LETTER OF TRANSMITTAL FOR VENDOR DOCUMENTS

To, CLIENT: DATE:


M/s.Amazon seller services
30.12.19
Private Limited

PROJECT: CONTRACTOR
TRANSMITTAL NO. &
DATE:
PROPOSED CCU1
E-Mail Dated 26.12.19
Warehouse at Kolkata.
M/S FLUIDLINE ENGINEERS &
FAB. PVT. LTD.

SUBJECT: CRN REF. NO.:


FPS -Shop drawings-
Approval
PL-191228-12:AMZCCU1-3
Dear Sir,

We are herein conveying our approval/ comments on the documents listed below. Approval/ comments conveyed herein neither
relieves the vendor/ contractor of his contractor of his contractual obligations and his responsibilities for correctness of
dimensions, materials of construction, weights, quantities, design details, assembly fits, performance requirements and conformity
of the supplies with the Local statutory Laws as may be applicable, nor does it limit the purchaser's rights under the contract.

Yours faithfully

For C.R. Narayana Rao (Consultants) Private Limited

R.Palaniappan
Associate Vice President - Mechancal

CODE
A. Document approved as submitted; proceed with fabrication/ F. Correct original of the document to reflect our
construction. comments and resubmit for records.

B. Document approved subject to comments noted proceed G. Documents of this category are for information
with fabrication/ construction considering our comments. only and not for approval information furnished on
the document is noted.

C. Our comments are noted on the enclosed marked-up print. H. Document reviewed only against our previous
comments and other revisions highlighted and
identified by the vendor.

D. Our comments are noted in the enclosure/ attached to this transmittal. I. Document returned without review.

E. Correct original of the document to reflect our comments J. Print not enclosed.
and resubmit for approval.

Sl. No. Vendor's Ref. No. Title Make Code

SHOP DRAWINGS
FIRE SPRINKLER & WATER CURTAIN
1 ESR-WH-08-SPK-02 RO E
SYSTEM LAYOUT FOR PHASE-2
WATER CURTAIN SYSTEM LAYOUT
2 ESR-WH-08-CUR-04 RO E
FOR PHASE-2
FIRE SPRINKLER SYSTEM LAYOUT
3 ESR-WH-08-SPK-03 RO E
FOR MEZZANINE FLOOR PHASE-2
FIRE HYDRANT SYSTEM LAYOUT
4 ESR-WH-08-HYD-01 RO E
FOR PHASE-2
FIRE WATER CURTAIN SYSTEM
5 ESR-WH-08-CUR-05 LAYOUT FOR MEZZANINE FOR RO E
PHASE-2
FIRE SPRINKLER DROPPER LAYOUT
6 ESR-WH-08-SPK-06 RO B
FOR PHASE-2
(Please tick the relevant column)

Main Contractor PMC Client Others

M/s.Amazon seller
services Private Limited

COMMENTS
1 FLEPL/BOM07/DS/15 / Rev 0 / FIRE SPRINKLER & WATER CURTAIN SYSTEM LAYOUT FOR PHASE-2
a Sprinkler locations shall be coordinated with rafters,cross bracings and it shall shown in the drawing.
b Additional Support for Branchlines,Mains Shall be provided as per FMDS - 2-0 Clause 2.5.4.5.2.2 & 2.5.4.5.2.3
c Provide at least one pipe support every 12 ft (3.6 m) for vertical run as per FMDS 2-0.
d Pipe support load calculations shall be submitted as per FMDS 2-0.
e Hydraulic calculations for water curtian system shall be subnitted for our review.

2 ESR-WH-08-CUR-04 / WATER CURTAIN SYSTEM LAYOUT FOR PHASE-2 / R0


a Hydraulic calculations for water curtian system shall be submitted for our review.
b Operaion logic and integration with Fire alarm for activation of deluge valve shall be submitted.
c Deluge valve control panel locations shall be shown in the drawing.

3 ESR-WH-08-SPK-03 / FIRE SPRINKLER SYSTEM LAYOUT FOR MEZZANINE FLOOR PHASE-2 / R0


a Layout shall be updated in the ground floor plan.
b Sprinkler locations shall be coordinated with mezzanine beams and it shall shown in the drawing.
c Sprinkler shall be extended upto Grid-J.
d Canteen shall be provided with K-115 QR Sprinklers.
e Each crossmain shall be provided with Flushing line separately.
f Hydraulic calculations for Sprinkler system shall be subnitted for our review.
g Remotest sprinklers shall be marked in the drawing.
h Inspector test connection shall be shown for each alarm valve.

4 ESR-WH-08-HYD-01 / FIRE HYDRANT SYSTEM LAYOUT FOR PHASE-2 /R0


a Internal hydrant locations shall be coordinated with shelving and processing layout.
b Section along dock areas shall be submitted for review.
c Near emergency staircases/exits pipes shall be routed underground.

5 ESR-WH-08-CUR-05 / FIRE WATER CURTAIN SYSTEM LAYOUT FOR MEZZANINE FOR PHASE-2 / R0
a Hydraulic calculations for water curtian system shall be submitted for our review.
b Operaion logic and integration with Fire alarm for activation of deluge valve shall be submitted.
c Deluge valve control panel locations shall be shown in the drawing.

6 ESR-WH-08-SPK-06 / RE SPRINKLER DROPPER LAYOUT FOR PHASE-2 / R0


a Tapping for Below duct sprinklers and AHU Mezzanine sprinklers shall be provided as per GFC Drawing(yet to be issued).