SAUDI ARAMCO ID/PIEU - 30-Nov-2017 - REV. 2017.09.00 (Standards Cutoff - September 30, 2017) Rev. 2017.09.

00 30-Sep-17
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
ELEVATED FLARE--Stack, Tip & Igniter SATIP-F-007-01 30-Nov-17 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

1.1 Review Lifting Plan SAIC-F-2032 SAIC-F-2032 RH RH


RECEIVING
2.0
INSPECTION
Equipment Verification & Visual
2.1
Inspection
SAIC-F-2031 SAIC-F-2031 W W
Contractor's routine inspection on weekly
2.2 Storage & Preservation SAIC-F-2032 SAIC-F-2032 W S basis.

3.0 INSTALLATION

3.1 Pre-Installation Inspection SAIC-M-2006 SAIC-M-2006 H W


Stack, Tip & Pilot Igniter erection SAIC-M-2007 SAIC-M-2007
3.2
inspection SATR-M-2002 SATR-M-2002 W W

3.3 Access (ladders & platforms) SAIC-M-2010 SAIC-M-2010 W W


Flange Joint, Gasket Verification & Bolt SAIC-L-2014 SAIC-L-2014 See Note 1 of the General Notes in addition to
3.4
Tightening SATR-L-2001 SATR-L-2001 H W a minimum of 10%.

3.5 Welding See remarks See remarks Refer SATIP-W-011-01

3.6 Painting See remarks See remarks See applicable SATIP-H series

3.7 Insulation See remarks See remarks Refer to SATIP-N-001-01

Refer to SATIP-N-110-01, N-120-01or N-140-


3.8 Refractory Installation / Verification See Remarks See Remarks
01

4.0 PRE-COMMISSIONING

Tightness test or Service test (if


4.1 Refer to SATIP-A-004-05
applicable)
SAIC-F-2033 SAIC-F-2033
4.2 Piping Reinstatement/Final Inspection
SATR-A-2011 SATR-A-2011 H S

4.3 Final Inspection / Punchlisting SA-6133 H

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 30-Nov-2017 - REV. 2017.09.00 (Standards Cutoff - September 30, 2017) Rev. 2017.09.00 30-Sep-17
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
ELEVATED FLARE--Stack, Tip & Igniter SATIP-F-007-01 30-Nov-17 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

GENERAL NOTES

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may
1
adjust the levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative
4
in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 30-Nov-2017 - REV. 2017.09.00 (Standards Cutoff - September 30, 2017)

Saudi Aramco: Company General Use


Rev. 2017.09.00

###

Saudi Aramco: Company General Use


###

Saudi Aramco: Company General Use


### ###

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 30-Nov-2017 - REV. 2017.09.00 (Standards Cutoff - September 30, 2017)

Saudi Aramco: Company General Use


Rev. 2017.09.00

###

Saudi Aramco: Company General Use


###

Saudi Aramco: Company General Use


### ###

Saudi Aramco: Company General Use

You might also like