Professional Documents
Culture Documents
1
Process Group
Knowledge Area
Initiating Planning Executing Monitoring & Controlling Closing
4.5. Monitor & Control
4.3.Direct & Manage Project 4.7. Close
4. Project Integration 4.1. Develop project 4.2. Develop project management Project Work
Work Project or
Management charter plan 4.6. Perform Integrated
4.4.Manage Project Knowledge Phase
Change Control
5.1. Plan Scope Management
5.Project Scope 5.2. Collect Requirements 5.5. Validate Scope
Management 5.3. Define Scope 5.6. Control Scope
5.4. Create WBS
2 24 10 12 1
2
7. Cost
Management
Processes
Processes involved in
• Plan Cost Management
1 planning, estimating,
budgeting, financing,
• Estimate Costs managing and
2 controlling costs so
that the project can be
• Determine Budget
3 completed within the
approved budget.
• Control Costs
4
IN-4
Gantt Chart
IN-6
Example (1)
Budget At Compilation BAC = $100
IN-7
PV, EV and AC
8
www.pmhouse.org
Example
Wall Construction
Time = 1 week per wall
Cost = SR 1,000 per
wall, materials and labor
Total Schedule = 4
weeks
Total Cost = SR 4,000
Working days 5 day
per week starting on
Sunday and finish on
Thursday by 5 PM
Assume production is
linear
IN-9
5 pm Wednesday, Week 2
IN-10
5 pm Wednesday, Week 2
IN-11
5 pm Wednesday, Week 2
12
5 pm Wednesday, Week 2
Earned Value
PV SR1,800
EV SR1,600
AC SR2,250
Schedule Variance = EV - PV
= SR1,600 - SR1,800
= (SR200)
Cost Variance = EV - AC
= SR1,600 - SR2,250
= (SR650)
IN-13
5 pm Wednesday, Week 2
Performance Indices
PV SR1,800
EV SR1,600
AC SR2,250
SPI = EV / PV
= SR1,600 / SR1,800
= .9
CPI = EV / AC
= SR1,600 / SR2,250
= .7
IN-14
1
Case 1
Chart Title
2,000
1,800
1,600
1,400
1,200
Axis Title
1,000
800
600
400
200
-
PV EV AC
Series1 1,860 1,860 1,860
IN-15
2-A
Case 2
1,950
1,900
1,850
1,800
1,750
1,700
1,650
1,900 1,700
1,600
PV AC
1,800
1,600
1,400
1,200
1,000
800
600
400
200
1,900 1,500 1,700
-
PV EV AC
This is the worst kind of scenario, where all performance indicators are
negative.
18
Estimate At Completion Calculation Methods
Method 1 Method 2
Ø If we know that we can finish the Ø If the original estimates were
rest of the work as it was originally flawed, we should build new
planned … estimates for all the remaining
amount for the rest of the work Ø ETC is the Estimate to Complete
IN-19
Estimate At Completion Calculation Methods
Method 3 Method 4
Ø If we assume that past
ØWe will consider both CPI and SPI ,
performance is a good indicator of
future performance this method is most useful when the
Ø Use actual to-date plus budgeted project schedule is a factor impacting
amount for the rest of the work, the ETC effort
modified by a performance factor,
such as CPI ØEAC = AC + (BAC –EV)
Ø EAC = AC + (BAC –EV) (CPI x SPI )
(CPI )
Ø EAC = BAC/CPI
= $100,000/0.83
= $120,481 (rounded off)
20
EXAMPLE 1
Given:
BAC = 200
ACc = 120
EVc = 80
CPIc = 0.666
Assuming that current variances are
atypical , the estimate at completion
(EAC) is:
A. 120.
B. 160.
C. 200.
D. 240.
21
EXAMPLE 2
Given:
BAC = 200
ACc = 120
EVc = 80
CPIc = 0.666
Assuming that current variances are
typical of future variances, the
estimate at completion (EAC) is:
A. 220.
B. 260.
C. 300.
D. 320.
22
To-Complete Performance index (TCPI)
IN-23
1. You are a project manager working on a project that requires 100
widgets to be built in five weeks. You have just begun week
three, with an overall budget of US $10,000. To date you have
spent US $2,000 with 40 widgets successfully built. What does
the cost variance tell you in this circumstance?
IN-24
2- You are a project manager for a small construction project.
Your project was budgeted for US $72,000 over a six week
period. As of today, you've spent US $22,000 of your budget to
complete work that you originally expected would cost US
$24,000. According to your schedule, you should have spent
US $21,000 by this point. Based on these circumstances, your
project could be BEST described as:
A. Over budget
B. On budget
C. Under budget
D. Not having enough information provided
IN-25
3- A cost Performance Index (CPI) of 0.89 means:
A. At this time, we expect the total project to cost 89% more than
planned.
B. When the project is completed we will have spent 89% more
than planned.
