Schedules
Sep, 2015
Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 2
National Highways Authority of India Schedules
SCHEDULE - A
1 The Site
1.1 Site of the Four-Lane Project Highway shall include the land, buildings, structures
and road works as described in Annex-I of this Schedule-A.
1.2 The dates of handing over the Right of Way to the Contractor are specified in Annex-
II of this Schedule-A.
1.3 An inventory of the Site including the land, buildings, structures, road works, trees
and any other immovable property on, or attached to, the Site shall be prepared
jointly by the Authority Representative and the Contractor, and such inventory shall
form part of the memorandum referred to in Clause 8.2.1 of this Agreement.
1.4 The alignment plans of the Project Highway are specified in Annex-III. In the case of
sections where no modification in the existing alignment of the Project Highway is
contemplated, the alignment plan has not been provided. Alignment plans have only
been given for sections where the existing alignment is proposed to be modified.
1.5 The status of the environment clearances obtained or awaited is given in Annex IV.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 3
National Highways Authority of India Schedules
Annex - I
(Schedule-A)
Site
1. Site
The site of project highway is a section of National Highway -48(New NH 75) , which
starts from Addahole (Near Gundya) to Bantwal Cross from Chainage 263+000 to
328+000. The length is 65.00 km. The land, carriageway and structures comprising
the Site are described below.
2. Land
The Site of the Project Highway comprises the land described below:
Existing km Existing
Sl.no ROW
From to varying in m
1 263.000 285.000 20-25
2 285.000 312.000 25-30
3 312.000 322.000 20-25
4 322.000 328.000 25-30
3. Carriageway
The type of the existing pavement is flexible. The present configuration of the carriageway is
presented as below:
4. Major Bridge
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 4
National Highways Authority of India Schedules
Nil
6. Grade separators
Nil
7. Minor bridges
2 269.180 2 x 18.20 RCC Solid Slab Stone Masonry Open Foundation 8.00
4 274.350 3 x 8.60 RCC Solid Slab Stone Masonry Open Foundation 8.00
5 277.650 1 x 8.50 RCC Solid Slab Stone Masonry Open Foundation 8.50
6 279.680 1 x 8.60 RCC Solid Slab Stone Masonry Open Foundation 8.50
RCC Deck
7 283.450 2 x 12.80 above stone Stone Masonry Open Foundation 9.00
arch masonry
8 286.330 3 x 8.00 RCC Solid Slab Stone Masonry Open Foundation 8.50
9 298.005 1 x 8.00 RCC Solid Slab Stone Masonry Open Foundation 8.00
11 306.460 1 x 8.00 RCC Solid Slab Stone Masonry Open Foundation 9.00
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 5
National Highways Authority of India Schedules
10. Culverts
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 6
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 7
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 8
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 9
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 10
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 11
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 12
National Highways Authority of India Schedules
The details of Bus Stop without Busbay on the site are as follows:
1 282.000 LHS
2 282.600 LHS
3 283.200 LHS
4 286.100 RHS
5 287.550 LHS
6 289.400 LHS
7 290.700 LHS
8 291.600 LHS
9 293.250 RHS
10 294.300 LHS
11 297.500 LHS
12 298.150 LHS
13 300.300 RHS
14 303.250 RHS
15 304.000 RHS
16 305.000 RHS
17 305.800 RHS
18 308.700 LHS
19 311.750 LHS
20 312.700 LHS
21 313.100 LHS
22 314.250 RHS
23 315.100 RHS
24 316.600 LHS
25 318.650 LHS
26 319.200 LHS
27 321.500 RHS
28 322.100 RHS
29 323.000 LHS
30 324.500 RHS
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 13
National Highways Authority of India Schedules
Right Hand
Sl. No. Existing km Length (m) Left Hand Side
Side
Nil
Type of
Existing Km
Sl. No Side
Masonary/cc Earthen
From To Length, Km
(Pucca) (Kuchha)
1 277.000 278.100 1.1 LHS Kuchha
2 277.000 278.700 1.7 RHS Kuchha
3 278.950 279.450 0.5 LHS Kuchha
4 278.900 279.150 0.25 RHS Kuchha
5 279.800 280.050 0.25 LHS Kuchha
6 280.350 280.550 0.2 LHS Kuchha
7 280.650 281.100 0.45 LHS Kuchha
8 281.000 281.100 0.1 RHS Pucca
9 281.350 281.650 0.3 LHS Kuchha
10 281.900 282.150 0.25 RHS Pucca
11 282.250 282.450 0.2 RHS Pucca
12 282.700 282.850 0.15 RHS Pucca
13 282.950 283.050 0.1 LHS Kuchha
14 283.800 283.950 0.15 LHS Kuchha
15 286.050 286.20 0.15 LHS Pucca
16 286.950 287.050 0.1 LHS Kuchha
17 286.950 287.750 0.8 RHS Kuchha
18 288.050 288.380 0.32 LHS Kuchha
19 290.700 290.850 0.15 LHS Kuchha
20 291.050 291.400 0.35 LHS Kuchha
21 291.650 291.850 0.2 LHS Pucca
22 292.050 293.000 0.95 LHS Kuchha
23 293.050 293.150 0.1 LHS Kuchha
24 293.700 293.950 0.25 LHS Kuchha
25 294.130 294.250 0.13 LHS Pucca
26 294.300 294.800 0.5 RHS Kuchha
27 295.700 295.950 0.25 LHS Kuchha
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 14
National Highways Authority of India Schedules
Type of
Existing Km
Sl. No Side
Masonary/cc Earthen
From To Length, Km
(Pucca) (Kuchha)
28 296.350 296.650 0.3 LHS Kuchha
29 296.700 296.780 0.07 LHS Kuchha
30 297.600 297.750 0.15 RHS Kuchha
31 303.000 303.300 0.3 LHS Kuchha
32 303.400 303.580 0.18 RHS Kuchha
33 304.080 304.610 0.54 RHS Kuchha
34 305.700 306.030 0.32 LHS Kuchha
35 305.780 306.550 0.78 RHS Kuchha
36 306.350 306.750 0.4 LHS Kuchha
37 306.600 306.700 0.1 RHS Kuchha
38 307.350 307.600 0.25 RHS Kuchha
39 309.150 309.380 0.23 LHS Kuchha
40 310.050 310.200 0.15 LHS Kuchha
41 310.100 310.550 0.45 RHS Kuchha
42 310.550 311.200 0.65 LHS Kuchha
43 311.480 311.780 0.3 LHS Kuchha
44 312.000 312.200 0.2 LHS Pucca
45 312.300 312.700 0.4 LHS Pucca
46 312.750 312.850 0.1 LHS Pucca
47 313.100 313.600 0.5 LHS Pucca
48 313.100 313.200 0.1 RHS Pucca
49 313.350 313.680 0.32 RHS Pucca
Category of Cross
Sl. No. Location Arms At Grade/Separated
Road
Gundya,km SH-37 , To
1 3 At grade
261.300 Subramanya
Ichilampady, SH-37 , To
2 3 At grade
km 279.000 Dharmasthala
(NH: National Highway, SH: State Highway, MDR: Major District Road)
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 15
National Highways Authority of India Schedules
Type of Leads to
Sl. No Existing Km
Junction LHS RHS
1 264.650 3 Legged Shiratka Road
2 268.160 3 Legged Kalapa Road
3 268.440 3 Legged Koothkodi Road
4 280.650 3 Legged Village Road
5 285.220 3 Legged Village Road
6 290.460 3 Legged Village Road
7 294.650 3 Legged Village Road
8 298.550 3 Legged Puttur
9 301.680 4 Legged Village Road Village Road
10 305.820 3 Legged Village Road
11 306.800 3 Legged Village Road
12 309.360 3 Legged Village Road
13 309.790 3 Legged Village Road
14 310.230 3 Legged Village Road
15 310.800 3 Legged Village Road
16 311.070 3 Legged Village Road
17 313.650 3 Legged Village Road
18 314.530 3 Legged Village Road
19 316.380 3 Legged Village Road
20 317.360 3 Legged Village Road
21 318.290 3 Legged Village Road
22 318.830 3 Legged Village Road
23 321.360 3 Legged Village Road
24 322.310 4 Legged Pane Mangalore Shamboor
25 322.380 3 Legged Old NH
26 322.894 3 Legged Village Road
15. Bypasses
Nil
Nil
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 16
National Highways Authority of India Schedules
Kilometre stones exist along the entire length of the project highway except in few
places. The relationship between the “Existing Chainage” and the “Design Chainage”
as per field survey is given below.
Proposed
Sl. No Existing Km Remarks
Chainage
1 263 255+703
2 264 256+703
3 265 257+715
4 267 259+668
5 268 260+708
6 269 261+743
7 271 263+788
8 272 264+818
9 273 265+868
10 274 266+880
11 275 267+500
12 276 268+198
13 277 269+198
14 278 270+230
15 279 271+248
16 280 272+251
17 281 273+238
18 282 274+246
19 283 275+241
20 284 276+222
21 285 277+190
22 286 278+170
23 287 279+150
24 288 280+141
25 289 281+142
26 290 282+145
27 291 283+196
28 292 284+104
29 293 285+096
30 294 286+012
31 295 286+911
32 296 287+888
33 297 288+814
34 298 289+800
35 299 290+829
36 300 291+768
37 301 292+792
38 302 293+831
39 303 294+923
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 17
National Highways Authority of India Schedules
Proposed
Sl. No Existing Km Remarks
Chainage
40 304 295+677
41 305 296+495
42 306 297+401
43 307 298+262
44 308 299+118
45 309 300+081
46 310 300+982
47 311 301+935
48 312 302+864
49 313 303+870
50 314 304+838
51 315 305+820
52 316 306+812
53 317 307+748
54 318 308+769
55 319 309+732
56 320 310+681
57 321 311+705
58 322 312+693
59 323 313+695
60 324 314+678
61 325 315+655
62 326 316+708
63 328 318+755
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 18
National Highways Authority of India Schedules
Annex - II
(Schedule-A)
The dates on which the Authority shall provide Right of Way to the Contractor on different stretches of the Site are stated below:
Details of Land
Proposed ROW
Design Chainage Details of Land Required Availability
Total Land to
(in M)
Sl. Name of the
No village Existing Additional Total Possession Land be
Length land area Land already Available Acquired Date of
(in available required Required taken (in Sqm) (in Sqm) Providing
From To Km) (in Sqm) (in Sqm) (in Sqm) (in Sqm) (7+10) (9-11) ROW
1 2 3 4 5 6 7 8 9 10 11 12 13
I PART RIGHT OF WAY (FULL WIDTH)
1 Shirady 261.560 261.800 0.240 30 7200 0 7200 0 7200 0
At the
2 Rekhya 267.000 267.150 0.150 30 4500 0 4500 0 4500 0 time of
TOTAL 0.390 11700 11700 11700 appointed
Say 1.17 Ha 1.17Ha 1.17Ha date
II PART RIGHT OF WAY (PART WIDTH)
1 Shirady RHS 255.500 255.740 0.240 30 864 6336 7200 0 864 6336
2 Shirady RHS 255.890 256.800 0.910 30 3278 24022 27300 0 3278 24022
3 Shirady RHS 256.800 257.160 0.360 30 1298 9502 10800 0 1298 9502
4 Shirady RHS 259.320 260.980 1.660 30 8968 40832 49800 0 8968 40832
5 Shirady RHS 260.980 261.900 0.920 30 3314 24286 27600 0 3314 24286
6 Konaje LHS 262.300 263.000 0.700 30 2521 18479 21000 0 2521 18479
7 Shirady 263.000 263.500 0.500 45 9300 13200 22500 0 9300 13200
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal Cross (Design chainage 318+755)
19
National Highways Authority of India Schedules
Details of Land
Proposed ROW
Design Chainage Details of Land Required Availability
Total Land to
(in M)
Sl. Name of the
No village Existing Additional Total Possession Land be
Length land area Land already Available Acquired Date of
(in available required Required taken (in Sqm) (in Sqm) Providing
From To Km) (in Sqm) (in Sqm) (in Sqm) (in Sqm) (7+10) (9-11) ROW
1 2 3 4 5 6 7 8 9 10 11 12 13
8 shirady 263.500 263.740 0.240 30 864 6336 7200 0 864 6336
9 263.740 265.000 1.260 30 583 37217 37800 0 583 37217
Nujibal Thila +
10 265.000 265.900 0.900 45 13916 26584 40500 0 13916 26584
Rekhya
11 265.900 266.050 0.150 30 69 4431 4500 0 69 4431
12 266.250 266.700 0.450 30 208 13292 13500 0 208 13292
13 266.700 266.850 0.150 30 70 4430 4500 0 70 4430
14 Rekhya 267.150 267.740 0.590 30 274 17426 17700 0 274 17426
Within
15 267.740 268.000 0.260 30 7242 558 7800 0 7242 558 150 days
16 Ichalampady 268.280 269.700 1.420 30 39550 3050 42600 0 39550 3050 from
17 269.700 269.900 0.200 45 8570 430 9000 0 8570 430 appointed
18 269.900 272.100 2.200 45 58225 40775 99000 0 58225 40775 date
Kowkrady
19 272.280 273.970 1.690 45 44726 31324 76050 0 44726 31324
20 273.970 275.350 1.380 45 30451 31649 62100 0 30451 31649
Nellyadi
21 275.500 275.700 0.200 45 3980 5020 9000 0 3980 5020
22 275.700 277.600 1.900 45 58589 26911 85500 0 58589 26911
Konalu
23 277.600 278.470 0.870 45 26828 12322 39150 0 26828 12322
Konalu
24 277.600 278.500 0.900 45 12735 27765 40500 0 12735 27765
Masjid Area
25 Golitattu 278.470 282.650 4.180 45 136938 51162 188100 0 136938 51162
26 282.650 282.720 0.070 45 1224 1926 3150 0 1224 1926
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal Cross (Design chainage 318+755)
20
National Highways Authority of India Schedules
Details of Land
Proposed ROW
Design Chainage Details of Land Required Availability
Total Land to
(in M)
Sl. Name of the
No village Existing Additional Total Possession Land be
Length land area Land already Available Acquired Date of
(in available required Required taken (in Sqm) (in Sqm) Providing
