Data Tanah timbunan

q = 1.5 t/m² (Beban lalu dan perkerasan jalan) diatas timbunan No


ɣtimb = 1.9 t/m² 0.57735
ø = 30 ˚ 1
δ = 20 ˚ 2
c = 0 3
h = 6.5 4
Tult = 100 KN/m 5
6
Data Tanah Asli 7
8
ɣ sat = 1.686 t/m³ 9
ø = 0
δ = 0
cu = 0.5 t/m²
c = 0.3333

FsID = 1.1
FSCR = 2
FSCD = 1
FSBD = 1
FSrencana = 1.5

Ka = 0.3333
Ơv1 = 1.5 t/m²
Ơv2 = 13.85 t/m²
Ơh1 = 0.500 t/m²
Ơh2 = 4.6167 t/m²

Tallow = 45.455 KN/m


= 4.5455 t/m
Kedalaman Ơh SV-Pilih Layer No. Depth (z) Spacing SV
FS SV (m) Tan δ
(m) (t/m²) (m) (m) (m)
6.5 4.617 1.5 0.656 0.5 9 (top) 1 1 0.364
6 4.300 1.5 0.705 0.5 8 2 1 0.364
5.5 3.983 1.5 0.761 0.5 7 3 1 0.364
5 3.667 1.5 0.826 0.5 6 3.75 0.75 0.364
4.5 3.350 1.5 0.905 0.75 5 4.5 0.75 0.364
3.75 2.875 1.5 1.054 0.75 4 5 0.5 0.364
3 2.400 1.5 1.263 1 3 5.5 0.5 0.364
2 1.767 1.5 1.715 1 2 6 0.5 0.364
1 1.133 1.5 2.674 1 1 (bottom) 6.5 0.5 0.000
Ơh (t/m²) Le Le min Le used Lr L L used Lo Lo min Lo used

1.133 1.2291 2 2 3.175 5.175 6 1 1 1


1.767 0.9580 1 1 2.598 3.598 6 0.5 1 1
2.400 0.8676 1 1 2.021 3.021 6 0.5 1 1
2.875 0.6236 1 1 1.588 2.588 3 0.5 1 1
3.350 0.6055 1 1 1.155 2.155 3 0.5 1 1
3.667 0.3977 1 1 0.866 1.866 3 0.5 1 1
3.983 0.3927 1 1 0.577 1.577 3 0.5 1 1
4.300 0.3886 1 1 0.289 1.289 3 0.5 1 1
4.617 0.7171 1 1 0.000 1.000 3 0.5 1 1
Data Tanah timbunan

q = 1.5 t/m² (Beban lalu dan perkerasan jalan) diatas timbunan No


ɣtimb = 1.9 t/m² 0.57735
ø = 30 ˚ 1
δ = 20 ˚ 2
c = 0 3
h = 3.5 4
Tult = 100 KN/m 5
6
Data Tanah Asli 7
8
ɣ sat = 1.686 t/m³ 9
ø = 0
δ = 0
cu = 0.5 t/m²
c = 0.3333

FsID = 1.1
FSCR = 2
FSCD = 1
FSBD = 1
FSrencana = 1.5

Ka = 0.3333
Ơv1 = 1.5 t/m²
Ơv2 = 8.15 t/m²
Ơh1 = 0.500 t/m²
Ơh2 = 2.7167 t/m²

Tallow = 45.455 KN/m


= 4.5455 t/m
Kedalaman Ơh SV-Pilih Layer No. Depth (z) Spacing SV
FS SV (m) Tan δ
(m) (t/m²) (m) (m) (m)
6.5 4.617 1.5 0.656 0.5 9 (top) 1 1 0.364
6 4.300 1.5 0.705 0.5 8 2 1 0.364
5.5 3.983 1.5 0.761 0.5 7 3 1 0.364
5 3.667 1.5 0.826 0.5 6 3.75 0.75 0.364
4.5 3.350 1.5 0.905 0.75 5 4.5 0.75 0.364
3.75 2.875 1.5 1.054 0.75 4 5 0.5 0.364
3 2.400 1.5 1.263 1 3 5.5 0.5 0.364
2 1.767 1.5 1.715 1 2 6 0.5 0.364
1 1.133 1.5 2.674 1 1 (bottom) 6.5 0.5 0.000
Ơh (t/m²) Le Le min Le used Lr L L used Lo Lo min Lo used

1.133 1.2291 2 2 1.443 3.443 6 1 1 1


1.767 0.9580 1 1 0.866 1.866 6 0.5 1 1
2.400 0.8676 1 1 0.289 1.289 6 0.5 1 1
2.875 0.6236 1 1 -0.144 0.856 6 0.5 1 1
3.350 0.6055 1 1 -0.577 0.423 6 0.5 1 1
3.667 0.3977 1 1 -0.866 0.134 6 0.5 1 1
3.983 0.3927 1 1 -1.155 -0.155 6 0.5 1 1
4.300 0.3886 1 1 -1.443 -0.443 6 0.5 1 1
4.617 0.7171 1 1 -1.732 -0.732 6 0.5 1 1
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA FAKULTAS TEKNIK SIPIL DAN PERENCANAAN PROGRAM
STUDI TEKNIK SIPIL

KASUS 1.
DESAIN PERKUATAN TIMBUNAN APPROACHING FLY-OVER DENGAN
MENGGUNAKAN GEOTEXTILE.

