Professional Documents
Culture Documents
PRE CH APP
REV. DATE DESCRIPTION P. EC. R.
Dragon’s Eye Golf Club
Table of Contents
1. INTRODUCTION........................................................................................................ 3
1.1. Intent of the Works........................................................................................................... 3
1.2. Base Plan & Proposal Plan..............................................................................................4
1.3. Specification & Target Dates............................................................................................ 4
1.4. Title, Parties, and Project Team.......................................................................................7
APPENDIX TO THE CONDITIONS OF CONTRACT......................................................................
AGREEMENT..................................................................................................................................
2. GENERAL CONDITIONS...........................................................................................8
2.1. Contractor's Site Assessment...........................................................................................8
2.2. The Designer.................................................................................................................... 8
2.3. Contract Drawings............................................................................................................ 8
2.4. The Project Manager........................................................................................................ 9
2.5. Site Supervision............................................................................................................... 9
2.6. Programmes..................................................................................................................... 9
2.7. Meetings & Communications........................................................................................... 9
2.8. Monitoring of Programme................................................................................................ 9
2.9. Health and Safety at Work etc.......................................................................................10
2.10. Workmanship & Materials.............................................................................................. 10
2.11. General Site Practice..................................................................................................... 11
2.12. Records Plans................................................................................................................ 12
3. PROGRAMME OF WORKS.....................................................................................13
4. TECHNICAL SPECIFICATIONS...............................................................................14
4.1. Initial Work..................................................................................................................... 14
4.2. Topsoil & Ground Conditions.......................................................................................... 17
4.3. Earthworks, Excavation & Carting.................................................................................19
4.4. Water Feature Construction........................................................................................... 23
4.5. Drainage & Trenching Work........................................................................................... 26
4.6. Fairway Contouring & Fairway Feature Construction.....................................................31
4.7. Construction of Greens Complexes and Tees................................................................33
4.8. Sand Handling & Spreading........................................................................................... 41
4.9. Fairway, Feature & Rough Seedbed Preparation...........................................................43
4.10. Seeding, Sprigging & Turfing......................................................................................... 45
4.11. Cart-path Construction................................................................................................... 51
4.12. Landscaping Works........................................................................................................ 53
4.13. Other Works................................................................................................................... 58
5. Drawings & Appendices Schedule........................................................................61
5.1. APPENDIX 1 – Schedule of Areas and Volumes...........................................................63
5.2. Bills of Quantities........................................................................................................... 63
5.3. Schedule of Dayworks.................................................................................................... 67
5.4. Labour............................................................................................................................ 68
6. Form of Tender...........................................................................................................
6.1. APPENDIX 1 to the Form of Tender...................................................................................
6.2. APPENDIX 2 to the Form of Tender...................................................................................
6.3. APPENDIX 3 to the Form of Tender...................................................................................
Dragon’s Eye Golf Club
1. INTRODUCTION
1.1. Introduction and Intent of the Works
Dragon’s Eye Golf Club lies within the proposed Kovai Hills Resort, a new
prestige leisure, residential and Commercial Township on the outskirts of
Coimbatore, second largest city in the state of Tamil Nadu, India. The
Resort will encompass a hotel, spa, hospital, golf course with clubhouse
and golf academy, as well as villas and office accommodation.
Coimbatore, the ‘Manchester of the South’, is situated at an elevation of
about 400 metres. The temperature during both summers and winters
varies anywhere between 37 'C to 25 'C. The highest temperature is 41°C
and lowest is 12°C.
Due to the presence of the mountains and passes, major parts of the area
benefit from the south-western monsoon in the months from June to
August. After a warm, humid September, the regular monsoon starts from
October lasting till early November. These monsoons are brought about by
the retreating north-eastern monsoon. Annual rainfall is around 61cm.
The intention at Kovai Hills Resort is to form an international-standard golf
course constructed and presented to the highest level, and suitable for the
playing of championship-level golf and also good, testing, but fair golf for a
clientele of international golf tourists and Indian golfers.
The course on plan measures over 7,000 yards, Par 72 from the back tees,
with the holes featuring water, trees, and varied slopes to influence strategy
and variety. This minimum length must be preserved during construction.
Academy facilities will include a 9-hole pitch-and-putt course, 60-bay
double-deck driving range (constructed by others), practice putting/chipping
areas and mini-golf (family ’crazy-golf’).
Construction methods, workmanship and quality of finish shall allow the
golf course to be capable of being efficiently maintained to a high,
international quality using standard maintenance equipment and methods.
Part 1 of this Specification covers general construction works, Part 2 of the
Specification covers the irrigation system supply and installation works,
which overlaps with Part 1 primarily on the on the arrangement for
trenching works. The work is currently programmed for three phases of
execution.
Access, climatic, soils and other information can be provided through the
Client:
Rakindo Developers Private Ltd
No. 1 Subbaraya Avenue,
Alwarpet,
Chennai
India – 600 018.
Dragon’s Eye Golf Club -4-
1.5 Specification
The work consists of the following basic elements:
NB – Earthworks Strategy
Excess soil from the driving range recontouring and area of holes 1 to 3, 9 to 18 is
to be excavated and carted to the bedrock areas on the golf course area Holes 4 to
8. The programming of this shall be agreed before construction begins with the
Designer.
Dragon’s Eye Golf Club -7-
Parties:
a) The Client is:
Rakindo Developers Private Ltd
Of:
No. 1 Subbaraya Avenue,
Alwarpet,
Chennai
India – 600 018.
Of:
2. GENERAL CONDITIONS
2.1. Contractor's Site Assessment
The Contractor must check all key conditions on site, and shall make
such allowance in his tender as he deems necessary at his sole
discretion to carry out the completion of the contract in accordance
with the Contract Documents and to the complete satisfaction of the
Project Manager and Designer.
No claim on the grounds of lack of knowledge of such conditions will
be considered.
2.6. Programmes
The intended Construction Programme, provided by the Designer and
Project Manager in conjunction with the Contractor, expresses the key
dates related to the Works. This programme must be adhered to since
it provides the interface with the other Contractors and the overall
programme, which includes other aspects. This overall project
programme is available for inspection, and will be amended jointly by
the above parties on agreement, as the work progresses.
