DRAWING LIST

SHEET DRAWING NO TITLE


0 OF 6 P1 - 92 - C3 - DW - 002 - 00 - C Drawing List
1 OF 6 P1 - 92 - C3 - DW - 002 - 00 - C Layout Access Road
2 OF 6 P1 - 92 - C3 - DW - 002 - 00 - C Detail Section Access Road & Detail Drainase
3 OF 6 P1 - 92 - C3 - DW - 002 - 00 - C Structure Platform & Rencana Pondasi Sumuran Jembatan
4 OF 6 P1 - 92 - C3 - DW - 002 - 00 - C Tampak Samping Jembatan, Detail Abutment & Potongan A-A
5 OF 6 P1 - 92 - C3 - DW - 002 - 00 - C Potongan B-B & Potongan C-C
6 OF 6 P1 - 92 - C3 - DW - 002 - 00 - C Detail Girder & Railing Samping Jembatan

NOTES :
1. ALL DIMENSION ARE IN MILLIMETERS
UNLESS OTHERWISE NOTED
2. ALL COORDINATES AND ELEVATION
ARE IN METERS UNLESS OTHERWISE
NOTED
3. MATERIAL
- CONCRETE PILE CAP : K-300
- LEAN CONCRETE : K-150
- DEFORMED BAR FOR : 400 MPa(BJTD40)
D 13mm
- PLAIN BAR FOR : 240 MPa(BJTP24)
D 13mm
- GROUTING : SIKAGROUT 215

DRAWING NO. TITLE

REFERENCE DRAWING

1 07/01/2019 ISSUED FOR APPROVE

0 21/12/2018 ISSUED FOR REVIEW


PREP'D APP'D CHK'D APP'D
REV. DATE DESCRIPTION
PMC PTPN X

PT. PERKEBUNAN NUSANTARA X


SURABAYA-INDONESIA

PT. PROSYS BANGUN PERSADA


JAKARTA-INDONESIA

PT. BARATA INDONESIA


GRESIK-INDONESIA

PROJECT :

EPCC PENINGKATAN KAPASITAS PG. GEMPOL KREP


DARI 6500 TCD MENJADI 8000 TCD TERINTEGRITAS
J
DENGAN PABRIK BIOETHANOL DAN COGENERATION
TITLE :
Drawing List

BARATA PMC PTPN X SCALE :


DESCRIPTION
SIGN DATE SIGN DATE SIGN DATE

DRAWN

CHECKE'D A3
APPROVED

DWG No. SHEET

P1 - 92 - C3 - DW - 002 - 00 - C 0 OF 6