PS-DC-186-500-0018
Sheet 1 of 12
NTPC Ref no VIN/1/TS/2/007
Plant area: TURBO GENERATOR
PROCEDURE FOR GENERATOR AIR TIGHTNESS TEST
2.0 OBJECTIVE
3.0 PROPOSAL
8.0 METHOD
10.0 APPENDICES
Station: NTPC-Vindhyachal BHEL Ref No.PS-DC-186-500-0018
Sheet 2 of 12
NTPC Ref no VIN/1/TS/2/007
Plant area: TURBO GENERATOR
PROCEDURE FOR GENERATOR AIR TIGHTNESS TEST
SL.NO STATUS
1.0 PLANT DETAILS
a. STATOR
Stator Frame
End Shields
Stator Core
Stator winding
Hydrogen coolers
b. ROTOR
Rotor Shaft
Rotor windings
Rotor Retaining Rings
Field Connections
c. BEARINGS
d. SHAFT SEALS
1.2 The two pole generator is designed with direct water cooling for
the stator winding, phase connectors and bushings and direct
Hydrogen cooling for rotor winding. Generator losses, such as
iron losses, windage losses and stray losses are also dissipated
through hydrogen. The generator frame is pressure – resistant,
gastight and equipped with major components mentioned above.
The hydrogen coolers are arranged vertically inside the turbine
end stator end field.
Signatures
NTPC BHEL
Station: NTPC-Vindhyachal BHEL Ref No.PS-DC-186-500-0018
Sheet 3 of 12
NTPC Ref no VIN/1/TS/2/007
Plant area: TURBO GENERATOR
PROCEDURE FOR GENERATOR AIR TIGHTNESS TEST
SL.NO STATUS
1.3 The Generator is provided with the following auxiliaries which are
essential for generator operation.
Signatures
NTPC BHEL
Station: NTPC-Vindhyachal BHEL Ref No.PS-DC-186-500-0018
Sheet 4 of 12
NTPC Ref no VIN/1/TS/2/007
Plant area: TURBO GENERATOR
PROCEDURE FOR GENERATOR AIR TIGHTNESS TEST
SL.NO STATUS
2.0 OBJECTIVE
3.0 PROPOSAL
3.1 Testing of pipe between CO2 Bottle Rack and Hydrogen Unit at a
pressure of 4.8 bar of Nitrogen gas for 2 Hrs.
Signatures
NTPC BHEL
Station: NTPC-Vindhyachal BHEL Ref No.PS-DC-186-500-0018
Sheet 5 of 12
NTPC Ref no VIN/1/TS/2/007
Plant area: TURBO GENERATOR
PROCEDURE FOR GENERATOR AIR TIGHTNESS TEST
SL.NO STATUS
3.2 Testing of pipe between Hydrogen Bottle rack and Hydrogen Unit
at a pressure of 4.8 bar of Nitrogen gas for 2 Hrs.
3.3 Testing of Pipe between Nitrogen Bottle rack and P.W. Tank at a
pressure of 5.0 bar of Nitrogen gas for 2 Hrs.
3.4 Leakage Test of Generator along with Gas System using air at
4.0 bar for 72 Hrs
4.3 Availability of
Signatures
NTPC BHEL
Station: NTPC-Vindhyachal BHEL Ref No.PS-DC-186-500-0018
Sheet 6 of 12
NTPC Ref no VIN/1/TS/2/007
Plant area: TURBO GENERATOR
PROCEDURE FOR GENERATOR AIR TIGHTNESS TEST
SL.NO STATUS
6.2 The test team should know well about the procedures to be
adopted in case of damage to machinery or injury to personnel
connected to the activity.
7.2 Seal oil system commissioned and put into operation for
continuous running.
7.6 Stator winding filled with primary water and primary water tank
kept pressure less. All the valves closed in P.W. System.
Connect a ‘U’ Tube manometer in Waste gas line of P.W. Tank
after valve MKF91 AA 505 and close valve MKF91 AA 506. Open
valve MKF91 AA 513 and AA 505. It is also required to observe
for any leakage into primary water system through stator
windings during air leakage test.
