Professional Documents
Culture Documents
FOR
A0 24 August 2021 SAEED IBRAHIM YASSER AHMED / A. AZIZ ISSUED FOR REVIEW
REV. DATE PREP’D CHK’D APPRV’D COMPANY APPROVED REASON FOR ISSUE
CLIENT DOC
PROJECT: TRUNK LINES DETAILED ENGINEERING YS2-03-C10017-TL-BOD-L-001
NO.
CONTRACTOR
CONTRACT NO: OMV/S2/DEV/GSS/2010/017/001 GE-OMV-FGS-TL-BOD-L-001
DOC NO:
FILE NAME:
CLIENT: OMV (YEMEN BLOCK S2) EXPLORATION GmBH REVISION: A0 Page: 1/26
CLIENT CONTRACTOR
FIELD GATHERING SYSTEM
TRUNKLINES DETAILED ENGINEERING
OMV (YEMEN BLOCK S2) PIPING DESIGN BASIS GRIFFIN ENERGY LTD. /
ZEN CHEMTECH / RISK WRITERS
EXPLORATION GMBH
th
A 16 August 2021 Issued for Review GP AS MK
APPR. BY
REV DATE REVISION DESCRIPTION PRPD. BY CHKD. BY APPR. BY
CLIENT
CLIENT CONTRACTOR
FIELD GATHERING SYSTEM
TRUNKLINES DETAILED ENGINEERING
OMV (YEMEN BLOCK S2) PIPING DESIGN BASIS GRIFFIN ENERGY LTD. /
ZEN CHEMTECH / RISK WRITERS
EXPLORATION GMBH
TABLE OF CONTENTS
1. INTRODUCTION ................................................................................................................................... 4
2. GENERAL ........................................................................................................................................... 11
1. INTRODUCTION
Griffin Energy Ltd. (GEL) (CONTRACTOR) is pleased to support OMV (Yemen Block S2,
Shabwah, Yemen) Exploration GmbH (OMVY) (COMPANY) to carry-out the Trunkline
Detailed Engineering for two (2) 12” Trunklines and one (1) 6” Trunkline buried between the
existing Central Processing Facility (CPF) and future three (3) Remote Manifold Stations
(RMS) located at the existing EPF’s in the field, covering an overall distance of approximately
22.443 km.
This document contains design basis considered to perform the detailed engineering activities
for the Trunklines and associated facilities.
1.1 OBJECTIVE
The objective of this document is to present the design data required for the detailed design of
piping.
The detailed engineering scope includes the following Trunklines and associated facilities;
Approx.
SN Trunk Line No. From To
Length (Km)
1 TL-1 (6”) Planned RMS-1 Location CPF 3.550 km
The Pipeline / Piping battery limits for the Trunklines will be as follows;
ii. TL-2a 12”/300/RF (EPF-2 to EPF-4) – Crude Oil/Natural Gas/Produced Water (Multi-
Phase Flow)
a. BL-1: EPF-2 facility, 8”/600/RF flanged connection with blind flange at the EPF-2 inlet
manifolds.
Line run 8”/600/RF from the manifolds to the area where the pig launcher is planned.
There spec-break from #600 to #300.
b. BL-2: EPF-2 facility, 8”/300/RF line at the joint to the Trunkline-2. There spec-break
from #600 to #300 when jointing into the Trunkline-2.
c. BL-3: EPF-2 facility, connection from the pig launcher PSV to the EPF-2 facility flare
system. Alternatively, if decision is made by COMPANY to install the RMS-2,
connection to the local drain tank. Exact location to be defined.
d. BL-4: EPF-2 facility, connection from the pig launcher to the local drain pit. Open lined
drain pit to be constructed. Exact location to be defined.
e. BL-5: EPF-2 facility, instrument air connection from the nearest instrument air header
to the pig launcher in 2”-NPT threaded galvanized piping. Line is intended for future
instrument air supply for actuated ball valves.
f. BL-6: BVS-1 @ New Trunk Line Diversion Station facility, 12”/300/RF flanged
connection with BVS-1. It is assumed that the area of the BVS-1 will be at new trunk
line diversion station.
g. BL-7: EPF-4 facility, Trunk Line is entering through the berm at the west-side of the
EPF- 4 facility in parallel with the six (6) direct flow lines. Trunk Line end and pig
receiver location inside the EPF-4 fence.