The Contractor must in turn provide with his tender details of the
proposed completion dates of particular items, and a method
statement that describes how the item is to be carried out. Throughout
the progress of the project, the Contractor shall provide regular and
updated programmes and schedules of completion of work stages and
working areas, and on delivery times for supplies and materials.
The Designer and Project Manager are empowered to object to, and may
require removal from the Site of any person employed by the Contractor
who, in the opinion of the Designer or Project Manager, is incompetent,
negligent, abusive, or commits misconduct in the performance of his
duties, or fails to conform with the requirements of site safety policy. Such
person shall not be employed again upon the Construction Contract
without the written permission of the Project Manager.
3. PROGRAMME OF WORKS
The intended programme for completion of the works is as follows.
There are inherent links between golf and villa plot programming with
effects and implications to be determined:
4. TECHNICAL SPECIFICATIONS
IMPORTANT NOTE:
All proposed levels given on plan refer nominally to the finished levels
in the topsoil layer, root zone level, or bunker sand level following
completion of the construction works. The Contractor shall take this
into account when carrying out the recontouring works.
Final ground levels may be vary from those proposed, following, and in
accordance with, the topsoil/sand placement details. It will be
necessary to pay particular attention to working-in re-contoured land
levels with surrounding tree-trunk levels. If in doubt, the Designer
should be consulted on the finished levels required.
Each stake shall be marked with black waterproof marker pen "Tee/Hole
No.", "Turning Point/Hole No.", and "Green/Hole No.".
In addition, key stakes are to have supplementary locating pegs, being 4
number iron re-bar set concrete, in a square away from the stake, thus
forming two diagonals from which the main stake can be re-set if disturbed.
All stations, stakes and pegs shall be preserved by the Contractor for their
and the Designer's use in locating all work under this Section. The
Contractor shall provide additional staking to further describe the work or to
indicate minor changes to be made in the limits of cut or fill areas, and
other areas.
Dragon’s Eye Golf Club - 15 -
As shown on the Staking and Clearing Plan, clearing work will be required
over the whole golf area, but there are only small areas of dense scrub to
clear. Otherwise the work is expected to be limited to open scrubland
clearance, and semi-mature tree removal. Trees to be preserved and/or
pruned shall be marked on site by the Project Manager.
The stumps and full root system to a depth of 1.0 metre shall be thoroughly
grubbed-out for every felled tree. All trunks, stumps and trimmings are to
be carted to an agreed and approved central storage point for disposal by
an agreed method.
A rate shall be given per mature retained tree for crown-lifting and pruning
by a professional tree surgeon, to be approved or requested on site by the
Project Manager..
The Contractor is to provide a price for :
Clearing and Felling
i) Thinning – zones as marked on plan to be thinned to allow mowing
equipment to pass around the remaining trees and bushes
ii) Crown lifting & Pruning; Deciduous tree
c) Protection of services
Services within and around the working site are to be marked clearly along
the full length to protect poles and wires, and restrict working under the
cables and over pipelines, preserving an adequate safety margin. The
Contractor must liaise with the service owner to determine how these lines
should be treated and safety measures to be taken.
Dragon’s Eye Golf Club - 16 -
c) Topsoil screening
A proportion of topsoil is to be screened on site to remove all but the
smallest stones, and used during the fine finishing works to greens aprons
and other key areas. If any clean soil is found on site (stone free siltation
soil from valley areas, etc.), this shall be reported to the Project Manager
who may choose to retain this in lieu of a proportion of the screening work.
4.2.2 Existing Topsoil Cleaning
Where topsoil is not to be lifted or moved, and following general clearance
and construction work, the existing soil is to be cleaned by removal of all
large rocks over 100mm in size, and tree/bush stumps and roots. All
efforts must be taken to retain as much topsoil in the process as possible.
Roots shall be lifted and carted to an agreed tip or certified burning point.
The soil should be mechanically raked to pull-up rocks from the top 200-
300mm, with these rocks being collected, loaded and carted to on-site
disposal points as agreed with the Project Manager.
4.2.3 Carting of Materials and Quality
Prior to stripping and/or hauling of the excess topsoil and subsoil, the
Contractor shall receive approval from the Project Manager for the point of
deposition for each type and quality of material, in accordance with an
earthworks and material carting strategy to be drawn-up and agreed by the
Contractor and Project Manager.
Material gathered from the site prior to and during topsoil handling shall be
deposited in accordance with a programme agreed with the Project
Manager.
4.2.4 Soil material imported from Non-golf zones on Site
Soil material from other parts of the site (built areas) may be made
available for use within golf areas. The Contractor shall include for
handling this material from within the golf area boundary for inclusion on
the golf course earthworks strategy. The Contractor shall discuss and
clarify this point with the Project Manager prior to beginning construction
works.
Dragon’s Eye Golf Club - 19 -
to execute the work. The intent of the Recon touring Plan is only to
assist the Contractor to make his own calculations. No guarantee of
accuracy of total quantity or quality of cut/fill and borrow material
available at each site is made, but instead only estimates based on
plan and surface observation. Unless otherwise stated, the Contractor
shall assume that no fill material will need to be imported and the cut/fill
balance will be obtained from within the site area
6) General Fill Material - This material will include existing subsoil, small
stones and rocks, but will expressly exclude rocks in excess of 100mm
maximum dimension, and any material of an organic nature.
Excavation shall be carried out with soil material being kept separate from
rock material wherever possible, to allow the latter to be covered over with
a screen of soil material as described above.
4.3.4 Borrow Areas
Borrow areas are to be used as a source of suitable, stable fill material for
stockpiles at green, tee, fairway bunker and mound sites, and as
necessary for filling other areas on the golf course.
All borrow area extents shall receive prior approval from the Designer on
position and amount of fill to be taken, and for all changes, additions
deletions and adjustments in area, depth, and quality of material that are
contemplated.
4.3.5 Quality of Material
All unclassified fill material removed from borrow areas and used for
feature stockpiles and other fill shall be stable, suitable material reasonably
free from boulders and any foreign matter which would otherwise restrict its
use for the shaping of golf course features.
The Contractor shall immediately bring to the attention of the Designer or
Project Manager any unforeseen and unsuitable matter, or excessively
hard-dig conditions discovered during his work before proceeding further.