Signatures
NTPC BHEL
Station: NTPC-Vindhyachal BHEL Ref No.PS-DC-186-500-0018
Sheet 7 of 12
NTPC Ref no VIN/1/TS/2/007
Plant area: TURBO GENERATOR
PROCEDURE FOR GENERATOR AIR TIGHTNESS TEST
SL.NO STATUS
7.7 Instrument air supply connected before valve MKG25 AA 501. Air
for filling should be free from moisture, oil and any mechanical
impurity.
7.10 Soap solution kept ready to check the leakages during test.
7.11 All the instruments in gas system are mounted as per scheme.
7.12 All the valves provided in H2 Unit are kept open so that all the
lines are pressurized during air filling. All valves connected to
vents are kept closed.
7.14 Vent valves provided in oil drain lines are closed viz., MKA21 AA
502, MKA 22 AA 502, MKA 23 AA 502, MKA 23 AA 512, MKA 24
AA 502.
7.15 Valves provided in gas impulse line for valve A1, A2 in seal Oil
system are opened.
Signatures
NTPC BHEL
Station: NTPC-Vindhyachal BHEL Ref No.PS-DC-186-500-0018
Sheet 8 of 12
NTPC Ref no VIN/1/TS/2/007
Plant area: TURBO GENERATOR
PROCEDURE FOR GENERATOR AIR TIGHTNESS TEST
SL.NO STATUS
7.16 Values MKG69 AA 504 and MKG69 AA 501 are opened to take
dryers in service.
8.0 METHOD
Signatures
NTPC BHEL
Station: NTPC-Vindhyachal BHEL Ref No.PS-DC-186-500-0018
Sheet 9 of 12
NTPC Ref no VIN/1/TS/2/007
Plant area: TURBO GENERATOR
PROCEDURE FOR GENERATOR AIR TIGHTNESS TEST
SL.NO STATUS
8.4 Leakage Test of Generator along with Gas System using Air.
Open valve MKG25 AA 501 and fill air in generator and gas
piping upto pressure of 4 Bar. During filling observe the
performance of pressure regulating valve of seal oil system and
maintain the H2 and air side seal oil Pressure as recommended.
Close valve MKG25 AA 501 as soon as pressure in the casing
reaches 4 bar.
I During the air leakage test, apply Soap Solution at all joints for
checking leakages in following areas:
Signatures
NTPC BHEL
Station: NTPC-Vindhyachal BHEL Ref No.PS-DC-186-500-0018
Sheet 10 of 12
NTPC Ref no VIN/1/TS/2/007
Plant area: TURBO GENERATOR
PROCEDURE FOR GENERATOR AIR TIGHTNESS TEST
SL.NO STATUS
Signatures
NTPC BHEL
Station: NTPC-Vindhyachal BHEL Ref No.PS-DC-186-500-0018
Sheet 11 of 12
NTPC Ref no VIN/1/TS/2/007
Plant area: TURBO GENERATOR
PROCEDURE FOR GENERATOR AIR TIGHTNESS TEST
SL.NO STATUS
Iii Observe for any pressure rise in P.W. tank during test by means
of Water ‘U’ manometer provided for this purpose. If any increase
is observed, stator winding system should be checked for
leakage.
IV Continue the test till the rate is well within specified limit. If no
leakage is observed, pressure drop should be checked for 72 hrs.
continuously.
Z 273+T1 273 + T2
VG = Generator volume, m3
Signatures
NTPC BHEL
Station: NTPC-Vindhyachal BHEL Ref No.PS-DC-186-500-0018
Sheet 12 of 12
NTPC Ref no VIN/1/TS/2/007
Plant area: TURBO GENERATOR
PROCEDURE FOR GENERATOR AIR TIGHTNESS TEST
SL.NO STATUS
If air loss is higher, checks should be carried out for detecting the
leakage areas.
10.0 APPENDICES
Gas System
P.W. System
Signatures