From the pig receiver, line run 8”/300/RF via new pipe sleeper to the EPF-4 inlet
manifold area ending with a blind flange 8”/300/RF.
h. BL-8: EPF-4 facility, connection from the pig receiver PSV to the EPF-4 flare system.
Exact location to be defined.
CLIENT CONTRACTOR
FIELD GATHERING SYSTEM
TRUNKLINES DETAILED ENGINEERING
OMV (YEMEN BLOCK S2) PIPING DESIGN BASIS GRIFFIN ENERGY LTD. /
ZEN CHEMTECH / RISK WRITERS
EXPLORATION GMBH
i. BL-9: EPF-4 facility, connection from the pig receiver to the local drain pit. Open lined
drain pit to be constructed. Exact location to be defined.
j. BL-10: EPF-4 facility, instrument air connection from the nearest instrument air header
to the pig receiver in 2”-NPT threaded galvanized piping. Line is intended for future
instrument air supply for actuated ball valves.
iii. TL-2b 12”/300/RF (BVS-1 @ New Trunk Line Diversion Station to CPF) – Crude
Oil/Natural Gas/Produced Water (Multi-Phase Flow) or Crude Oil (Single-Phase)
a. BL-1: BVS-1 @ New Trunk Line Diversion Station facility, 12”/300/RF flanged connection
with Trunkline-2 which is coming from EPF#2 in the area of BVS-1. It is assumed that the
area of the BVS-1 will be at new trunk line diversion station.
b. BL-2: CPF facility, pig receiver installation inside the CPF-fence close to the CPF inlet
manifold area. Battery limit at the CPF inlet manifold (Trunk Line manifold skid) i.e. a
12”/300/RF connection.
c. BL-3: CPF facility, connection from the pig receiver PSV to the existing closed drain tank.
Exact location to be defined.
d. BL-4: CPF facility, connection from the pig receiver to the existing closed drain tank.
Exact location to be defined.
e. BL-5: CPF facility, instrument air connection from the nearest instrument air header to the
pig launcher in 2”-NPT threaded galvanized piping. Line is intended for future instrument
air supply for actuated ball valves.
iv. TL-2c 12”/300/RF (EPF-4 through BVS-1 to CPF) – Crude Oil (single Phase Flow)
a. BL-1: EPF-4 facility, 6”/150/RF flanged connection with blind flange in the area of the
discharge line of crude oil export pump skid. It is assumed that the area of the crude oil
pump skid will be close to the existing crude oil storage tanks T-401…T-404.
Line run of 6”/150/RF through the EPF-4 facility on a new pipe sleeper joining the line run
8”/300/RF at the EPF-4 inlet manifolds. From there, further line run on a new pipe sleeper
to the Trunkline-2 pig receiver area. Then subsurface under the new BSV-1 fence and
bund wall to the new diversion station of the trunk lines to the CPF.
CLIENT CONTRACTOR
FIELD GATHERING SYSTEM
TRUNKLINES DETAILED ENGINEERING
OMV (YEMEN BLOCK S2) PIPING DESIGN BASIS GRIFFIN ENERGY LTD. /
ZEN CHEMTECH / RISK WRITERS
EXPLORATION GMBH
b. BL-2: BVS-1 @ New Trunk Line Diversion Station facility, 12”/300/RF flanged connection
with Trunkline-2 which is coming from EPF#4 in the area of BVS-1. It is assumed that the
area of the BVS-1 will be at new trunk line diversion station.
c. BL-3: CPF facility, pig receiver installation inside the CPF-fence close to the CPF inlet
manifold area. Battery limit at the CPF inlet manifold (Trunk Line manifold skid) i.e. a
12”/300/RF connection.
d. BL-4: CPF facility, connection from the pig receiver PSV to the existing closed drain tank.
