Professional Documents
Culture Documents
Art111 PDF
Art111 PDF
Repair
Hamid CHABANE
Commandement des Forces Navales
Introduction
Productivity and competitiveness in shipbuilding industry depend to a great extent on the
economy of scale. Achieving economic sustainability becomes a top priority goal. This issue
is even more critical for small shipyards intended to produce ships of between 1000 and
5000 DWT, for the related market segment is characterised by an intense and tough
competition.
In addition production processes are rather different than repair and maintenance works.
Their needs are quite different and often irreconcilable, and whilst the former may not
systematically yield benefits despite being technologically efficient, the latter can still prove
highly competitive and profitable. A possible solution could reside in a combination between
a suitable product mix made of high added value ships and appropriate repair activities.
Then a question arises whether it is possible or not to combine the two activities within a
single shipyard in order to address its performances in periods of fluctuating demand? Visibly
this would only be realized through a balanced share of some facilities and resources.
The viability of such a solution will obviously depend on the ability of the shipyard to share
some resources and conjugate jobs and tasks from the two separate departments by
identifying and taking advantage of their similarities. Therefore the layout of the concerned
facilities ought to be methodically designed and implemented and should not develop
according to peculiar circumstances.
This study aims to investigate how could those similarities and interdependencies be
exploited to address the shipyard performances in periods of fluctuating demand?
The study will be based on a thorough and extensive analysis of the work processes that are
implemented by the two industrial activities taking into consideration the practices currently
applied by shipyards of similar features, and emphasizing work organisations that are based
on Group Technology concepts. The layout design will then be carried out and optimised by
means of Muther’s systematic procedure in three steps contemplating respectively:
• a production layout,
• a repair layout,
• a mixed layout combining both production and repair activities,
the latter being developed upon a combination of the results relating to the first two cases.
Work Organization
2.1 Facility Layout Definition
Figure 1 - Effect of Group Technology on the activity pace of a shipyard (Storch et al.,
1988)
products are subdivided into sub-groups independently of the final location on the ship. The
logic is the same as that of HBCM. Indeed, both ZOFM and HBCM must be planned
simultaneously, i.e. a ZOFM can only be applied if an HBCM is implemented.
Methodology
3.1 Review of the Systematic Layout Planning Design Method
Until the advent of systematic approaches in the 1970s, layout planning was perceived as an
abstract achievement, and most of the approaches which were undertaken resulted from a
combination of experience, customs and established procedures.
Richard Muther is the first designer who ever formalised in a well structured pattern the
layout planning design process (Muther, 1973). It is quite evident that such an approach
helps avoiding obvious insignificant mistakes that might yield unwanted consequences over
a long term.
Layouts are designed to satisfy existing demands in defined contexts. The proficiency in
designing good layouts is ineffective if the demand is ill identified and defined. There could
be no good solution to a false problem, for too simplistic assumptions would represent an
unrealistic situation leading to a useless answer (Apple, 1991). Two questions are central:
• What is to be produced?
• How much is to be produced?
A great attention must be paid to the initial data which must be reliable and accurately
defined and estimated. The basic data that are required as input to the procedure amount to
five, viz.: the Product P, the Quantity Q, the Routing or Process R, the Supporting Services
S, and the Time T (figure 4) (Muther, 1973).
often unlikely especially in the case of a new design. Yet, it must be pointed that a
conventional graphical procedure can sometimes prove more valuable and productive for a
simple layout, while some probabilistic methods can reveal more appropriate in the case of
irregular service performance due to a random demand.
outsourced products and services account for 50% to 80% of the total cost of a new project
in shipbuilding industry.
Consequently there must be a strategic approach to make-vs.-buy decision-making process.
Products and services likely to be outsourced must be carefully and thoroughly evaluated
because outsourcing will inevitably entail reduction in self-sufficiency and flexibility of the
shipyard (Wilson et al., 2001).
Establishing the rates of the desired closeness between all the facilities is a laborious
process. It is a subjective approach, which requires minimum background and experience
about the activities to be implemented within the projected facilities.
The flows of materials, personnel and information were taken into consideration. The Activity
Relationship Chart (REL) was compiled and reported in table 3.