Sebuah fly-over dengan tinggi 6.5 meter akan dibangun sebagai sebuah jalan baru
alternative untuk mengurai kemacetan pada suatu kota. Fly-over ini didesain dengan adanya
timbunan jalan sebagai jalan pendekat (approaching road) sepanjang 500 meter. Ketinggian
maksimal timbunan jalan adalah 6.5 meter. Timbunan jalan ini akan dibangun diatas tanah
dasar lunak. Dengan ketinggian timbunan yang relative tinggi dan kondisi tanah dasar yang
lunak maka perlu dibuat perkuatan timbunan untuk menghindari bahaya kelongsoran dari
timbunan tersebut. Perkuatan telah ditentukan dengan menggunakan geotextile dengan
kuat tarik ultimate sebesar 100 KN/m’. Terdapat 3 alternatif pemasangan geotextile dalam
desain ini yaitu :
a) Geotextile digunakan sebagai penguat timbunan dengan adanya kemiringan slope 1:1,5 (Alternatif 1)
b) Geotextile digunakan sebagai dinding penahan tanah (Alternatif 2);

Ilustrasi dimensi timbunan dapat dilihat pada Gambar 1 dan Gambar potongan berikut ini.

Alternatif 1

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAHKELOMPOK 6 (KELAS A) 7


INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA FAKULTAS TEKNIK SIPIL DAN PERENCANAAN PROGRAM
STUDI TEKNIK SIPIL

Alternatif 2.

DATA TAMBAHAN:
Data tanah dasar diberikan di Lampiran
Data timbunan adalah: ɣtimb = 1.9 t/m; ; Ø = 30
Beban (lalu lintas dan perkerasan jalan) diatas timbunan adalah 1.5 t/m

DIMINTA:
Rencanakan jumlah kebutuhan geotextile untuk alternatif 1 dan Alternatif 2

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAHKELOMPOK 6 (KELAS A) 8


INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

(ALTERNATIF 1; H = 6,5 m)

Dari Analisa Geoslope didapat data berikut dari 4 kali percobaan:

Kordinat Pusat R Momen Resistance Digunakan Geotekstile sebagai timbunan (embankments):


No SF
X Y (m) (KNm)
1 0.367 37.25 32.5 10.2 1780.9 Faktor Pemasangan Faktor Rangkak Faktor Kimia Faktor Biologi T ult T allow (Si)
2 0.383 39.25 31.675 9.8 1384.1 F Sc F Scr F Scd F Sid KN/m' KN/m'
3 0.395 36.3 34 11.5 2442.3 1,1 - 2,0 2,0 - 3,0 1,0 - 1,5 1,0 - 1,3
100 32.795
4 0.4 36.65 34.2 11.7 2536 1.2 2.1 1.1 1.1

Perhitungan data nomor 1 (Paling Kritis)

SF 0.367 Jarak antar lapisan Geoteks (m) = 0.3


M Resistance 1780.9 kNm Data Timbunan
Kordinat Pusat ( 37.25 ; 32.5 ) ɣt = 1.9 t/m³ = 19 kN/m³ Ka = 0.333
Kordinat Puncak Timbunan (Y) 31.5 Ø= 30 °
Kordinat Awal Timbunan (Y) 25 c= 0
Tinggi Timbunan 6.5 m Data tanah asli lapis 1
Kuat tarik ultimate geotextile 100 kN/m ɣt = 1.637 t/m³ = 16.37 kN/m³ Ka = 1
Beban lalulintas 1.5 t/m³ = 15 kN/m Ø= 0°
M Dorong 4852.6 kNm c= 5 KN/m2
SF Rencana 1.3 H= 5 m
M Resistance Rencana 6308.4 kNm E= 0.8
ΔM Resistance Rencana 4527.5 kNm q 15 KN/m2

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
9
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