4.3.6 Fill Stockpiles
Other than excess topsoil material, the lakes, in-situ cut & fill, and other
borrow areas as designated on site by the Designer and/or Project
Manager are to provide the fill material for the golf features. Approximate
fill requirement is shown on the Re-contouring Plan, and schedule of cut/fill
volumes for each feature.
Load and cart fill material from source areas to golf features:
a) At green sites requiring fill, unclassified fill material shall be stockpiled in
accordance with the directions of the Project Manager, normally in an
approximate circle of 30 to 50 metres in diameter.
b) At tee sites, unclassified fill material shall be placed along the line of the
tee to the approximate length indicated on the plan and to a maximum
width of 15m.
c) At fairway bunker and mound sites, unclassified fill shall be stockpiled in
an oval in accordance with the outline given on plan.
NB - Heights of fill shall be determined by the basic levels shown on the
Re-contouring Plan and /or as directed by the Designer or Project
Manager.
4.3.7 Imported Fill
The imported fill from non-golf areas is to be used within the golf course for
general fill, i.e. for mounding and lower-order re-contouring.
Additional fill may be imported onto the site from the non-golf area.
Loading, carting,deposition and shaping is to be costed pro-rata with other
rates for this work within this section.
NB - Additional cut-off drainage may be required where a significant
mound is formed beyond the extend of the proposed drainage sytem for
the golf course.
Dragon’s Eye Golf Club - 22 -
land-drain to a depth of 400mm cover and backfill with clean, fine hard
stone, to remove water-pressure build-up under the liner.
1 to 2-metres depth
Finish the sides and base with a roughened surface, using a toothed
bucket to help key-in the topsoil, and spread 200mm of topsoil. Sprig, or
seed with an approved, low-maintenance, rhizomatous seed mix, and
fertilise.
b) For 10 metres from the outflow point, and other areas where erosion is
a risk, the watercourse bed and sides are to be finished with a revetment
formed from selected rounded, 250 to 350mm random-sized and light
coloured stones collected from site or otherwise imported, set in mass
concrete, as protection during storm-flow conditions.
c) Gabion Construction – Along watercourse edge at selected sections,
construct stabilising gabion banks in accordance with the detailed drawings
provided by others, and set at a minimum angle of 45 and 90-degrees.
4.4.11 Footbridges
As indicated on the master plan, buggy/footbridges are to be installed in
accordance with the positions shown, and in conjunction with detail
engineering drawings on bridge structure, abutments and installation
provided by the Client’s Civil Engineering Consultants.
NB - The rates for trenching works will also be used in the Specification;
Part 2 for Irrigation work.
a) Main Drains - Where trenching is carried out in topsoil areas, the topsoil
shall be carefully stripped and stored prior to trenching over a suitable
width for the size of the trench, and replaced after the work is completed.
b) Lateral drains – drain lines are to be backfilled with permeable fill, and
so all spoil is to be elevated and removed from the trenches.
4.5.4 Drainage Pipe Installation and Backfilling
a) Unperforated Drain
In the previously excavated trenches, install sealed uPVC 110mm, 160mm
& 225mm nominal diameter main drains as shown on the Drawing. All pipe
materials shall conform to BS 4962; 1989, European Standard ISO/DIS
8771
Main drains within the site shall be laid at a minimum depth of 450mm
depth of cover unless otherwise agreed, and to a minimum fall of 1 in 200.
All joints in the line of drains shall be made with purpose made junction
connectors, or by other approved proprietary means according to the type
of pipe.
Purpose-made reducers shall be fitted where a reduction in pipe size is
necessary, cap-type end-stops shall be provided to seal open ends and all
connections between mains shall be formed with purpose made junctions
of appropriate sizes.
Drain trenches shall be evenly graded, using laser-levelling equipment or
similar approved method, with the trench bed being to a tolerance of +/-
10mm maximum over the graded length, and with a trench width of not
more than 100mm wider than the pipe diameter.
The trench bottom shall be smooth, and shaped to bed, fit and secure the
pipes centrally at the required invert depths.
Dragon’s Eye Golf Club - 28 -
b) Perforated Drain
In the previously excavated trenches, install perforated uPVC 80mm,
110mm & 160mm nominal diameter main drains as shown on the Drawing.
Main drains within the site shall be laid at a minimum depth of 450mm
depth of cover unless otherwise agreed, and to a minimum fall of 1 in 200.
Perforated plastic drain pipes to ISO/DIS 8771 standards and of sizes
shown on drawing shall be used for the main drains. All joints in the line of
drains shall be made with purpose made junction connectors, or by other
approved proprietary means according to the type of pipe.
Purpose-made reducers shall be fitted where a reduction in pipe size is
necessary, cap-type end-stops shall be provided to seal open ends and all
connections between mains shall be formed with purpose made junctions
of appropriate sizes.
Drain trenches shall be evenly graded, using laser-levelling equipment or
similar approved method, with the trench bed being to a tolerance of +/-
10mm maximum over the graded length, and with a trench width of not
more than 100mm wider than the pipe diameter. The trench bottom shall
be smooth, and shaped to bed, fit and secure the pipes centrally at the
required invert depths.
The stone permeable fill shall either:
a) Be brought to the surface if serving as a cut-off drain;
backfill drain trenches of perforated drains up to 150 mm from ground
level using an approved 6-10 mm gauge clean hard stone chippings,
previously analysed and accepted by the Designer. Cover the permeable
fill with a 50mm firmed depth of approved coarse sand or grit blinding
(choker) layer, finishing to the surface with an approved medium–fine
grade clean sand. OR:
4.6.2 Equipment
The style of contouring intended requires intricate fine shaping which will in
turn require the use of either small Caterpillar or equivalent D3, D4, D5 Hi-
Drive PAT-blade fitted Dozers, and/or a minimum of 2 no. 360-degree
tracked Excavators fitted with Power-Tilt buckets.
4.6.3 Limits of Work
This area of work under this Section shall include all irrigated fairway and
rough areas, and any non-irrigated rough areas or other areas disturbed
within the limits of work under this section. Areas not included under this
Section are all Tees and Greens.