From To Km) (in Sqm) (in Sqm) (in Sqm) (in Sqm) (7+10) (9-11) ROW
1 2 3 4 5 6 7 8 9 10 11 12 13
27 Bajathur 283.400 286.550 3.150 45 55072 86678 141750 0 55072 86678
28 286.830 287.490 0.660 45 11539 18161 29700 0 11539 18161
29 287.490 287.700 0.210 45 1432 8018 9450 0 1432 8018
30 Uppinangady 287.840 288.420 0.580 45 3954 22146 26100 0 3954 22146
31 288.900 290.140 1.240 45 8454 47346 55800 0 8454 47346
32 290.460 292.670 2.210 45 15066 84384 99450 0 15066 84384
33 292.670 293.450 0.780 45 7299 27801 35100 0 7299 27801
34 Nekkiladi 293.450 294.200 0.750 45 7019 26731 33750 0 7019 26731
35 294.200 295.480 1.280 45 11979 45621 57600 0 11979 45621 Within
36 295.900 295.980 0.080 45 749 2851 3600 0 749 2851 150 days
Nekkiladi from
37 293.450 294.200 0.750 45 25192 8558 33750 0 25192 8558 appointed
Masjid Area
date
38 295.980 296.350 0.370 45 6007 10643 16650 0 6007 10643
Biliyur
39 296.500 296.600 0.100 45 1623 2877 4500 0 1623 2877
40 296.700 297.580 0.880 45 14287 25313 39600 0 14287 25313
41 Perne 298.000 299.970 1.970 45 34947 53703 88650 0 34947 53703
42 Kadeshvailya 299.970 300.380 0.410 45 3077 15373 18450 0 3077 15373
43 Kedila 300.380 300.800 0.420 45 2104 16796 18900 0 2104 16796
44 300.960 301.620 0.660 45 3306 26394 29700 0 3306 26394
45 301.730 302.100 0.370 45 1853 14797 16650 0 1853 14797
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal Cross (Design chainage 318+755)
21
National Highways Authority of India Schedules
Details of Land
Proposed ROW
Design Chainage Details of Land Required Availability
Total Land to
(in M)
Sl. Name of the
No village Existing Additional Total Possession Land be
Length land area Land already Available Acquired Date of
(in available required Required taken (in Sqm) (in Sqm) Providing
From To Km) (in Sqm) (in Sqm) (in Sqm) (in Sqm) (7+10) (9-11) ROW
1 2 3 4 5 6 7 8 9 10 11 12 13
46 302.450 303.300 0.850 45 4258 33992 38250 0 4258 33992
47 303.300 304.550 1.250 45 19561 36689 56250 0 19561 36689
Peraje
48 304.800 306.150 1.350 45 21127 39623 60750 0 21127 39623
49 306.150 306.220 0.070 45 1545 1605 3150 0 1545 1605
Mani
50 306.320 308.550 2.230 45 49207 51143 100350 0 49207 51143
51 308.660 308.890 0.230 45 4634 4816 9450 0 4634 4816
52 308.890 309.900 1.010 45 29877 15573 45450 0 29877 15573
Balthila
53 310.050 311.650 1.600 45 47330 24670 72000 0 47330 24670
54 Goltha Majalu 311.650 313.530 1.880 45 32282 52318 84600 0 32282 52318
Goltha Majalu Within
55 313.530 314.040 0.510 90 17515 28385 45900 0 17515 28385
Toll 150 days
Goltha Majalu from
56 314.040 314.160 0.120 130 5953 9647 15600 0 5953 9647
Toll appointed
Pane date
57 Mangalore 314.160 314.240 0.080 130 1713 8687 10400 0 1713 8687
Toll
58 Pane 314.240 314.660 0.420 90 6226 31574 37800 0 6226 31574
Mangalore
59 Toll 314.660 314.900 0.240 45 1779 9021 10800 0 1779 9021
60 315.230 315.940 0.710 45 5262 26688 31950 0 5262 26688
61 Narikombu 315.940 317.850 1.910 45 29470 56480 85950 0 29470 56480
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal Cross (Design chainage 318+755)
22
National Highways Authority of India Schedules
Details of Land
Proposed ROW
Design Chainage Details of Land Required Availability
Total Land to
(in M)
Sl. Name of the
No village Existing Additional Total Possession Land be
Length land area Land already Available Acquired Date of
(in available required Required taken (in Sqm) (in Sqm) Providing
From To Km) (in Sqm) (in Sqm) (in Sqm) (in Sqm) (7+10) (9-11) ROW
1 2 3 4 5 6 7 8 9 10 11 12 13
62 B.Muda 317.850 318.755 0.905 45 6464 35026 41490 0 6464 35026
TOTAL 56.535 973747 1489393 2463140 0 973747 1489393
97.374 148.939 148.939
Say Ha Ha 246.314 97.37 Ha Ha
III BALANCE RIGHT OF WAY
1 Shirady 255.740 255.890 0.150 30 0 4500 4500 0 0 4500
2 Shirady + 261.900 262.000 0.100 30 0 3000 3000 0 0 3000
3 Konaje 262.000 262.300 0.300 30 0 9000 9000 0 0 9000
4 266.850 267.000 0.150 30 0 4500 4500 0 0 4500
Nujibalthila
5 266.050 266.250 0.200 30 0 6000 6000 0 0 6000
6 Kowkrady Within
272.100 272.280 0.180 45 0 8100 8100 0 0 8100
150 days
7 Nellyadi 275.350 275.500 0.150 45 0 6750 6750 0 0 6750 from
8 282.720 283.400 0.680 45 0 30600 30600 0 0 30600 appointed
Bajathur
9 286.550 286.830 0.280 45 0 12600 12600 0 0 12600 date
10 287.700 287.840 0.140 45 0 6300 6300 0 0 6300
11 Uppinangady 288.420 288.940 0.520 45 0 23400 23400 0 0 23400
12 288.700 288.900 0.200 45 0 9000 9000 0 0 9000
13 290.140 290.460 0.320 45 0 14400 14400 0 0 14400
14 295.150 295.300 0.150 45 0 6750 6750 0 0 6750
15 Nekkiladi 295.480 295.900 0.420 45 0 18900 18900 0 0 18900
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal Cross (Design chainage 318+755)
23
National Highways Authority of India Schedules
Details of Land
Proposed ROW
Design Chainage Details of Land Required Availability
Total Land to
(in M)
Sl. Name of the
No village Existing Additional Total Possession Land be
Length land area Land already Available Acquired Date of
(in available required Required taken (in Sqm) (in Sqm) Providing
From To Km) (in Sqm) (in Sqm) (in Sqm) (in Sqm) (7+10) (9-11) ROW
1 2 3 4 5 6 7 8 9 10 11 12 13
16 293.450 294.200 0.750 45 0 8558 8558 0 0 8558
17 296.350 296.500 0.150 45 0 6750 6750 0 0 6750
Biliyur
18 297.600 297.700 0.100 45 0 4500 4500 0 0 4500
19 297.580 297.890 0.310 45 0 13950 13950 0 0 13950
20 Perne 297.890 298.000 0.110 45 0 4950 4950 0 0 4950
21 300.800 300.960 0.160 45 0 7200 7200 0 0 7200
Kedila
22 301.620 301.730 0.110 45 0 4950 4950 0 0 4950
Within
23 302.100 302.450 0.350 45 0 15750 15750 0 0 15750 150 days
24 Peraje 304.550 304.800 0.250 45 0 11250 11250 0 0 11250 from
25 306.220 306.320 0.100 45 0 4500 4500 0 0 4500 appointed
Mani
26 308.550 308.680 0.130 45 0 5850 5850 0 0 5850 date
27 Balthila 309.900 310.050 0.150 45 0 6750 6750 0 0 6750
Panemangalore
28
Bypass 314.900 315.230 0.330 45 0 14850 14850 0 0 14850
TOTAL 6.940 0 273608 273608 0 0 273608
Say 27.36 Ha 27.36 Ha 27.36 Ha
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal Cross (Design chainage 318+755)
24
National Highways Authority of India Schedules
Annex - III
(Schedule-A)
Alignment Plans
The existing alignment of the Project Highway shall be modified in the following sections as
per the alignment plan indicated below:
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 25
National Highways Authority of India Schedules
Annex - IV
(Schedule-A)
Environment Clearances
Since the length of the project is less than 100 kms, the project shall not require
Environment Clearance, as per the amendment of EIA Notification 2006 issued by MoEF
So 2559 (E) dated 22.08.2013.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 26
National Highways Authority of India Schedules
SCHEDULE - B
(See Clause 2.1)
Development of the Project Highway shall include design and construction of the
Project Highway as described in this Schedule-B and in Schedule-C.
Rehabilitation and augmentation shall include four laning and strengthening of the
Project Highway as described in Annex-I of this Schedule-B and in Schedule-C.
The Project Highway shall be designed and constructed in conformity with the
Specifications and Standards specified in Annex-I of Schedule-D.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 27
National Highways Authority of India Schedules
Annex - I
(Schedule-B)
Description of Four-Laning
1.1 The Project Highway shall follow the existing alignment unless otherwise specified
by the Authority and shown in the alignment plans specified in Annex III of
Schedule-A. Geometric deficiencies, if any, in the existing horizontal and vertical
profiles shall be corrected as per the prescribed standards for [Plain/Rolling] terrain
to the extent land is available.
1.2.1 Four lane divided Carriageway with paved shoulder shall be undertaken. The paved
carriageway shall be 18 m, 19 m and 23 m wide excluding the Median & Service Road
in accordance with the typical cross sections drawings in the Manual.
Provided that in the built-up areas the width of the carriageway shall be as specified
in the following table:
1.2.2 Except as otherwise provided in this Agreement, the width of the paved carriageway
and cross-sectional features shall conform to paragraph 1.1 above.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 28
National Highways Authority of India Schedules
2.1 General
Geometric design and general features of the Project Highway shall be in accordance
with Section 2 of the Manual.
The design speed shall be the minimum design speed of 80 km per hr for plain/
rolling terrain for the stretch 255.703 to 318.755 unless otherwise specified.
In the following sections, where improvement of the existing road geometrics to the
prescribed standards is not possible, the existing road geometrics shall be improved
to the extent possible within the given right of way and proper road signs and safety
measures shall be provided at the below locations.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 29
National Highways Authority of India Schedules
There are 36 no’s of realignments in the project highway. The details of realignments to be
provided are given below;
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 30
National Highways Authority of India Schedules
Design Chainage
Sl. No Length in m Proposed ROW (m) Remarks
From to
1 255+703 263+000 7297 30 Ghat Section & Forest
2 263+000 263+500 500 45
3 263+500 265+100 1600 30 Forest
4 265+100 265+900 800 45
5 265+900 269+700 3800 30 Forest
6 269+700 313+530 43830 45
7 313+530 314+040 510 90 Toll Plaza
8 314+040 314+250 210 130 Toll Plaza
9 314+250 314+670 420 90 Toll Plaza
10 314+670 318+755 4085 45
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 31
National Highways Authority of India Schedules
following sections.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 32
National Highways Authority of India Schedules
(b) In open country, paved shoulders of 1.5 m width shall be provided and
earthen shoulder 2.0 m width shall be covered with 150 mm thick compacted
layer of granular material.
(c) Design and specifications of paved shoulders shall conform to the requirements
specified in Section 2.6 of the Manual.
2.6.2 Lateral clearance: The width of the opening at the underpasses shall be as follows:
Vertical
Sl. Existing Design Span clearance Location Remarks, if any
No Chainage Chainage /Opening (m)
On
1 Realignm 257.992 1 x 7.0 4.50 - EUP (Elephant Underpass)
ent
To
3 278+510 270+740 1 x 24.00 5.50 Uni Directional
Dharmastala
4 281+990 274+240 1 X 7.00 3.00 Nellyadi PUP
Bi Directional
4x20+1x24 Uppinangadi VUP with viaduct span.
5 300+210 291+973 5.50
+4x20 Junction As per Section:3 (b) of
Schedule B
Bi Directional
4x20+1x24 Puttur Road VUP with viaduct span.
6 316+020 306+840 5.50
+4x20 Junction As per Section:3 (b) of
Schedule B
Bi Directional VUP with
4x20+1x24 viaduct span.
7 321+710 312+394 5.50 Goltha Majalu
+4x20 As per Section:3 (b) of
Schedule B
8 326+300 317+015 1 X 7.00 3.0 * Narikombu PUP
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 33
National Highways Authority of India Schedules
Note: Width and of the structure and vertical clearance shall be as per IRC SP 84 – 2014
2.7.1 Lateral and vertical clearances at overpasses shall be as per Section 2.11 of the
Manual.
2.7.2 Lateral clearance: The width of the opening at the overpasses shall be as follows:
Location
Span/opening
Sl. No (chainage) Remarks
(m)
(from km to km)
Nil
Service roads & Slip Roads shall be constructed at the locations and for the lengths
indicated below:
(a) Service road: Service road shall be provided at the following locations
Note: - Service road to Main Carriageway tapering shall be provided as per IRC-SP-84-2014 Section 2.12.2.3
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 34
National Highways Authority of India Schedules
(b) Slip road: Slip road shall be provided at the following locations
2.9.1 Grade separated structures shall be provided as per Section 2.13 of the Manual. The
requisite particulars are given below:
2.9.2 In the case of grade separated structures, the type of structure and the level of the
Project Highway and the cross roads shall be as follows:
Sl.
