Pile OD 0.25 m
Pile ID 0.2 m
Area 1 0.049 m2
Area 2 0.031 m2
Annular Space Area 0.018 m2
Pile Length 12 m
Volume of one pile Annular space 0.21 m3
Number of piles 154 Nos
Total volume of Grout 32.7 m3
WC Ratio 0.42
Total volume of Grout 32.7 m3
Volume of Water Reqd 13.72 m3 (WC*Grout Volume)
Cement Quantity 18.94 m3 (Grout Volume - Volume of Water)
Volume of cement per bag 0.03 m3/bag
Cement required 545.6 bags
WC Ratio 0.42
Total Volume of grout 13.6
Volume of Water Reqd 5.71
Cement Quantity 7.88
Volume of cement per bag 0.0347
Cement required 227.0
772.5 bags