Jarak titik
Sisa
longsor ke T allow Momen ΔM τ2 Le
No Tinggi Jumlah τ1 Στ Le Lr s (m) Lo Ltot
lapisan (Si) penahan Resistance Keterangan (KN/m 2
pakai
Lapis Timbunan Lapis (KN/m2) (KN/m2) (m) (m) H (m) (m)
geotekstile (KN/m') geotekstile kumulatif ) (m)
(m)
(m)
1 7.5 6.5 65.591 491.932 491.932 2 tambah lapis 50.410 5 55.410 1.924 2 11.1 56.17 1 15
2 7.2 6.2 65.591 472.255 964.187 2 tambah lapis 48.335 48.335 96.670 1.103 2 11 54.27 1 14
3 6.9 5.9 65.591 452.578 1416.765 2 tambah lapis 46.261 46.261 92.521 1.152 2 10.8 52.37 1 14
4 6.6 5.6 65.591 432.900 1849.665 2 tambah lapis 44.186 44.186 88.372 1.206 2 10.7 50.47 1 14
5 6.3 5.3 65.591 413.223 2262.889 2 tambah lapis 42.111 42.111 84.223 1.266 2 10.5 48.57 1 14
6 6.0 5.0 65.591 393.546 2656.434 2 tambah lapis 40.037 40.037 80.073 1.331 2 10.2 46.67 1 14
7 5.7 4.7 65.591 373.869 3030.303 2 tambah lapis 37.962 37.962 75.924 1.404 2 10 44.77 1 14
8 5.4 4.4 65.591 354.191 3384.494 2 tambah lapis 35.887 35.887 71.775 1.485 2 9.76 42.87 1 13
9 5.1 4.1 32.795 167.257 3551.751 1 tambah lapis 33.813 33.813 67.626 0.788 1 9.49 40.97 1 12
10 4.8 3.8 32.795 157.418 3709.170 1 tambah lapis 31.738 31.738 63.476 0.840 1 9.22 39.07 1 12
11 4.5 3.5 32.795 147.580 3856.749 1 tambah lapis 29.664 29.664 59.327 0.898 1 8.92 37.17 1 11
12 4.2 3.2 32.795 137.741 3994.490 1 tambah lapis 27.589 27.589 55.178 0.966 1 8.6 35.27 1 11
13 3.9 2.9 32.795 127.902 4122.393 1 tambah lapis 25.514 25.514 51.029 1.044 2 8.28 33.37 1 12
14 3.6 2.6 32.795 118.064 4240.457 1 tambah lapis 23.440 23.440 46.879 1.137 2 7.97 31.47 1 11
15 3.3 2.3 32.795 108.225 4348.682 1 tambah lapis 21.365 21.365 42.730 1.247 2 7.62 29.57 1 11
16 3.0 2.0 32.795 98.386 4447.068 1 tambah lapis 19.290 19.290 38.581 1.381 2 7.24 27.67 1 11
17 2.7 1.7 32.795 88.548 4535.616 1 cukup 17.216 17.216 34.432 1.548 2 6.86 25.77 1 10

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
10
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

1.Check Internal Stability

Pa = 1/2 x Htimb2 x γtimb x Ka Berat ABC = LuasABC x γtimb x 1m tegak lurus


Pa = 133.792 kN = (1/2x9.75x6.5) x 19 x 1
tan δ = tan 2/3 φ = 602.0625 kN
tan δ = tan 2/3 x 30° CHECK
tan δ = 0.36 133.79 < 146.089 Maka AMAN
SF Jalan Permanen = 1.5

2. Check Overall Stability

SF = Mpenahan MReksis + ΔΣMR


> 1.3 > 1.3
Mpendorong Mpendorong

= 1780.9 + 4527.5 1.302 > 1.3


> 1.3
4852.6 AMAN

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
11
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

3. Check Fondation Stability

s'v0 = 15 KN/m2 + 6.5 m x 19 KN/m3


= 138.5 KN/m2
Pa2 = ( 138.5 KN/m2 - 2 x 5 KN/m2 ) + 0,5 x(30m)2 x 16.37 KN/m3
= 8009 KN/m'
Pp = 0,5 x(30m)2 x 16.4 KN/m3 + 2 x 5 KN/m2 30 m
= 7666.5 KN/m'
8009 < 7666.5 + 2 x 5 KN/m2 x 9.75 m
1.3
8009 > 5972.308
TIDAK AMAN
karna untuk kontrol foundation stability tidak aman, maka harus dilakukan
perbaikan tanah untuk tanah dasarnya dikarenakan tanah dasar terlalu lembek

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
12
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
13
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
14
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
15
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
16
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
17
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

KASUS 1 (ALTERNATIF 1; H = 3,5 m)

Dari Analisa Geoslope didapat data berikut dari 4 kali percobaan:

Kordinat Pusat R Momen Resistance Digunakan Geotekstile sebagai timbunan (embankments):


No SF
X Y (m) (KNm)
1 0.502 37.25 32.5 10.3 1261.3 Faktor Pemasangan Faktor Rangkak Faktor Kimia Faktor Biologi T ult T allow (Si)
2 0.468 34.325 31.5 8.5 922.47 F Sc F Scr F Scd F Sid KN/m' KN/m'
3 0.480 34.35 29 5.25 381.45 1,1 - 2,0 2,0 - 3,0 1,0 - 1,5 1,0 - 1,3
100 32.795
4 0.477 34.75 28.55 4.8 313.78 1.2 2.1 1.1 1.1

Perhitungan data nomor 1 (Paling Kritis)

SF 0.468 Jarak antar lapisan Geoteks (m) = 0.3

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
18
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