Cross road at Remarks, if any
No Location/ Design Type of Length
Existing
Chainage Chainage structure (m) Existing Raised Lowered
Level Level Level
24.00
1 278+510 270+740 VUP To Dharmastala
184.00 Uppinangadi Junction
VUP with viaduct span.
2 300+210 291+973 VUP
As per Cl:3 (b) of
Schedule B
3 316+020 306+840 VUP 184.00 Puttur Road Junction
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 35
National Highways Authority of India Schedules
Sl.
Cross road at Remarks, if any
No Location/ Design Type of Length
Existing
Chainage Chainage structure (m) Existing Raised Lowered
Level Level Level
VUP with viaduct span.
As per Cl:3 (b) of
Schedule B
184.00 At Goltha Majalu
VUP with viaduct span.
4 321+710 312+394 VUP
As per Cl:3 (b) of
Schedule B
20.00
5 327+920 318+745 VUP At BC Road cross
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 36
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 37
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 38
National Highways Authority of India Schedules
Kowkrady 2
Eccentric
69 270+340 271+010 670 6 Slip Road RHS Lane VUP -
Left
270+740
Kowkrady 2
70 271+010 271+090 80 6 Concentric Slip Road RHS Lane VUP-
270+740
71 271+090 271+320 230 1 Realignment
Eccentric
72 271+320 271+610 290 1A
Left
73 271+610 271+780 170 1 Realignment
Eccentric
74 271+780 272+000 220 1A
Right
75 272+000 272+440 440 1 Realignment
Eccentric
76 272+440 272+510 70 1A
Right
77 272+510 272+640 130 1 Realignment
Eccentric
78 272+640 272+740 100 1A
Left
79 272+740 273+840 1100 1A Eccentric
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 39
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 40
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 41
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 42
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 43
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 44
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 45
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 46
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 47
National Highways Authority of India Schedules
Note: - Median & Carriageway width tapering shall be provided as per IRC-SP-84-2014 Section
no 2.5.4 and section 2.12.2.3
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 48
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal
Cross (Design chainage 318+755) 49
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal Cross (Design chainage 318+755) 50
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal Cross (Design chainage 318+755) 51
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal Cross (Design chainage 318+755) 52
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal Cross (Design chainage 318+755) 53
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal Cross (Design chainage 318+755) 54
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal Cross (Design chainage 318+755) 55
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal Cross (Design chainage 318+755) 56
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal Cross (Design chainage 318+755) 57
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal Cross (Design chainage 318+755) 58
National Highways Authority of India Schedules
All intersections and grade separators shall be as per Section 3 of the Manual.
Existing intersections which are deficient shall be improved to the prescribed
standards.
Properly designed intersections shall be provided at the locations and of the types
and features given in the tables below:
Major Junctions
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 59
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Note:
The contractor shall take up ‘Detailed Engineering study’ to ascertain further details of all
intersections and treatment of the intersections shall be designed in accordance with the
latest guidelines mentioned out in section-3 of Manual.
Minor Intersections:-
In addition to the above listed Major and Minor intersections, other minor
intersections consisting of Earthen road, BT road etc. which are not listed above shall
also be considered for minor improvements. These intersections shall be re-graded
to match with the Edge of the Main Carriageway with due regard to physical
conditions of the site available and within the PROW. The entire cross roads shall be
connected to the highway through properly designed entry and exit curves. The
minimum values for the entry and exit curves of cross roads shall be as per Section
3.2.2 of the Manual.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 60
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Minimum
Length Of Road to be
Sl. Existing Design Salient Improvement carried
viaduct to Remarks
No Chainage Chainage Features be provided Proposed over/under the
structure
RHS Towards Cross Road
Dharmasthala. carried under
Uni
1 278+510 270+740 Super Nil VUP the structure -
direction
structure – RHS Towards
PSC Girder Dharmasthala
RHS
80 m +80 m Cross Road
Towards
(On Either carried under
Uppinangadi. Bi
2 300+210 291+973 side of VUP structure - RHS
Super direction
obligatory Towards
structure –
Span) Uppinangadi
PSC Girder
LHS Towards 80 m +80 m Cross Road
Puttur (On Either carried under
Bi
3 316+020 306+840 Super side of VUP structure - LHS
direction
structure – obligatory Towards
PSC Girder Span) Puttur
LHS Towards 80 m +80 m Cross Road
Vittal (On Either carried under
4 321+710 312+394 Super side of VUP the structure - Bi direction
structure – obligatory LHS Towards
RCC Girder Span) Vittal
RHS
Cross Road
Towards
carried under
Bantwal Bi
5 327+920 318+750 Nil VUP structure - RHS
Super direction
Towards
structure –
Bantwal
RCC Girder
RCC Box
On Elephant
6 257+992 Type Nil EUP -
Realignment Crossing
Structure
RCC Box
Pedestrian
7 272+940 265+747 Type Nil PUP School
Crossing.
Structure
RCC Box
Pedestrian
8 281+990 274+240 Type Nil PUP School
Crossing.
Structure
RCC Box PUP
Pedestrian
9 326+300 317+015 Type Nil PUP (Existing
Crossing.
Structure Widening)
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 61
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
4.2 Raising of the existing road shall be as per Section 4.2 of Manual.
5 PAVEMENT DESIGN
5.1 Pavement design shall be carried out in accordance with Section 5 of the Manual.
Rigid pavement is proposed for the carriage way and paved shoulder of entire
project stretch, including Service Road, Bus bay, Truck Lay Bye, Rest area and toll
plaza locations.
Rigid pavement shall be designed for a minimum design period of 30 years. Stage
construction shall not be permitted.
6 ROADSIDE DRAINAGE
Drainage system including surface and subsurface drains for the Project Highway shall
be provided as per Section 6 of the Manual.
Longitudinal Drains
(a) RCC Covered Drain (Between Main Carriageway and service road)
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 62
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 63
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Design Chainage
Sl. No Length in m Side Total Length m
From To
1 262+390 263+100 710 Both 1420
2 263+385 265+500 2115 Both 4230
3 265+835 270+340 4505 Both 9010
4 271+090 273+840 2750 Both 5500
5 274+790 291+440 16650 Both 33300
6 292+440 303+440 11000 Both 22000
7 303+990 306+490 2500 Both 5000
8 307+340 308+790 1450 Both 2900
9 309+040 312+090 3050 Both 6100
10 312+990 314+800 1810 Both 3620
11 315+750 318+280 2530 Both 5060
Total Length in m 98140
Note: The locations of RCC drain, earthen drain mentioned above are bare minimum and tentative and
has to be provided as per the manual and as per the site requirement.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 64
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Median drain shall be provided to drain off rain water. The drain should have
adequate longitudinal slope to the nearest culvert to drain off transversely. In super
elevated sections the longitudinal drains should be designed to take the discharge
from one side carriage way also median shall be turfed or paved and could be
crowned for drainage across the pavement. In super elevated sections combination of
covered longitudinal and cross drains shall be provided as per Section 6.3 of Manual.
Design Chainage
Sl. No
From To
1 256.116 256.198
2 256.264 256.371
3 256.673 256.719
4 256.987 257.041
5 257.092 257.211
6 257.457 257.528
7 257.612 257.657
8 257.808 257.855
9 257.969 258.041
10 258.269 258.290
11 258.378 258.461
12 258.555 258.653
13 258.723 258.734
14 258.800 258.854
15 258.909 258.982
16 259.075 259.248
17 260.137 260.194
18 260.504 260.527
19 260.658 261.284
20 261.615 261.904
21 262.239 262.655
22 262.866 263.145
23 263.401 263.852
24 264.054 264.086
25 264.687 264.869
26 265.403 265.460
27 265.613 265.720
28 266.299 266.369
29 266.644 266.711
30 266.955 267.005
31 267.330 267.581
32 267.897 267.988
33 268.671 268.719
34 269.099 269.215
35 269.620 269.731
36 270.011 270.034
37 270.537 270.559
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 65
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Design Chainage
Sl. No
From To
38 270.715 270.753
39 270.930 270.998
40 271.183 271.379
41 271.721 271.791
42 272.025 272.180
43 272.537 272.861
44 272.970 273.283
45 273.327 273.406
46 273.580 273.974
47 274.207 274.381
48 274.770 275.069
49 275.388 275.445
50 275.830 275.883
51 276.090 276.162
52 276.456 276.633
53 276.905 277.028
54 277.274 277.282
55 277.488 277.508
56 278.046 278.069
57 278.334 278.430
58 278.819 279.039
59 279.353 279.371
60 279.655 279.809
61 280.078 280.110
62 280.721 280.777
63 281.092 281.140
64 281.448 281.497
65 281.753 281.871
66 282.130 282.188
67 282.431 282.519
68 282.892 283.177
69 283.528 283.737
70 283.992 284.042
71 284.392 284.548
72 285.437 285.492
73 285.765 285.781
74 286.305 286.338
75 286.633 286.690
76 287.150 287.234
77 287.490 287.560
78 287.833 288.307
79 288.779 288.812
80 289.202 289.383
81 289.566 289.644
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 66
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Design Chainage
Sl. No
From To
82 289.776 289.796
83 290.312 290.443
84 290.905 290.981
85 291.209 291.426
86 291.838 291.889
87 292.410 292.455
88 292.916 293.127
89 293.431 293.613
90 293.693 293.728
91 293.978 294.115
92 294.353 294.382
93 294.647 294.744
94 294.899 295.217
95 295.433 295.521
96 295.865 295.996
97 296.313 296.544
98 297.477 297.531
99 297.987 298.163
100 298.391 298.578
101 298.691 299.360
102 299.487 299.609
103 299.814 299.832
104 300.052 300.078
105 300.287 300.494
106 300.601 300.675
107 300.973 301.138
108 301.323 301.510
109 301.626 301.831
110 302.082 302.292
111 302.410 302.589
112 302.811 303.027
113 303.400 303.427
114 303.689 303.818
115 304.149 304.362
116 305.000 305.092
117 305.359 305.614
118 305.809 305.855
119 306.054 306.192
120 306.367 306.570
121 307.055 307.070
122 307.314 307.440
123 307.691 307.776
124 308.204 308.250
125 308.507 308.563
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 67
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Design Chainage
Sl. No
From To
126 308.715 308.941
127 309.085 309.116
128 309.718 309.856
129 310.050 310.114
130 310.256 310.378
131 310.669 310.892
132 311.008 311.214
133 311.395 311.423
134 311.559 311.801
135 311.848 311.910
136 312.138 312.318
137 312.509 312.515
138 312.768 312.810
139 313.189 313.362
140 313.544 313.977
141 314.675 314.896
142 314.997 315.090
143 315.222 315.330
144 315.475 315.509
145 315.654 315.760
146 316.099 316.254
147 316.316 316.653
148 317.136 317.402
7 DESIGN OF STRUCTURES
7.1 General
7.1.1 All bridges, culverts and structures shall be designed and constructed in
accordance with section 7 of the Manual and shall conform to the cross-sectional
features and other details specified therein.
7.1.2 Width of the carriageway of new bridges and structures more than 60.0 m length
having carriageway width less than 7.5m.
7.1.3 The following structures shall be provided with footpaths with following features:
Major Bridges:
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 68
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Existing Proposed
Sl. Name of
Chainage Chainage Remarks
No River/Bridge
(km) (km)
[Railings-(0.5) + Footpath-(1.5) + Crash
Kumaradhara
1 300+700 292+642 Barriers-(0.5x2) + Kerb Shyness-(0.5x2) +
River
Carriageway-8.5] = 12.5m ( LHS )
[Railings-(0.5) + Footpath-(1.5) + Crash
Netravathi
2 326+930 317+886 Barriers-(0.5x2) + Kerb Shyness-(0.5x2) +
River
Carriageway-8.5] = 12.5m (RHS)
Minor Bridges:
Existing Proposed
Sl. No Chainage Chainage Remarks
(km) (km)
[Railings-(0.5) + Footpath-(1.5) + Crash Barriers-(0.5x2) + Kerb
1 264+100 256+773
Shyness-(0.5x2) + Carriageway-8.5] = 1x12.5m ( LHS )
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 69
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Existing Proposed
Sl. No Chainage Chainage Remarks
(km) (km)
7.1.5 The following structures shall be designed to carry utility services specified in table
below:
Major Bridges
Existing Proposed
Sl. Utility services to be
Chainage Chainage Remarks
No carried
(km) (km)
Ducts shall be left over below the
OFC, telephone, water
1 264+100 256+773 raised footpath/ inside crash
supply pipe line
barrier/by clamps
Ducts shall be left over below the
OFC, telephone, water
2 - 261+945 raised footpath/ inside crash
supply pipe line
barrier/by clamps
Ducts shall be left over below the
OFC, telephone, water
3 271+300 264+144 raised footpath/ inside crash
supply pipe line
barrier/by clamps
Ducts shall be left over below the
OFC, telephone, water
4 274+350 267+130 raised footpath/ inside crash
supply pipe line
barrier/by clamps
Ducts shall be left over below the
OFC, telephone, water
5 277+650 269+882 raised footpath/ inside crash
supply pipe line
barrier/by clamps
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 70
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Existing Proposed
Sl. Utility services to be
Chainage Chainage Remarks
No carried
(km) (km)
7.1.6 Cross-section of the new culverts and bridges at deck level for the Project Highway
shall conform to the typical cross-sections given in section 7 of the Manual.
