1162003020
Tugas UAS – Manajemen Proyek
The project workbook allows project managers, team members, sponsors, and stakeholders to easily track and monitor project activities. Any of these
worksheets can easily be broken out into separate documents.
Data Filling out the Data sheet completes the header portion of all remaining sheets in the project workbook.
Minicharter The Project Minicharter sheet can be used as a charter for small projects or a summarization of a full charter for larger projects.
The Stoplight Report sheet contains a status report that can be used to keep sponsors, team members, and stakeholders informed
Stoplight of project progress.
Budget The Budget sheet allows you to track original budget, expenditures to date, and any cost variance.
The Cost/Benefit Analysis sheet allows you to review the proposed project and potential alternatives and make a project selection
CBA based on a greater ROI (return on investment).
The Risk Management Matrix sheet allows you to identify, qualify, quantify, and prioritize risks (events that might happen; the
Risks uncertainty of a project), create mitigation and contingency plans, and assign risks owners.
Issues The Issues Log sheet allows you to identify and monitor project issues (unplanned events that have happened).
The Action Items sheet allows you to track and monitor action items assigned to team members. Action items are tasks that must be
Action done but are too insignificant from a time perspective to track in your project schedule.
The Deliverable Milestones sheet allows you to identify major deliverable milestones and the due dates, objectives, assumptions,
Miles and constraints relevant to that deliverable milestone.
The Work Breakdown Structure sheet includes the activities that must be completed during a project, the effort required, all relevant
WBS dates, and the resources assigned to do the work.
Roster The Roster sheet provides contact information for all those involved on the project.
The Roles and Responsibilities sheet shows the primary role of team members, any deliverables in which they are involved, and the
R&R percentage of time they are expected to work on the project.
The Resource Assignment Matrix sheet shows you what type of resource is responsible for, or somehow involved with, each
RAM deliverable. The tasks listed are samples; you should update the RAM with tasks appropriate for your project.
RCM The Resource Commitment Matrix sheet shows how many effort hours each person on the project has been allocated by month.
A&C The Assumptions and Constraints sheet allows you to track project assumptions and constraints.
Decision The Decision Log sheet allows you to track all major decisions made during the course of the project.
The Communication Plan sheet allows you to detail your communication plan: how you are going to communicate, whom you will
Comm be communicating with, how often, in what format, etc.
Stake The Stakeholder Analysis sheet allows you to identify stakeholders, their role, and their requirements.
Expectations The Expectations sheet allows you to identify and track the expectations of various stakeholders.
Chg Log The Change Control Log sheet allows you to track all change requests that are in process or finalized.
Deliver The Deliverable Acceptance Log sheet allows you to track the status of deliverable acceptances.
PERT The PERT Analysis sheet allows you to perform PERT analysis on WBS tasks.
Delphi The Delphi Exercise sheet allows you to develop estimates for WBS tasks through the Delphi technique.
TimeSum The Timesheet Totals sheet allows you to track effort hours of your entire team by individual and by month.
Timesheet The Timesheet can be used by each team member to submit effort hours by activity, by month.
The Initial Project Size Estimate sheet allows you to estimate, at high-levels (40,000 ft. view), the size of a project. This estimate
Size Est should not be considered final as requirements and technical specifications typically have not been fully developed yet.
The Resource Loading sheet allows you to identify the work effort required, the duration, and the allowed commitment level of each
Res Load person assigned to the project.
Qual Metrics The Project Quality Metrics sheet allows you to identify critical success criteria, related quality metrics, and their priority.
Source: www.iappm.org
Project PENGADAAN RENOVASI GEDUNG III LANTAI 3 SAYAP SELATAN SEKRETARIAT KABINET
Project manager M.Yusuf syamsul assegaf
Sponsor CV EMERAL
Project artifacts Sekretariat Kabinet
Last updated 27/01/2019
Project #
Proyek ini meliputi pekerjaan konstruksi pada renovasi ruang kerja lantai 3 sayap selatan sekretariat
kabinet
Project Minicharter
Project PENGADAAN RENOVASI GEDUNG III LANTAI 3 SAYAPProject
SELATAN # SEKRETARIAT KABINET
#REF!