Additional areas within the general golf course may be designated by the
Designer for rough contour development, and shall be completed as part of
the work under this Section.
4.6.4 Sand Bunkers
Shape, form and drain the sand bunkers as per the item below for
greenside bunkering; for drainage refer to point 4.7.4 (c)
4.6.5 Fairway Grass Bunkers & Hollows
Where the Designer calls for grass bunkers or hollows to be created, these
features, and the associated mounding, shall be shaped such that their
lines will be smooth and flowing and blend gracefully with the surrounding
areas so that they may be easily maintained.
All grass bunker and grass hollows shall be shaped to provide surface
drainage and the elimination of any water holding pockets or depressions,
unless these points are specifically to be drained by pipes or soak-away.
Dragon’s Eye Golf Club - 32 -
http://www.usga.org/turf/course_construction/green_articles/putting_green_
guidelines.html
The proposed rootzone material is not available commercially, and so is to
be mixed at the site in a dedicated mixing plant area. Mixing is to be
carried out on a solid, preferably concrete base of sufficient size to
accomodate mixing plant and storage mounds of rootzone. This is to
prevent contamination of the imported sand and the rootzone mix with
loose particles from the working base material. After ,mixing as large a
batch as possible in the restrictions of the mixing area, the rootzone shall
then be carted to each individual working site (green)
The selected sand for the rootzone mix must be checked at source for
consistent quality using the methods described in the USGA website, page:
http://www.usga.org/turf/articles/construction/greens/quality_control_sampli
ng.html
Other proposed additives, i.e. peat or other organic matter, zeolite, etc
must also be tested and approved prior to starting the mixing operation.
The method for mixing is outlined in the following USGA guidelines:
http://www.usga.org/turf/articles/construction/greens/quality_control.html
A sample of the lab tested and approved mix is to be kept on site at all
times for visual assessment of conformity of the rootzone. A test-mix of the
rootzone shall be made on-site, and then tested to prove conformity with
the laboratory approved mix. The Contractor shall be responsible for all
laboratory and associated testing costs
As a precaution, the Contractor shall check deliveries of all materials for
conformity to the specification before allowing unloading, and inform the
Project Manager of any problems. The Contractor shall be responsible for
replacing any materials of a substandard nature which have been installed
without adequate vetting.
Greens are to have in addition to the putting surface, a rootzoned collar of
minimum 1 metre width constructed in accordance with the detail cross-
section drawing. The practice chipping green is to be finished as per the
tees only, with topsoil and a sand dressing of 50mm
Dragon’s Eye Golf Club - 34 -
c) Rootzone Sand
The sand for the formulation of the rootzone on all putting surfaces, etc.,
shall be a uniform, clean, sharp product, tested and approved by a USGA-
certified laboratory, and supplied by a reputable supplier operating a good
quality control system. The Contractor shall be responsible for protecting
rootzone stockpiles against contamination with dust, soil, etc., and loss of
sand due to wind, rain or other natural cause during and after mixing.
The Contractor shall supply a medium-fine sand for the basis of the rootzone mix,
within the following imits:
Dragon’s Eye Golf Club - 35 -
d) Organic Material
Organic material for use in the rootzone mixture on putting surfaces, etc.,
is to be a natural peat, humus, composted manure, Coir, or other material
with a minimum 85% by wieght of organic matter (as tested by a loss on
ignition method at a certified USGA Laboratory). It shall be free of lumps,
roots, stones and other contaminants. The acidity range shall be from pH
5.0 to pH 7.5 and the maximum moisture content 70% by weight, on both
tested and delivered materials.
The material shall be graded or chopped into a form which renders it easy
to mix without clumping, but not so fine that it ‘blows’ easily. However, the
Contractor shall protect against contamination and wind erosion of the
stockpiles. Baled or compressed block material is preferred for ease of
mixing amount calculation, and sustainable sources of organic material will
be favoured over non-sustainable sources.
In order to achieve a suitable rootzone mix, an additive of a manufactured
or processed material may be added to the sand, such as Zeolite, pumice,
dried seaweed, Alginure, etc. as approved by the Designer. Zeolite of 0.5
to 2mm partical size is ideal for turf rootzone mixes. Amount used in the mix is to
be determined during the rootzone testing and recommendations by the
Laboratory, but will be based on the following maximum and minimum amounts:
Mixing of the sand and organic elements of the rootzone mix shall be
carried out under the direction of the Project Manager and by the
Contractors team dedicated to this operation only, for the duration of the
mixing operation, and under the strict and constant supervision of a skilled
operative, using a high standard of quality control to ensure uniform and
homogeneous mix of rootzone. The preferred method of blending approved
sand and organic matter together to form the root zone shall be by an auger-
type machine designed specifically for the purpose.
Ratios of materials must be accurately monitored to ensure conformity with
the recommendations of the analysing laboratory (STRI Ltd, or European
Turf Laboratories, Scotland are recommended). Mixing must be carried out
to the point where a uniform mix has been truly achieved, using an
approved method.
4.7.4 Construction Method
a) Greens
i) Shaping
The greens and tees and bunkers shall be moulded as shown on the plans
or sketches of the Designer, located in accordance with the reference
points previously installed. The position, size and shape of the associated
mounds and slopes, and the direction of the flow of surface drainage shall
be indicated on the plans or sketches by the Designer.
Topsoil will be stripped and stockpiled and unclassified imported fill
stockpiled at all green and tee locations indicated on the Rough Grading
Plan and the previous section on Fill Stockpiles. Topsoil will be either re-
used on the surrounds or, if poor in quality, for low-priority roughs or carry
areas
Greens and tees shall be rough-shaped and tracked-down firm with a 360-
excavator as specified, using material from the fill stockpile. This material
clean and stable, to allow a firm and solid base for the shaping and
drainage work. Stone contaminated fill will cause problems in trenching
and firming, and must be avoided as a shaping material for the bed of the
greens. Using such material, no stabilising geotextile layer should be need
on the base of the green.
The mounds and valleys of the greens shall be shaped into smooth,
curving lines as indicated on the plans or sketches or as otherwise
designated by the Designer or Consultant in the field. Their lines and
slopes shall blend harmoniously with the surrounding contours.