7.2 Culverts
7.2.1 Overall width of all culverts shall be equal to the roadway width of the approaches.
The existing culverts at the following locations shall be re-constructed as new culverts:
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 71
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 72
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 73
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
All existing culverts which are not to be reconstructed shall be widened to the
roadway width of the Project Highway as per the typical cross section given in
section 7 of the Manual. Repairs and strengthening of existing structures where
required shall be carried out.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 74
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 75
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
7.2.4 Additional new culverts shall be constructed as per particulars given in the table
below:
a) New Culverts:
Proposed Proposed
Sl. No Chainage Type Of Span Arrangement (m)
(km) Structure
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 76
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Proposed Proposed
Sl. No Chainage Type Of Span Arrangement (m)
(km) Structure
1 260+922 Box Culvert 1x2x2
2 261+044 Box Culvert 1x2x2
3 262+014 Box Culvert 1x2x2
4 262+290 Box Culvert 1x2x2
5 262+381 Box Culvert 1x2x2
6 264+962 Box Culvert 1x2x2
7 265+124 Box Culvert 1x6x3
8 266+064 Box Culvert 1x2x2
9 266+220 Box Culvert 1x2x2
10 266+653 Box Culvert 1x2x2
11 267+391 Pipe Culvert 1x1.20
12 267+554 Pipe Culvert 1x1.20
13 267+583 Pipe Culvert 1x1.20
14 267+621 Box Culvert 1x2x2
15 267+993 Pipe Culvert 1x1.20
16 268+130 Pipe Culvert 1x1.20
17 268+254 Box Culvert 1x2x2
18 268+930 Box Culvert 1x2x2
19 275+521 Box Culvert 1x2x2
20 277+930 Pipe Culvert 1x1.2
21 278+034 Box Culvert 1x2x2
22 279+273 Box Culvert 1x2x2
23 279+652 Pipe Culvert 1x1.20
24 280+572 Pipe Culvert 1x1.20
25 282+494 Pipe Culvert 1x1.20
26 282+694 Box Culvert 1x3x2
27 282+762 Pipe Culvert 1x1.20
28 282+934 Box Culvert 1x2x2
29 283+290 Pipe Culvert 1x1.20
30 283+344 Box Culvert 1x3x2
31 284+560 Pipe Culvert 1x1.20
32 285+234 Box Culvert 1x2x2
33 285+294 Pipe Culvert 1x1.20
34 285+474 Pipe Culvert 1x1.20
35 285+610 Box Culvert 2x3x2
36 285+793 Pipe Culvert 1x1.20
37 286+551 Pipe Culvert 1x1.20
38 286+633 Pipe Culvert 1x1.20
39 286+734 Box Culvert 2x2x2
40 286+824 Pipe Culvert 1x1.20
41 287+073 Pipe Culvert 1x1.20
42 287+300 Pipe Culvert 2x1.20
43 287+721 Pipe Culvert 1x1.20
44 287+914 Pipe Culvert 1x1.20
45 288+044 Pipe Culvert 1x1.20
46 288+362 Pipe Culvert 1x1.20
47 288+863 Pipe Culvert 1x1.20
48 288+971 Pipe Culvert 1x1.20
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 77
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Proposed Proposed
Sl. No Chainage Type Of Span Arrangement (m)
(km) Structure
49 290+741 Pipe Culvert 1x1.20
50 295+201 Box Culvert 1x2x2
51 295+574 Pipe Culvert 1x1.20
52 295+714 Pipe Culvert 1x1.20
53 295+884 Pipe Culvert 1x1.20
54 296+362 Pipe Culvert 1x1.20
55 296+593 Pipe Culvert 1x1.20
56 296+894 Box Culvert 1x2x2
57 297+564 Box Culvert 1x2x2
58 297+821 Pipe Culvert 1x1.20
59 298+013 Pipe Culvert 1x1.20
60 298+040 Pipe Culvert 1x1.20
61 298+103 Pipe Culvert 1x1.20
62 299+022 Pipe Culvert 1x1.20
63 301+304 Pipe Culvert 1x1.20
64 301+640 Pipe Culvert 1x1.20
65 302+084 Pipe Culvert 1x1.20
66 302+252 Box Culvert 2x2x2
67 302+563 Pipe Culvert 1x1.20
68 302+623 Pipe Culvert 1x1.20
69 303+613 Box Culvert 1x2x2
70 303+754 Pipe Culvert 1x1.20
71 304+822 Pipe Culvert 1x1.20
72 305+483 Pipe Culvert 1x1.20
73 306+353 Pipe Culvert 1x1.20
74 308+541 Box Culvert 1x2x2
75 308+642 Box Culvert 1x2x2
76 308+674 Box Culvert 1x2x2
77 309+451 Box Culvert 1x2x2
78 309+912 Pipe Culvert 1x1.20
79 314+615 Pipe Culvert 1x1.20
80 314+795 Pipe Culvert 1x1.20
i) At Major Junctions
Design Span
Chainage No of Arrangement
Sl. No Type Remarks
Culverts
(km) (m)
1 270+210 3 Legged 1 1 x 1.2
2 289+860 3 Legged 1 1 x 1.2
3 292+850 3 Legged 1 1 x 1.2
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 78
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Design Span
Chainage No of Arrangement
Sl. No Type Remarks
Culverts
(km) (m)
4 313+080 3 Legged 1 1 x 1.2
5 315+390 3 Legged 1 1 x 1.2
6 316+570 4 Legged 2 1 x 1.2
Design Span
No of
Sl. No Chainage Type Arrangement Remarks
Culverts
(km) (m)
1 259+590 3 Legged 1 1 x 1.2
2 263+100 3 Legged 1 1 x 1.2
3 263+380 3 Legged 1 1 x 1.2
4 266+480 4 Legged 2 1 x 1.2
5 272+880 3 Legged 1 1 x 1.2
6 273+050 3 Legged 1 1 x 1.2
7 273+600 3 Legged 1 1 x 1.2
8 274+980 3 Legged 1 1 x 1.2
9 276+920 3 Legged 1 1 x 1.2
10 279+120 4 Legged 2 1 x 1.2
11 279+520 3 Legged 1 1 x 1.2
12 282+300 3 Legged 1 1 x 1.2
13 282+680 3 Legged 2 1 x 1.2
14 284+820 3 Legged 1 1 x 1.2
15 285+500 3 Legged 1 1 x 1.2
16 288+600 4 Legged 2 1 x 1.2
17 291+330 4 Legged 2 1 x 1.2
18 293+140 3 Legged 1 1 x 1.2
19 295+930 4 Legged 2 1 x 1.2
20 296+320 3 Legged 1 1 x 1.2
21 299+300 3 Legged 1 1 x 1.2
22 300+100 3 Legged 1 1 x 1.2
23 302+300 4 Legged 2 1 x 1.2
24 303+420 4 Legged 2 1 x 1.2
25 303+720 3 Legged 1 1 x 1.2
26 304+480 3 Legged 1 1 x 1.2
27 305+290 3 Legged 1 1 x 1.2
28 307+900 3 Legged 2 1 x 1.2
29 308+780 3 Legged 1 1 x 1.2
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 79
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Design Span
No of
Sl. No Chainage Type Arrangement Remarks
Culverts
(km) (m)
30 309+480 3 Legged 1 1 x 1.2
31 310+870 3 Legged 1 1 x 1.2
32 311+590 4 Legged 2 1 x 1.2
33 314+360 3 Legged 1 1 x 1.2
34 315+620 3 Legged 1 1 x 1.2
35 316+640 3 Legged 1 1 x 1.2
36 317+150 3 Legged 1 1 x 1.2
37 318+050 4 Legged 2 1 x 1.2
Note :
a) The location of new culverts of Box/Pipe type with the span configuration specified
above is tentative and shall be finalized in consultation with Authority’s Engineer.
b) Any additional requirement of culverts found during the project implementation
stage, the same shall be deemed to be covered within in the scope of work.
c) All Repairs shall be carried out as per present site conditions. The repair works to be
carried out as per IRC standards and in consultation with Authority’s Engineer and
NHAI, the repair requirements to be assessed at the time of construction for actual
requirements.
Location at
Sl. No. km Type of repair required
All Repairs shall be carried out as per present site conditions. The repair works to be
carried out as per IRC standards and in consultation with Authority’s Engineer and
NHAI, the repair requirements to be assessed at the time of construction for actual
requirements.
Note:
(a) Any additional requirement of culverts found during the project implementation
stage, the same shall be deemed to be covered within the scope of work.
(b) The exact location of culverts shall be finalized as per site condition and location of
stream along the project alignment.
7.2.6 Floor protection works shall be as specified in the relevant IRC Codes and
Specifications.
7.3 Bridges
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 80
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 81
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Additional New bridges at the following locations on the Project Highway shall be
constructed.
Total
Existing Proposed Name of Proposed Overall
Sl. Proposed Width of
Chainage Chainage River / Type of Length Remarks
No Span (m) structure
(km) (km) Bridge Structure (m)
(m)
Total
Existing Proposed Overall
Sl. Proposed Width of
Chainage Chainage Length Remarks
No Span (m) structure
(km) (km) (m)
(m)
1 264+100 256+773 1x10.30 10.30 1 x 12.50 New 2 - Lane Bridge on LHS
New 2 x 2 - lane bridge on
2 - 261+945 2 x 19.00 38.00 2 x 12.50
LHS & RHS
3 271+300 264+144 2 x 18.30 36.60 1 x 12.50 New 2 lane bridge on RHS
4 274+350 267+130 3 x 8.60 25.80 1 x 12.50 New 2 - lane bridge on RHS.
5 277+650 269+882 1 x 8.50 8.50 1 x 12.50 New 2 - Lane Bridge on LHS
6 279+680 271+895 1 x 8.60 8.60 1 x 12.50 New 2 - Lane bridge on RHS.
7 283+450 275+704 2 x 12.70 25.40 1 x 12.50 New 2 lane bridge on RHS
8 286+330 278+481 3 x 8.00 24.00 1 x 12.50 New 2 - lane bridge on RHS.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 82
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Total
Existing Proposed Overall
Sl. Proposed Width of
Chainage Chainage Length Remarks
No Span (m) structure
(km) (km) (m)
(m)
9 298+750 290+547 2 x 11.75 23.50 1 x 12.50 New 2 lane bridge on RHS
New 2 x 2 - lane bridge on
10 - 297+890 1 x 9.00 9.00 2 x 12.50
LHS & RHS
11 308+820 299+945 2 x 10.00 20.00 1 x 12.50 New 2 lane bridge on RHS
12 314+080 304+934 1 x 10.00 10.00 1 x 12.50 New 2 - Lane Bridge on LHS
13 325+250 315+910 2 x15.00 30.00 1 x 12.50 New 2 - lane bridge on RHS.
Note : The proposed length is tentative and the same shall be finalized in consultation with Authority’s
Engineer, Any change in total length and span arrangement shall be deemed to be covered
within the scope of work.
Additional New Minor Bridges Proposed on Service Roads & Slip Roads
Span
Sl. Existing Design Total Width of
Arrangeme Remarks
No km Chainage structure (m)
nt (m)
Nil
Note : The proposed length is tentative and the same shall be finalized in consultation with Authority’s Engineer, Any change in
total length and span arrangement shall be deemed to be covered within the scope of work.
7.3.3 The railings of existing bridges shall be replaced by crash barriers at the following
locations:
Minor Bridges
Existing Proposed
Sl.
Chainage Chainage Remarks
No
(km) (km)
1 264+100 256+773
2 271+300 264+144
3 274+350 267+130
4 277+650 269+882
5 279+680 271+895
6 283+450 275+704
7 286+330 278+481
8 298+005 289+813
9 298+750 290+547
10 308+820 299+945
11 314+080 304+934
12 325+250 315+910
7.3.4 Repairs/replacements of railing/parapets of the existing bridges shall be undertaken
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 83
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
as follows:
Major Bridges
Existing Proposed
Sl. No Remarks
Chainage (km) Chainage (km)
1 300+700 292+642
2 326+930 317+886
Not Applicable
Road over-bridges (road over rail) shall be provided at the following level crossings,
as per GAD drawings attached:
Nil
Road under-bridges (road under railway line) shall be provided at the following level
crossings, as per GAD drawings attached:
Location of Level
crossing Number and length of span
Sl. No
(chainage km) (m)
Nil
The grade separated structures shall be provided at the locations and of the type and
length specified in Section 2.9 and 3(b) of this Annex-I.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 84
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
The existing bridges and structures to be repaired/strengthened, and the nature and
extent of repairs /strengthening required are given below:
A. Bridges
Major Bridges:
Existing Proposed
Name of Nature and extent of repairs /
Sl. No Chainage Chainage
River/Bridge strengthening to be carried out
(km) (km)
Kumaradhara Repair to flooring and protection
1 300+700 292+642
River works/Railings/Wearing Coat
Netravathi Repair to flooring and protection
2 326+930 317+886
River works/Railings/Wearing Coat
Minor Bridges:
Existing Proposed
Proposed Nature and extent of repairs /
Sl. No Chainage Chainage
Span (m) strengthening to be carried out
(km) (km)
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 85
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
B. ROB / RUB
span
Existing Design arrangement Overall Total width of the
Sl. No (m)
km Chainage Length structure
Nil
PUP
Location
Proposed
Sl. of Nature and extent of repairs /strengthening to be
chaiange
No. Structure carried out
(Km)
(km)
1 326+300 317+015 Repair to protection works/Railings/Wearing Coat
Note:
(a) A schedule for repair and rehabilitation of bridges to be prepared based on detailed
inspection and to get approved from Authority’s Engineer before taking up this work
subjected to a minimum rehabilitation measures that are mentioned and any other
defects found as per site conditions. The concessionaire is bound to conduct any non
destructive test on bridges which are in distressed condition as instructed by
Authority’s Engineer at no extra cost to NHAI.