Exact location to be defined.
e. BL-5: CPF facility, connection from the pig receiver to the existing closed drain tank.
Exact location to be defined.
f. BL-6: CPF facility, instrument air connection from the nearest instrument air header to the
pig launcher in 2”-NPT threaded galvanized piping. Line is intended for future instrument
air supply for actuated ball valves.
a. BL-1: EPF-3 facility, 6”/150/RF flanged connection with blind flange in the area of the
discharge line of crude oil export pump skid. It is assumed that the area of the crude oil
pump skid will be close to the existing crude oil storage tanks T-401…T-404.
Line run of 6”/150/RF through the facility to the inlet manifold area where the Trunk Line- 3
pig launcher location is planned.
b. BL-2: 6”/150/RF line jointing the Trunkline-3. There spec-break from #150 to #300 when
jointing into the trunkline-3.
c. BL-3: EPF-3 facility, connection from the pig launcher PSV to the local drain pit. Open lined
drain pit to be constructed. Exact location to be defined.
d. BL-4: EPF-3 facility, connection from the pig launcher to the local drain pit. Open lined drain
pit to be constructed. Exact location to be defined.
Remark: a subsurface drain tank may be constructed as an alternative to an open drain pit.
e. BL-5: EPF-3 facility, instrument air connection from the nearest instrument air header to the
pig launcher in 2”-NPT threaded galvanized piping. Line is intended for future instrument air
supply for actuated ball valves.
CLIENT CONTRACTOR
FIELD GATHERING SYSTEM
TRUNKLINES DETAILED ENGINEERING
OMV (YEMEN BLOCK S2) PIPING DESIGN BASIS GRIFFIN ENERGY LTD. /
ZEN CHEMTECH / RISK WRITERS
EXPLORATION GMBH
f. BL-6: BVS-2 @ New Trunk Line Diversion Station facility, 12”/300/RF flanged connection
with BVS-2. It is assumed that the area of the BVS-2 will be at new trunk line diversion
station.
g. BL-7: EPF-4 facility, Trunk Line is entering through the berm at the west-side of the EPF- 4
facility in parallel with the six (6) direct flow lines. Trunk Line end and pig receiver location
inside the EPF-4 fence.
From the pig receiver, line run 8”/300/RF via new pipe sleeper to the EPF-4 inlet manifold
area ending with a blind flange 8”/300/RF.
h. BL-8: EPF-4 facility, connection from the pig receiver PSV to the EPF-4 flare system. Exact
location to be defined.
i. BL-9: EPF-4 facility, connection from the pig receiver to the local drain pit. Open lined drain
pit to be constructed. Exact location to be defined.
Remark: a subsurface drain tank may be constructed as an alternative to an open drain pit.
j. BL-10: EPF-4 facility, instrument air connection from the nearest instrument air header to
the pig receiver in 2”-NPT threaded galvanized piping. Line is intended for future instrument
air supply for actuated ball valves.
vi. TL-3b 12”/300/RF (BVS-2 @ New Trunk Line Diversion Station to CPF) – Crude
Oil/Natural Gas/Produced Water (Multi-Phase Flow) or Crude Oil (Single-Phase)
a. BL-1: BVS-2 @ New Trunk Line Diversion Station facility, 12”/300/RF flanged connection
with Trunkline-3 which is coming from EPF#3 in the area of BVS-2. It is assumed that the
area of the BVS-2 will be at new trunk line diversion station.
b. BL-2: CPF facility, pig receiver installation inside the CPF-fence close to the CPF inlet
manifold area. Battery limit at the CPF inlet manifold (Trunk Line manifold skid) i.e. a
12”/300/RF connection.
c. BL-3: CPF facility, connection from the pig receiver PSV to the existing closed drain tank.
Exact location to be defined.
d. BL-4: CPF facility, connection from the pig receiver to the existing closed drain tank. Exact
location to be defined.
