Professional Documents
Culture Documents
Three Dimensional Strut and Tie Analysis
Three Dimensional Strut and Tie Analysis
Abstract: A 3D indeterminate strut-and-tie model is developed for the analysis of a footing system to explain the cause of cracking and
to develop a rehabilitation solution. The performance predicted with the model, simulating the sequence of construction, is well correlated
Downloaded from ascelibrary.org by UNIVERSITE LAVAL on 06/20/14. Copyright ASCE. For personal use only; all rights reserved.
with the field observations. The prediction thus explains the cause of cracking and concludes that phased construction is its main source.
From numerical prediction, posttensioning forces are recommended to close the existing cracks and to prevent new ones. In developing
an approach to rehabilitating a cracked structure, the stiffness of the analytical model needs to be properly selected. For this reason, five
different levels of stiffness are used to cover the lower and upper bounds for both cracked and uncracked situations. A 3D finite-element
solid modeling is also conducted.
DOI: 10.1061/共ASCE兲1084-0680共2002兲7:1共14兲
CE Database keywords: Footings; Rehabilitation; Three-dimensional models; Struts; Ties; Cracking.
The remaining force in the column goes directly to the interior known to develop a rehabilitation method. Since the structure is
piles represented by nodes 36 and 48. indeterminate, the dimensions of each member affect the internal
The elevation view, Fig. 4共a兲, shows the force flows in the longi- force distribution. The stiffness of the struts and ties is loading/
tudinal direction of the footing. It can be seen that the column cracking dependent. In a typical design process that considers
forces are distributed among a few piles, either directly to the top only the strength limit, the sizes of struts and ties are first as-
of the piles or to the top of the footer first and then to the top of sumed and then optimized. Several iterations are usually con-
the piles. ducted, and the final design provides detailings to match the as-
The isometric view is given in Fig. 4共b兲. For clarity, only a partial sumptions. For this existing structure, whose structural
model is shown. The possible tension members are defined as performance from service to strength limits needs to be investi-
tension ties 共dashed lines兲, and compression members are defined gated, the stiffness 共or size兲 of each strut and tie member varies,
as compression struts 共solid lines兲. These assumptions were veri-
depending on the loading level, i.e., the service or strength limit
fied by analysis. In other words, if the analysis predicted a com-
states. By assuming no cracking for the piles, the actual sizes of
pressive force in a tension tie, then the tie would be changed into
piles, 0.61⫻0.61 m (24⫻24 in.), were used to model the pile
a compression strut and vice versa.
In the present analytical model, all 48 piles that are 24.4 m 共80 ft兲 elements. However, the sizes of struts and ties were varied to
in length are assumed pinned at the bottom tips. In addition, two consider the effect of cracking.
piles are restrained at the top in the X and Y directions for nu- Three models were used to simulate the uncracked situation
merical stability. The piles are modeled with beam elements. 共strictly speaking, cracking is required to form a strut-and-tie
The existing force distribution in the footing system needs to be model兲. The objective of simulating an uncracked structure was to
predict the distribution of internal forces before cracking, which
may help explain the cracking patterns and the cause of cracking.
In the model designated as F12, all ties and struts were assumed
as 0.3⫻0.3 m (12⫻12 in.). In the model designated as F120, the
struts and ties were assumed to be 100 times as stiff as model F12
to consider the large stiffness of concrete footer and pile cap
before cracking. These two models, F12 and F120, should cover
the lower and upper bounds of stiffness before cracking. Given
the pile size of 0.61⫻0.61 m (24⫻24 in.), and the footer of 2.44
m 共96 in.兲 in width, the strut members were assumed as 0.61
⫻0.61 m (24⫻24 in), and the ties as one-half the footer width,
i.e., 1.22⫻1.22 m (48⫻48 in.) in the model Tie 48. The stiffness
of this model lies between the F12 and F120 models.