(b) All the drainage spout pipes are to be connected suitably by a pipe and brought down
through the supports from superstructure and pier/abutment cap and leaving into
the rivers/streams/nallas.
1 270+807 (VUP)
2 291+973 (VUP)
4 306+840 (VUP)
5 312+394 (VUP)
7 318+745 (VUP)
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 86
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
8.1 Traffic control devices and road safety works shall be provided in accordance with
section 9 of the Manual.
a) Road Signs: Road signs shall be provided as per Section 9.2 of the manual. The
locations for these provisions shall be finalised in consultation with Authority’s
Engineer.
b) Road Markings: Road Markings shall be provided as per Section 9.3 of the manual.
The locations for these provisions shall be finalised in consultation with Authority’s
Engineer.
c) LED Traffic Beacons: These shall be provided in the entire Project Highway near
pedestrian crossings, public gathering places (Educational Institutions, Hospitals,
Worshipping Places, etc.),cross roads, & median openings. The locations for these
provisions shall be finalised in consultation with Authority’s Engineer.
d) Reflective Pavement Markers (Road Studs): Reflective Pavement Markers shall be
provided as per Section 9.5 of the manual. The locations for these provisions shall be
finalised in consultation with Authority’s Engineer.
e) Crash Barrier: The New Jersey concrete crash barrier shall be provided at Built-up
locations and W Metal Beam Crash Barrier shall be provided at High Embankment &,
Bridge approaches and curve locations where radius is less than 450m. The locations
for these provisions shall be as per Section 9.7 of manual and finalised in
consultation with Authority’s Engineer in addition to the table below.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 87
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 88
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Note: - The road side safety crash barrier shall be provided as per manual of Specification (IRC SP 84 2014). The
length of New jersey crash barrier and W Metal beam crash barrier given in above table is minimum any
increase are decrease in length as specified shall not be treated as a change of scope.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 89
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
f) Work Zone Traffic Management Plan (WTMPs): Work zone traffic Management
Plan (WTMPs) shall be prepared as per Section 9.9 of manual.
8.2 Specifications of the reflective sheeting shall be as per Section 9.2.3 of manual.
9 ROADSIDE FURNITURE
9.1 Roadside furniture shall be provided in accordance with the provisions of Section 9
of the Manual.
a) Overhead signs: Cantilever and Gantry sign Location and their sizes shall be
finalized in consultation with Authority’s Engineer.
The Minimum 9 nos of Cantilever sign & 9 nos Gantry sign shall be provided along the
project highway. The locations for these provisions shall be finalised in consultation
with Authority’s Engineer.
b) Road Boundary Stone (RBS): shall be provided for the entire Project Highway as
per Section 9.8 of the Manual.
d) Pedestrian facilities:
2 Both
Service road
II. Pedestrian guardrail: To be provided at each bus bay/bus stop location for
the entire length.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 90
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
10 COMPULSORY AFFORESTATION
11 HAZARDOUS LOCATIONS
The safety barriers shall also be provided at the following hazardous locations:
Not Applicable
13 CHANGE OF SCOPE
14 PROTECTION WORK
The Protection Works shall be provided as per the list given below.
a) Location of RCC Retaining wall in Valley portion of Ghat Section, Hair Pin Bend
locations and High Embankment locations.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 91
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
b) Location of Breast wall in Hill cutting of Ghat Section for slope protection works
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 92
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
SCHEDULE - C
(See Clause 2.1)
PROJECT FACILITIES
1 Project Facilities
The Contractor shall construct the Project Facilities in accordance with the provisions
of this Agreement. Such Project Facilities shall include:
Each of the Project Facilities shall be constructed in accordance with the Manual of
Specifications and Standards specified in IRC: SP: 84-2014, and also specified in Annex I of
Schedule C.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 93
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Annex - I
(Schedule-C)
Project Facilities
(a) Toll plaza;
Existing Design
Sl. No Location Name
Chainage Chainage
Toll Plazas shall be provided at proposed design chainage 314+075 and Rigid
pavement shall be provided at all toll plaza location including tapers. The Toll plaza
shall be provided in accordance with section 10 of Manual.
Truck lay - byes shall be provided in accordance with section 12.4 of Manual.
Proposed locations for truck lay-byes are given below:
Bus bays and bus shelters shall be provided in accordance with section 12.5 of
Manual.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 94
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
The bus bays and bus shelters are proposed at the following locations:
Design
Sl. No Side Location Name Remarks
Chainage
1 259+550 LHS Shirady Bus bay with Bus Shelter
2 259+650 RHS Shirady Bus bay with Bus Shelter
3 263+350 LHS Uddane Bus Shelter
4 263+350 RHS Uddane Bus Shelter
5 266+730 LHS Rekhya Bus bay with Bus Shelter
6 266+570 RHS Rekhya Bus bay with Bus Shelter
7 270+170 LHS Kowkrady Bus bay with Bus Shelter
8 270+100 RHS Kowkrady Bus bay with Bus Shelter
9 273+550 LHS Kowkrady Bus bay with Bus Shelter
10 273+650 RHS Kowkrady Bus bay with Bus Shelter
11 275+100 LHS Nellyadi Bus bay with Bus Shelter
12 275+240 RHS Nellyadi Bus bay with Bus Shelter
13 279+450 LHS Golitattu Bus bay with Bus Shelter
14 279+550 RHS Golitattu Bus bay with Bus Shelter
15 284+750 LHS Bajathur Bus bay with Bus Shelter
16 284+900 RHS Bajathur Bus bay with Bus Shelter
17 288+100 LHS Uppinangady Bus bay with Bus Shelter
18 288+200 RHS Uppinangady Bus bay with Bus Shelter
19 292+800 LHS Nekkiladi Bus bay with Bus Shelter
20 293+200 RHS Nekkiladi Bus bay with Bus Shelter
21 301+180 LHS kedila Bus bay with Bus Shelter
22 308+820 LHS Mani Bus Shelter
23 308+950 RHS Mani Bus Shelter
24 311+550 LHS Belthila Bus bay with Bus Shelter
25 311+650 RHS Belthila Bus bay with Bus Shelter
Existing Name /
Sl. No Design Chainage Side
Chainage Location
Near
1 277+810 270+000 LHS Ichalampady
village
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 95
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
(h) Others:
Other project facilities listed below shall be provided in accordance with relevant
section 12 of the Manual.
1. Lighting Facility;
S
Description Design Chainage
Sl. No
Highmast Light
1
Toll Plaza 314+075
Street Lighting
Built up Location - Double arm Street light at Median
From Ch 263+135 to 263+385
From Ch 273+840 to 274+060
at Median From Ch 274+390 to 274+790
From Ch 303+440 to 303+990
From Ch 308+790 to 309+040
From Ch 314+800 to 315+750
Built up Location - Single arm Street at foot path
From Ch 263+135 to 263+385
From Ch 273+840 to 274+060
at Footpath From Ch 274+390 to 274+790
From Ch 303+440 to 303+990
2
From Ch 308+790 to 309+040
From Ch 314+800 to 315+750
Rest Area 270+000
Truck Lay byes 305+750,308+050
Toll plaza
314+075
location
Bus Bays & Bus
Locations mentioned in section (f) of Schedule-C.
Shelter Locations
PUP , VUP–Double arm Street light
(Edge of the carriage way both sides)
From Ch 265+500 to 265+835
At
From Ch 270+340 to 271+090
Structures
From Ch 273+840 to 274+390
From Ch 291+440 to 292+540
From Ch 306+490 to 307+340
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 96
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
S
Description Design Chainage
Sl. No
(b) In addition to the manual, Highmast lighting shall be provided at the following at grade
intersections.
Sl.no Description Design Chainage
Highmast Light
1 At grade
270+210,289+860,292+850,313+080,315+390,316+570
Intersections
3. Crane Services
5. Communication system
Operation and Maintenance Centre shall be provided as per Section 12.13 of the
manual.
8. Rainwater Harvesting
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 97
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Note: In case of any discrepancy in number or location of any of the project facilities mentioned in this
Annex-I, the Authority’s Engineer shall finalize the number/location of these facilities as per site
requirement.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 98
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
SCHEDULE - D
(See Clause 2.1)
1 Construction
The Contractor shall comply with the Specifications and Standards set forth in
Annex-I of this Schedule-D for construction of the Project Highway.
2 Design Standards
Manual of Specifications and Standards for Four Laning of Highways (IRC: SP: 84-
2014), referred to herein as the Manual
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 99
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Annex - I
(Schedule-D)
All Materials, works and construction operations shall conform to the Manual of
Specifications and Standards for Four-Laning of Highways (IRC:SP:84-2014),
Engineering measures to ensure road safety (Morth letter no RW/NH-
35072/04/2004 S&R (R ) dated 27th April 2010) and MORTH Specifications for Road
and Bridge Works. Where the specification for a work is not given, Good Industry
Practice shall be adopted to the satisfaction of the Authority’s Engineer.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 100
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 101
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
SCHEDULE - E
MAINTENANCE REQUIREMENTS
1 Maintenance Requirements
1.1 The Contractor shall, at all times maintain the Project Highway in accordance with
the provisions of this Agreement, Applicable Laws and Applicable Permits.
1.2 The Contractor shall repair or rectify any Defect or deficiency set forth in Paragraph
2 of this Schedule-E within the time limit specified therein and any failure in this
behalf shall constitute non-fulfillment of the Maintenance obligations by the
Contractor. Upon occurrence of any breach hereunder, the Authority shall be entitled
to effect reduction in monthly lump sum payment as set forth in Clause 14.6 of this
Agreement, without prejudice to the rights of the Authority under this Agreement,
including Termination thereof.
1.3 All Materials, works and construction operations shall conform to the MORTH
Specifications for Road and Bridge Works, and the relevant IRC publications. Where
the specifications for a work are not given, Good Industry Practice shall be adopted.
In respect of any Defect or deficiency not specified in Annex - I of this Schedule-E, the
Authority’s Engineer may, in conformity with Good Industry Practice, specify the
permissible limit of deviation or deterioration with reference to the Specifications
and Standards, and any deviation or deterioration beyond the permissible limit shall
be repaired or rectified by the Contractor within the time limit specified by the
Authority’s Engineer.
5 Emergency repairs/restoration
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 102
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
The Contractor shall, through its engineer, undertake a daily visual inspection of the
Project Highway and maintain a record thereof in a register to be kept in such form
and manner as the Authority’s Engineer may specify. Such record shall be kept in safe
custody of the Contractor and shall be open to inspection by the Authority and the
Authority’s Engineer at any time during office hours.
The Contractor shall carry out a detailed pre-monsoon inspection of all bridges,
culverts and drainage system before [1st June] every year in accordance with the
guidelines contained in IRC: SP35. Report of this inspection together with details of
proposed maintenance works as required on the basis of this inspection shall be sent
to the Authority’s Engineer before the [10th June] every year. The Contractor shall
complete the required repairs before the onset of the monsoon and send to the
Authority’s Engineer a compliance report. Post monsoon inspection shall be done by
the [30th September] and the inspection report together with details of any damages
observed and proposed action to remedy the same shall be sent to the Authority’s
Engineer.
All damages occurring to the Project Highway on account of a Force Majeure Event or
default or neglect of the Authority shall be undertaken by the Authority at its own
cost. The Authority may instruct the Contractor to undertake the repairs at the rates
agreed between the Parties.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 103
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Annex - I
(Schedule-E)
The Contractor shall repair and rectify the Defects and deficiencies specified in this Annex-I
of Schedule-E within the time limit set forth in the table below.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 104
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 105
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 106
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
SCHEDULE - F
(See Clause 3.1.7(a))
APPLICABLE PERMITS
1 Applicable Permits
1.1 The Contractor shall obtain, as required under the Applicable Laws, the following
Applicable Permits:
(a) Permission of the State Government for extraction of boulders from quarry;
(b) Permission of Village Panchayats and Pollution Control Board for installation
of crushers;
(d) Permission of the State Government for drawing water from river/reservoir;
(e) Licence from inspector of factories or other competent Authority for setting
up batching plant;
(g) Clearance of Village Panchayats and Pollution Control Board for setting up
asphalt plant;
(h) Permission of Village Panchayats and State Government for borrow earth;
and
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 107
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
SCHEDULE – G
(See Clauses 7.1.1, 7.5.3 and 19.2)
Annex-I
(See Clause 7.1.1)
Performance Security
[The Chairman,
WHEREAS:
(B) The Agreement requires the Contractor to furnish a Performance Security for
due and faithful performance of its obligations, under and in accordance with
the Agreement, during the {Construction Period/ Defects Liability Period
and Maintenance Period} (as defined in the Agreement) in a sum of Rs ..................
cr. (Rupees ........................... crore) (the "Guarantee Amount").
1. The Bank hereby unconditionally and irrevocably guarantees the due and faithful
performance of the Contractor's obligations during the {Construction Period/ Defects
Liability Period and Maintenance Period} under and in accordance with the
Agreement, and agrees and undertakes to pay to the Authority, upon its mere first
written demand, and without any demur, reservation, recourse, contest or protest,
and without any reference to the Contractor, such sum or sums up to an aggregate
sum of the Guarantee Amount as the Authority shall claim, without the Authority
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 108
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
being required to prove or to show grounds or reasons for its demand and/or for the
sum specified therein.