Project manager M.Yusuf syamsul assegaf Sponsor CV EMERAL
Project artifacts Sekretariat Kabinet Updated 1/27/19
Sumber dana dari APBN, Persyaratan kualitas teknis (project manager sertifikat keahlian madya selama 3
Business need and tahun, site manager sertifikat keahlian mudah selama 3 tahun), Memiliki SDM Tenaga Teknis (pelaksana
business benefits interior, pelaksana mekanikal / elektrikal, pelaksana K3, pelaksana tukang kayu, dan drafter, Memiliki
kemampuan untuk menyediakan peralatan (scafolding, peralatan pemasangan kaca).
Objectives Memperbarui kulaitas dan fasilitas lantai 3 Sayap Selatan pada Gedung III Sekretariat Kabinet
Signature
Sponsor CV EMERAL
27-Jan-19
Signature
Project manager
M.Yusuf syamsul assegaf
27-Jan-19
Budget
Project PENGADAAN RENOVASI GEDUNG
ProjectIII
# LANTAI 3 SAYAP SELATAN SEKRETARIAT
#REF! KABINET
Project manager M.Yusuf syamsul assegaf Sponsor CV EMERAL
Project artifacts Sekretariat Kabinet Updated 27/01/2019
Budget Status
Approved Budget Planned Expenditures to Actual Expenditures to Variance
IDR 150.600.000,00 Date
IDR 750.000.000,00 Date IDR 750.000.000,00
Planned Remaining Budget Actual Remaining Budget Variance
IDR 720.500.000,00 IDR 740.000.000,00 IDR 19.500.000,00
Additional $ needed
Budget Details
Internal Expenses
Specialist Salaries Hourly Rate Hours Total Cost
Project Manager 300000 4 1200000
Site Manager 170000 5 850000
TOTAL COST SPECIALIST 2050000
Tenaga Teknis Hourly Rate Hours Total Cost
Pelaksana Interior 250000 6 1500000
Pelaksana Mekanikal 125000 5 625000
Pelaksana Elektrikal 145000 3 435000
Tukang Kayu 105000 6 630000
Drafter (Tukang Gambar) 180000 3 540000
TOTAL COST TENAGA AHLI 3730000
Peralatan Quantity Rate Quantity (Set)
SCAFOLDING
Main frame 200000 16 3200000
Ledder 145000 18 2610000
Joinpin 20000 7 140000
Catwalk 325000 35 11375000
Guard rail 435000 10 4350000
Jack base 80000 20 1600000
Clamp 40000 9 360000
Tangga 490000 1 490000
PERALATAN PEMASANGAN KACA
Curtain Wall 950000 35 33250000
Alumunium Composite Panel 345000 20 6900000
TOTAL COST PERALATAN 64275000
Total Internal Expenses 70055000
External Expenses
Consulting Costs Total Cost
Konsultan Proyek 47000000
Capital Expenditures Total Cost
Alat pelindung diri (APD) 25000000
APAR (Alat Pemadam Kebakaran) 9000000
Total External Expenses 81000000
Total Budget 151055000
Risk Management Matrix (Risk Register)
Project PENGADAAN RENOVASI GEDUNG III LANTAI 3 SAYAP SELATAN SEKRETARIAT KABINET
Project # #REF!
Project manager M.Yusuf syamsul assegaf Sponsor CV EMERAL
Project artifacts Sekretariat Kabinet Updated 27/01/2019
Detectability
Importance
Probability
Impact
Risk Response and Date Date to
ID Risk Description Category Trigger Event/Indicator Description Contingency Plan Owner Status Entered Review
If the risk becomes a
How will you respond to
What act or event initiates either the reality, what will you do Who
this risk and what actions
What is this risk? 0 risk occurrence or precipitates the in response, as a backup, monitors this
will you take to match
response strategy? or alternative/ risk?
that response?
workaround?