Two more models were used to simulate the cracked section and
to predict the existing internal force distribution of the footing
system. In model Tie3.3, the transformed area of each tie was
assumed as 84⫻84 mm (3.3⫻3.3 in.) that corresponds to the ac-
tual area of reinforcement 共3.11 in2兲 of the footer. In another
model, Tie01, which simulates the situation after the reinforce-
ment is broken, the sectional area of each tie was assumed as
2.5⫻2.5 mm (0.1⫻0.1 in.), a small nonzero number to prevent
numerical instability. In all analyses, the material properties of all
Fig. 2. Sketch of substructure 共pier 5兲
Fig. 3. Cracks 关共a兲 on top of; 共b兲 on side兴 of typical column footer 共pier 5兲
members were specified as concrete with f c⬘ ⫽28 MPa. As stated analysis of phase 1 loads, only the right portion of Fig. 2 that was
earlier, transformed areas were used for those ties that simulate constructed in phase 1 was modeled. For the analysis of phase 2
the reinforcement. loads, the whole structure was modeled as a unit, i.e., there is no
separation between the phase 1 and phase 2 structures. The loads
from phase 2 construction were applied on the phase 2 structure,
Application of Load
i.e., the left part in Fig. 2.
To simulate the two-phase construction, the application of loads Since loads can only be applied to the nodes in a strut-and-tie
to the model followed the sequence of construction. For the model, appropriate assumptions should be made to distribute the
Posttensioning Top of footer 2,224 共500兲 2 nodes each end 1,112 共250兲 PT t1
force for 共1, 4兲 and 共3, 6兲
service Bottom of footer 4,448 共1,000兲 2 nodes each end 2,224 共500兲 PT b1
共7, 10兲 and 共9, 12兲
Posttensioning Top of footer 2,224 共500兲 2 nodes each end 1,112 共250兲 PT t2
force for 共1, 4兲 and 共3, 6兲
ultimate
Bottom of footer 6,672 共1,500兲 2 nodes each end 3,336 共750兲 PT b2
共7, 10兲 and 共9, 12兲
loads to the nodes. As will be seen below, the self-weight of the Possibility of Cracking
substructure is about 47% of the total service load. The method of
applying the self-weight of the substructure in the strut-and-tie According to the construction drawings, the reinforcement pro-
model significantly influences the member forces. In this study, vided at the top of the footer is 2,006 mm2 共3.11 in.2兲, which
the self-weights of the pile cap, footer, and column were applied results in a capacity of 830 kN 共186.6 kips兲. The predicted total
to the nodes at the top of piles, the top of the pile cap, and the top tension force at the top of the footer constructed at phase 1 is
of the column footer, respectively, following the construction pro- calculated as twice the force of member 2 共along the footing tie兲
cess. The load calculations are summarized in Table 1, and load plus the along-footing component of member 11 共diagonal tie兲.
applications are shown in Fig. 5. For example, for the lower-bound force model F12 under service
After phase 1 construction, the structure experienced the self- load case DLL2 共column 7, Table 3兲, the total tension force at the
weight as well as live load ( P 5 ) shown in Fig. 5共a兲. After phase 2 top of footer is
construction, in addition to the self-weight of phase 1 that had 2x 共 367.2⫹365.5x cos共 7.13兲兲 ⫽1,459.8 kN
already been locked into the phase 1 structure, the entire structure
experienced the self-weight from phase 2 construction as well as As discussed earlier, models F12, F120, and Tie48 were intended
the live load 共P 11 and P 5 兲 shown in Fig. 5共b兲. The recommended to predict the precracking stresses. All these models predicted
posttensioning forces are also listed in Table 1 and shown in Fig. larger forces under the service load 共DLL2兲 at the top of the
5共b兲. These posttensioning forces were applied to the top and footer than the provided capacity. A similar calculation for the
bottom of the column footer to close the cracks and prevent new footer constructed at phase 2 gives a total tensile force of 903 kN
ones. Further discussion of these posttensioning forces will be that is also larger than the capacity of 830 kN. This observation
conducted later. indicates an underdesign of reinforcement and explains the trans-
It is noted that the live loads were assumed to be evenly dis- verse crackling at the top of the footer.
tributed to the column nodes in the calculations shown in Table 1. Model Tie3.3, intended to model the cracked section, predicted
Therefore, the middle column nodes 2 and 5 take the same live tension forces for members 174 and 175 under both dead load and
load as nodes 3 and 6 in phase 1 analysis, but take twice ( P 11 service load 共columns 6 and 7兲. This indicates that cracking on the
⫹ P 5 ) the live load of side column nodes 1, 3, 4, and 6 in the side faces of the footer is also possible, following the cracking of
phase 2 analysis. This is not completely accurate since the live the top of the footer. Predicted tension forces in members 6, 7,
load may shift more closely to one side. However, since the live and 11 also explain the along-footer cracking at the top of the
load plus impact 3,496 kN 共786 kips兲 is a small part of the total footer.