NB - The Designer reserves the right to alter the design of any green, tee,
fairway bunker or mound cluster at any time during the course of the
construction.
Where, in the opinion of the Designer, the size, shape, or slopes of the
greens, tees, fairway bunkers, and mound clusters shall be altered in order
to improve the design, such alteration shall be done by the Contractor at
the Designer's direction, at no additional charge to the Client.
Finer shaping shall be carried out using Tilt-bucket fitted tracked
excavators, at the request of the Designer.
ii) Greens Construction
Dragon’s Eye Golf Club - 37 -
The greens are to be formed using the 'Coring' technique, that is where the
full finished putting surface and surrounds contouring is formed at the
subgrade level, and then the putting green and collar area is cut out at a
uniform depth in accordance with the shaping, to the required depth.
Excess material will be smoothed out over the surrounds.
The moulded sub-grade of the greens shall be smoothed and compacted
sufficiently by the use of the Tilt-bucket tracked Excavators to prevent any
future settling or the creation of any water-holding depressions in the
surface.
The depth of cut for the green is to allow for a minimum 150 mm settled
depth of topsoil to be laid over the sub-grade of the surrounds beyond the
collar, and layer depths of:
b) Tees Construction
i) Turf - The subgrade of tees shall be such that the teeing surfaces are
smooth, and absolutely to grade, with no pockets or irregularities, and
having good surface drainage by sloping the entire surface at 0.5%
gradient from front down to rear. Side slopes of the tees shall be graded
so as to blend smoothly with surrounding contours and to permit mowing
by fairway and gang mowers wherever possible, using a maximum 1-in-4
slope.
The sub-grade must be firmly compacted to ensure that no settlement shall
occur. The surface of the subgrade must be finished, and remain as an
even surface with a tolerance of plus or minus 6mm from the grade,
checked with a 3-metre levelling bar and pegs.
Over the sub-grade of the tee, a 200mm deep stone-free sandy-loam type
topsoil layer is to be laid, with then a finish of 100mm settled depth of
topdressing of rootzone mix
All tees are to have lateral drains installed at 450mm depth of cover, with
premeable fill to the top of the topsoil level, and a spacing of no more than
5-metres, running diagonally across the grade,.
Dragon’s Eye Golf Club - 39 -
ii) Artificial turf mats – The driving range lower tee and the Pitch & Putt
course tees are proposed to be of artificial turf, type to be approved by the
Designer. Good quality artificial turf mats are to be fitted on a concrete
bed, underlay material and fixed in accordance with manufacturers
recommendations.
c) Drainage Installation
After the greens, tees and bunkers have been moulded and approved by
the Designer, underdrains shall be installed. Trenches for such
underdrains shall be cut into the subgrade so that all pipes will slope
uniformly, with a minimum slope of 0.5% (one half percent) in all lines.
Trenches shall be cut a minimum of 325mm deep, to true line and grade.
All pipe laid within the greens shall be 110mm diameter perforated pipe.
From the green to the junction pipe with the main fairway drainage system
shall be 110mm unperforated pipe. The Contractor shall include within the
greens, tees and bunker drainage rate for laying the main outfall pipe up to
a distance of 20 metres from the edge of the green, tee or bunker.
Before laying the pipe, a firm bedding under the bottom of the pipe of at
least 25mm of gravel shall be installed. The upper end of each line shall be
sealed with a proprietary plastic cap to prevent ingress of material. Any
pipes left temporarily open before connection shall be capped for similar
puproses. All outfalls shall be protected by a screen at point of discharge.
Under no circumstances shall the drain pipe of the green run through a
bunker.
All spoil from trenches must be cleared up and deposited off of the
prepared surface. All drains must be tested prior to final backfilling to prove
the gradient and freedom from blockages.
After the underdrains are installed, the trenches containing perforated pipe
shall be completely backfilled with permeable fill. The trenches beyond the
green containing un-slotted pipe shall be backfilled with suitable fill to the
sub-grade and a 250mm minimum final layer of existing topsoil.
d) Greens Material Placement
Permeable Layer - After all underdrains are installed and backfilled, a layer
of permeable fill shall be placed to a uniform thickness of 125mm over the
entire putting surface and 1-metre collar. The Contractor shall be careful to
maintain the contours of the moulded subgrade when placing this layer in
order not to change the design of the feature.
Blinding - After installation of the 125mm permeable layer, a minimum
50mm layer of the specified blinding layer sand or stone shall be placed by
hand over the entire putting surface and 1 metre collar of the green.
Rootzone - The rootzone shall be spread uniformly over the 50mm blinding
layer without disturbing it, incorporating a plastic barrier to the vertical face
of the rootzone/topsoil interface to prevent future weed-grass root
incursion. This barrier shall be 40 or 60 grade HD Polyethylene, 450mm
deep, staked at 0.5-metre intervals with canes to keep it upright during the
laying operation. Following laying of both rootzone and topsoil, the barrier
shall be cut back flush with the surface.
Dragon’s Eye Golf Club - 40 -
e) Surrounds Topsoiling
Depending on the programme of works, topsoiling shall be carried out
either before or after irrigation system installation around the green. It shall
be spread and carefully graded as required to tie smoothly into the collars,
and surrounds, to a minimum 200mm depth to a distance of around 6
metres from the putting surface and on teeing surfaces, reducing to a
minimum of 150mm beyond, and on all tee banks. Where the collar
material is feathered-out beyond the putting green, the total depth of
underlying topsoil and sand top layer shall remain at 200mm.
Topsoil shall not be required in the intended sanded areas of the bunkers.
However, all edges, noses, and slopes into the bottom of the bunkers shall
be topsoiled with a full depth of at least 150mm, so that these areas may
be turfed or seeded for erosion control. The final outline of sand areas will
be determined by the Designer in the field.
Special care must be taken to ensure that no contouring is lost during the
re-topsoiling operation, and that all shaping is preserved. This is best
achieved by hand-work and depth-gauging.
The final finish of the topsoil is critical and must be carefully done, using a
Toro or Smithco bunker rake fitted with York rakes and/or small levelling bar
with a maximum width of 1 metre to smooth out or ‘float’ the surfaces
without moving so much material that contouring is lost.
Hand labour can be used as an alternative only as a supplement to this
operation.