Biaya aktual sangat jauh Membuat perencanaan
1 Perencanaan dan Keuangan 0,32 4 2 5,12 Low Estimasi biaya tidak tepat Accountant CLOSE 23/10/2018 27/10/2018
meleset dan keuangan yang baru
Mengejar pekerjaan yang
2 Peralatan 0,37 4 4 11,84 High Tidak memadai Proyek akan terhambat tertinggal dengan sesuai Procurement CLOSE 22/11/2018 25/11/2018
standar pekerjaan
Proyek mengalami
3 Lokasi dan Lingkungan 0,22 4 3 5,28 Low Salah dalam memilih lokasi Memastikan keamanan Surveyor CLOSE 24/10/2018 25/10/2018
gangguan
Menyiapkan material
Terdapat retakan pada
4 Alam 0,41 3 3 7,38 Medium Bencana Alam (Gempa Bumi) untuk memperbaiki BMKG OPEN 24/10/2018 03/11/2018
bangunan
retakan
Mengasuransikan untuk
5 Kecelakaan Kerja 0,45 5 2 9,00 Medium Pekerja tertimpa material Cidera pada pekerja HSE OPEN 28/11/2018 02/12/2018
pengobatan pekerja
Mengeluarkan biaya lebih
Struktur bangunan tidak Quality
6 Material 0,29 3 6 10,44 Medium Kualitas material tidak baik (over budgeting) untuk CLOSE 23/11/2018 30/11/2018
kuat Control
penggantian material
Memberi bimbingan dan
Terganggunya
7 Human Error 0,24 4 6 11,52 High Kelalaian pekerja mengidentifikasi faktor Safetyman OPEN 04/12/2018 07/12/2018
pelaksanaan proyek
utama
Planned Actual
Milestone Description Objectives Assumptions Constraints
Completion Completion
ID
6 Pekerjaan finishing
Memasang saluran pipa Mengalirkan fluida ke pompa Saluran listrik dan air Memenuhi keamanan kondisi
a) Instalasi perpipaan 5 hari 7 hari operasi pada tenaga kerja, dan
listrik dan pipa air atau mesin menjangkau seluruh ruangan
lingkungan sekitar
Memasang sambungan Menentukan besaran daya Mencegah konslet pada arus Menghindari pemakaian listrik
b) Pekerjaan Mekanikal dan Elektrikal 2 hari 4 hari
listrik listrik yang diperlukan listrik yang berlebihan
Mengatur intensitas cahaya
Memasang lampu Lampu memiliki daya tahan yang
c) Pemasangan lampu 2 Hari 2 Hari yang baik sesuai dengan Menghindari gangguan
ruangan lama
kebutuhan ruangan terhadap pekerja yang
Keramik memiliki daya tahan
Menambah kekuatan lantai, Keramik tidak mudah pecah
d) Pemasangan lantai Memasang keramik lantai 3 Hari 3 Hari yang lama hingga bertahun-
mempermudah kebersihan dan retak
tahun
Mengurangi sinar UV yang Menambah pencahayaan pada Kaca memiliki kemampuan
e) Pemasangan kaca Memasang kaca gedung 3 Hari 2 Hari
masuk ke ruangan ruangan untuk mereduksi panas
Work Breakdown Structure
Project PENGADAAN RENOVASI GEDUNG III LANTAI 3 SAYAP
Project # SELATAN
#REF! SEKRETARIAT KABINET
Project manager M.Yusuf syamsul assegaf Sponsor CV EMERAL
Project artifacts Sekretariat Kabinet Updated 27/01/2019
Dependencies
Effort Planned Estimate to
ID Task Status Cost Start Date Actual Completion Resource
Hours Completion Completion
3 b) Gudang material dan peralatan A,B OPEN 8 26-Oktober-2018 4 hari 5 hari 3 hari Work tools
4 c) Base camp proyek A OPEN 6 31-Oktober-2018 4 hari 3 hari 5 hari Tenda, Alas tidur
5 e) Pagar proyek A,C OPEN 8 02-Nov-18 3 hari 2 hari 2 hari Traffic cone, Road barrier
6 f) Jalan Kerja C,D OPEN 8 05-Nov-18 3 hari 4 hari 3 hari Stick cone, Police line
8 a) Pengadaan tenaga ahli B,C,E CLOSE 4 11-Nov-18 5 hari 6 hari 6 hari Database, Worksheet
9 b) Kebutuhan listrik kerja F OPEN 8 17-Nov-18 5 hari 5 hari 6 hari Genset, bahan bakar
13 a) Pengaturan lebar ruangan F OPEN 4 27-Nov-18 5 hari 3 hari 4 hari Software, Internet
Pekerjaan finishing
03-Desember-
15 a) Instalasi perpipaan J OPEN 6 5 hari 7 hari 6 hari Jointing tackle
2018
05-Desember-
16 b) Pekerjaan Mekanikal dan Elektrikal K,G OPEN 4 2 hari 3 hari 2 hari Multimeter, voltmeter, ohm meter
2018
07-Desember-
17 c) Pemasangan lampu L OPEN 2 2 Hari 3 hari 2 Hari Stick lampu
2018
10-Desember-
18 d) Pemasangan lantai M CLOSE 7 3 Hari 5 hari 3 Hari Wedge+Clip tile, tile leveling
2018
13-Desember-
19 e) Pemasangan kaca N CLOSE 7 3 Hari 6 hari 2 Hari Tools set
2018
Resource Assignment Matrix
Project PENGADAAN RENOVASI GEDUNG III LANTAI 3 SAYAP SELATAN SEKRETARIAT KABINET
Project # #REF!