service load 34,975 共7,863 kips兲, the above approximation is ac-
ceptable for the substructure analysis in this study. Phased Construction
Two observations were made from Table 3. First, for models F12,
Analysis Results F120, and Tie48, the tie forces of members 2, 11, and 22 共built in
phase 1兲 are significantly larger than those of their counterparts,
The load cases examined in this study are summarized in Table 2. members 1, 8, and 19 共built in phase 2兲 under dead load DL2,
For convenience of discussion, the numbering definitions of service load DLL2, and ultimate load UDLL2. This explains why
members are shown in Fig. 6. Again, only a partial model is the cracking of the footer built in phase 1 is much more severe
shown for clarity. The predicted forces of selected members are than that of phase 2.
summarized in Table 3. As discussed earlier, the true stiffness of Second, for typical phase 1 tie members 2, 11, and 22, the dead-
each member is not known for a section with cracks. Therefore, load case DL 共column 9, which assumes a nonphased construc-
the member forces of all five models discussed earlier were ex- tion兲 predicts less tension forces than does the corresponding load
amined under all the load cases to predict the lower and upper case DL2 共column 6, which considers phased construction兲. This
bounds of forces. A few observations were made as follows. indicates that phased construction is more critical for cracking
2 F12 288.89 330.82 466.55 331.70 367.24 508.33 242.69 ⫺183.24 ⫺95.72
2 F120 324.24 368.99 518.61 378.39 410.05 560.62 245.82 ⫺254.81 ⫺171.21
2 Tie48 313.75 358.38 504.73 356.28 389.74 535.78 239.03 ⫺205.36 ⫺88.86
⫺14.43 ⫺0.55
Downloaded from ascelibrary.org by UNIVERSITE LAVAL on 06/20/14. Copyright ASCE. For personal use only; all rights reserved.
8 F12 0.00 0.00 0.00 190.20 225.16 323.12 237.89 ⫺315.51 ⫺269.81
8 F120 0.00 0.00 0.00 206.79 238.04 336.64 241.59 ⫺415.35 ⫺382.31
8 Tie48 0.00 0.00 0.00 196.54 229.44 326.89 234.06 ⫺355.27 ⫺286.57
8 Tie3.3 0.00 0.00 0.00 37.39 43.01 60.79 39.85 ⫺55.50 ⫺54.05
8 Tie01 0.00 0.00 0.00 0.04 0.05 0.06 0.03 ⫺0.04 ⫺0.04
11 F12 286.09 327.67 462.15 329.45 365.50 506.50 246.03 ⫺186.31 ⫺102.59
11 F120 319.27 363.43 510.88 373.99 405.92 555.48 246.38 ⫺247.88 ⫺164.12
11 Tie48 309.73 353.88 498.45 352.52 386.55 532.12 242.23 ⫺201.59 ⫺86.47
11 Tie3.3 78.49 89.49 125.91 80.49 86.29 117.21 41.17 ⫺14.41 ⫺0.54
11 Tie01 0.10 0.11 0.16 0.10 0.11 0.15 0.05 ⫺0.01 0.01
19 F12 0.00 0.00 0.00 103.90 125.95 182.91 164.18 ⫺442.50 ⫺642.81
19 F120 0.00 0.00 0.00 263.42 311.56 446.91 348.23 ⫺391.73 ⫺575.06