Legend
1 Steel stockyard 15
2 Steel work hall
3 Outfitting centre
4 Pipe shop
5 General purpose shop
6 Paint shop
7 Warehouse
8 Units and blocks storage areas 13
17
16 12 7
14
3 8 9 11
4
9 Erection areas
10 Lifting and handling installations
11 Quays
12 Production supporting services
5 10 10
2
13 Training centre
14 Managers and administrative offices
15 Transportation station, parking 6
16 Catering services
17 Health and medical service
1
1
15
17
1 1 7
3 9
4 8
11
10
2
15
Legend
14 16 1 Steel stockyard
15
2 Steel work hall
3 Outfitting centre
4 Pipe shop
5 General purpose shop
6 Paint shop
7 Warehouse
11
10
12 7 8 Units and blocks storage areas
9 Erection areas
17
10 Lifting and handling installations
11 Quays
4 3 8 8 8 12 Production supporting services
13 5 13 Training centre
14 Managers and administrative offices
2 15 Transportation station, parking
16 Catering services
17 Health and medical service
1 6 Pathways
11
9
9
10
10
10
10
Table 4 - Average utilisation of the docking installations of a repair facility - 1st case
2 facilities of L=40 m
40
3 facilities of L=70 m ==> may service for 4 months naval vessels of L=40 m
2 facilities of L=110 m ==> may service for 5 months merchant ships of L=100 m
1 facility L=150 m ==> may service for 1 months merchant ships of L=100 m
(m)
1 facility L=200m ==> may service for 6 months merchant ships of L=150 m
70
Utilisation of facilities L=40 m and L= 70 m ~83%
Utilisation of facilities L=110 m L= 150 m and L=200 m ~92%
110 1 month allowance for routine maintenance operations
Possibilities:
100
1 Synchrolift of 3000 tonnes up to 5000 tonnes with 5 bays
Merchant ships
categories (m)
(2x110x20 + 3x70x20 )
150 2 slipways of 40x10 m and D=200 tonnes
2 docking facilities of 150x30 m and D=6500 tonnes up to 10000 tonnes
1 docking facility of 200x30 m and D=12000 tonnes up to 15000 tonnes
200
Symposium International : Qualité et Maintenance au Service de l’Entreprise
QUALIMA01 - Tlemcen 2004
Table 5
Average utilisation of the docking installations of a repair facility – 2nd case
100 Possibilities:
categories
Table 6
Maximum utilisation of the berthing installations of a repair facility
Months 1 2 3 4 5 6 7 8 9 10 11 12 There are no particular restrictions concerning the
required berthing capacities.
30 Lay-up requires berth accommodation hence it is
included in the berthing requirements.
Naval vessels categories
150 month of L=300 m
(m)
200
300
Symposium International : Qualité et Maintenance au Service de l’Entreprise
QUALIMA01 - Tlemcen 2004
1 1
Legend 14
1 Docking facilities
2 Berths
3 Steel shop
4 Machine shop
5 Electrical shop
6 Carpenter shop 17
7 Paint shop
8 Afloat repair shop 1
9 Warehouse 17 9
10 Lifting installations
11 Treatment plant
12 Administrative offices 1
13 Technical services
14 Health-medical service
15 Training centre
16 Catering services
17 Transportation station 5
and parking
3
10
4
11
6
7
8
1
2
Design of a mixed shipyard facility layout for ship production and repair
Bearing in mind the various considerations that were invoked for the selection of the facilities
that ought to be retained for shipbuilding and shiprepair respectively, the aim is to define
which might be shared between the two activities and which should be segregated.
Consequently, the following selection was established:
All the data and assumptions of the previous two cases were adopted. The completion of the
whole process yielded many configurations. One configuration alternative is reproduced in
figure 10.
Symposium International : Qualité et Maintenance au Service de l’Entreprise
QUALIMA01 - Tlemcen 2004
Legend
1 Docking facilities
2 Berths
3 Steel shop
4 Machine shop
5 Electrical shop
6 Carpenter shop Berth 6 Berth 7
1 1
7 Paint shop B th 1
8 Afloat repair shop Berth 4 Berth 5
9 Warehouse 17
10 Lifting installations
11 Treatment plant
12 Administrative offices 17
13 Technical services
14 Health-medical service
15 Training centre
16 Catering services 6
17 Transportation station 15
Berth 3
and parking
1 8
Berth 2
14 B th 1
Dock 2
3 Dock 1
Bay 3 Bay 7
11 7
Bay 6
Bay 2
Transfer platform
Bay 5
Berth 1 Bay 1
Bay 4
Lifting platform
14
17
5 17
5 17
5 14
Berth 6 Berth 7
Berth 4 Berth 5
4 4 4
1 2 3
Berth 3
16 15
13
22
12
Berth 2
21
B th 1
18 23 Dock 2
19 20
Dock 1
9 8 7 10 11 Bay 3 Bay 7
Bay 6
Bay 2 Transfer platform
Bay 5
Berth 1 Bay 1
Bay 4
Lifting platform
Conclusion
The present study aimed to investigate whether a small shipyard intended to produce ships
of between 1000 and 5000 DWT could supplement this activity with a substantial repair
workload without disrupting its work organisation?