M Resistance 922.5 kNm Data Timbunan


Kordinat Pusat (34.325 ; 31.5 ) ɣt = 1.9 t/m³ = 19 kN/m³ Ka = 0.333
Kordinat Puncak Timbunan (Y) 28.5 Ø= 30 °
Kordinat Awal Timbunan (Y) 25 c= 0
Tinggi Timbunan 3.5 m Data tanah asli lapis 1
Kuat tarik ultimate geotextile 100 kN/m ɣt = 1.637 t/m³ = 16.37 kN/m³ Ka = 1
Beban lalulintas 1.5 t/m³ = 15 kN/m Ø= 0°
M Dorong 1971.09 kNm c= 5 KN/m2
SF Rencana 1.3 H= 5 m
M Resistance Rencana 2562.42 kNm E= 0.8
ΔM Resistance Rencana 1639.9 kNm q 15 KN/m2

Jarak titik
longsor ke Sisa Tinggi T allow Momen ΔM τ1 τ2 Στ Le
No penahan Resistance Jumlah Le Lr Lo Ltot
Lapis geotekstile Timbunan
lapisan (Si) Lapis Keterangan (KN/m2) (KN/m2) (KN/m2) (m) pakai (m) sH (m) (m) (m)
(m) (KN/m') geotekstile kumulatif (m)
(m)
1 6.5 3.5 32.795 426.341 426.341 1 tambah lapis 29.6636 5 34.664 1.537 2 8.40 37.17 1 12
2 6.2 3.2 32.795 406.664 833.005 1 tambah lapis 27.5889 27.5889 55.178 0.966 1 8.29 35.27 1 11
3 5.9 2.9 32.795 386.987 1219.992 1 tambah lapis 25.5143 25.5143 51.029 1.044 2 8.14 33.37 1 12
4 5.6 2.6 32.795 367.309 1587.302 1 tambah lapis 23.440 23.440 46.879 1.137 2 7.97 31.47 1 11
5 5.3 2.3 32.795 347.632 1934.934 1 cukup 21.3651 21.3651 42.730 1.247 2 7.77 29.57 1 11

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
19
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

1.Check Internal Stability

Pa = 1/2 x Htimb2 x γtimb x Ka Berat ABC = LuasABC x γtimb x 1m tegak lurus


Pa = 38.792 kN = (1/2x5.25x3.5) x 19 x 1
tan δ = tan 2/3 φ = 174.563 kN
tan δ = tan 2/3 x 30° CHECK
tan δ = 0.36 38.7917 < 42.357 Maka AMAN
SF Jalan Permanen = 1.5
2. Check Overall Stability

SF = Mpenahan MReksis + ΔΣMR


> 1.3 > 1.3
Mpendorong Mpendorong

= 922.47 + 1639.9 1.450 > 1.3


> 1.3
1971.1 AMAN

3. Check Fondation Stability

s'v0 = 15 KN/m+2 3.5 m x 19 KN/m3


= 81.5 KN/m2

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
20
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

Pa2 = ( 81.5 KN/m2 - 2 x 5 KN/m2 ) + 0,5 x(30m)2 x 16.37 KN/m3


= 7724 KN/m'
Pp = 0,5 x(30m)2 x 16.4 KN/m3 + 2 x 5 KN/m2 30 m
= 7666.5 KN/m'
7724 < 7666.5 + 2 x 5 KN/m2 x 5.25 m
1.3
7724 > 5937.692
TIDAK AMAN
karna untuk kontrol foundation stability tidak aman, maka harus dilakukan
perbaikan tanah untuk tanah dasarnya dikarenakan tanah dasar terlalu lembek

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
21
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
22
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
23
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
24
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
25
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
26
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

DATA PERENCANAAN KASUS 1 ALTERNATIF 2:

Data Tanah Timbunan Data Tanah Asli


q Lalu lintas = 1.5 t/m² ϒ sat = 1.686 t/m³ Tult = 100 KN/m
ϒTimbunan = 1.9 t/m² ø = 0 FsID = 1.1
ø = 30 ˚ δ = 0 FSCR = 2
δ = 20 ˚ cu = 0.5 t/m² FSCD = 1
Tan δ = 0.364 Tan δ = 0 FSBD = 1
c = 0 c = 0.333 t/m² FSrencana = 1.5
HTimbunan = 6.5 m

INTERNAL STABILITY :
Ka = tan² (45-ø/2)
= tan² (45-30°/2)
Ka = 0.33333

1 Menghitung tekanan vertikal dan horisontal


∂v1 = q ∂h1 = (∂v1 x Ka) - 2c√ka
= 1.5 t/m² = 0.500 t/m²
∂v2 = ∂v1 + (ϒ x 6.5 m) ∂h2 = (∂v2 x Ka) - 2c√ka
= 1.5 + 12.35 = 4.617 t/m²
= 13.85 t/m²