C. The project is only progressing at 89% of that planned.
D. The project is only getting 89 cents out of every dollar invested.
IN-26
4- A Schedule Performance Index (SPI) of 0.76 means:
A. We are over budget.
B. We are a head of schedule.
C. We are only progressing at 76% of the rate originally planned.
D. We are only progressing at 24% of the rate originally planned.
IN-27
Types of Cost
• Direct Costs:
Cost that are directly
attributable to the
work on project. Direct
Examples are team Cost
travel, team wages,
recognition and cost
of material used on
the project Total
• Indirect costs Cost
Overhead items or
costs incurred for the
benefit of more than Indirect
one project. Examples Cost
include taxes, fringe
benefits, and janitorial
services.
IN-28
Types of Cost
Direct Indirect Variable Fixed
Cost Cost Cost Cost
Fringe Cost of
Team travel Benefits Set-up
material
Team Janitorial
wages services Supplies Rental
Cost of
material
IN-29
Depreciation
Straight Line Depreciation Accelerated Depreciation
The same amount of depreciation is There are two forms of accelerated
taken each year, A US $ 1,000 item with depreciation:
a ten year useful life and no salvage
1. Double Declining Balance
value (how much item is worth at the end
2. Sum of the Years Digits.
of its life) would be depreciated at US
They depreciate faster than straight line.
$100 per year calculations.
You do not have to know what these two forms
means or do any
30
Life Cycle Costing
IN-31
Trends & Emerging Practices In Project Cost
Management
Include the expansion of earned value management (EVM) to include the concept of earned
schedule (ES).
* Schedule Variance (time)= Earned Schedule – Actual Time
=( ES - AT = SV )
* Schedule Performance Index (index) = Earned Schedule / Actual Time
=( ES / AT = SPI )
* Independent Time Estimate at Compete (time) =
= Planned Duration / Schedule Performance Index (time)
$ IEAC = ( PD / SPI )
Time Now
INPUTS
INPUTS T&T OUTPUTS
35
www.pmhouse.org
Cost Management Plan
IN-36
7.2 Estimate Costs
INPUTS
INPUTS T&T OUTPUTS
38
www.pmhouse.org
Cost Estimation (T & T)
• House A is very similar to • As per latest market • House B will cost the
following:
house B. prices, it costs around
• $60,000 for foundation
• House a cost $300,000 $2000 to build 1m2.
• $70,000 for building,
• House B will cost • House B is 100m2
isolation & roof
$300,000. • House B will cost
• $25,000 for heating/cooling
100*2,000 = $200,000
system
• TTL = $155,000
IN-39
Higher
Most Likely
PERT Weighted Average =
Probability of
Occurrence
IN-41
7.3 Determine Budget
INPUTS
INPUTS T&T OUTPUTS
43
www.pmhouse.org
Cost Baseline
ØThe cost baseline is the
approved version of the
time-phased project
budget, excluding any
management reserves,
which can only be
changed through formal
change control
procedures
Ø It is developed as a
summation of the
approved budgets for the
different schedule
activities.
IN-44
7.4 Control Costs
INPUTS
INPUTS T&T OUTPUTS
46
www.pmhouse.org
Forecasting
48
Earned Value Analysis
IN-49
Project Management Plan Vs Project Documents
Project Management Plan Project Documents
1. Scope management plan 1. Activity attributes 19. Quality control measurements
2. Requirements management plan 2. Activity list 20. Quality Metrics
A. Divide by SPI.
B. Multiply by SPI.
C. Multiply by CPI.
D. Divide by CPI.
52
www.pmhouse.org
Q2- Estimate at completion (EAC) is a periodic evaluation of:
A. The cost of work completed.
B. The value of work performed.
C. The anticipated total cost at project completion.
D. What it will cost to finish the job.
53
www.pmhouse.org
Q3- If earned value (EV) = 350, actual cost (AC) =
400,planned value (PV) = 325, what is cost variance (CV) ?
A. 50
B. -75
C. 400
D. -50
54
www.pmhouse.org
Q4-Which of the following is NOT needed in order to come
up with a project estimate?
A. A WBS
B. A network diagram
C. Risks
D. A change control system
55
www.pmhouse.org
Q5- Which of the following is an example of a parametric
estimate?
56
www.pmhouse.org
Q6- Which type of cost is team training?
A. Direct
B. NPV
C. Indirect
D. Fixed
57
www.pmhouse.org
Q7-Project setup costs are an example of:
A. Variable costs.
B. Fixed costs.
C. Overhead costs.
D. Opportunity costs.
58
www.pmhouse.org
Q8- Earned value analysis an example of:
A. Performance reporting.
B. Planning control.
C. Ishikawa diagrams.
D. Integrating the project components into a whole.
59
www.pmhouse.org
Q9-The difference between the cost baseline and the cost
budget can be BEST described as:
60
www.pmhouse.org
Q10- Who has the cost risk in a fixed price (FP) contract?
A. The team
B. The buyer
C. The seller
D. Management
61
www.pmhouse.org
62