You are on page 1of 13

SAUDI ARAMCO ID/PID - 24-Mar-2016 - REV. 2015.09.01 (Standards Cutoff - September 6, 2015) Rev. 2015.09.

01 6-Sep-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Review of Welding documents - WPS, PQR and WPQ
related to Overlay Welding & Cladding SAIC-W-2017 24-Mar-16 WELD-
Restoration/Repair
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A General requirements

All weld documents shall be submitted to SA for technical approval


prior to start of work (per SAEP-352). The Welding documents
SAES-W-010,
include the Welding Procedure Specifications (WPS), Qualification
A1 Section 7.1.1 &
Test Records (PQR), Weld Description & Weld Map (Attachment 3)
7.1.9
See Attachment 1.

Originals of all test records, mill certificates, etc. including records


SAES-W-010,
A2 from independent test laboratory shall be made available for review
Para. 7.1.11
by Saudi Aramco upon request.

WPSs, PQRs, Weld Maps, & Weld Descriptions shall be available at SAES-W-010,
A3
work site for verification at any time by authorized SA inspector. Para. 7.1.8

For shop fabrication In-Kingdom and all field fabrication and


installation, the Welding Procedure Specifications (WPSs) and
Procedure Qualification Records (PQRs) shall be prepared as per
SAES-W-010,
A4 format of ASME Section IX (NMA App. B). See Attachment 2.
Para. 7.1.3
Commentary Note: Standardized PQR forms from an approved
independent test laboratory are acceptable. Equivalent WPS form
from a contractor may be acceptable if approved by CSD.

All corrosion-resistant weld overlays, including clad restoration, shall


conform with ASME SEC VIII reqts (Div. 1 or Div. 2) & W-014. SAES-W-014,
A5
Commentary Note: Refer to ASME SEC VIII D1, Part UCL and Para. 4.1
ASME SEC VIII D2, Article F-5 for specific requirements.

Repairs to integrally clad material shall not be done without the


SAES-W-014,
A6 specific approval of CSD. Any weld repairs to the cladding shall
Para. 4.7
meet the requirements for weld overlays.

The minimum deposit thickness shall be specified in the engineering


SAES-W-014,
A7 design but shall not be less than 3 mm for corrosion-resistant
Para. 4.2
overlays.

The direction of overlay deposition shall be circumferential unless


otherwise approved by CSD.
SAES-W-014,
A8 Commentary Note: Some components and geometries, such as
Para. 4.3
small diameter nozzles, or special applications may not permit
welding in a circumferential direction.

Single layer overlays require prior approval by CSD. Additional


SAES-W-014,
A9 qualification and production tests may be required, as determined by
Para. 4.9
CSD.

Ferrite measurements shall be performed in accordance with AWS SAES-W-014,


A10
A4.2 Para. 4.8

SAES-W-014,
A11 All chemical analysis methods shall conform to ASME/ASTM A751.
Para. 4.11

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID - 24-Mar-2016 - REV. 2015.09.01 (Standards Cutoff - September 6, 2015) Rev. 2015.09.01 6-Sep-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Review of Welding documents - WPS, PQR and WPQ
related to Overlay Welding & Cladding SAIC-W-2017 24-Mar-16 WELD-
Restoration/Repair
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

B Overlay Procedure Qualification Requirements

All weld overlays shall be qualified in accordance with ASME SEC SAES-W-014,
B1
IX. Para. 5.1

The WPS shall indicate the minimum deposit thickness qualified and
the minimum number of layers required. The number of layers used
SAES-W-014,
B2 for the Procedure Qualification Record (PQR) shall be recorded and
Para. 5.2
shall be the minimum number of layers specified on the WPS and
used in production.

For all processes and all layers, the heat input specified on the WPS
SAES-W-014,
B3 shall not exceed the heat input recorded on the PQR by more than
Para. 5.3
10%.

For the SAW and Electro-slag processes, any change in the flux
SAES-W-014,
B4 brand, trade name, or designation shall be considered an essential
Para. 5.4
variable.