2 Menghitung Sv ( Tebal Geotextile)


1
Tallow = Tult ( )
FSID x FSCR x FSCD x FSBD
1
= 100 ( )
1.1 x 2 x 1 x 1
= 45.455 KN/m
= 4.5455 t/m

contoh untuk kedalaman 6.5 m


Tallow 4.5455
Sv = = = 0.656 m → Sv Dipilih = 0.5 m
SF x ∂h 1.5 x 4.617

3 Menghitung Le ( Panjang geotextile yang berada dalam anchorage zone)


apabila nilai Le pada lapis paling bawah harus mengikutkan tanah
* khusus pada lapisan tanah
Sv x ∂h x FS
Le =
[(C1 + ∂v (tan δ1)] + [(C2 + ∂v (tan δ2)]
0.5 x 4.617 x 1.5
=
[(0 + (19 x 6.5) (tan 20)] + [(0.333 + (19 x 6.5) (tan 0)]

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
27
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

= 0.717 m → Le dipakai = 1 m

apabila nilai Le pada lapis berikutnya menggunakan rumus perhitungan sebagai berikut
Sv x ∂h x FS
Le =
2 x [(C + ∂v (tan δ)]

4 Menghitung LR (Panjang Geotextile yang berada didepan bidang longsor)


Contoh untuk kedalaman 6.5 m
LR = ( H - Z ) x tan (45-ø/2)
= (6.5 - 6.5) x tan (45-30/2)
= 0 m

5 Menghitung Lo (Panjang Lipatan Geotextile)


contoh untuk kedalam 6.5 m
1
Lo = x Le
2
1
= x 0.717 m
2
= 0.500 m → Lo dipakai = 1 m

6 Berikut tabel perhitungan Sv

Kedalaman Ơh SV-Pilih
No FS SV (m)
(m) (t/m²) (m)
1 6.5 4.617 1.5 0.66 0.5
2 6 4.300 1.5 0.70 0.5
3 5.5 3.983 1.5 0.76 0.5
4 5 3.667 1.5 0.83 0.5
5 4.5 3.350 1.5 0.90 0.5
6 4 3.033 1.5 1.00 1
7 3 2.400 1.5 1.26 1
8 2 1.767 1.5 1.72 1
9 1 1.133 1.5 2.67 1

Layer Depth Spacing Ơh Le Le L


Le Lr L Lo Lo min Lo used
No. (z) (m) SV (m) (t/m²) min used used
9 1 1 1.133 1.229 2 2 3.175 5.175 6 1 1 1
8 2 1 1.767 0.958 1 1 2.598 3.598 6 0.5 1 1
7 3 1 2.400 0.868 1 1 2.021 3.021 6 0.5 1 1
6 4 1 3.033 0.822 1 1 1.443 2.443 3 0.5 1 1
5 4.5 0.5 3.350 0.404 1 1 1.155 2.155 3 0.5 1 1
4 5 0.5 3.667 0.398 1 1 0.866 1.866 3 0.5 1 1

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
28
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

3 5.5 0.5 3.983 0.393 1 1 0.577 1.577 3 0.5 1 1


2 6 0.5 4.300 0.389 1 1 0.289 1.289 3 0.5 1 1
1 6.5 0.5 4.617 0.717 1 1 0.000 1.000 3 0.5 1 1

EXTERNAL STABILITY :
1 Cek terhadap guling
Pa1 = 0.5 t/m² x 6.5 m
= 3.250 Ton yp1 = 3.25 m
Pa1 Cos ø = 3.25 ton x cos 30°
= 2.815 Ton xp1 = 6.25 m
Pa1 Sin ø = 3.25 ton x sin 30°
= 1.625 Ton

Pa2 = 1/2 * (4.617 t/m²- 0.5 t/m²) x 6.5 m


= 13.379 Ton yp2 = 2.167 m
Pa2 Cos ø = 13.379 ton x cos 30°
= 11.587 Ton xp2 = 7.872 m
Pa2 Sin ø = 13.379 ton x sin 30°
= 6.690 Ton

W1 = 3 m x 6 m x 1 x 1.9 t/m² x1 = 3m
= 34.20 Ton
W2 = 3.5 m x 3 m x 1 x 1.9 t/m² x2 = 1.5 m
= 19.950 Ton

Momen Penahan Momen Pendorong


M1 = Pa1 sin ø x XP1 M1 = Pa1 cos ø x yP1
= 1.625 ton x 6.25 m = 2.815 ton x 3.25 m
= 10.156 T.m = 9.147 T.m
M2 = Pa2 sin ø x XP2 M2 = Pa2 cos ø x yP2
= 6.690 ton x 7.872 m = 11.587 ton x 2.167
= 52.662 T.m = 25.105 T.m
M3 = W1 x X1
= 34.20 ton x 3 m Ʃ M = M1 + M 2
= 102.60 T.m = 34.252 T.m
M4 = W2 x X2
= 19.950 ton x 1.5 m
= 29.925 T.m

ƩM = M1 + M 2 + M 3 + M 4
= 195.343 T.m

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
29
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