Production processes are rather different than repair and maintenance works. Their needs
are different and often irreconcilable.
From the investigation it emerged that the implementation of Group Technology concepts
profoundly modified the work organisation within shipyards as it shaped their respective
layouts. Its generalisation was motivated by the need to reduce production costs whilst
maximising the resources utilisation.
For the purpose of the study, three cases were considered in sequence: a production layout,
a repair layout and a mixed layout designed to handle both building and repair activities. In
either case, the systematic layout planning method proposed by Muther was applied. It
consists of a procedure that thoroughly contemplates all the production processes of the
enterprise starting from the material procurement and taking into account the actual
prevailing environment.
The technique reveals robust and efficient since it can address situations where the available
data are neither sufficiently detailed nor exhaustive as it may be the case at an early stage of
a project. In this way, though flows are important they do not impact alone the layout pattern.
Therefore other supporting services that do not deal with volumes of flows might be taken
into consideration such as the purchasing or the production engineering department for
instance.
The two first cases were separately developed upon basic assumptions regarding the
product mix, the repair workload and the respective work organisations. A thorough analysis
of the practices implemented in shipyards of similar sizes and features was achieved.
Subsequently the study of a mixed layout was developed by merging the results of the
previous two cases, analysing which resources ought to be segregated, or partially or totally
shared based on their respective impact on the work processes.
Various configurations alternatives were then generated in order to illustrate the wide range
of possibilities that are offered to the planner. The selected layouts exhibit forms and
arrangements that are characteristic of the correspondent types of activity.
The main limitations to this work reside in the various assumptions essentially relating to the
productivity targets and the flows of elements that were required in order to achieve the
diverse analyses. Nonetheless the emphasis was on the application of a methodology of
layout design based on the procedure outlined by Muther which reveals a perfectly efficient
layout planning method adapted for the very early stage of a new project when quantitative
data are only broadly defined.
Symposium International : Qualité et Maintenance au Service de l’Entreprise
QUALIMA01 - Tlemcen 2004
References
1. Apple, J. M. (1991). Plant layout and material handling. Malabar, Fla., Krieger.
2. Baba, Koichi, (2000). Production technology survey of selected Asian shipyards.
NSRP, Maritech Engineering Japan, November 1, 2001, from website
www.nsrp.org/documents/asian_benchmarking.pdf
3. Bruce, G. J. and Garrard, I. (1999). The business of shipbuilding. Honk Kong, Llp.
4. Bruce, G., Clark, J., (1992). Productivity measures as a tool for performance
improvement. The Royal Institution of Naval Architects, Spring Meetings, 27 April
1992, paper No 2.
5. Chirillo, D. L., (1979). Outfit planning. NSRP, US Department of Commerce.
6. Drewry, (2001). Global Shiprepair Market Outlook to 2005. Shipping Consultants
Publications, June 2001, from website www.drewry.co.uk/frame2.phtml?loc=
info/mr049.phtml on 30/06/2003
7. Francis, R. L., and White, J. A., (1974). Facility layout and location – An analytical
approach. Prentice-Hall Inc., Englewoods Cliffs, New Jersey.
8. Garcia L., F. V., Torroja, J. (1994). The role of CAD/CAE/CAM in engineering for
production. Proceedings of the 8th ICCAS International Conference on Computer
Applications in Shipbuilding, Sept. 5-9, 1994, Bremen, Germany, Berry Rasmusson
Reklam AB.
9. Koenig, P. C., (2002). Technical and economic breakdown of value added in
shipbuilding. Journal of Ship Production, Vol. 18, No. 1, February 2002, pp. 13-18.