2. A letter from the Authority, under the hand of an officer not below the rank of
[General Manager in the National Highways Authority of India], that the Contractor
has committed default in the due and faithful performance of all or any of its
obligations under and in accordance with the Agreement shall be conclusive, final
and binding on the Bank. The Bank further agrees that the Authority shall be the
sole judge as to whether the Contractor is in default in due and faithful performance
of its obligations during and under the Agreement and its decision that the
Contractor is in default shall be final and binding on the Bank, notwithstanding any
differences between the Authority and the Contractor, or any dispute between them
pending before any court, tribunal, arbitrators or any other authority or body, or by
the discharge of the Contractor for any reason whatsoever.
3. In order to give effect to this Guarantee, the Authority shall be entitled to act as if
the Bank were the principal debtor and any change in the constitution of the
Contractor and/or the Bank, whether by their absorption with any other body or
corporation or otherwise, shall not in any way or manner affect the liability or
obligation of the Bank under this Guarantee.
4. It shall not be necessary, and the Bank hereby waives any necessity, for the
Authority to proceed against the Contractor before presenting to the Bank its
demand under this Guarantee.
5. The Authority shall have the liberty, without affecting in any manner the liability of
the Bank under this Guarantee, to vary at any time, the terms and conditions of the
Agreement or to extend the time or period for the compliance with, fulfillment and/
or performance of all or any of the obligations of the Contractor contained in the
Agreement or to postpone for any time, and from time to time, any of the rights and
powers exercisable by the Authority against the Contractor, and either to enforce or
forbear from enforcing any of the terms and conditions contained in the Agreement
and/or the securities available to the Authority, and the Bank shall not be released
from its liability and obligation under these presents by any exercise by the
Authority of the liberty with reference to the matters aforesaid or by reason of time
being given to the Contractor or any other forbearance, indulgence, act or omission
on the part of the Authority or of any other matter or thing whatsoever which under
any law relating to sureties and guarantors would but for this provision have the
effect of releasing the Bank from its liability and obligation under this Guarantee
and the Bank hereby waives all of its rights under any such law.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 109
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
7. The Guarantee shall cease to be in force and effect on ****$. Unless a demand or claim
under this Guarantee is made in writing before expiry of the Guarantee, the Bank
shall be discharged from its liabilities hereunder.
8. The Bank undertakes not to revoke this Guarantee during its currency, except with
the previous express consent of the Authority in writing, and declares and warrants
that it has the power to issue this Guarantee and the undersigned has full powers to
do so on behalf of the Bank.
9. Any notice by way of request, demand or otherwise hereunder may be sent by post
addressed to the Bank at its above referred branch, which shall be deemed to have
been duly authorised to receive such notice and to effect payment thereof forthwith,
and if sent by post it shall be deemed to have been given at the time when it ought to
have been delivered in due course of post and in proving such notice, when given by
post, it shall be sufficient to prove that the envelope containing the notice was posted
and a certificate signed by an officer of the Authority that the envelope was so posted
shall be conclusive.
10. This Guarantee shall come into force with immediate effect and shall remain in force
and effect for up to the date specified in paragraph 8 above or until it is released
earlier by the Authority pursuant to the provisions of the Agreement.
(Address)
NOTES:
(i) The bank guarantee should contain the name, designation and code number of the
officer(s) signing the guarantee.
(ii) The address, telephone number and other details of the head office of the Bank as
well as of issuing branch should be mentioned on the covering letter of issuing
branch.
$ Insert date being 2 (two) years from the date of issuance of this Guarantee (in accordance
with Clause 7.2 of the Agreement).
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 110
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Annex - II
(Schedule - G)
(See Clause 7.5.3)
[The Chairman,
WHEREAS:
(A) [name and address of contractor] (hereinafter called the "Contractor") has executed
an agreement (hereinafter called the "Agreement") with the [name and address of the
authority], (hereinafter called the "Authority") for the construction of the *****
section of [National Highway No. **] on Engineering, Procurement and Construction
(the "EPC") basis, subject to and in accordance with the provisions of the Agreement.
(B) In accordance with Clause 7.5.3 of the Agreement, the Contractor may withdraw the
retention money (hereinafter called the "Retention Money") after furnishing to the
Authority a bank guarantee for an amount equal to the proposed withdrawal.
NOW, THEREFORE, the Bank hereby unconditionally and irrevocably guarantees and
affirms as follows:
1. The Bank hereby unconditionally and irrevocably undertakes to pay to the Authority,
upon its mere first written demand, and without any demur, reservation, recourse,
contest or protest, and without any reference to the Contractor, such sum or sums up
to an aggregate sum of the Guarantee Amount as the Authority shall claim, without
the Authority being required to prove or to show grounds or reasons for its demand
and/or for the sum specified therein.
2. A letter from the Authority, under the hand of an officer not below the rank of [General
Manager in the National Highways Authority of India], that the Contractor has committed
default in the due and faithful performance of all or any of its obligations for under and in
accordance with the Agreement shall be conclusive, final and binding on the Bank. The Bank
further agrees that the Authority shall be the sole judge as to whether the Contractor is in
default in due and faithful performance of its obligations during and under the Agreement
and its decision that the Contractor is in default shall be final, and binding on the Bank,
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 111
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
notwithstanding any differences between the Authority and the Contractor, or any dispute
between them pending before any court, tribunal, arbitrators or any other authority or body,
or by the discharge of the Contractor for any reason whatsoever.
3. In order to give effect to this Guarantee, the Authority shall be entitled to act as if
the Bank were the principal debtor and any change in the constitution of the
Contractor and/or the Bank, whether by their absorption with any other body or
corporation or otherwise, shall not in any way or manner affect the liability or
obligation of the Bank under this Guarantee.
4. It shall not be necessary, and the Bank hereby waives any necessity, for the
Authority to proceed against the Contractor before presenting to the Bank its
demand under this Guarantee.
5. The Authority shall have the liberty, without affecting in any manner the liability of
the Bank under this Guarantee, to vary at any time, the terms and conditions of the
Retention Money and any of the rights and powers exercisable by the Authority
against the Contractor, and either to enforce or forbear from enforcing any of the
terms and conditions contained in the Agreement and/or the securities available to
the Authority, and the Bank shall not be released from its liability and obligation
under these presents by any exercise by the Authority of the liberty with reference
to the matters aforesaid or by reason of time being given to the Contractor or any
other forbearance, indulgence, act or omission on the part of the Authority or of any
other matter or thing whatsoever which under any law relating to sureties and
guarantors would but for this provision have the effect of releasing the Bank from
its liability and obligation under this Guarantee and the Bank hereby waives all of its
rights under any such law.
8. The Guarantee shall cease to be in force and effect 90 (ninety) days after the date of
the Completion Certificate specified in Clause 12.4 of the Agreement.
9. The Bank undertakes not to revoke this Guarantee during its currency, except with the
previous express consent of the Authority in writing, and declares and warrants that it has
the power to issue this Guarantee and the undersigned has full powers to do so on behalf of
the Bank.
10. Any notice by way of request, demand or otherwise hereunder may be sent by post
addressed to the Bank at its above referred branch, which shall be deemed to have
been duly authorised to receive such notice and to effect payment thereof forthwith,
and if sent by post it shall be deemed to have been given at the time when it ought to
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 112
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
have been delivered in due course of post and in proving such notice, when given by
post, it shall be sufficient to prove that the envelope containing the notice was posted
and a certificate signed by an officer of the Authority that the envelope was so posted
shall be conclusive.
11. This Guarantee shall come into force with immediate effect and shall remain in force
and effect up to the date specified in paragraph 8 above or until it is released earlier
by the Authority pursuant to the provisions of the Agreement.
NOTES:
(i) The bank guarantee should contain the name, designation and code number of the
officer(s) signing the guarantee.
(ii) The address, telephone number and other details of the head office of the Bank as
well as of issuing branch should be mentioned on the covering letter of issuing
branch.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 113
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Annex - III
(Schedule - G )
(See Clause 19.2)
WHEREAS:
(A) [name and address of contractor] (hereinafter called the "Contractor") has executed an
agreement (hereinafter called the "Agreement") with the [name and address of the
authority], (hereinafter called the "Authority") for the construction of the ***** section
of [National Highway No. **] on Engineering, Procurement and Construction (the "EPC")
basis, subject to and in accordance with the provisions of the Agreement
(B) In accordance with Clause 19.2 of the Agreement, the Authority shall make to the
Contractor an interest free advance payment (herein after called "Advance Payment")
equal to 10% (ten per cent) of the Contract Price; and that the Advance Payment shall be
made in three installments subject to the Contractor furnishing an irrevocable and
unconditional guarantee by a scheduled bank for an amount equivalent to 110% (one
hundred and ten percent) of such installment to remain effective till the complete and
full repayment of the installment of the Advance Payment as security for compliance
with its obligations in accordance with the Agreement. The amount of
{first/second/third} installment of the Advance Payment is Rs. ------ cr. (Rupees
------------------------ crore) and the amount of this Guarantee is Rs. ----------- cr.
(Rupees ------ crore) (the "Guarantee Amount")*.
(C) We, ....................................... through our branch at ................................................ (the
"Bank") have agreed to furnish this bank guarantee (hereinafter called the
"Guarantee") for the Guarantee Amount.
“This Guarantee shall also be operatable at our_________________________________branch at
New Delhi, from whom, confirmation regarding the issue of this guarantee or extension
/ renewal ther of shall be made available on demand. In the contingency of this
guarantee being invoked and payment thereunder claimed, the said branch shall accept
invocation letter and make payment of amounts so demanded under the said
invocation.”
NOW, THEREFORE, the Bank hereby, unconditionally and irrevocably, guarantees and affirms
as follows:
1. The Bank hereby unconditionally and irrevocably guarantees the due and faithful
repayment on time of the aforesaid instalment of the Advance Payment under and in
accordance with the Agreement, and agrees and undertakes to pay to the Authority,
upon its mere first written demand, and without any demur, reservation, recourse,
contest or protest, and without any reference to the Contractor, such sum or sums up to
an aggregate sum of the Guarantee Amount as the Authority shall claim, without the
Authority being required to prove or to show grounds or reasons for its demand and/or
for the sum specified therein.
$ The Guarantee Amount should be equivalent to 110% of the value of the applicable
instalment.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 114
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
2. A letter from the Authority, under the hand of an officer not below the rank of [General
Manager in the National Highways Authority of India], that the Contractor has
committed default in the due and faithful performance of all or any of its obligations for
the repayment of the instalment of the Advance Payment under and in accordance with
the Agreement shall be conclusive, final and binding on the Bank. The Bank further
agrees that the Authority shall be the sole judge as to whether the Contractor is in
default in due and faithful performance of its obligations during and under the
Agreement and its decision that the Contractor is in default shall be final and binding
on the Bank, notwithstanding any differences between the Authority and the
Contractor, or any dispute between them pending before any court, tribunal,
arbitrators or any other authority or body, or by the discharge of the Contractor for any
reason whatsoever.
3. In order to give effect to this Guarantee, the Authority shall be entitled to act as if the
Bank were the principal debtor and any change in the constitution of the Contractor
and/or the Bank, whether by their absorption with any other body or corporation or
otherwise, shall not in any way or manner affect the liability or obligation of the Bank
under this Guarantee.
4. It shall not be necessary, and the Bank hereby waives any necessity, for the Authority
to proceed against the Contractor before presenting to the Bank its demand under this
Guarantee.
5. The Authority shall have the liberty, without affecting in any manner the liability of the
Bank under this Guarantee, to vary at any time, the terms and conditions of the
Advance Payment or to extend the time or period of its repayment or to postpone for
any time, and from time to time, any of the rights and powers exercisable by the
Authority against the Contractor, and either to enforce or forbear from enforcing any of
the terms and conditions contained in the Agreement and/or the securities available to
the Authority, and the Bank shall not be released from its liability and obligation under
these presents by any exercise by the Authority of the liberty with reference to the
matters aforesaid or by reason of time being given to the Contractor or any other
forbearance, indulgence, act or omission on the part of the Authority or of any other
matter or thing whatsoever which under any law relating to sureties and guarantors
would but for this provision have the effect of releasing the Bank from its liability and
obligation under this Guarantee and the Bank hereby waives all of its rights under any
such law.
7. Notwithstanding anything contained hereinbefore, the liability of the Bank under this
Guarantee is restricted to the Guarantee Amount and this Guarantee will remain in
force for the period specified in paragraph 8 below and unless a demand or claim in
writing is made by the Authority on the Bank under this Guarantee all rights of the
Authority under this Guarantee shall be forfeited and the Bank shall be relieved from
its liabilities hereunder.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 115
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
8. The Guarantee shall cease to be in force and effect on ****.$ Unless a demand or claim
under this Guarantee is made in writing on or before the aforesaid date, the Bank shall
be discharged from its liabilities hereunder.
9. The Bank undertakes not to revoke this Guarantee during its currency, except with the
previous express consent of the Authority in writing, and declares and warrants that it
has the power to issue this Guarantee and the undersigned has full powers to do so on
behalf of the Bank.
10. Any notice by way of request, demand or otherwise hereunder may be sent by post
addressed to the Bank at its above referred branch, which shall be deemed to have
been duly authorised to receive such notice and to effect payment thereof forthwith,
and if sent by post it shall be deemed to have been given at the time when it ought to
have been delivered in due course of post and in proving such notice, when given by
post, it shall be sufficient to prove that the envelope containing the notice was posted
and a certificate signed by an officer of the Authority that the envelope was so posted
shall be conclusive.
11. This Guarantee shall come into force with immediate effect and shall remain in force
and effect up to the date specified in paragraph 8 above or until it is released earlier by
the Authority pursuant to the provisions of the Agreement.
$Insert a date being 90 (ninety) days after the end of one year from the date of payment of the
Advance payment to the Contractor (in accordance with Clause 19.2 of the Agreement).
