NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
1 Cement and sand (1:3)
with an approved Trowel 3 Plasterer workers output 9 days
2,074m2 = 3.5m2/h
plasticizer as specified;
steel troweled to: - Bucket 6 general labor
19mm Thick plastering in 3.5m2/hr x 9 =
two coats troweled finish 31.5m2/hr
to exposed surfaces of
brick wall and exposed (2,074m2/31.5
concrete surfaces m2/hr)/8hr =
internally to be skimmed 8.23 days
to a fine finish
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: INTERNAL WALL FINISHES (Tiling Work) (masjid) PAGE NO: 2/4

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
2 Supply and lay tiles size
300mm x 300mm bedded 50m2 Hammer 2 Plasterer workers output 1 day
and jointed in cement = 2.60m2/h
mortar (1:3) on and Tiles cutter 2 general labor
including cement and 2.60m2/hr 4 =
sand (1:3) screeded Trowel 10.4m2/hr
backing to manufacture
Measuring (50m2/10.4m2/
detail
tape hr)/8hr = 0.6
day
Pencil

Wheel barrow

Buckets
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: INTERNAL WALL FINISHES (Painting) (masjid) PAGE NO: 3/4

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
3 Prepare and apply one
undercoat and two 2,074m2 Paint brush 4 painters workers output 6 days
finishing coats of = 5.0m2/hr
emulsion paint to Paint roller 5 general labor
surfaces of plastered 5.0m2/hr x 9 =
brick wall. Roller tray 45m2/hr

Frame (2,074m2/45m2
/hr)/8 hr = 5.76
Scaffolding days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: INTERNAL WALL FINISHES (Pebble wash) (masjid) PAGE NO: 4/4

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
4 Pebble wash of approved
quality, standard color 120m2 Measuring 1 skilled labor workers output 2 days
and pattern, bedded and tape = 2.7m2/h
jointed on cement and 2 general labor
sand (1:3) screed and Spirit level 2.7m2/h x 3 =
pointed with matching 8.1m2/hr
colored cement to wall Trowel
(120m2/8.1m2/
buckets hr)/8hr = 1.85
days