For single layer weld overlays, any decrease in overlap (As stated in
PQR) between adjacent beads needs requalification. SAES-W-014,
B5
Note: The overlap or spacing must be measured and recorded on Para. 5.5
the PQR and specified on the WPS.

The following elements shall be analyzed and specified for the


deposit chemistry for all stainless steel and nickel-based alloy weld
metal overlays:
SAES-W-014,
B6 C, Ni, Cr, Cu, Mo, Mn, Fe, plus any other significant elements that
Para. 5.6
are intentionally added to either the base metal or filler metal (e.g.,
Nb or Ti for stabilized stainless steel grades).

The chemistry of the overlay shall be measured at 1.5 mm below the


minimum specified overlay thickness. This is regardless of the SAES-W-014,
B7
thickness of the as-welded deposited thickness in the procedure Para. 5.7
qualification.

Inconel Alloy N06625 overlays shall have a maximum iron content of


SAES-W-014,
B8 10%.
Para. 5.7
Monel overlays shall have a maximum iron content of 4.5%.

The chemical composition of weld deposit shall be within the range


SAES-W-014,
B9 specified for the UNS number of the CRA clad material except for
Para. 5.8
the iron.

For PMI, the chemistry shall be checked on the final finished surface
of the production weld overlay.
SAES-W-014,
B10 Commentary Note:
Para. 5.9
Note: For overlay materials other than those listed above, the
elements to be analyzed shall be specified by CSD.

For austenitic stainless steel weld overlays, the ferrite content shall
SAES-W-014,
B11 be checked in the as-welded condition and shall be between 3 and
Para. 5.10
10 FN.

PQR hardness testing is required for weld overlays in:


a) Hydrogen service components of any wall thickness.
b) Sour service components of any wall thickness. SAES-W-014,
B12
c) For pressure vessels in any service if the base metal wall Para. 5.11
thickness is greater than 38 mm.

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID - 24-Mar-2016 - REV. 2015.09.01 (Standards Cutoff - September 6, 2015) Rev. 2015.09.01 6-Sep-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Review of Welding documents - WPS, PQR and WPQ
related to Overlay Welding & Cladding SAIC-W-2017 24-Mar-16 WELD-
Restoration/Repair
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Hardness testing shall be in accordance with Standard Drawing AB-
036386. The maximum allowable hardness is VHN 250 for the base
metal and HAZ of all overlays and for the weld metal deposit of
austenitic stainless steel corrosion-resistant overlays.
Note: The hardnesses for the weld deposit of hardfacing overlays
SAES-W-014,
B13 and nickel-based corrosion-resistant overlays will depend on the
overlay material and the application. For sour service applications, Para. 5.11
NACE MR0175/ISO 15156 requirements for the weld metal overlay
must be met.

Hydrogen disbonding tests are additionally required to qualify weld


overlay procedures when both the design temperature exceeds
SAES-W-014,
B14 350°C and the hydrogen partial pressure exceeds 5 MPa. (Also see
Para. 7.1.1
SAIC-W-2020)

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID - 24-Mar-2016 - REV. 2015.09.01 (Standards Cutoff - September 6, 2015) Rev. 2015.09.01 6-Sep-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Review of Welding documents - WPS, PQR and WPQ
related to Overlay Welding & Cladding SAIC-W-2017 24-Mar-16 WELD-
Restoration/Repair
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

C Qualification of Welders & Welding operators for Weld Overlays

SAES-W-014,
All welders & welding operators for weld overlays shall be qualified
C1 Para. 4.10;
per ASME SEC IX QW-380.
ASME Sec IX

REMARKS:

REFERENCE DOCUMENT: 1. SAES-W-010, Welding Requirements for Pressure Vessels, (08 September 12.)
2. SAES-W-014, Weld Overlays and Welding of Clad Materials, (11 March 2013)
3. ASME SEC VIII D1 Pressure Vessels (2013 Edition)
4. ASME SEC VIII D2 Pressure Vessels, Alternative Rules (2013 Edition)
5. ASME SEC IX Welding and Brazing Qualifications (2013 Edition)
6. AWS A4.2 Std Proc for Calibrating Magnetic Instr to Measure Delta Ferrite Content of Austenitic & Duplex Austenitic-Ferritic SS Weld Meta