Ʃ M Penahan 195.343
SF = = = 5.703 > 3 OK
Ʃ M Pendorong 34.252

2 Cek Terhadap Geser


c + (ƩV/B) tan δ' B
SF =
Ʃ Pa cos δ

0.333 + (34.20 ton + 19.950 ton + 1.625 ton + 6.690 ton/3) x 0.364 x 3
SF =
2.815 ton + 11.587 ton
= 4.467 > 3 OK

3 Cek Terhadap Bearing Capacity (Daya dukung tanah)


c = 0.333 t/m²
Nc = 5.6
Nq = 1
Nϒ = 0

Pult = cNc + qNq + 0.5 B ϒ Nϒ


= (0.333 x 5.6) + 0 + (0.5 x 3 x 1.686 x 0)
= 1.867 t/m²

Pact = (ϒtimb x H) + c
= (1.9 t/m² x 6.5) + 0.333 t/m²
= 12.683 t/m²

Pult 1.867
SF = = = 0.147 > 3 NOT OK
Pact 12.683

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
30
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

DATA PERENCANAAN KASUS 1 ALTERNATIF 2:

Data Tanah Timbunan Data Tanah Asli


q Lalu lintas = 1.5 t/m² ϒ sat = 1.686 t/m³ Tult = 100 KN/m
ϒTimbunan = 1.9 t/m² ø = 0 FsID = 1.1
ø = 30 ˚ δ = 0 FSCR = 2
δ = 20 ˚ cu = 0.5 t/m² FSCD = 1
Tan δ = 0.364 Tan δ = 0 FSBD = 1
c = 0 c = 0.333 t/m² FSrencana = 1.5
HTimbunan = 6.5 m

INTERNAL STABILITY :
Ka = tan² (45-ø/2)
= tan² (45-30°/2)
Ka = 0.33333

1 Menghitung tekanan vertikal dan horisontal


∂v1 = q ∂h1 = (∂v1 x Ka) - 2c√ka
= 1.5 t/m² = 0.500 t/m²
∂v2 = ∂v1 + (ϒ x 6.5 m) ∂h2 = (∂v2 x Ka) - 2c√ka
= 1.5 + 12.35 = 4.617 t/m²
= 13.85 t/m²

2 Menghitung Sv ( Tebal Geotextile)


1
Tallow = Tult ( )
FSID x FSCR x FSCD x FSBD
1
= 100 ( )
1.1 x 2 x 1 x 1
= 45.455 KN/m
= 4.5455 t/m

contoh untuk kedalaman 6.5 m


Tallow 4.5455
Sv = = = 0.656 m → Sv Dipilih = 0.5 m
SF x ∂h 1.5 x 4.617

3 Menghitung Le ( Panjang geotextile yang berada dalam anchorage zone)


apabila nilai Le pada lapis paling bawah harus mengikutkan tanah
* khusus pada lapisan tanah
Sv x ∂h x FS
Le =
[(C1 + ∂v (tan δ1)] + [(C2 + ∂v (tan δ2)]
0.5 x 4.617 x 1.5
=
[(0 + (19 x 6.5) (tan 20)] + [(0.333 + (19 x 6.5) (tan 0)]

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
31
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

= 0.717 m → Le dipakai = 1 m

apabila nilai Le pada lapis berikutnya menggunakan rumus perhitungan sebagai berikut
Sv x ∂h x FS
Le =
2 x [(C + ∂v (tan δ)]

4 Menghitung LR (Panjang Geotextile yang berada didepan bidang longsor)


Contoh untuk kedalaman 6.5 m
LR = ( H - Z ) x tan (45-ø/2)
= (6.5 - 6.5) x tan (45-30/2)
= 0 m

5 Menghitung Lo (Panjang Lipatan Geotextile)


contoh untuk kedalam 6.5 m
1
Lo = x Le
2
1
= x 0.717 m
2
= 0.500 m → Lo dipakai = 1 m

6 Berikut tabel perhitungan Sv

Kedalaman Ơh SV-Pilih
No FS SV (m)
(m) (t/m²) (m)
1 6.5 4.617 1.5 0.66 0.5
2 6 4.300 1.5 0.70 0.5
3 5.5 3.983 1.5 0.76 0.5
4 5 3.667 1.5 0.83 0.5
5 4.5 3.350 1.5 0.90 0.5
6 4 3.033 1.5 1.00 1
7 3 2.400 1.5 1.26 1
8 2 1.767 1.5 1.72 1
9 1 1.133 1.5 2.67 1

Layer Depth Spacing Ơh Le Le L


Le Lr L Lo Lo min Lo used
No. (z) (m) SV (m) (t/m²) min used used
9 1 1 1.133 1.229 2 2 3.175 5.175 6 1 1 1
8 2 1 1.767 0.958 1 1 2.598 3.598 6 0.5 1 1
7 3 1 2.400 0.868 1 1 2.021 3.021 6 0.5 1 1
6 4 1 3.033 0.822 1 1 1.443 2.443 3 0.5 1 1
5 4.5 0.5 3.350 0.404 1 1 1.155 2.155 3 0.5 1 1
4 5 0.5 3.667 0.398 1 1 0.866 1.866 3 0.5 1 1

