Daewoo Engineering & Construction said on October 25 that it has won a project to build gas-fueled
combined cycle thermal power plants in Algeria at US$1,113 million. The project calls for building
1,200-megawatt power plants (three 400-MW plants) in Cap Djinet, Boumerdes Province, 65 kilometers
east of Algiers, the capital of Algeria.
The project was commissioned by the Algerian Society for Electricity Production (SPE), an affiliate of
the state-owned electricity utility Sonelgaz (National Society for Electricity and Gas).
The length of the construction project is three years and four months, with Daewoo E&C taking charge
of all processes from design, engineering, procurement, construction, and management.
sunee@hankyung.com
enews@hankyung.com
Article in Korea
이번 프로젝트는 알제리의 수도 알제에서 동쪽으로 65㎞ 떨어진 부메르데스주 캅지넷 지역에 1200㎿
급(400㎿급 3기) 발전소를 짓는 공사다.
english.hankyung.com/news/apps/news.view?nkey=201210261101181&setct=print&popup=1 1/2