NOTES:
(i)
The bank guarantee should contain the name, designation and code number of the
officer(s) signing the guarantee.
(ii)
The address, telephone number and other details of the head office of the Bank as well
as of issuing branch should be mentioned on the covering letter of issuing branch.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 116
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
SCHEDULE - H
(See Clauses10.1.4 and 19.3)
1.1 The Contract Price for this Agreement is Rs. _______________ Crores.
1.2 Proportions of the Contract Price for different stages of Construction of the Project
Highway shall be as specified below:
C- New 4-lane
realignment/bypass/reconstruction
(Length-28.687 kms, [TCS-
1,1C,2,3,3A,3B,3C,3D,4,5,6,7,7A,8,8A,9)
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 117
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 118
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
(a)ROB
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 119
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
a)Busbay [2.43%]
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 120
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
* The above list is illustrative and may require modification as per the scope of the work.
* Contractor shall submit detailed designs, drawings and estimates prepared on the basis of
scope of work and specifications laid down herein above and draw a realistic Schedule-H for
review and approval of the authority Engineer. Authority Engineer will approve the same with
the consent of the authority for implementation.
1.3.1 Road works including approaches to minor bridges, Major Bridges and Structures
(excluding service roads).
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 121
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Procedure for estimating the value of road work done shall be as follows:
Table 1.3.1
Stage of Payment Percentage - Payment Procedure
weightage
A-2-lane Widening and Unit of measurement is linear length.
strengthening of existing road Payment of each stage shall be made on pro
(1) Earthwork up to top of the sub- [1.30%] rata basis on completion of a stage in a length
grade of not less than 10 (ten) percent of the total
(2) Granular work (sub-base, base, [2.12%] length. @
shoulders)
(3) Rigid Pavement [13.57%]
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 122
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 123
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
@. For example, if the total length of rigid pavement work to be done is 100 km, the cost per km
of rigid pavement work shall be determined as follows:
Cost per km = P x weightage for road work x weightage for Rigid pavement work x (1/L)
L = Total length in km
Similarly, the rates per km for stages (1), (2) and (4) above shall be worked out.
Procedure for estimating the value of Major Bridge works and of ROB/RUB shall be as stated in
table 1.3.2:
Table 1.3.2
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 124
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
(1) Foundation: On completion of the Cost of each Major Bridge shall be determined
[29.14%]
foundation work including on pro rata basis with respect to the total linear
foundations for wing and return length (m) of the Major Bridges. Payment shall
walls be made on completion of each stage of a Major
Bridge as per the weightage given in this table
(2) Sub-structure: On completion of
abutments, piers up to the [7.13%]
abutment/pier cap
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 125
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
1.3.3 Structures
Procedure for estimating the value of structure work shall be as stated in table 1.3.3:
Table 1.3.3
Procedure for estimating the value of other works done shall be as stated in table 1.3.4:
Table 1.3.4
Stage of Payment Weightage Payment Procedure
Unit of measurement is linear length in km. Cost
(i) Service roads/Slip per km shall be determined on pro rata basis
Roads [19.54%] with respect to the total length of the service
roads. Payment shall be made for completed
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 126
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 127
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
2.2 Payment for Maintenance shall be made in quarterly installments in accordance with the
provisions of Section 19.7.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 128
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
SCHEDULE - I
(See Clause 10.2.4)
DRAWINGS
1 Drawings
In compliance of the obligations set forth in Clause 10.2 of this Agreement, the
Contractor shall furnish to the Authority’s Engineer, free of cost, all Drawings listed in
Annex-I of this Schedule-I.
2 Additional Drawings
If the Authority’s Engineer determines that for discharging its duties and functions
under this Agreement, it requires any drawings other than those listed in Annex-I, it may
by notice require the Contractor to prepare and furnish such drawings forthwith. Upon
receiving a requisition to this effect, the Contractor shall promptly prepare and furnish
such drawings to the Authority’s Engineer, as if such drawings formed part of Annex-I of
this Schedule-I.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 129
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Annex - I
(Schedule - I)
List of Drawings
(d) Drawings of bus-bay and bus shelters with furniture and drainage system
(e) Drawing of a truck parking lay bye with furniture and drainage system
(f) Drawings of road furniture items including traffic signage, marking, safety
barriers, etc.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 130
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
SCHEDULE - J
(See Clause 10.3.2)
During Construction period, the Contractor shall comply with the requirements set forth
in this Schedule-J for each of the Project Milestones and the Scheduled Completion
Date. Within 15 (fifteen) days of the date of each Project Milestone, the Contractor shall
notify the Authority of such compliance along with necessary particulars thereof.
2 Project Milestone-I
2.1 Project Milestone-I shall occur on the date falling on the 180th (one hundred and
eightieth) day from the Appointed Date (the “Project Milestone-I”).
2.2 Prior to the occurrence of Project Milestone-I, the Contractor shall have commenced
construction of the Project Highway and submitted to the Authority duly and validly
prepared Stage Payment Statements for an amount not less than 10% (ten per cent) of
the Contract Price.
3 Project Milestone-II
3.1 Project Milestone-II shall occur on the date falling on the 365th (three hundred and sixty
fifth) day from the Appointed Date (the “Project Milestone-II”).
3.2 Prior to the occurrence of Project Milestone-II, the Contractor shall have continued with
construction of the Project Highway and submitted to the Authority duly and validly
prepared Stage Payment Statements for an amount not less than 30% (thirty per cent)
of the Contract Price.
4 Project Milestone-III
4.1 Project Milestone-III shall occur on the date falling on the [550th (five hundred and
fiftieth)] day from the Appointed Date (the “Project Milestone-III”).
4.2 Prior to the occurrence of Project Milestone-III, the Contractor shall have continued with
construction of the Project Highway and submitted to the Authority duly and validly
prepared Stage Payment Statements for an amount not less than 60% (sixty per cent) of
the Contract Price.
5.1 The Scheduled Completion Date shall occur on the [913th (Nine hundred and thirteenth)]
day from the Appointed Date.
5.2 On or before the Scheduled Completion Date, the Contractor shall have completed
construction in accordance with this Agreement.
6 Extension of time
Upon extension of any or all of the aforesaid Project Milestones or the Scheduled
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 131
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Completion Date, as the case may be, under and in accordance with the provisions of this
Agreement, the Project Completion Schedule shall be deemed to have been amended
accordingly.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 132
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
SCHEDULE - K
Tests on Completion
1.1 The Contractor shall, no later than 30 (thirty) days prior to the likely completion of
construction, notify the Authority’s Engineer and the Authority of its intent to subject
the Project Highway to Tests, and no later than 10 (ten) days prior to the actual date of
Tests, furnish to the Authority’s Engineer and the Authority detailed inventory and
particulars of all works and equipment forming part of Works.
1.2 The Contractor shall notify the Authority’s Engineer of its readiness to subject the
Project Highway to Tests at any time after 10 (ten) days from the date of such notice,
and upon receipt of such notice, the Authority’s Engineer shall, in consultation with the
Contractor, determine the date and time for each Test and notify the same to the
Authority who may designate its representative to witness the Tests. The Authority’s
Engineer shall thereupon conduct the Tests itself or cause any of the Tests to be
conducted in accordance with Article 12 and this Schedule-K.
2 Tests
2.1 Visual and physical test: The Authority’s Engineer shall conduct a visual and physical
check of construction to determine that all works and equipment forming part thereof
conform to the provisions of this Agreement. The physical tests shall include tests
mentioned in the IRC manual.
2.2 Riding quality test: Riding quality of each lane of the carriageway shall be checked with
the help of a calibrated bump integrator and the maximum permissible roughness for
purposes of this Test shall be [2,000 (two thousand)] mm for each kilometre.
2.3 Tests for bridges: All major and minor bridges shall be subjected to the rebound
hammer and ultrasonic pulse velocity tests, to be conducted in accordance with the
procedure described in Special Report No. 17: 1996 of the IRC Highway Research Board
on Nondestructive Testing Techniques, at two spots in every span, to be chosen at
random by the Authority’s Engineer. Bridges with a span of 15 (fifteen) metres or more
shall also be subjected to load testing.
2.4 Other tests: The Authority’s Engineer may require the Contractor to carry out or cause
to be carried additional tests, in accordance with Good Industry Practice, for
determining the compliance of the Project Highway with Specifications and Standards.
2.5 Environmental audit: The Authority’s Engineer shall carry out a check to determine
conformity of the Project Highway with the environmental requirements set forth in
Applicable Laws and Applicable Permits.
2.6 Safety Audit: The Authority’s Engineer shall carry out, or cause to be carried out, a safety
audit to determine conformity of the Project Highway with the safety requirements and
Good Industry Practice.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 133
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
All Tests set forth in this Schedule-K shall be conducted by the Authority’s Engineer or
such other agency or person as it may specify in consultation with the Authority.
4 Completion Certificate
Upon successful completion of Tests, the Authority’s Engineer shall issue the Completion
Certificate in accordance with the provisions of Article 12.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 134
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
SCHEDULE - L
(See Clause 12.2 and 12.4)
PROVISIONAL CERTIFICATE
2 Works that are incomplete on account of Time Extension have been specified in the
Punch List appended hereto, and the Contractor has agreed and accepted that it shall
complete all such works in the time and manner set forth in the Agreement. In addition,
certain minor works are incomplete and these are not likely to cause material
inconvenience to the Users of the Project Highway or affect their safety. The Contractor
has agreed and accepted that as a condition of this Provisional Certificate, it shall
complete such minor works within 30 (thirty) days hereof. These minor works have also
been specified in the aforesaid Punch List.
3 In view of the foregoing, I am satisfied that the Project Highway from km ** to km ** can
be safely and reliably placed in service of the Users thereof, and in terms of the
Agreement, the Project Highway is hereby provisionally declared fit for entry into
operation on this the ………… day of ……….. 20…...
(Signature) (Signature)
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 135
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
COMPLETION CERTIFICATE
2 It is certified that, in terms of the aforesaid Agreement, all works forming part of Project
Highway have been completed, and the Project Highway is hereby declared fit for entry
into operation on this the ……… day of ……… 20…..
(Signature)
(Name)
(Designation)
(Address)
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 136
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
SCHEDULE - M
(See Clauses 14.6, 15.2 and 19.7)
1.1 Monthly lump sum payments for maintenance shall be reduced in the case of non-
compliance with the Maintenance Requirements set forth in Schedule-E.
1.2 Any deduction made on account of non-compliance with the Maintenance Requirements
shall not be paid even after compliance subsequently. The deductions shall continue to
be made every month until compliance is done.
1.3 The Authority’s Engineer shall calculate the amount of payment reduction on the basis
of weightage in percentage assigned to non-conforming items as given in Paragraph 2.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 137
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
2.2 The amount to be deducted from monthly lump-sum payment for non compliance of
particular item shall be calculated as under:
R=P/IOO x M x L1/L
L1 = Non-complying length
The total amount of reduction shall be arrived at by summation of reductions for such
items/Defects/deficiency or non compliance.
For any Defect in a part of one kilometer, the non-conforming length shall be taken as
one kilometer.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 138
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
SCHEDULE - N
(See Clause 18.1.1)
1.1 The provisions of the Model Request for Proposal for Selection of Technical Consultants,
issued by the Ministry of Finance in May 2009, or any substitute thereof shall apply for
selection of an experienced firm to discharge the functions and duties of an Authority’s
Engineer.
1.2 In the event of termination of the Technical Consultants appointed in accordance with
the provisions of Paragraph 1.1, the Authority shall appoint another firm of Technical
Consultants forthwith and may engage a government-owned entity in accordance with
the provisions of Paragraph 3 of this Schedule-N.
2 Terms of Reference
The Terms of Reference for the Authority’s Engineer (the “TOR”) shall substantially
conform with Annex 1 to this Schedule N.
Notwithstanding anything to the contrary contained in this Schedule, the Authority may
in its discretion appoint a government-owned entity as the Authority’s Engineer;
provided that such entity shall be a body corporate having as one of its primary
functions the provision of consulting, advisory and supervisory services for engineering
projects; provided further that a government-owned entity which is owned or
controlled by the Authority shall not be eligible for appointment as Authority’s Engineer.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 139
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Annex – I
(Schedule - N)
1 Scope
1.1 These Terms of Reference (the “TOR”) for the Authority’s Engineer are being specified
pursuant to the EPC Agreement dated ........... (the “Agreement), which has been entered
into between the [name and address of the Authority] (the “Authority”) and .......... (the
“Contractor”) for Four-Laning of Package II construction of the Addahole (Near
Gundya) - Bantwal Cross section of National- Highway No. 75 (Old NH-48) in the
State of Karnataka on Engineering, Procurement, Construction (EPC) basis, and a copy of
which is annexed hereto and marked as Annex-A to form part of this TOR.
1.2 The TOR shall apply to construction and maintenance of the Project Highway.
2.1 The words and expressions beginning with or in capital letters and not defined herein
but defined in the Agreement shall have, unless repugnant to the context, the meaning
respectively assigned to them in the Agreement.
2.2 References to Articles, Clauses and Schedules in this TOR shall, except where the context
otherwise requires, be deemed to be references to the Articles, Clauses and Schedules of
the Agreement, and references to Paragraphs shall be deemed to be references to
Paragraphs of this TOR.
2.3 The rules of interpretation stated in Clauses 1.2, 1.3 and 1.4 of the Agreement shall
apply, mutatis mutandis, to this TOR.
3. General
3.1 The Authority’s Engineer shall discharge its duties in a fair, impartial and efficient
manner, consistent with the highest standards of professional integrity and Good
Industry Practice.
