Fire Proofing Pre-placement/ Site Preparation Inspection SAIC-B-1001 30-Apr-17 CIVIL-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

The surface preparation and coating requirements shall be specified


SAES-B-006
A1 on the applicable construction drawings and shall comply with SASD
Sec. 8.4
Drawings AD-036711, AC-036404 & AC-036915.

Steel surfaces that are to be insulated, fireproofed with cementitious


materials or covered with intumescent or other proprietary SAES-B-006
A2
fireproofing such as lightweight concrete, shall be coated in Sec. 8.4
accordance with SAES-H-101V, APCS-1B.

Minimum Cleanliness Level per SAES-H-101V (APCS-1B)


SAES-B-006
A3 Initial: Sa 2-1/2 (SP10)
Sec. 8.4
Touch-up: Sa 2-1/2 (SP10) St 3 (SP3) for areas less than 0.1 m²

Required Profile per SAES-H-101V (APCS-1B): 40-65 micrometers,


minimum-maximum SAES-B-006
A4
Abrasive: 1000161068 (08-220-865), 1000161203 (08-220-895) or Sec. 8.4
1000160374 (08-202-900).

SAES-B-006
A5 All openings between fireproofing and substrate shall be fully sealed.
Sec. 8.1.4

Wire mesh for concrete fireproofing shall be 4"x 4"-10ga x 10ga or SASD
A6
2"x 2"- 14ga x 14ga shall be installed in preparation for fireproofing. AD-036711

Surface preparation for proprietary fireproofing complies with the SAES-B-006


A7
manufacturer's recommendations and approved procedure. Sec. 8.2.1

REMARKS:

REFERENCE DOCUMENTS:
1- SAES-B-006 -- Fireproofing for Plants, 20 November 2011
2- SASD-AD-036711 -- Concrete Fireproofing for Structural Members, 1 September 2000
3- SASD-AC-036404 -- Flame Impingement Shield for Flangeless Valves-- 31 Dec 1994
4- SASD-AC-036915 -- Details: Fireproofing Specifications for Columns and Vessel Skirts, 1 March 1999

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 30-Apr-2017 - REV. 2015.03.00 (Standards Cutoff - March 2015)

Saudi Aramco: Company General Use


Rev. 2015.03.00

30-Apr-17

Saudi Aramco: Company General Use


###

Saudi Aramco: Company General Use

You might also like