Project manager M.Yusuf syamsul assegaf Sponsor CV EMERAL
Project artifacts Sekretariat Kabinet Updated 27/01/2019
Quality Control
General Affair
Procurement
Accountant
Safetyman
Surveyor
BMKG
HRD
HSE
Project Task
Project Management and Requirements
Perencanaan Finishing
6 a) Instalasi persiapan ✔️
b) Pekerjaan mekanikal dan elektrikal ✔️
c) Pemasangan lampu ✔️
d) Pemasangan lantai ✔️
e) Pemasangan kaca ✔️
Resource Commitment Matrix
Project PENGADAAN RENOVASI GEDUNG III LANTAI 3 SAYAP SELATAN SEKRETARIAT KABINET
Project manager M.Yusuf syamsul assegaf
Project artifacts Sekretariat Kabinet
1 Menetapkan sebagai kantor sebagai lokasi pemantauan Mempermudah pemantauan proyek A OPEN 22-Oct
4 Menjamin keamanan kerja dalam lingkungan proyek Menjamin keamanan lingkungan sekitar proyek A OPEN 23-Oct
Menghindari gangguan dari proyek pada lingkungan
5 Menetapkan jalan utk kerja A OPEN 22-Oct
sekitar
Memenuhi kriteria yang disyaratkan oleh project
6 Menseleksi SDM yang dibutuhkan C OPEN 26-Sep
manager
7 Merencanakan kebutuhan sumberdaya listrik Tersedia mesin pengganti yaitu genset C OPEN 25-Oct
8 Meliputi scafolding dan peralatan pemasangan kaca Sertifikat kemampuan alat yang masih berlaku C OPEN 26-Oct
Mendapatkan infromasi tentang kecelakaan yang
9 Meliputi helm, sarung tangan, kaca mata C CLOSE 28-Nov
timbul pada pekerjaan sejenis
Menyesuaikan pada masing-masing divisi kerja yang
10 Menentukan tata letak dan fasilitas C CLOSE 05-Dec
membutuhkan ruangan besar atau kecil
11 Memasang saluran pipa listrik dan pipa air Saluran listrik dan air menjangkau seluruh ruangan A OPEN 06-Dec
12 Memasang sambungan listrik Mencegah konslet pada arus listrik A OPEN 09-Dec
13 Memasang lampu ruangan Lampu memiliki daya tahan yang lama A OPEN 11-Dec
Keramik memiliki daya tahan yang lama hingga
14 Memasang keramik lantai A OPEN 10-Dec
bertahun-tahun
15 Memasang kaca gedung Menambah pencahayaan pada ruangan A OPEN 13-Dec
Decision Log
Project PENGADAAN RENOVASI GEDUNG III LANTAI 3 SAYAP SELATAN
Project # SEKRETARIAT#REF!