ATTACHMENTS:
Attachment 1 - SAES-W-010, Attachments A & B Weld Map & Weld Description Table
Attachment 2 - ASME IX, NMA APP. B, SAMPLE WPS & PQR FORMS

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID - 24-Mar-2016 - REV. 2015.09.01 (Standards Cutoff - September 6, 2015) Rev. 2015.09.01 6-Sep-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Review of Welding documents - WPS, PQR and WPQ
related to Overlay Welding & Cladding SAIC-W-2017 24-Mar-16 WELD-
Restoration/Repair
Attachment 1 - SAES-W-010, ATT. 3 Weld Map

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID - 24-Mar-2016 - REV. 2015.09.01 (Standards Cutoff - September 6, 2015) Rev. 2015.09.01 6-Sep-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Review of Welding documents - WPS, PQR and WPQ
related to Overlay Welding & Cladding SAIC-W-2017 24-Mar-16 WELD-
Restoration/Repair
Attachment 2 - ASME IX, NMA APP. B, SAMPLE WPS & PQR FORMS

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID - 24-Mar-2016 - REV. 2015.09.01 (Standards Cutoff - September 6, 2015) Rev. 2015.09.01 6-Sep-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Review of Welding documents - WPS, PQR and WPQ
related to Overlay Welding & Cladding SAIC-W-2017 24-Mar-16 WELD-
Restoration/Repair
Attachment 2 - ASME IX, NMA APP. B, SAMPLE WPS & PQR FORMS

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID - 24-Mar-2016 - REV. 2015.09.01 (Standards Cutoff - September 6, 2015) Rev. 2015.09.01 6-Sep-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Review of Welding documents - WPS, PQR and WPQ
related to Overlay Welding & Cladding SAIC-W-2017 24-Mar-16 WELD-
Restoration/Repair

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID - 24-Mar-2016 - REV. 2015.09.01 (Standards Cutoff - September 6, 2015) Rev. 2015.09.01 6-Sep-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Review of Welding documents - WPS, PQR and WPQ
related to Overlay Welding & Cladding SAIC-W-2017 24-Mar-16 WELD-
Restoration/Repair
Attachment 2 - ASME IX, NMA APP. B, SAMPLE WPS & PQR FORMS

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID - 24-Mar-2016 - REV. 2015.09.01 (Standards Cutoff - September 6, 2015) Rev. 2015.09.01 6-Sep-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Review of Welding documents - WPS, PQR and WPQ
related to Overlay Welding & Cladding SAIC-W-2017 24-Mar-16 WELD-
Restoration/Repair

Attachment 2 - ASME IX, NMA APP. B, SAMPLE WPS & PQR FORMS

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID - 24-Mar-2016 - REV. 2015.09.01 (Standards Cutoff - September 6, 2015) Rev. 2015.09.01 6-Sep-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Review of Welding documents - WPS, PQR and WPQ
related to Overlay Welding & Cladding SAIC-W-2017 24-Mar-16 WELD-
Restoration/Repair

Attachment 2 - ASME IX, NMA APP. B, Additional Forms (Info Only)

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID - 24-Mar-2016 - REV. 2015.09.01 (Standards Cutoff - September 6, 2015) Rev. 2015.09.01 6-Sep-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Review of Welding documents - WPS, PQR and WPQ
related to Overlay Welding & Cladding SAIC-W-2017 24-Mar-16 WELD-
Restoration/Repair

Attachment 2 - ASME IX, NMA APP. B, Additional Forms (Info Only)

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID - 24-Mar-2016 - REV. 2015.09.01 (Standards Cutoff - September 6, 2015) Rev. 2015.09.01 6-Sep-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Review of Welding documents - WPS, PQR and WPQ
related to Overlay Welding & Cladding SAIC-W-2017 24-Mar-16 WELD-
Restoration/Repair

Saudi Aramco: Company General Use

You might also like