The day before we start the immersion, We attended first on the orientation at Aparri Main Office last
October 22,2019.We discuss about for our safetiness during the work immersion at the field. They can
also remind us to prepare for the actual work immersion. We need to be safe and have a presence of
mind in the work immersion.

February 3,2020 first day of our work immersion but before we went to field, We met first Engineer
Algeron R. Orquia for safety briefing and after that we immediately proceed to actual work with sir
Russele Dupaya and sir Joseph lingan. Our first deployment is in Municipality of Gattaran West we did
Tapping operation,Change meter,Reconnect and the Third day we did not work at the field,but we where
tasked to get the materials that needs in working at the main Office Aparri. The fourth day we change
the transformer at the logac lallo and then we make change meter based,tapping operation and
reconnect in the different location Gattaran west.

On the second week we rotated with the group from Gattaran East, Leaded by sir Eduardo Reboroso and
sir Virjillo Saludares This is the most enjoyable route because the lineman is a joker. In our first day our
crew was late because for their meeting at Gattaran Sub Office at the time is 11:00 in the morning so we
took our lunch in one restaurant in Centro Gattaran, and after that we go now to the newagac to tapping
the service drop of one house. The second day we go to Cabayu to reconnect the house and were go in
my house to eat for our lunch and after that lunch we go now to San Carlos to Reconnecting,Tapping and
we go now to Piña Weste to advice the people for their illegal connection.The following days we do
Change meter,Reconnet and Tapping in the different part of Gattaran east.

The third week we where assigned in Allacapan leaded by sir Erick juan and sir Zander Pascua The first
day we where go to Alig Valley to change the fuse tube and to reconnect and tapping.The second day we
went to the Main Office in Aparri to deliver the dis abled service to repair it and make it work again and
then we get some materials that needs in substation.The third day Web do Change the Transformer in
Nagattatan alig valley and then we make clearing operation in the different location in allacapan ares.
The following days we do Change meter,Tapping and Reconnect.

Our last week in work immersion,leaded by sir Justice Agatep and sir Rodel Villanueva we were able to
have a quick rest because it a long way before we reached Lasam.During my first day sir Rodel teach the
part of Transformer and what is the purpose of the cut, out after that we where going Abaryungan war
to inspect of one house. The second day we do Change meter,Tapping,Reconnect in the different
location in Lasam.We enjoy our work together with the linemans because while working, we are having
fun. We then tried to go home late because of our work and we are happy even because we are tired
And I've been enjoying through our work immersion and I'll be hoping someday I'll become part of
CGELCO II someday.And I appreciate the attitude of other people in different situation during the our
work immersion. And thank you my teacher,linemans and the God to give me strength,ability and
knowledge to apply in our work immersion.