This work on features, fairways and rough areas shall have been
completed prior to work under this Section, and floated-off smoothly ready
for the cultivations. Such previous work shall have included the provision
of adequate surface drainage for all designated areas.
4.9.2 Cultivation
All areas to be grassed shall be thoroughly loosened by an acceptable
method; discing, harrowing, rotivating, rolling, or other suitable means
(including hand work) to a minimum depth of 150mm below topsoil surface
level prior to fine finish grading. The Contractor must avoid over-working
the soil to a powdery consistency.
These areas shall be machine and hand worked as necessary to eliminate
stones, lumps, and soil clods, with all deleterious material being carted
away and buried in an area acceptable to the Designer.
Cultivation shall include the removal of equipment ruts and tracks, areas of
compaction or erosion, and any other undesirable soil conditions which
would prevent the proper formation of a fine seedbed.
Cultivation shall be accomplished only under proper conditions. The
Designer or Client may, at his discretion, request the cessation of
cultivation operations during periods of sever drought, excessive soil
moisture, dusty or other unsatisfactory soil conditions.
The Contractor must ensure that no damage whatsoever occurs to the
irrigation system; the pipes, sprinklers, hydrants, etc., or any other
previously executed work. Any such damage shall be made good by the
Contractor at his expense.
Under no circumstances shall any previous shaping and subtle contouring
work be lost due to soil movement during cultivation. Wide and heavy-duty
power harrows and rotivators shall not be used where this may occur. The
Dragon’s Eye Golf Club - 43 -
Contractor must allow for the use of maximum 1-metre wide power harrows
and stone buriers, working in an orientation such a way that fine contouring
is not lost, i.e. up and down slopes rather than across breaks in grade, or
alternatively for all such work to be carried out or finished by hand.
4.9.3 Removal of Extraneous Material
An initial clearance of large rocks will be required, following loosening by
heavy raking equipment. A further, cleaning operation following basic
cultivation will be required, followed by a stone-burying operation prior to
fine finishing.
Sticks, stones, weeds, and other debris greater than 50mm in size which
might interfere with the formation of a finely pulverised seedbed, impair
planting, or create problems of maintenance shall be removed from the soil
to a depth of 75mm. All material shall be carted to an agreed dumping
point(s).
4.9.4 Finishing/Grading
Greens, tees, bunkers and all areas to be planted shall be graded and
floated to provide surface drainage with the elimination of water holding
depressions and pockets. Undulations and unsightly variations in grade
that will not permit the use of normal mowing equipment without scalping
or missed cuts, shall be eliminated for the proper use of such equipment.
Seedbed preparation of the green and tee surfaces shall include breaking
of any capping, fine smoothing and levelling; using a Smithco or Toro
mechanical bunker rake with a 1-metre maximum width levelling bar and
drag-mat, and carefully hand raking using light, 1-metre landscape rakes
to eliminate any pockets, ridges or unwanted undulations and remove any
remaining stones.
Special attention shall be given to the tie-in of the rootzone mix of the
putting surface and collar of the green and tee surfaces with the topsoil.
These areas shall be lightly raked and firmed (‘heeling-in’) to provide a
smooth, uniform surface without ridges, depressions or other specified
changes in level.
The greens and tee complexes shall be fine-finished out to the point where
the mechanical finishing of the fairways and rough meets, with the join
between being graded out fully before seeding, with all stones and rakings
collected and removed to tip.
iii) Turfing (Sodding) - Bunker edges, steep banks, and other areas may
be required to be turfed with a specified pre-grown turf. A rate per m.sq is
to be given by the Contractor for this turfing work. Turf may be required for
correction of general erosion problems, with the allowable budget, as
specified by the Project Manager
4.10.2 Sprigs
All sprigs shall be certified as to genetic purity and shall be inspected and
certified as to freedom from pests and disease by the local and governing
Turfgrass or Agricultural Departments.
All sprigs shall come from a nursery subject to approval by the Project
Manager, who have the right to inspect all turfgrass stolons as they are
delivered and planted, and the right to reject any sprigs or loads of grass
delivered that are deemed unsuitable for planting, and for the purpose of
the contractor guaranteeing healthy fresh stolons applied and planted.
All stolons shall be removed from the grass farms and delivered to the golf
course site within twenty-four (24) hours, and kept moist and as cool as
possible on the truck. Any sprigs dehydrated at the golf course site prior to
planting may also be rejected.
Supply a weed free turf grown on approved soil or rootzone material and
consisting of no less than 99% of the required and approved grass species
and cultivar composition
All turf shall be of a variety approved by the Project Manager and
commercially grown within 250 kilometers of the golf course, unless
otherwise approved in writing by the Project Manager. It shall be cut and
delivered within twenty-four (24) hours. It shall be free from noxious weeds
and grasses. It shall have a soil layer no less than 12 millimeters and no
more than 25 millimeters in thickness and shall have enough moisture to
allow for proper rolling and handling. It is assumed that the sod shall be cut
in standard sizes. Variation of this standard roll must be approved by
Project Manager prior to delivery of the sod to the site.
Turf grown on organic soils to be planted on mineral soils, or visa versa will
only be permitted when written consent from the owner has be obtained
and the contractor has signed a release to accept any damage and/or
repair cost for improper rooting of turf due to this soil texture discontinuity.
ii) Under the direction of the Project Manager, and following analyses and
recommendations from the Designer, Lime or Sulphur shall be similarly
applied and worked into the soil surface at the stated rate to correct any pH
imbalances.
- Provisional -
iii) Additives – Allow for the supply and application of a 15% mixed
volume/volume of Zeolite into the surface of the greens and tees root
zone material and bunker bank topsoil prior to seeding. The Zeolite is
to be lightly mixed in to the top 100mm of the root zone.
- Provisional -
4.10.6 Seeding
i) Sowing shall be carried out during suitable, calm weather conditions.
Work during wind and wet conditions which affects soil conditions or the
even application of seed and fertiliser shall not be allowed.
The seed shall be spread using a method and machinery that ensures
uniform spread and overlap between passes, with all equipment calibrated
for the correct application rate prior to seeding. Seed must not be spread
onto any non-golf turf areas, in order to protect the natural vegetation.