19 Tie48 0.00 0.00 0.00 198.10 239.00 346.28 302.06 ⫺660.79 ⫺988.87
19 Tie3.3 0.00 0.00 0.00 13.09 15.51 22.26 17.72 ⫺29.31 ⫺36.54
19 Tie01 0.00 0.00 0.00 0.01 0.01 0.02 0.01 ⫺0.02 ⫺0.02
22 F12 123.40 137.72 191.49 165.59 186.90 261.52 158.70 ⫺374.04 ⫺553.31
22 F120 423.97 477.90 668.19 473.05 520.60 718.14 344.02 ⫺182.33 ⫺303.26
22 Tie48 266.39 298.20 415.33 337.35 377.33 525.31 295.47 ⫺519.69 ⫺805.70
22 Tie3.3 21.79 24.65 34.54 25.26 27.70 38.13 17.92 ⫺17.46 ⫺21.11
22 Tie01 0.03 0.03 0.05 0.03 0.04 0.05 0.03 ⫺0.02 ⫺0.02
174 F12 ⫺148.82 ⫺170.32 ⫺240.13 ⫺217.63 ⫺270.35 ⫺397.32 ⫺319.73 ⫺392.67 ⫺580.35
174 F120 ⫺112.66 ⫺128.36 ⫺180.53 ⫺143.08 ⫺190.98 ⫺289.94 ⫺271.38 ⫺243.82 ⫺347.81
174 Tie48 ⫺161.11 ⫺183.88 ⫺258.86 ⫺229.67 ⫺285.47 ⫺419.66 ⫺343.08 ⫺312.99 ⫺462.18
174 Tie3.3 363.08 413.35 581.10 205.56 158.47 165.06 ⫺275.80 ⫺35.47 ⫺107.62
174 Tie01 514.40 586.25 824.64 330.09 283.45 327.90 ⫺268.16 75.21 39.89
175 F12 ⫺429.62 ⫺491.39 ⫺692.55 ⫺513.00 ⫺565.74 ⫺781.35 ⫺365.30 ⫺693.52 ⫺871.48
175 F120 ⫺417.23 ⫺474.00 ⫺665.59 ⫺501.43 ⫺535.22 ⫺725.19 ⫺284.63 ⫺573.51 ⫺753.23
175 Tie48 ⫺491.07 ⫺559.66 ⫺787.22 ⫺578.82 ⫺630.35 ⫺864.30 ⫺376.80 ⫺635.31 ⫺850.07
175 Tie3.3 143.05 162.83 228.88 159.58 181.62 255.28 152.20 ⫺1,134.43 ⫺1,218.95
175 Tie01 334.85 381.62 536.80 355.32 391.07 539.50 249.47 ⫺1,157.67 ⫺1,209.39
than nonphased construction and also that phased construction is force provided, designated as load case PT – DLL2 in Table 2, are
the main cause of the severe cracking of phase 1 structure. given in column 10, Table 3. In the second case, to obtain com-
pression forces under the ultimate-load case, posttensioning
forces of 2,224 kN 共500 kips兲 and 6,672 kN 共1,500 kips兲 were
Posttensioning Force applied at the top and bottom of the footer, respectively 共Table 1兲.
To close the cracking on the top of the footing, i.e., to obtain This case is designated as load case PT – UDLL2 in Table 2, and
compression force in members such as 2 and 11, two levels of the results are shown in column 11, Table 3.
posttensioning forces were examined. In the first case, to gain To avoid future cracking due to overloading and other environ-
compression under service load, 2,224 kN 共500 kips兲 and 4,448 mental effects, such as temperature change, the higher values of
kN 共1,000 kips兲 posttensioning forces were applied at the top and 2,224 kN 共500 kips兲 and 6,672 kN 共1,500 kips兲 were recom-
bottom of the footing, respectively 共Table 1兲. The total member mended. These forces correspond to two and six tendons 共with
forces resulting from the service load plus the posttensioning 7-0.6⬙ strands兲 at the top and bottom of the footer, respectively.