KABINET
Project manager Muhammad Yusuf Syamsul Assegaf Sponsor CV EMERAL
Project artifacts Sekretariat Kabinet Updated 27/01/2019
a) Kantor proyek / direksi keet Dpat terjadinya kesalahan dalam penginputan data Procurement OPEN 22-Oct
Banyaknya material dan peralatan di dalam gudang
b) Gudang material dan peralatan / stock yard yang menyebabkan material berada diluar gudang Procurement OPEN 22-Oct
hingga rentan hilang
Tempat tinggal dari pekerja proyek dapat dibuat
c) Base camp proyek Surveyor OPEN 22-Oct
disekitar proyek
Surveyor/BMK
e) Pagar proyek Menjaga agar pagar proyek berada pada tempatnya OPEN 23-Oct
G
Membuat jalan khusus pekerja proyek agar tidak
f) Jalan Kerja HSE OPEN 22-Oct
menggagu kariawan yang sedang bekerja
Risk
ID Stakeholder Role Impact Influence Needs Responsibility
Tolerance
a) Instalasi perpipaan J 4 8 11
K
b) Pekerjaan Mekanikal dan Elektrikal K, G 1 5 9
L
c) Pemasangan lampu L 2 7 10
M
N d) Pemasangan lantai M 4 8 12
e) Pemasangan kaca N 2 5 10
O
17 7 24 24 8 32
10 7 17 H I
B 17 0 24 24 0 32
10 0 17 45 8 53 53 5 58 58 0 58 58 0 58
0 10 10 17 5 22 28 5 33 33 3 36 L M N O
A C F G 45 0 53 53 0 58 58 0 58 58 0 58
0 0 10 17 0 22 28 0 33 42 9 45
10 8 18
Jalur Kritis pada Proyek ini adalah :A - B -
D 33 5 38 38 7 45 C-E-F-J -K-L -M-N-O
14 4 22 22 6 28 J K
E 33 0 38 38 0 45
22 0 28
PERT Analysis
Project PENGADAAN RENOVASI GEDUNG III LANTAI 3Project
SAYAP#SELATAN
#REF!
SEKRETARIAT KABINET
Project Manager M.Yusuf syamsul assegaf Sponsor CV EMERAL
Project Artifacts Sekretariat Kabinet Updated 27/01/2019
15/15
Most PERT Comp' Std +1 Std -1 Std +2 Std -2 Std +3 Std -3 Std
ID Task Likely Min Max Est ed Est Dev Dev Dev Dev Dev Dev Dev
Perencanaan Site Plan
a) Kantor proyek / direksi keet 4,00 7,00 10,00 5,50 7,64 0,50 8,14 7,14 8,64 6,64 9,14 6,14
b) Gudang material dan peralatan / stock yard 4,00 6,00 9,00 5,17 7,18 0,50 7,68 6,68 8,18 6,18 8,68 5,68
c) Base camp proyek 4,00 11,00 15,00 7,00 9,72 0,67 10,39 9,06 11,06 8,39 11,72 7,72
e) Pagar proyek 3,00 8,00 12,00 5,33 7,41 0,67 8,07 6,74 8,74 6,07 9,41 5,41
f) Jalan Kerja 3,00 5,00 10,00 4,50 6,25 0,83 7,08 5,42 7,92 4,58 8,75 3,75
Perhitungan Kebutuhan Sumber Daya
a) Pengadaan tenaga ahli 5,00 9,00 14,00 7,17 9,95 0,83 10,79 9,12 11,62 8,29 12,45 7,45
b) Kebutuhan listrik kerja 5,00 7,00 12,00 6,50 9,03 0,83 9,86 8,19 10,69 7,36 11,53 6,53
Pengadaan perlatan untuk pekerjaan persiapan 4,00 4,00 6,00 4,33 6,02 0,33 6,35 5,69 6,69 5,35 7,02 5,02
Pengadaan K3 1,00 3,00 7,00 2,33 3,24 0,67 3,91 2,57 4,57 1,91 5,24 1,24
Pekerjaan Renovasi Lantai
a) Pengaturan lebar ruangan 5,00 8,00 16,00 7,33 10,19 1,33 11,52 8,85 12,85 7,52 14,19 6,19
Pekerjaan finishing 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
a) Instalasi perpipaan 5,00 9,00 12,00 6,83 9,49 0,50 9,99 8,99 10,49 8,49 10,99 7,99
b) Pekerjaan Mekanikal dan Elektrikal 2,00 6,00 9,00 3,83 5,32 0,50 5,82 4,82 6,32 4,32 6,82 3,82
c) Pemasangan lampu 2,00 8,00 12,00 4,67 6,48 0,67 7,15 5,81 7,81 5,15 8,48 4,48
d) Pemasangan lantai 3,00 7,00 11,00 5,00 6,94 0,67 7,61 6,28 8,28 5,61 8,94 4,94
e) Pemasangan kaca 3,00 6,00 10,00 4,67 6,48 0,67 7,15 5,81 7,81 5,15 8,48 4,48