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
32
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

3 5.5 0.5 3.983 0.393 1 1 0.577 1.577 3 0.5 1 1


2 6 0.5 4.300 0.389 1 1 0.289 1.289 3 0.5 1 1
1 6.5 0.5 4.617 0.717 1 1 0.000 1.000 3 0.5 1 1

EXTERNAL STABILITY :
1 Cek terhadap guling
Pa1 = 0.5 t/m² x 6.5 m
= 3.250 Ton yp1 = 3.25 m
Pa1 Cos ø = 3.25 ton x cos 30°
= 2.815 Ton xp1 = 6.25 m
Pa1 Sin ø = 3.25 ton x sin 30°
= 1.625 Ton

Pa2 = 1/2 * (4.617 t/m²- 0.5 t/m²) x 6.5 m


= 13.379 Ton yp2 = 2.167 m
Pa2 Cos ø = 13.379 ton x cos 30°
= 11.587 Ton xp2 = 7.872 m
Pa2 Sin ø = 13.379 ton x sin 30°
= 6.690 Ton

W1 = 3 m x 6 m x 1 x 1.9 t/m² x1 = 3m
= 34.20 Ton
W2 = 3.5 m x 3 m x 1 x 1.9 t/m² x2 = 1.5 m
= 19.950 Ton

Momen Penahan Momen Pendorong


M1 = Pa1 sin ø x XP1 M1 = Pa1 cos ø x yP1
= 1.625 ton x 6.25 m = 2.815 ton x 3.25 m
= 10.156 T.m = 9.147 T.m
M2 = Pa2 sin ø x XP2 M2 = Pa2 cos ø x yP2
= 6.690 ton x 7.872 m = 11.587 ton x 2.167
= 52.662 T.m = 25.105 T.m
M3 = W1 x X1
= 34.20 ton x 3 m Ʃ M = M1 + M 2
= 102.60 T.m = 34.252 T.m
M4 = W2 x X2
= 19.950 ton x 1.5 m
= 29.925 T.m

ƩM = M1 + M 2 + M 3 + M 4
= 195.343 T.m

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
33
INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA
FAKULTAS TEKNIK SIPIL DAN PERENCANAAN
PROGRAM STUDI TEKNIK SIPIL

Ʃ M Penahan 195.343
SF = = = 5.703 > 3 OK
Ʃ M Pendorong 34.252

2 Cek Terhadap Geser


c + (ƩV/B) tan δ' B
SF =
Ʃ Pa cos δ

0.333 + (34.20 ton + 19.950 ton + 1.625 ton + 6.690 ton/3) x 0.364 x 3
SF =
2.815 ton + 11.587 ton
= 4.467 > 3 OK

3 Cek Terhadap Bearing Capacity (Daya dukung tanah)


c = 0.333 t/m²
Nc = 5.6
Nq = 1
Nϒ = 0

Pult = cNc + qNq + 0.5 B ϒ Nϒ


= (0.333 x 5.6) + 0 + (0.5 x 3 x 1.686 x 0)
= 1.867 t/m²

Pact = (ϒtimb x H) + c
= (1.9 t/m² x 6.5) + 0.333 t/m²
= 12.683 t/m²

Pult 1.867
SF = = = 0.147 > 3 NOT OK
Pact 12.683

TUGAS TIMBUNAN DAN KONSTRUKSI PENAHAN TANAH


KELOMPOK 6 (KELAS A)
34
DATA PERENCANAAN :

Data Tanah Timbunan Data Tanah Asli


q Lalu lintas = 1.5 t/m² ϒ sat = 1.686 t/m³ Tult = 100 KN/m
ϒTimbunan = 1.9 t/m² ø = 0 FsID = 1.1
ø = 30 ˚ δ = 0 FSCR = 2
δ = 20 ˚ cu = 0.5 t/m² FSCD = 1
Tan δ = 0.364 Tan δ = 0 FSBD = 1
c = 0 c = 0.333 t/m² FSrencana = 1.5
HTimbunan = 3.5 m

INTERNAL STABILITY :
Ka = tan² (45-ø/2)
= tan² (45-30°/2)
Ka = 0.33333

1 Menghitung tekanan vertikal dan horisontal


∂v1 = q ∂h1 = (∂v1 x Ka) - 2c√ka
= 1.5 t/m² = 0.500 t/m²
∂v2 = ∂v1 + (ϒ x 3.5 m) ∂h2 = (∂v2 x Ka) - 2c√ka
= 1.5 + 6.65 = 2.717 t/m²
= 8.15 t/m²