CLIENT CONTRACTOR
FIELD GATHERING SYSTEM
TRUNKLINES DETAILED ENGINEERING
OMV (YEMEN BLOCK S2) PIPING DESIGN BASIS GRIFFIN ENERGY LTD. /
ZEN CHEMTECH / RISK WRITERS
EXPLORATION GMBH
e. BL-5: CPF facility, instrument air connection from the nearest instrument air header to the
pig launcher in 2”-NPT threaded galvanized piping. Line is intended for future instrument air
supply for actuated ball valves.
vii. TL-3c 12”/300/RF (EPF-4 through BVS-2 to CPF) – Crude Oil (single Phase Flow)
a. BL-1: EPF-4 facility, 6”/150/RF flanged connection with blind flange in the area of the
discharge line of crude oil export pump skid. It is assumed that the area of the crude oil
pump skid will be close to the existing crude oil storage tanks T-401…T-404. Line run of
6”/150/RF through the EPF-4 facility on a new pipe sleeper joining the line run 8”/300/RF at
the EPF-4 inlet manifolds. From there, further line run on a new pipe sleeper to the
Trunkline-3 pig receiver area. Then subsurface under the new BSV-2 fence and bund wall to
the new diversion station of the trunk lines to the CPF.
b. BL-2: BVS-2 @ New Trunk Line Diversion Station facility, 12”/300/RF flanged connection
with Trunkline-3 which is coming from EPF#4 in the area of BVS-2. It is assumed that the
area of the BVS-2 will be at new trunk line diversion station.
c. BL-3: CPF facility, pig receiver installation inside the CPF-fence close to the CPF inlet
manifold area. Battery limit at the CPF inlet manifold (Trunk Line manifold skid) i.e. a
12”/300/RF connection.
d. BL-4: CPF facility, connection from the pig receiver PSV to the existing closed drain tank.
Exact location to be defined.
e. BL-5: CPF facility, connection from the pig receiver to the existing closed drain tank. Exact
location to be defined.
f. BL-6: CPF facility, instrument air connection from the nearest instrument air header to the
pig launcher in 2”-NPT threaded galvanized piping. Line is intended for future instrument air
supply for actuated ball valves.
CLIENT CONTRACTOR
FIELD GATHERING SYSTEM
TRUNKLINES DETAILED ENGINEERING
OMV (YEMEN BLOCK S2) PIPING DESIGN BASIS GRIFFIN ENERGY LTD. /
ZEN CHEMTECH / RISK WRITERS
EXPLORATION GMBH
2. GENERAL
International System (SI) Units are used throughout the design with the exception of (nominal)
pipe sizes which are expressed as external diameter in inches.
International System (SI) Units are used throughout the design with the exception of (nominal)
pipe sizes which are expressed as external diameter in inches.
2.5 ABBREVIATIONS
3. PIPING DESIGN
Threaded pipe nipples between headers and vent, drain and instrument isolation
valves shall be Schedule 160 for CS and Schedule 80S for SS in the size range 1/2” to
2” NPS.
Piping 2” NPS and above shall be butt-welded. All weld joints in piping 1 1/2” NPS and
below shall be socket welded using socket weld fittings.
Galvanized piping requiring welding shall be galvanized after fabrication. Electro less
nickel plating may be substituted for galvanizing on certain fittings with COMPANY’s
approval. Galvanized piping shall comply with the requirements of ASTM A123.
All piping materials except for bolts / nuts and gaskets shall be supplied with material
certificates conforming to European Standard EN 10204, Type 3.1. Bolts / nuts and
gaskets shall be supplied with material certificates conforming to European Standard
EN 10204, Type 2.2 and 2.1 respectively.
Cast iron, ductile or malleable iron, aluminum, plastic or copper-bearing alloys shall not
be used in hydrocarbon service.
Piping design pressure is based on flange maximum-allowable working pressure in
accordance with ASME B16.5, unless otherwise noted.
Asbestos gaskets shall not be used.
Machined or threaded surfaces shall not be blast cleaned or coated and shall be
preserved in accordance with Shell ENSIS or equivalent.
