PRODUCTIVITY ANALYSIS OF DIAPHARAGM

WALL RIG

Presented By:
Anshul Kushwaha
Shylender Kandi
Naveen Manchala
PRODUCTIVITY

❑ It is the measure of the efficiency of man, machine or even


an activity.

❑ How to quantify productivity?


❑ Is it Output / Input
❑ Is it the quantity of work done per man per day
❑ Or is it expressed it in terms of cost

❑ It can be expressed in any way to suit the scenario.


PRODUCTIVITY MODELS

❑ Economic Models

❑ Project-Specific Models

❑ Activity-Oriented Models
PRODUCTIVITY MODELS

❑Economic Model:
Productivity = Total value of output
labor + materials + equipment + energy + capital
❑Project-Specific Model:
Productivity= Output
labor+ materials+ equipment
PRODUCTIVITY MODELS

❑Activity oriented model:


Labor productivity = Output
Labor cost
(or)
Output
Workhour
(or)
Labor cost or Workhour
Output
PROJECT DETAILS

Project : “Design and Construction Underground Stations and


Tunnel including Finishes and excluding PHE, Electrical and
HVAC from Chainage 14328.88m To Chainage 11882.88m for
Ahmedabad Metro Rail Project Phase-1”
PROJECT DETAILS

❑ Client : Metro Link Express for Gandhinagar & Ahmedabad


(MEGA ) Company Ltd.

❑ Contractor : AFCONS Infrastructure Ltd.

❑ Project Value : 775 Crores

❑ Project Duration : 39 Months


SAILENT FEATURES OF UG-01

❑ Project Length – 2446 m


❑ Twin Tunnel Length – 1712 m (Inner Dia = 5.80 m )
❑ Underground Station – 02 Nos
❑ Kankaria East Station ( 220 m)
❑ Kalupur Station ( 220 m)
❑ Cut and Cover – 211 m
❑ Underground Shaft
❑ Launching Shaft
❑ Retrieval Shaft
LAUNCHING SHAFT DETAILS

❑ Dimensions of Launching Shaft


❑ Length = 80 m
❑ Width = 22 m

❑ Dimension of Diaphragm Wall Panel


❑ Length = 6 m
❑ Width = 0.8 m
❑ Depth = 16 m

❑ Numbers of Diaphragm Wall Panel = 31


D-WALL LAYOUT PLAN FOR LAUNCHING SHAFT
CONSTRUCTION SEQUENCE OF DIAPHRAGM WALL

1. Centering and Marking for 8. Removal of Stopend of adjacent


Guidewall D-Wall (for primary and
2. Construction of Guidewall secondary panel)
3. Marking of Stopend position on 9. Lowering of Stopend
Guidewall 10. Lowering of Reinforcement cage
4. Area Levelling for equipment 11. Lowering of tremie
marching 12. Bentonite Flushing
5. Equipment marching and 13. Concreting
mobilization
14. Removal of Tremie
6. Grabbing and pouring Bentonite
7. Sounding and Verticality check
(By Koden)
CONSTRUCTION OF GUIDE WALL
TRENCHING ( GRABBING PROCESS)
TRENCHING ( GRABBING PROCESS)
KODEN ( VERTICALITY CHECK )
LOWERING OF STOPEND
REINFORCEMENT CAGE LOWERING
BENTONITE FLUSHING

❑ The density of bentonite


increases as it mixes with the
sand.
❑ Bentonite flushing is done to
maintain the density of
bentonite slurry in the trench.
❑ Bentonite is continuously
added to the trench from one
end and removed from the
another end.
❑ This process is done till the
polymer density falls below
1.2 g/cc
CONCRETING

Concreting by Two Tremie Concreting by Single Tremie


TIME CYCLE FORMAT
AFONS INFRASTRUCTURE LIMITED
AHMEDABAD METRO UG-1 PROJECT
LOCATION : APPAREL PARK DATE 8-Nov
D-WALL TIME CYCLE
PANEL NO : SDW 16 ( Closing) NIGHT SHIFT Wednesday

20:00

21:00

22:00

23:00

0:00

1:00

2:00

3:00

4:00

5:00

6:00

7:00

8:00
S.No ACTIVITY ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## DURATION

1 Trenching 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 90

2 Verticality Check (KODEN) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 40

3 Trimming & Cleaning 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 20

4 Stop End Lowering 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

5 Stop End Removal 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 0 0 0 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 120