Sow the seed in two transverse passes, using either hand labour or turf-
tyred equipment only.
Areas other than tees and greens surfaces - Following seeding, the soil
shall be carefully rolled with a (Cambridge-type) ridged roller at right angles
to the direction of slope, wherever possible, to help prevent surface run-off
and wind erosion, and if required subsequently given a final float over the
surface with a very light drag-mat or hand raking with a 1-metre landscape
rake to remove all seeding marks.
Greens putting surfaces & tees - After planting and fertilizing is
completed, the seed/sprigs shall be very lightly raked into the top six
millimeters of the green bed surface. Rootzone surfaces shall receive a
final tracking-in using a Bunker-rake machine with ‚knobbly’ tyres
(approximately 15mm square tread size at 25mm spacing, to form
depressions to hold seed and water), working forwards and backwards
sequentially over the surfaces.
Dragon’s Eye Golf Club - 48 -
Where the seed is so small that it is difficult to calibrate the application rate
properly, the seed shall be bulked-up using a fine, dry silver sand in strict
proportions, and the equipment calibrated this way.
NB - Hydraulic application of seed would be permitted ONLY with written
approval by the Project Manager.
iii) Mulching
The contractor shall mulch all seeded areas with an approved wheat or oat
straw that is free of mold or mildew, weed free, and is free flowing through
the straw blower. No hay material will be acceptable for mulch. Within
twenty-four (24) hours after any given area is seeded, vegetative mulching
material shall be evenly placed over all seeded areas at the rate of
approximately 3.5 metric tons per hectare. The proper mulch application
when viewed straight down shall appear to be 50% mulch straw and 50%
of the soil surface below.
Mulching materials shall be kept in place with an approved binding
emulsion applied at a minimum rate of 250 litres per metric ton of mulch or
by methods approved to prevent displacement of material, such as
crimping. Other such binders will be considered by the Project Manager.
Emulsion shall be non-toxic to plants and shall be so prepared that it will
not change in transportation or storage. Mulch and binder shall be applied
simultaneously. Mulching which is displaced shall be replaced at once but
only after the seeding or other work which prepared the mulching and
which work was damaged as a result of displacement of mulching
materials has been acceptably repaired.
4.10.7 Sprigging
Sprigs shall be carefully harvested from the on-site turf nursery and
transported quickly to the planting site in covered containers. Plant-out the
sprigs by hand in a 50mm grid and well watered-in over the immediate and
establishment period using clean water only.
- Provisional -
4.10.8 Turfing (Sodding)
Where required, on steep banks where seeding is not feasible, or where a
particular visual or maintenace effect is required, approved turf is to be
laid. Turf samples must be presented to the Designer for approval, and
shall be free of weed-grasses, grown on a suitable soil or rootzone material
matching that laid on the golf course, laid on a firmed, prepared seedbed,
using boards to prevent compaction and surface marking.
No turf shall be hauled to or laid in place if damage to the course will result
from such hauling. All turf shall be delivered when the ground will support
the hauling vehicle. No turf shall be laid in place until the area to be turfed
has been approved by the Project Manager as being ready to receive it.
Dragon’s Eye Golf Club - 49 -
Turf will be laid and staked as described above, and rolled in every place
possible before soaking with water. Hand watering is desirable so as not to
over-water adjacent seeded areas with the use of irrigation heads.
All turf on slopes of four to one (4:1) and greater will also be pegged as per
the detail drawings. Peg the turf to banks using either 150mm-long wooden
pegs or galvanised, hooked steel pins, ensuring a close-butted finish, with
turves laid stretcher-bond.
Close-but all joints on all sides. All turf on slopes less than four to one (4:1)
will be rolled by hand or by mechanized roller to tamp butted joints and
flatten irregularities before soaking with water. Brush-in medium-fine sand
to fill inbetween turves and roll where possible with a light hand–roller.
Fertilise with the 15:15:15 fertiliser or similar.
Drainage will be via a pipe and permeable fill brought up to the surface,
running along the upper side of the sections of path where the slope and
catchment area is such that storm water flows would cause path surface
erosion problems. A linear rate per metre will be taken from the drainage
work section for this.
4.11.4 Passing Bays
Where required, passing bays will be constructed to the same standard as
the adjacent path, being of 1.5 metre width, and with smoothly-curved run-
in/run-out sections as given on plan.
4.11.5 Turning Circles
Turning circles are to have an edging formed from selected, rounded, site-
sourced rocks, laid in an accurately set-out circle, and set in mass concrete
with the concrete edge raised 25mm above the finished surfacing level.
Cut-off drainage using 80mm lateral pipes with permeable fill to the surface
as detailed in the ‚Drainage’ section shall be installed where required.
4.11.6 Road-Crossing Point
On the Driving Range access path, a crossing point is required over the
main access road. The proposal is to install dropped-kerbs, non-slip
surfacing and baffle barriers to form a formal controlled crossing point on
these holes. (full specification by others)
4.11.7 Golf Cart Parking Areas
At the driving range an area as marked on plan is to be stripped of topsoil
and subsoil to a depth of 300mm, a geotextile mat placed over the subsoil,
and a layer of 250mm clean hard 25 to 50mm stone supplied and levelled,
finished with 50mm of selected and approved fine crushed stone finishing
material.
Finish the edges straight and with topsoil abutting the stone layers, raked
and seeded. (full specification by others)
4.11.8 Clubhouse Area Traffic Island
A landscaped cart-path island is planned in front of the Clubhouse. The
island has a radius of 4.5 metres, and is to be constructed using selected
approved stone blocks, set level and true in a concrete haunching, with
selected stone-free topsoil placed within the central area to a depth of
300mm.
4.11.9 Watercourse Crossing Points
To be designed by Client’s EngineerArchitect.
Deciduous trees:
[List to follow]
During the first growing season, water constantly during dry periods.
Spray conifers with S600 Anti-transpirant in April of the first season to
reduce water loss. Any trees failing due to poor planting or watering shall
be replaced by the Contractor.
Other trees:
[List to follow]
Dragon’s Eye Golf Club - 53 -
Larger trees are to be planted into a prepared pit of minimum 0.5 cubic
metre, deep enough not to restrict the full length of the roots when
exposed ensuring that the tree is planted to the same point on the
root/trunk dividing point as it was originally.