Impact testing shall be carried out for piping based on thickness & design min
temperature indicated in the piping class. Test temperature shall not be higher than the
minimum design temperature. Impact test requirement shall be as per ASME B31.3 &
shall be conducted in accordance with ASTM 370. Certificate of impact toughness
properties is required from manufacturer.
Component not listed in the individual piping classes shall be considered out of
specification components & shall, in general, be identified as specialty items with the
specialty code number in Process & Instrumentation Diagrams (P&IDs) and piping
drawings.
When a line of one material specification is connected to a line of higher material
specification, the connecting line shall be constructed of the higher material
specification or pressure rating up to & including the first block valve.
CLIENT CONTRACTOR
FIELD GATHERING SYSTEM
TRUNKLINES DETAILED ENGINEERING
OMV (YEMEN BLOCK S2) PIPING DESIGN BASIS GRIFFIN ENERGY LTD. /
ZEN CHEMTECH / RISK WRITERS
EXPLORATION GMBH
4. DESIGN PHILOSOPHY
The plant layout shall be based on ensuring adequate access, to allow construction,
inspection, maintenance and operation to be performed in a safe and efficient manner.
The alignment of equipment and pipe shall offer an organized appearance. The layout
shall be in accordance with, but not limited to the design practices described in these
criteria.
Where dynamic loading, limited pressure drops or other severe service condition
applies, particular care shall be taken in routing pipe lines.
Piping and all other services shall be arranged so as to permit ready access of Cranes
for removal of Equipment for inspection and servicing.
All utility and process piping shall be located above ground, and major lines shall be
located in overhead pipe ways.
Lines that must be run below grade, and must be periodically inspected or replaced,
shall be identified on the P&ID’s; these lines must be placed in covered concrete
trenches. Sleeper-ways shall not be used in process areas where they may block
access for personnel and equipment.
Fire protection system shall be designed as per NFPA and as per statutory
requirements.
Where sleeper ways are used the elevations shall be staggered to permit ease of
crossing or change of direction at intersections. Flat turns may be used when entire
sleeper ways change direction. Flat turns must not be used within pipe racks.
CLIENT CONTRACTOR
FIELD GATHERING SYSTEM
TRUNKLINES DETAILED ENGINEERING
OMV (YEMEN BLOCK S2) PIPING DESIGN BASIS GRIFFIN ENERGY LTD. /
ZEN CHEMTECH / RISK WRITERS
EXPLORATION GMBH
Spacing and routing of piping shall be such that expanding/contracting lines (including
insulation) will not clash with adjacent lines, structures, instruments and electrical
equipment during warm up and cool down.
4.3.1 Valves
Piping shall be arranged so that valves can be operated easily.
Frequently operated valves shall be located in such a way that the valves are easily
accessible from grade, platforms, stairs or ladders, and that the bottom of a hand
wheel is located less than 1.8 m above the operating floor level.
Other valves should also be accessible where they are located at more than 1.8 m
above the operating floor level. Chain-operated valves, shall not be used.
For valves in trenches, if hand wheels are located more than 300 mm below the cover
plate, the valves shall be provided with extension stems extending to within 100 mm
below the cover plate.
Manually operated valves, which are used in conjunction with locally mounted flow
indicators, shall be placed at the same operating level and located where the
instrument can be readily observed.
Double block valves with a bleeder connection shall be provided with interconnecting
piping where intolerable contamination could result from valve leakage.
Where block valves are installed in branch lines from headers, the valves shall be
located in horizontal runs at high points so that lines will drain both ways.
All valves shall be so installed that the stems are not below horizontal positions unless
otherwise specified.
All valves shown on the piping and instrument flow diagrams as located at nozzles of
equipment, such as towers and reservoirs, shall be connected directly to the nozzles.
Battery limit valves, if required, shall be grouped together and consideration shall be
given to provide a common operation platform.
Vent, drain and sampling valves on process lines, not connected to a piping system,
shall be provided with appropriate end closures.
Vents shall be located at high points of pipelines when necessary.
Drains shall be located at low points to empty pipelines or equipment after testing or
during maintenance (i.e. for every loop).
Vent valves shall be the globe or gate type and drain valves the gate type.