2 Menghitung Sv ( Tebal Geotextile)


1
Tallow = Tult ( )
FSID x FSCR x FSCD x FSBD
1
= 100 ( )
1.1 x 2 x 1 x 1
= 45.455 KN/m
= 4.5455 t/m

contoh untuk kedalaman 6.5 m


Tallow 4.5455
Sv = = = 1.115 m → Sv Dipilih = 0.75 m
SF x ∂h 1.5 x 4.617

3 Menghitung Le ( Panjang geotextile yang berada dalam anchorage zone)


apabila nilai Le pada lapis paling bawah harus mengikutkan tanah
* khusus pada lapisan tanah
Sv x ∂h x FS
Le =
[(C1 + ∂v (tan δ1)] + [(C2 + ∂v (tan δ2)]
0.5 x 4.617 x 1.5
=
[(0 + (19 x 6.5) (tan 20)] + [(0.333 + (19 x 6.5) (tan 0)]
= 1.110 m → Le dipakai = 1 m
apabila nilai Le pada lapis berikutnya menggunakan rumus perhitungan sebagai berikut
Sv x ∂h x FS
Le =
2 x [(C + ∂v (tan δ)]

4 Menghitung LR (Panjang Geotextile yang berada didepan bidang longsor)


Contoh untuk kedalaman 6.5 m
LR = ( H - Z ) x tan (45-ø/2)
= (6.5 - 6.5) x tan (45-30/2)
= 0 m

5 Menghitung Lo (Panjang Lipatan Geotextile)


contoh untuk kedalam 6.5 m
1
Lo = x Le
2
1
= x 0.717 m
2
= 0.500 m → Lo dipakai = 1 m

6 Berikut tabel perhitungan Sv

Kedalaman Ơh SV-Pilih
No FS SV (m)
(m) (t/m²) (m)
1 3.5 2.717 1.5 1.12 0.75
2 2.75 2.242 1.5 1.35 0.75
3 2 1.767 1.5 1.72 1
4 1 1.133 1.5 2.67 1

Layer Depth Spacing Ơh Le Le L


Le Lr L Lo Lo min Lo used
No. (z) (m) SV (m) (t/m²) min used used
4 1 1 1.133 1.229 2 2 1.443 3.443 4 1 1 1
3 2 1 1.767 0.958 2 2 0.866 2.866 4 1 1 1
2 2.75 0.75 2.242 0.663 2 2 0.433 2.433 4 1 1 1
1 3.5 0.75 2.717 1.110 2 2 0.000 2.000 4 1 1 1

EXTERNAL STABILITY :
1 Cek terhadap guling
Pa1 = 0.5 t/m² x 3.5 m
= 1.750 Ton yp1 = 1.75 m
Pa1 Cos ø = 1.75 ton x cos 30°
= 1.516 Ton xp1 = 4.25 m
Pa1 Sin ø = 1.75 ton x sin 30°
= 0.875 Ton

Pa2 = 1/2 * (2.717 t/m²- 0.5 t/m²) x 3.5 m


= 7.204 Ton yp2 = 1.167 m
Pa2 Cos ø = 7.204 ton x cos 30°
= 6.239 Ton xp2 = 5.239 m
Pa2 Sin ø = 7.204 ton x sin 30°
= 3.602 Ton

W1 = 3.5 m x 4 m x 1 x 1.9 t/m² x1 = 2m


= 26.60 Ton

Momen Penahan Momen Pendorong


M1 = Pa1 sin ø x XP1 M1 = Pa1 cos ø x yP1
= 0.875 ton x 4.25 m = 1.516 ton x 1.75 m
= 3.719 T.m = 2.652 T.m
M2 = Pa2 sin ø x XP2 M2 = Pa2 cos ø x yP2
= 3.602 ton x 5.239m = 6.239 ton x 1.167
= 18.871 T.m = 7.279 T.m
M3 = W1 x X1
= 36.60 ton x 2 m Ʃ M = M1 + M 2
= 53.20 T.m = 9.931 T.m

ƩM = M1 + M 2 + M 3 +
= 75.790 T.m

Ʃ M Penahan 75.790
SF = = = 7.632 > 3 OK
Ʃ M Pendorong 9.931

2 Cek Terhadap Geser


c + (ƩV/B) tan δ' B
SF =
Ʃ Pa cos δ

0.333 + (26.60 ton + 0.875 ton + 3.602 ton/4) x 0.364 x 4


SF =
1.516 ton + 6.239 ton
= 5.499 > 3 OK

3 Cek Terhadap Bearing Capacity (Daya dukung tanah)


c = 0.333 t/m²
Nc = 5.6
Nq = 1
Nϒ = 0
Pult = cNc + qNq + 0.5 B ϒ Nϒ
= (0.333 x 5.6) + 0 + (0.5 x 3 x 1.686 x 0)
= 1.867 t/m²

Pact = (ϒtimb x H) + c
= (1.9 t/m² x 3.5) + 0.333 t/m²
= 6.983 t/m²

Pult 1.867
SF = = = 0.267 > 3 NOT OK
Pact 6.983