3.2 The Authority’s Engineer shall perform the duties and exercise the authority in
accordance with the provisions of this Agreement, but subject to obtaining prior written
approval of the Authority before determining:
(d) any other matter which is not specified in (a), (b) or (c) above and which creates an
obligation or liability on either Party for a sum exceeding Rs. 5,000,000 (Rs. fifty lakh).
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 140
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
3.3 The Authority’s Engineer shall submit regular periodic reports, at least once every
month, to the Authority in respect of its duties and functions under this Agreement. Such
reports shall be submitted by the Authority’s Engineer within 10 (ten) days of the
beginning of every month.
3.4 The Authority’s Engineer shall inform the Contractor of any delegation of its duties and
responsibilities to its suitably qualified and experienced personnel; provided, however,
that it shall not delegate the authority to refer any matter for the Authority’s prior
approval in accordance with the provisions of Clause 18.2.
3.5 The Authority’s Engineer shall aid and advise the Authority on any proposal for Change
of Scope under Article 13.
3.6 In the event of any disagreement between the Parties regarding the meaning, scope and
nature of Good Industry Practice, as set forth in any provision of the Agreement, the
Authority’s Engineer shall specify such meaning, scope and nature by issuing a reasoned
written statement relying on good industry practice and authentic literature.
4 Construction Period
4.1 During the Construction Period, the Authority’s Engineer shall review the Drawings
furnished by the Contractor along with supporting data, including the geo-technical and
hydrological investigations, characteristics of materials from borrow areas and quarry
sites, topographical surveys, and the recommendations of the Safety Consultant in
accordance with the provisions of Clause 10.1.6. The Authority’s Engineer shall
complete such review and send its observations to the Authority and the Contractor
within 15 (fifteen) days of receipt of such Drawings; provided, however that in case of a
Major Bridge or Structure, the aforesaid period of 15 (fifteen) days may be extended
upto 30 (thirty) days. In particular, such comments shall specify the conformity or
otherwise of such Drawings with the Scope of the Project and Specifications and
Standards.
4.2 The Authority’s Engineer shall review any revised Drawings sent to it by the Contractor
and furnish its comments within 10 (ten) days of receiving such Drawings.
4.3 The Authority’s Engineer shall review the Quality Assurance Plan submitted by the
Contractor and shall convey its comments to the Contractor within a period of 21
(twenty-one) days stating the modifications, if any, required thereto.
4.4 The Authority’s Engineer shall complete the review of the methodology proposed to be
adopted by the Contractor for executing the Works, and convey its comments to the
Contractor within a period of 10 (ten) days from the date of receipt of the proposed
methodology from the Contractor.
4.5 The Authority’s Engineer shall grant written approval to the Contractor, where
necessary, for interruption and diversion of the flow of traffic in the existing lane(s) of
the Project Highway for purposes of maintenance during the Construction Period in
accordance with the provisions of Clause 10.4.
4.6 The Authority’s Engineer shall review the monthly progress report furnished by the
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 141
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Contractor and send its comments thereon to the Authority and the Contractor within 7
(seven) days of receipt of such report.
4.7 The Authority’s Engineer shall inspect the Construction Works and the Project Highway
and shall submit a monthly Inspection Report bringing out the results of inspections and
the remedial action taken by the Contractor in respect of Defects or deficiencies. In
particular, the Authority’s Engineer shall include in its Inspection Report, the
compliance of the recommendations made by the Safety Consultant.
4.8 The Authority’s Engineer shall conduct the pre-construction review of manufacturer's
test reports and standard samples of manufactured Materials, and such other Materials
as the Authority’s Engineer may require.
4.9 For determining that the Works conform to Specifications and Standards, the Authority’s
Engineer shall require the Contractor to carry out, or cause to be carried out, tests at
such time and frequency and in such manner as specified in the Agreement and in
accordance with Good Industry Practice for quality assurance. For purposes of this
Paragraph 4.9, the tests specified in the IRC Special Publication-11 (Handbook of Quality
Control for Construction of Roads and Runways) and the Specifications for Road and
Bridge Works issued by MORTH (the “Quality Control Manuals”) or any
modification/substitution thereof shall be deemed to be tests conforming to Good
Industry Practice for quality assurance.
4.10 The Authority’s Engineer shall test check at least 20 (twenty) percent of the quantity or
number of tests prescribed for each category or type of test for quality control by the
Contractor.
4.11 The timing of tests referred to in Paragraph 4.9, and the criteria for acceptance/
rejection of their results shall be determined by the Authority’s Engineer in accordance
with the Quality Control Manuals. The tests shall be undertaken on a random sample
basis and shall be in addition to, and independent of, the tests that may be carried out by
the Contractor for its own quality assurance in accordance with Good Industry Practice.
4.12 In the event that results of any tests conducted under Clause 11.10 establish any Defects
or deficiencies in the Works, the Authority’s Engineer shall require the Contractor to
carry out remedial measures.
4.13 The Authority’s Engineer may instruct the Contractor to execute any work which is
urgently required for the safety of the Project Highway, whether because of an accident,
unforeseeable event or otherwise; provided that in case of any work required on
account of a Force Majeure Event, the provisions of Clause 21.6 shall apply.
4.14 In the event that the Contractor fails to achieve any of the Project Milestones, the
Authority’s Engineer shall undertake a review of the progress of construction and
identify potential delays, if any. If the Authority’s Engineer shall determine that
completion of the Project Highway is not feasible within the time specified in the
Agreement, it shall require the Contractor to indicate within 15 (fifteen) days the steps
proposed to be taken to expedite progress, and the period within which the Project
Completion Date shall be achieved. Upon receipt of a report from the Contractor, the
Authority’s Engineer shall review the same and send its comments to the Authority and
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 142
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
4.15 The Authority’s Engineer shall obtain from the Contractor a copy of all the Contractor’s
quality control records and documents before the Completion Certificate is issued
pursuant to Clause 12.4.
4.16 Authority’s Engineer may recommend to the Authority suspension of the whole or part
of the Works if the work threatens the safety of the Users and pedestrians. After the
Contractor has carried out remedial measure, the Authority’s Engineer shall inspect
such remedial measures forthwith and make a report to the Authority recommending
whether or not the suspension hereunder may be revoked.
4.17 In the event that the Contractor carries out any remedial measures to secure the safety
of suspended works and Users, and requires the Authority’s Engineer to inspect such
works, the Authority’s Engineer shall inspect the suspended works within 3 (three) days
of receiving such notice, and make a report to the Authority forthwith, recommending
whether or not such suspension may be revoked by the Authority.
4.18 The Authority’s Engineer shall carry out, or cause to be carried out, all the Tests
specified in Schedule-K and issue a Completion Certificate or Provisional Certificate, as
the case may be. For carrying out its functions under this Paragraph 4.18 and all matters
incidental thereto, the Authority’s Engineer shall act under and in accordance with the
provisions of Article 12 and Schedule-K.
5. Maintenance Period
5.1 The Authority’s Engineer shall aid and advise the Contractor in the preparation of its
monthly Maintenance Programme and for this purpose carry out a joint monthly
inspection with the Contractor.
5.2 The Authority’s Engineer shall undertake regular inspections, at least once every month,
to evaluate compliance with the Maintenance Requirements and submit a Maintenance
Inspection Report to the Authority and the Contractor.
5.3 The Authority’s Engineer shall specify the tests, if any, that the Contractor shall carry
out, or cause to be carried out, for the purpose of determining that the Project Highway
is in conformity with the Maintenance Requirements. It shall monitor and review the
results of such tests and the remedial measures, if any, taken by the Contractor in this
behalf.
5.5 The Authority’s Engineer shall examine the request of the Contractor for closure of any
lane(s) of the Project Highway for undertaking maintenance/repair thereof, and shall
grant permission with such modifications, as it may deem necessary, within 5 (five) days
of receiving a request from the Contractor. Upon expiry of the permitted period of
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 143
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
closure, the Authority’s Engineer shall monitor the reopening of such lane(s), and in case
of delay, determine the Damages payable by the Contractor to the Authority under
Clause 14.5.
6.1 The Authority’s Engineer shall determine the costs, and/or their reasonableness, that
are required to be determined by it under the Agreement.
6.2 The Authority’s Engineer shall determine the period of Time Extension that is required
to be determined by it under the Agreement.
6.3 The Authority’s Engineer shall consult each Party in every case of determination in
accordance with the provisions of Clause 18.5.
7. Payments
7.1 The Authority’s Engineer shall withhold payments for the affected works for which the
Contractor fails to revise and resubmit the Drawings to the Authority’s Engineer in
accordance with the provisions of Clause 10.2.4 (d).
(a) within 10 (ten) days of receipt of the Stage Payment Statement from the Contractor
pursuant to Clause 19.4, determine the amount due to the Contractor and recommend
the release of 90 (ninety) percent of the amount so determined as part payment,
pending issue of the Interim Payment Certificate; and
(b) within 15 (fifteen) days of the receipt of the Stage Payment Statement referred to in
Clause 19.4, deliver to the Authority and the Contractor an Interim Payment Certificate
certifying the amount due and payable to the Contractor, after adjustments in
accordance with the provisions of Clause 19.10.
7.3 The Authority’s Engineer shall, within 15 (fifteen) days of receipt of the Monthly
Maintenance Statement from the Contractor pursuant to Clause 19.6, verify the
Contractor’s monthly statement and certify the amount to be paid to the Contractor in
accordance with the provisions of the Agreement.
7.4 The Authority’s Engineer shall certify final payment within 30 (thirty) days of the
receipt of the final payment statement of Maintenance in accordance with the provisions
of Clause 19.16.
The Authority’s Engineer shall perform all other duties and functions as specified in the
Agreement.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 144
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
9 Miscellaneous
9.2 The Authority’s Engineer shall retain at least one copy each of all Drawings and
Documents received by it, including ‘as-built’ Drawings, and keep them in its safe
custody.
9.3 Within 90 (ninety) days of the Project Completion Date, the Authority’s Engineer shall
obtain a complete set of as-built Drawings, in 2 (two) hard copies and in micro film form
or in such other medium as may be acceptable to the Authority, reflecting the Project
Highway as actually designed, engineered and constructed, including an as-built survey
illustrating the layout of the Project Highway and setback lines, if any, of the buildings
and structures forming part of Project Facilities; and shall hand them over to the
Authority against receipt thereof.
9.4 The Authority’s Engineer, if called upon by the Authority or the Contractor or both, shall
mediate and assist the Parties in arriving at an amicable settlement of any Dispute
between the Parties.
9.5 The Authority’s Engineer shall inform the Authority and the Contractor of any event of
Contractor’s Default within one week of its occurrence.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 145
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
SCHEDULE - O
(a) The estimated amount for the Works executed in accordance with Clause 19.3.1
subsequent to the last claim;
(b) Amounts reflecting adjustments in price for the aforesaid claim;
(c) The estimated amount of each Change of Scope Order executed subsequent to
the last claim;
(d) Amounts reflecting adjustment in price, if any, for (c) above in accordance with
the provisions of Clause 13.2.3 (a);
(e) Total of (a), (b), (c) and (d) above;
(f) Deductions:
(i) Any amount to be deducted in accordance with the provisions of the
Agreement except taxes;
(ii) Any amount towards deduction of taxes; and
(i) Total of (i) and (ii) above.
(g) Net claim: (e) – (f) (iii);
(h) The amounts received by the Contractor upto the last claim:
(i) For the Works executed (excluding Change of Scope orders);
(ii) For Change of Scope Orders, and
(iii) Taxes deducted
Note: The Contractor shall submit its claims in a form acceptable to the Authority.
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 146
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
SCHEDULE - P
(See Clause 20.1)
INSURANCE
1.1 The Contractor shall effect and maintain at its own cost, from the Appointed Date till the
date of issue of the Completion Certificate, the following insurances for any loss or
damage occurring on account of Non Political Event of Force Majeure, malicious act,
accidental damage, explosion, fire and terrorism:
(a) insurance of Works, Plant and Materials and an additional sum of [15 (fifteen)]
per cent of such replacement cost to cover any additional costs of and incidental
to the rectification of loss or damage including professional fees and the cost of
demolishing and removing any part of the Works and of removing debris of
whatsoever nature; and
(b) insurance for the Contractor's equipment and Documents brought onto the Site
by the Contractor, for a sum sufficient to provide for their replacement at the
Site.
1.2 The insurance under paragraph 1.1 (a) and (b) above shall cover the Authority and the
Contractor against all loss or damage from any cause arising under paragraph 1.1 other
than risks which are not insurable at commercial terms.
The Contractor shall effect and maintain insurance cover for the Works from the date of
issue of the Completion Certificate until the end of the Defects Liability Period for any
loss or damage for which the Contractor is liable and which arises from a cause
occurring prior to the issue of the Completion Certificate. The Contractor shall also
maintain other insurances for maximum sums as may be required under the Applicable
Laws and in accordance with Good Industry Practice.
3.1 The Contractor shall insure against its liability for any loss, damage, death or bodily
injury, or damage to any property (except things insured under Paragraphs 1 and 2 of
this Schedule or to any person (except persons insured under Clause 20.9), which may
arise out of the Contractor's performance of this Agreement. This insurance shall be for
a limit per occurrence of not less than the amount stated below with no limit on the
number of occurrences.
The insurance cover shall be not less than: Rs. [*****]
3.2 The insurance shall be extended to cover liability for all loss and damage to the
Authority's property arising out of the Contractor’s performance of this Agreement
excluding:
(a) the Authority's right to have the construction works executed on, over, under, in
or through any land, and to occupy this land for the Works; and
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 147
Cross (Design chain age 318+755)
National Highways Authority of India Schedules
Four Laning of Package II:Addahole (Near Gundya )(Design Chainage 255+703) to Bantwal 148
Cross (Design chain age 318+755)