6 Cage Shifting & Lowering 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 60

7 Tremie Lowering 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 0 0 0 0 0 0 0 0 0 30

8 Concreting 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

9 Breakdown 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

10 IDLE 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 90

11 Others 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 1 1 1 0 0 0 0 0 0 270

TOTAL 720

S.No REMARKS
1 22:30 - 23:00 - Break
BREAKDOWN, OTHERS 2 01:00 - 05:00 - Cage Welding Work
& IDLE REMARKS 3 06:30 - 07:00 - Muck shifting
4 07:00 - 08:00 - Wait for Concrete
5 Stop End Removal of SDW-15 & SDW17
ACTUAL TIME CYCLE OF D-WALL
ACTIVITY TIME ( In Mins) TIME ( In Hrs )
TRENCHING 398 6.64
KODEN (VERTICALITY CHECK) 204 3.40
CLEANING 55 0.92
STOP END LOWERING 67 1.12
STOP END REMOVAL 76 1.27
CAGE LOWERING 86 1.44
TREMIE LOWERING 58 0.97
CONCRETING 267 4.45
BREAKDOWN 329 5.49
IDLE 130 2.17
OTHER 486 8.10
TOTAL 2149 35.80
DIAPHRAGM WALL TIME CYCLE (PLAN VS ACTUAL)
MPSA PRINCIPLE

❑ Objectives of Productivity Measure System is to identify if there


is the problem in the productivity.

❑ Measure the factors Significant (Critical) activities, it can be


labor intensive as well as machine intensive.

❑ MPSA Principle : Measured Productivity for Significant Activities

❑ Here, trenching is the most significant activity.


TIME CYCLE

Trenching
Others 18%
23%
Trenching
Koden
Cleaning
Stop End Lower
Koden Stop End Removal
9%
IDLE Cage Lowering
6% Tremie Lowering
Cleaning Concrete
3%
Stop End Lower Breakdown
3% IDLE
Stop End Removal
Breakdown Others
4%
15% Cage Lowering
4%
Tremie Lowering
Concrete
3%
12%
DIAPHRAGM WALL RIG DETAILS

❑ Casagrande KRC 2HD - B250


XP-2
❑ The XP-2 technology monitors
the instantaneous power and
hydraulic flows
❑ Costs 470 Lacs
❑ Trenches of different width
can be grabbed using
different width jaw
DIAPHRAGM WALL RIG DETAILS

❑ A control panel is installed in


the driver’s cabin
❑ It displays information such
as
❑ Drilled depth
❑ Moving speed
❑ X Deviation
❑ Y Deviation
❑ Z Rotation
❑ It is continuously monitored
during the grabbing process.
GRABBING PATTERN OF DIAPHRAGM WALL
GRABBING SEQUENCE
PRODUCTIVITY ANALYSIS

❑ Total Scope for Diaphragm Wall = 182 m


❑ Size of 1 Diaphragm wall Panel = 6 m X 0.8 m
❑ Depth of Diaphragm Wall = 16 m
❑ Number of Bites require for 1 Panel = 3
❑ Total time require in complete trenching process = 6.6 Hours
❑ Time require for trenching of 1 Bite = (6.6/3) = 2.2 Hours
PRODUCTIVITY ANALYSIS

❑ Productivity = Output / Input

Output = Grabbing in Rm

Input = Working hours of Piling Rig

❑ Actual Productivity = Grabbing (in m) / Time(in hours)

= 16 / 2.2 = 7.27 Rm / Hr

❑ Planned Productivity = 10 Rm / Hr
PRODUCTIVITY ANALYSIS

❑ Percentage decrease in Productivity of D-Wall Rig


= (Planned Productivity – Actual Productivity)*100
Planned Productivity

= {(10-7.27)/10}*100 = 27.3 %
Rm / Hour

0
2
4
8
6
12
14

10
SDW 11
SDW 12
SDW 22
SDW 23
SDW 21
SDW 20
SDW 19
SDW 09
SDW 25
SDW 10
SDW 24
SDW 13
ACTUAL PRODUCTIVITY SDW 15
SDW 17
SDW 16
SDW 14
SDW 18
SDW 08
SDW 26
SDW 07
SDW 04
SDW 06
SDW 02
PLANNED PRODUCTIVITY

SDW 05
ACTUAL Vs PLANNED PRODUCTIVITY

SDW 03
SDW 32
SDW 31
SDW 27
SDW 28
SDW 29
SDW 30
CONSEQUENCES

❑ Planned Duration for Construction of Diaphragm Wall in Launching


Shaft = 68 Days

❑ Actual Duration for Construction of Diaphragm Wall in Launching


Shaft = 103 Days

❑ Number of Days lagging behind = 35 Days ( Almost 50% more than


the Planned Schedule)

❑ Per month Hire charges of D-Wall Rig = 11 Lacs

❑ Leads to 17 Lacs more cost only for Rig Hire charges.


REASONS FOR LOW PRODUCTIVITY OF D-WALL RIG

❑ Commissioning of D-Wall Rig is not done properly

❑ Lack of periodic maintenance

❑ Frequently breakdown of equipment

❑ Time taken by the operator to adopt the site conditions.

❑ Inadequate weather (Rainfall)


REASONS FOR SCHEDULE OVERRUN

❑ Almost 7 Days D-Wall Rig remains breakdown

❑ 11 days because of delay in Cage fabrication work and Stopend


removal

❑ Almost 5 Days have gone idle because of rainfall

❑ 8 Days delay due to hinderances caused by utilities during the


trenching of Guide wall

❑ 4 Days delays due to delay in approval of GFC drawings during the


construction