand at junction.
1.1 Introduction
Page 7
INTEGRATED DESIGN PROJECT 2 SKAA 3022
There are two types of pipe network system which are close loop system and
open end system. The requirement for this system depends on the number of the
buildings and for the consumer. With regard to close loop system, it is a pipe network
that used by various consumers and involved many facilities which needs more
distribution from the main pipe. Normally this system is more popular because it is
more efficient compared to the other. In case if pipe leaking occurred, it will not affect
the whole pipe network and only a certain part of this pie will be close. Thus, water
will distributes to consumer through the other alternative pipes. For the open end
system, it is used by single facilities (consumer) such as hotel, factory, school and
other premises. The problem with this system is if leaking occurs, it will affect the
whole system and the consumer would not get the water supply when the valve is
closed.
The design for water reticulation needs to fulfill all the requirements and water
guidelines that had been set up and standardized by the state water authority and
following JKR standards that is applied by Malaysian Water Association (MWA)
which is the “Design Guidelines For Water Supply Systems” and “Uniform Technical
Guidelines Water Reticulation And Plumbing” by Suruhanjaya Perkhidmatan Air
Negara (SPAN).
Page 8
INTEGRATED DESIGN PROJECT 2 SKAA 3022
A water supply distribution system may be classified into three typical types:
i. Gravity system
ii. Pumped system
iii. Combined gravity and pumped system
Page 9
INTEGRATED DESIGN PROJECT 2 SKAA 3022
There are various types of systems used in water distribution network, such
as dead end system, the close loop ring system, basic system, grid system, and radial
system.
Pipes, lining materials and joints used in water supply system works must not
cause a water quality hazard. Types of pipes commonly used in waterworks are
generally of the following materials:
Page 10
INTEGRATED DESIGN PROJECT 2 SKAA 3022
a) All pipe materials is using 150mm HDPE and 200mm M.S. pipe and shall
comply with the current Malaysian Standard or Local Authority.
b) Air valve shall be provided at peak/low points or drain/culvert crossing.
c) Adequate in line valves shall be provided to isolate sections of main to
facilitate maintenance.
d) Approved type of precast valve chambers shall be used
Page 11
INTEGRATED DESIGN PROJECT 2 SKAA 3022
the Project is 4.20 hectare which consists of 1 unit hotel with 400 rooms, 1 blocks of
condominium with 96 units and 2 blocks of shop lot with 130 units.
1.10 Objectives
Page 12
INTEGRATED DESIGN PROJECT 2 SKAA 3022
Standards and Malaysia Jabatan Kerja Raya (JKR) Standards, which was adapter to
MWA Design Guidelines for Water Supply System. Our main objectives is to design
the water reticulation system for the development as follows:
i. To design the size and to determine the storage capacity of the water tank.
ii. To determine the most economical size of water tank and pipes.
iii. To determine the water flow in each pipe.
iv. To ensure the residual pressure heads in both peak flow and fire flow
condition are satisfying.
v. To ensure the maximum flow velocity of 2.6 m/s is not surpassed.
vi. To determine the appropriate location of water tank, valves and fire
hydrants.
Page 13
INTEGRATED DESIGN PROJECT 2 SKAA 3022
CHAPTER 2
10.69 L Q1.85
hf = C1.85 D4.87
Where,
hf = head loss due to pipe friction, (m/km)
Q = Design flow, (m3/s)
C = pipe coefficient
D = internal diameter of pipe, (m)
Page 15
INTEGRATED DESIGN PROJECT 2 SKAA 3022
xiii. Air valves shall be installed at highest points, points that constitute
changes of direction and slope. For position of long
descending/ascending pipeline, the spacing shall be < 100m.
xiv. Scour valve shall be installed at lowest point in pipeline. Its size shall be
one third of pipeline diameter.
xv. Minimum riser for culvert crossing shall be 300mm.
xvi. Minimum hydraulic gradient in pipeline shall not fall below than 5.0 m
to the crown of the pipeline to avoid air pocket and column separation.
The procedures used in the design of water system for the proposed
project are follows:
i. Source of supply
In the project, the water is supplied by a tapping off point
from the water main that lay along the main road, which is
Jalan Mentigi and near Cameron Highland District Council
about 100 meters.
ii. Calculate the number of type of units shop lot and public facilities
& infrastructure. The number of type of building unit set out in the
site layout plan is used to estimate the water demand.
Page 16
INTEGRATED DESIGN PROJECT 2 SKAA 3022
W = ∑ (N X C) X F + Da
Where:
W = Average daily water demand
N = number of type of house
C = per unit consumption
P = service factor
Da = Additional water demand
Page 17
INTEGRATED DESIGN PROJECT 2 SKAA 3022
Average Water
Total Demand
No. Premises Type Demand / Unit Qty Unit Unit/ Day
Liter Gallon Liter Gallon
1 Hotel 1500 330 160 room 240000 52800
2 Condo @ Service Apartment 2000 440 270 unit 540000 118800
3 Business Lot (2 story) 3000 660 20 unit 60000 13200
Total 840000 184800
Page 18
INTEGRATED DESIGN PROJECT 2 SKAA 3022
must be considered for the design purpose. Refer Table 2.2 that outline in the
JKR Standards, the recommended risk category of fire flow requirement is
Class A Risk with the average total flow 4100 liter/min and the maximum
number of hydrant outlets used simultaneously is one unit. Moreover, the JKR
Pahang Standard recommends that the water of fire flow requirement is
discharge in 50 minutes duration with average flow 68.33 liter/second.
Page 20
INTEGRATED DESIGN PROJECT 2 SKAA 3022
The maximum velocity in the pipe are 2.6 m/s and its being use to
avoiding erosion in the extreme flow.
10.69 L Q1.85
hf = C1.85 D4.87
Where,
hf = head loss due to pipe friction, (m/km)
Q = Design flow, (m3/s)
C = pipe coefficient
D = internal diameter of pipe, (m)
Page 21
INTEGRATED DESIGN PROJECT 2 SKAA 3022
Page 22
INTEGRATED DESIGN PROJECT 2 SKAA 3022
CHAPTER 3
CONCLUSION
Based on the analysis made, the use of Reinforced Concrete Mushroom Tank
is necessary because of the total water demand for this proposed development site is
637,080 liters/day. The proposed tank size is 30 metres in diameter with the tank
height of 6 meter. The tank should be built with an elevated height of 10.6 meter from
the ground level to ensure sufficient water pressure for each of the premises. There are
2 types of pipe material used which is HDPE Pipe for peak flow and M.S. Pipe for
Fire Flow. All pipes are laid at 1 meter below ground level. The use of suction tank or
pump is not necessary because the water pressure inside the water tank is more than
7.62 meter. Fire Hydrant are placed at the suitable part of the node and following the
standard requirement of Fire Department to accommodates to the entire of the areas if
the fire happens to occurs. Schematic Plan and Layout Drawing includes all the pipe
Page 23
INTEGRATED DESIGN PROJECT 2 SKAA 3022
sizes, node numbers, pipe length, pressure head and demand flows for both peak and
fire flow.
Reference
The water reticulation system shall be designed in accordance with the following
guidelines:
“Design Guidelines For Water Supply Systems” by Malaysian Water
Association (MWA)
Uniform Technical Guideline Water Reticulation & Plumbing published by
Suruhanjaya Perkhidmatan Air Negara (SPAN)
Page 24