10 204 ⫺258.85 ⫺785.38 ⫺448.08 ⫺280.05 ⫺250.92 ⫺238.33 ⫺641.17 ⫺399.33 ⫺264.90 ⫺249.59
11 205 ⫺388.78 ⫺653.47 ⫺535.99 ⫺560.79 ⫺568.12 ⫺387.58 ⫺657.40 ⫺541.47 ⫺562.59 ⫺566.12
12 206 ⫺410.42 ⫺502.43 ⫺479.29 ⫺757.28 ⫺811.57 ⫺446.77 ⫺658.26 ⫺559.32 ⫺784.49 ⫺812.60
13 207 ⫺1,089.60 ⫺702.08 ⫺862.45 ⫺1,111.22 ⫺1,160.36 ⫺1,041.50 ⫺674.01 ⫺814.64 ⫺1,132.70 ⫺1,185.50
14 208 ⫺948.59 ⫺629.49 ⫺778.49 ⫺823.12 ⫺832.06 ⫺1,004.39 ⫺672.33 ⫺829.38 ⫺902.30 ⫺914.86
15 209 ⫺689.70 ⫺557.16 ⫺669.25 ⫺506.80 ⫺474.26 ⫺848.04 ⫺671.36 ⫺819.03 ⫺658.24 ⫺631.58
16 210 ⫺556.67 ⫺486.18 ⫺577.94 ⫺344.09 ⫺294.32 ⫺778.81 ⫺671.15 ⫺806.02 ⫺566.42 ⫺526.63
17 211 ⫺514.53 ⫺416.38 ⫺506.12 ⫺423.22 ⫺403.66 ⫺863.86 ⫺673.55 ⫺837.70 ⫺778.28 ⫺766.03
18 212 ⫺1,722.84 ⫺989.92 ⫺1,300.24 ⫺1,551.43 ⫺1,623.35 ⫺1,284.27 ⫺677.20 ⫺953.19 ⫺947.55 ⫺946.08
19 213 ⫺1,485.43 ⫺914.17 ⫺1,167.08 ⫺1,248.75 ⫺1,269.90 ⫺1,287.23 ⫺677.31 ⫺954.38 ⫺949.50 ⫺946.12
20 214 ⫺917.27 ⫺836.47 ⫺948.24 ⫺837.39 ⫺804.62 ⫺869.63 ⫺673.84 ⫺840.30 ⫺783.58 ⫺766.15
21 215 ⫺850.10 ⫺764.61 ⫺895.64 ⫺452.93 ⫺329.55 ⫺794.80 ⫺671.69 ⫺812.17 ⫺576.16 ⫺526.86
22 216 ⫺845.92 ⫺692.95 ⫺839.96 ⫺496.05 ⫺416.86 ⫺831.86 ⫺670.36 ⫺810.63 ⫺647.40 ⫺631.32
23 217 ⫺974.67 ⫺623.20 ⫺791.66 ⫺845.16 ⫺860.19 ⫺995.16 ⫺671.56 ⫺823.68 ⫺898.35 ⫺914.77
24 218 ⫺967.66 ⫺554.06 ⫺712.19 ⫺1,141.24 ⫺1,240.31 ⫺1,038.82 ⫺673.43 ⫺811.39 ⫺1,135.16 ⫺1,185.58
25 219 ⫺1,089.62 ⫺701.87 ⫺861.94 ⫺1,111.86 ⫺1,160.35 ⫺1,041.56 ⫺673.45 ⫺811.79 ⫺1,135.31 ⫺1,185.48
26 220 ⫺946.91 ⫺629.20 ⫺777.51 ⫺822.80 ⫺832.06 ⫺996.71 ⫺671.57 ⫺823.90 ⫺901.00 ⫺914.88
27 221 ⫺686.38 ⫺556.78 ⫺667.77 ⫺505.57 ⫺474.28 ⫺832.85 ⫺670.36 ⫺810.77 ⫺653.15 ⫺631.66
28 222 ⫺559.50 ⫺486.37 ⫺578.99 ⫺345.46 ⫺294.34 ⫺791.75 ⫺671.66 ⫺811.86 ⫺572.08 ⫺526.72
29 223 ⫺515.51 ⫺416.48 ⫺506.54 ⫺423.87 ⫺403.67 ⫺868.37 ⫺673.82 ⫺840.04 ⫺780.96 ⫺766.05
30 224 ⫺1,723.46 ⫺990.04 ⫺1,300.20 ⫺1,553.87 ⫺1,623.38 ⫺1,286.12 ⫺677.27 ⫺954.08 ⫺947.19 ⫺946.03
31 225 ⫺1,482.24 ⫺914.26 ⫺1,166.26 ⫺1,246.63 ⫺1,269.85 ⫺1,283.24 ⫺677.16 ⫺952.90 ⫺945.27 ⫺945.98