Valve bleeds shall be provided at control valve stations, level switches, level
controllers, and gauge glasses.
4.4 WELDING
In addition, the following codes and specifications referred in the code of fabrication shall
be followed for the welding specifications, consumable qualifications and non-destructive
test procedures:
The additional requirements mentioned in this specification, over and above those
obligatory as per codes, shall be followed wherever specified.
4.6 PAINTING
All un-insulated C.S & A.S piping, fittings, valves, vessels and drums etc. including
painting of identification marks on insulated lines.
Identification color bands on all piping as required including insulated aluminum clad,
galvanized, SS and non-ferrous piping.
Pipes, fittings & valve surfaces under insulation of carbon steel and alloy steel
insulated piping system.
CLIENT CONTRACTOR
FIELD GATHERING SYSTEM
TRUNKLINES DETAILED ENGINEERING
OMV (YEMEN BLOCK S2) PIPING DESIGN BASIS GRIFFIN ENERGY LTD. /
ZEN CHEMTECH / RISK WRITERS
EXPLORATION GMBH
Pipes, fittings, valves surfaces under insulation of stainless steel insulated piping
system.
All structural steel works, supports, walkways, handrails and platforms etc.
Pipeline / Piping system shall be properly supported taking into account the following
points:
o Load of bare pipe + fluid + insulation (if any)
o Load of bare pipe + water fill
o Load of valves and online equipment and instrument
o Thermal loads during operation
o Steam-out condition, if applicable
o Seismic Conditions / Seismic Anchor movement
o Wave loads
o Wind loads for piping at higher elevation
o Vibration due to two phase flow
o Loads due to internal pressure
o Any external loads/concentrated loads and cold load of springs
CLIENT CONTRACTOR
FIELD GATHERING SYSTEM
TRUNKLINES DETAILED ENGINEERING
OMV (YEMEN BLOCK S2) PIPING DESIGN BASIS GRIFFIN ENERGY LTD. /
ZEN CHEMTECH / RISK WRITERS
EXPLORATION GMBH
Following Minimum Load Case combinations shall be used for the analysis;
Where,
In addition to above load combinations, wave and wind combinations shall be used as
applicable.
Pipe supporting shall preferably follow the minimum basic span.
For sizes not covered or Guided by client, basic span shall be established based on
project requirement. For piping on rack or sleeper, as a minimum, providing resting
support on every grid of pipe rack / sleeper is mandatory. Depending on the pipe size,
as a rule, guides shall be provided on straight run of pipes at intervals. Unless
specifically becomes non-viable due to flexibility problems.
Additional supports, guides, anchors, special supports like spring supports and sway
braces shall be provided after detailed analysis of piping system to restrict the forces
experienced on nozzles of critical items like mounded bullets, pumps, compressors etc.
For lines which do not need any support otherwise but become unsupported by
opening of flange, etc, during maintenance and thereby may transfer the total load on a
small branch off, a permanent support shall be suitably provided which may be a spring
support also.
Bare pipes of size 6" and above, on sleepers, corrosion pads shall be provided.
Pads shall be provided for insulated pipes before welding the shoes for sizes 8" &
above.
Adequate stiffening shall be provided for the following:
o Lines in above 300#
o Lines having two phase flow
Pipe support design shall be such that deflection in piping systems due to sustained
loads shall not exceed 15mm, in any case, between two adjacent supports.
As far as possible long trunion types of supports (more than 0.5 M) are to be avoided.
In case long trunion support is unavoidable in straight length of pipe, trunion height to
be restricted to 0.5 M and balance height to be made up by providing extended
structure.
All pipes supports shall be so designed that there is no undue tension on equipment
flanges. Flange joints should not move away from each other in case of unbolting of
the joint.
CLIENT CONTRACTOR
FIELD GATHERING SYSTEM
TRUNKLINES DETAILED ENGINEERING
OMV (YEMEN BLOCK S2) PIPING DESIGN BASIS GRIFFIN ENERGY LTD. /
ZEN CHEMTECH / RISK WRITERS
EXPLORATION GMBH