10. Lamb, T., and Hellesoy, A., (2002). A shipbuilding productivity predictor. Journal of
Ship Production, Vol. 18, No. 2, May 2002, pp. 79-85.
11. Muther, R. (1973). Systematic layout planning. Cahners books.
12. Storch, R. L., Hammon, C. P., et al. (1988). Ship production. Centreville, Md., Cornell
Maritime Press.
13. Wilson, V., Wennberg, P., DeGraw, K., and Fleischer, M., (2001). An improved “Make
versus Buy” strategy for future material acquisition. Journal of Ship Production, Vol.
17, No. 2, May 2001, pp. 87-91.
14. Zenasni, M. (1989). Domestic ship repair yard and improvement strategy. MSc
Thesis, Department of Marine Technology, University of Newcastle upon Tyne, Sep
1989
Symposium International : Qualité et Maintenance au Service de l’Entreprise
QUALIMA01 - Tlemcen 2004
Appendices
Appendix 1
The following figures illustrate how far-eastern shipyards which pioneered in
implementing Group Technology considerably improved their performances.
Figure 2 – World market share of the Far East shipbuilders as a result of their
competitiveness
(Lloyd’s Register, 2003)
Symposium International : Qualité et Maintenance au Service de l’Entreprise
QUALIMA01 - Tlemcen 2004
Appendix 2
Main characteristics of the ship models of the production mix
CGT values of the three ship models comprising the production mix
DWT CGT
N. Type GT CGT
(Tonnes) Coefficient
1 Reefer 2028 1872 2.05 3837.6
2 Chemical carrier 2500 1731 1.70 2942.7
3 Combined cargo 3284 2561 1.60 4097.6
Symposium International : Qualité et Maintenance au Service de l’Entreprise
QUALIMA01 - Tlemcen 2004
Appendix 3 - ASME symbols and Muther's coding for the Activity REL diagram
Nbr
Symbol Activity/Facility Color Rating Value of Color
lines
Treatment,
Green
Sub-assembly, A 4 Red
Red
Assembly
Transport
Orange E 3 Orange
related
Storage,
Orange I 2 Green
Warehouses
Services and
supporting Blue U 0
activities
Office,
Grey X -1 Brown
Administration
Inspection,
Blue
Check areas
Symposium International : Qualité et Maintenance au Service de l’Entreprise
QUALIMA01 - Tlemcen 2004
Appendix 4
Space requirements of a production facility
Floorspace
Facility Employees Density
(m2)
Steel stockyard (1000 tonnes) 2 tonnes/m2 2000
Steelwork hall 40 100 m2/worker 4000
Outfitting centre 30 60 m2/worker 1800
Pipe shop 20 60 m2/worker 1200
General purpose shop 10 60 m2/worker 600
Paint shop ( 2 cells of 20x20 m) 15 2x20x20 = 800
Warehouse 5 320 m2/worker 1600
Units and blocks storage areas 3x20x20 =
(for 3 grand blocks of 20x20 m) 1200
Erection areas (for 3 ships) 130x20/platform 3x2600
Lifting installations 6 4x130x10
Quays (to secure at least 2 2x130x20 =
ships of length up to 130 m) 2x2600
Production supporting services 27 15 m2/worker ~ 400
Training centre 12 30 m2/trainee ~ 400
Managers-Administrative 24 15 m2/worker ~ 400
offices
Transportation station: covered 5 ~1000
facility including workshop,
office, storage room and
shelter for handling equipment
Parking for 100 private cars 12x100+8x50 =
1600
Catering services 10 400
Health and medical service 3 100
35700
Total 207
(excluded the circulation pathways)
Symposium International : Qualité et Maintenance au Service de l’Entreprise
QUALIMA01 - Tlemcen 2004
Appendix 5
Space requirements of a repair facility
N. Facility Floorspace (m2)
1 Docking facilities 29500
2 Berths 26000
3 Steel shop 5000
4 Machine shop 1000
5 Electrical shop 500
6 Carpenter shop 500
7 Paint shop 500
8 Afloat repair shop 500
9 Warehouse 1600
10 Lifting installations 23300
11 Treatment plant 500
12 Administrative offices 400
13 Technical services 400
14 Health-medical service 100
15 Training centre 400
Transportation station 1000
16
Parking 1600
17 Catering services 400
Total 92300
Symposium International : Qualité et Maintenance au Service de l’Entreprise
QUALIMA01 - Tlemcen 2004