Mix in one 25kg bag of planting compost with the excavated soil, fork-over
the bed of the pit, plant and firm the roots into place, watering afterwards.
Attach the tree to a pressure-treated softwood stake set a minimum of
600mm into the ground and with 500mm above ground. Firm the stake
into place to properly support the tree, using proprietary abrasion-free and
adjustable ties.. Protect the tree with a 1.2-metre high deer guard and
attach firmly to the stake to using ties. Apply in a radius of 1 metre around
the tree a minimum 100mm layer of mulching material
During the first growing season, water regularly during dry spells. Spray
conifers with S600 Anti-transpirant in April of the first season to reduce
water loss. Any trees failing due to poor planting or watering shall be
replaced by the Contractor.
During the first growing season, water regularly during dry spells. Spray
evergreens with S600 Anti-transpirant in April of the first season to reduce
water loss. Any plants failing due to poor planting or watering shall be
replaced by the Contractor.
4.12.4
Ornamental Seeding
P.C. cost is to be inserted into the Bills of Quantities to cover ad-hoc work
on seeding with semi-ornamental grasses, and wild flora species, in
accordance with general recommendations for seedbed preparation and
sowing, to be issued by the Project Manager prior to planting or sowing.
Species to be planted from the following list:
a) Grass:
Indigenous, locally gathered Reeds and Rushes
[List to follow]
b) Wild Flora:
[List to follow]
Dragon’s Eye Golf Club - 55 -
iii) As ii), but using a smaller machine on all of the greens, surrounds,
tees and banks, bunker mounding and other areas that a larger fairway
machine cannot work. The Contractor must strive to decompact all areas,
including greens surrounds banking, whilst avoiding fixed objects such as
hydrant boxes, sprinklers, drain covers and sumps, etc.
- Provisional -
4.13.4 Quality Measurements - Maintenance
i) Prior to handover of the maintenance of the course and subject to
acceptance by the Client, the Contractor must supply a detailed
internationally-qualified Agronomists report covering all aspects of the turf
status, with recommendations on further management by the Head
Greenkeeper to understand the maintenance needs required to continue
to maintain the golf course in the transferred condition.
ii) Prior to handover of the maintenance of the course and subject to
acceptance by the Client, the Contractor must supply a detailed
internationally-qualified Irrigation Consultants report report covering all
aspects of the turf and irrigation system, with recommendations on further
management by the Head Greenkeeper to understand the maintenance
needs required to continue to maintain the golf course in the transferred
condition.
iii) A comprehensive manual of construction details, record plans and
operting instructions shall also be provided as per the clause above in the
general contract conditions.
4.14 IRRIGATION
See separate Specification; PART 2 and documentation
NB
a) Items in Block lettering currently available on plan and/or digital format
b) All drawing numbers above will be preceded by the current master plan
number, i, e, MP_8
Dragon’s Eye Golf Club - 59 -
Bills of Quantities
Dragon’s Eye Golf Club - 61 -
PREAMBLE
1. The Bill of Quantities includes this Preamble, the parts of the Bill of
Quantities and the Summary.
2. In accordance with the Appendix to the Conditions of Contract, the
measurement of the Bill of Quantities has been prepared as described in
the Civil Engineering Standard Method of Measurement (CESMM) (3rd
Edition 1991) and as modified herein. The various Clauses within the
Preamble shall take precedence over the Civil Engineering Standard
Method of Measurement (2nd Edition 1985) in the event of any dispute.
3. The prices and rates to be inserted in the Schedule of Rates are to
be the full inclusive value of the work described under the several items,
including all costs and expenses which may be required in and for the
construction of the work described, together with all general risks, liabilities
and obligations set forth or implied in the documents on which the Tender is
to be based.
4. Each item shall be priced independently of any other work scheduled
in the Bills of Quantities. A price or rate is to be entered against each item
in the Bills of Quantities, whether quantities are stated or not. Items
against which no price is entered are to be considered as covered by other
prices or rates in the Bills.
5. The Form of Contract, the Conditions of Contract, the Specifications
and Drawings are to be read in conjunction with the Bills of Quantities.
6. General directions and descriptions of work and material given in the
Specifications are not necessarily repeated in the Bills of Quantities.
Reference is to be made to the Specifications for this information.
7. Day works shall be carried out in accordance with the rates and
prices stated in the Day work Schedule only when instructed by the
Engineer.
8. No additional charge shall be made to the Employer in respect of
carrying out the work in isolated sections, co-operation with any of the
Statutory Undertakers or any sub-contractor, or of a break in the continuity
of the Contractor’s operations between one stage and another. Prices and
rates are to include for the cost of all non-productive and temporary works
and for overtime involved in carrying out and completing the Works.
9. The quantities given in these Bills of Quantities are estimated and are
given for the purpose of enabling Contractors to make out their Tenders on
an equal basis and to enable the Engineer to compare them, but they are
not to be taken as a guarantee that the total quantities of work will be
executed or will not be exceeded. All the work will be measured on
completion and only the amount of work executed will be paid for at the
rates given in the Bills of Quantities or at rates analogous thereto. No claim
made by the Contractor arising from any increase, reduction or omission in
the Works will be considered by the Engineer.
10. The General Items shall be deemed to be spread over the whole of
the period that the Contractor is on site, and the amount of the General
Items to be paid in the monthly certificates shall be proportionately equal to
the total time the Contractor has spent on site up to the date of submission
of the certificate.
Dragon’s Eye Golf Club - 62 -
BILLS of QUANTITIES
Dragon’s Eye Golf Club - 64 -
Plant Schedule & Hire Rates to be used in the construction of the Works
Labour
The Contractor is to list below the rates for the various classes of
labour to be used when Day work is ordered. The rates quoted shall
be the “Amount of Wages” as described in the above-mentioned
Schedule of Day works.
1 Shaper
2 Working
Foreman
3 Plant
Operator
Level 1
4 Plant
Operator
Level 2
5 Tradesman
6 Truck Driver
7 Banksman
8 Labourer
Dragon’s Eye Golf Club - 66 -
FORM OF TENDER
[Client to insert]