32 226 ⫺912.13 ⫺836.56 ⫺946.93 ⫺831.11 ⫺804.49 ⫺862.61 ⫺673.53 ⫺837.44 ⫺775.70 ⫺765.93
33 227 ⫺836.87 ⫺764.68 ⫺893.04 ⫺440.96 ⫺329.33 ⫺775.76 ⫺671.12 ⫺805.69 ⫺562.41 ⫺526.50
34 228 ⫺858.32 ⫺693.10 ⫺842.90 ⫺510.00 ⫺417.17 ⫺849.03 ⫺671.36 ⫺819.17 ⫺664.04 ⫺631.92
35 229 ⫺981.88 ⫺623.32 ⫺793.65 ⫺850.33 ⫺860.29 ⫺1,005.82 ⫺672.34 ⫺829.58 ⫺904.91 ⫺914.97
36 230 ⫺970.17 ⫺554.18 ⫺713.34 ⫺1,138.34 ⫺1,240.21 ⫺1,043.94 ⫺674.03 ⫺814.99 ⫺1,132.73 ⫺1,185.40
37 231 ⫺443.06 ⫺684.62 ⫺581.96 ⫺748.14 ⫺772.57 ⫺447.07 ⫺658.40 ⫺559.72 ⫺784.98 ⫺812.61
38 232 ⫺367.00 ⫺617.12 ⫺508.99 ⫺524.85 ⫺527.57 ⫺387.82 ⫺657.44 ⫺541.60 ⫺562.58 ⫺566.11
39 233 ⫺208.48 ⫺536.68 ⫺331.51 ⫺232.63 ⫺218.63 ⫺238.47 ⫺641.20 ⫺399.43 ⫺264.75 ⫺249.58
40 234 ⫺160.68 ⫺418.46 ⫺219.68 ⫺184.07 ⫺178.85 ⫺192.99 ⫺582.38 ⫺275.32 ⫺239.95 ⫺236.57
41 235 ⫺203.00 ⫺386.53 ⫺276.33 ⫺249.57 ⫺245.90 ⫺289.41 ⫺631.71 ⫺419.26 ⫺402.54 ⫺402.41
42 236 ⫺728.91 ⫺1,013.50 ⫺905.67 ⫺1,062.11 ⫺1,099.43 ⫺495.04 ⫺658.77 ⫺618.04 ⫺627.26 ⫺631.63
43 237 ⫺547.23 ⫺845.58 ⫺728.86 ⫺794.09 ⫺811.43 ⫺494.18 ⫺658.76 ⫺617.63 ⫺626.75 ⫺631.62
44 238 ⫺281.39 ⫺658.53 ⫺423.68 ⫺388.35 ⫺382.87 ⫺289.55 ⫺631.89 ⫺419.47 ⫺402.69 ⫺402.41
45 239 ⫺178.65 ⫺469.89 ⫺250.01 ⫺176.20 ⫺162.08 ⫺193.68 ⫺582.49 ⫺275.64 ⫺240.35 ⫺236.58
46 240 ⫺258.22 ⫺785.40 ⫺447.92 ⫺279.49 ⫺250.91 ⫺237.51 ⫺641.17 ⫺398.85 ⫺264.27 ⫺249.56
47 241 ⫺388.25 ⫺653.56 ⫺535.88 ⫺560.52 ⫺568.11 ⫺386.84 ⫺657.89 ⫺541.15 ⫺562.28 ⫺566.11
48 242 ⫺411.50 ⫺502.67 ⫺479.73 ⫺758.31 ⫺811.59 ⫺448.82 ⫺659.52 ⫺560.90 ⫺785.89 ⫺812.63
Max⫽ ⫺160.68 ⫺386.53 ⫺219.68 ⫺175.69 ⫺162.07 ⫺192.79 ⫺582.38 ⫺275.28 ⫺239.72 ⫺236.56
Min⫽ ⫺1,723.46 ⫺1,013.50 ⫺1,300.24 ⫺1,553.87 ⫺1,623.38 ⫺1,287.23 ⫺677.31 ⫺954.38 ⫺1,135.31 ⫺1,185.58
Fig. 10. Stress in along-footing direction under substructure dead load 共nonphased construction兲
Fig. 11. Stress in along-footing direction under total dead load 共nonphased construction兲
Fig. 12. Stress in along-footing direction under total dead load 共phased construction兲