Professional Documents
Culture Documents
Approval
This is to endorse that three students of Chemical Engineering Dept. of Z.H. Sikder University
of Science & Technology have completed their industrial project report on “Tasnim Chemical
Complex Ltd.” heading Industrial
“Project on Chloro-Alkali process units of Tasnim Chemical Complex Ltd.”
The report is about to the partial fulfillment of the requirements for the degree of B.Sc in
Chemical Engineering Dept.
Their involvement was much appreciated and I wish for their stunning future.
Supervisor
Dr. Md. Amran Hossain
Lecturer & Co-Ordinator,
Dept. of Chemical Engineering
Z.H. Sikder University of Science and Technology .
Co-Supervisor
Hossain Mohammad Zakir
Abstract
This paper is on a 15 days long project carried out from 3 december 2018 to 18 december 2018 for the
accomplishment of the course ChE- 431 which is programmed for the industrial attachment as a curriculum of
the Department of Chemical engineering of Z.H. Sikder
University of Science and Technology. The project was carried out at the Tasnim Chemical Complex Ltd.
whose valued collaboration is highly appreciated. Tasnim Chemical Complex Ltd. is one of the renowned
chlor-alkali Industries in Bangladesh that is completely integrated in producing caustic soda and also
bleaching, NaOCl (clotech B), Cl2 as by products.
The topics covered, as team work, in this project were as follows: Feasibility survey, Plant layout, Process
description, Material Balance, Energy Balance, cost estimation, piping and instrumentation diagram, HAZOP
study,, etc. The program had been finally completed successfully by the kind cooperation of many people.
Acknowledgement
I am grateful for the contributions from many individuals leading towards the successful completion of our
program, especially those who gave the time to share their thoughtful criticisms & suggestions to improve it. I
am deeply owing a favor to them for their personal encouragement and professional assistance.
First, I would like to thank Tasnim Chemical Complex Ltd. to give us the opportunity to do the project work in
their industry. I convey my respectful gratitude to our Teacher and Project Supervisors, Department of
Chemical Engineering and, Z.H. SikderUniversity of Science and Technology, for his valued co-operation in
making this project paper.
It is a great pleasure for us to acknowledge our Program Coach Md. Masudur Rahman, Process In charge,
Tasnim Chemical Complex Ltd. for his assistance and co-operation given to us throughout all the working
time. Without his heartiest interest and support, it would be quite impossible for us to carry out our project
work in such an industry and to complete this report with its full richness in information.
3|Page
I also want to say with great thanks to Md. Rokan for the massive support of giving approach to the industry an
also for whole contribution.
Special thanks to Md sohel and Md. Abu Bakar, production engineers, for their constant support and heartiest
effort to help us make this program come to a success.
I also like to thank all the personnel of Tasnim Chemical Complex Ltd. for their kind cooperation, throughout
the period of the project work, with their sharing of the various engineering principles and techniques in the
theoretical and practical grounds that made me realize and understand the real complexity of manufacturing
processes and how to face them from the field of Chemical Engineering.
4|Page
Contents:
Serial No: Table of Contents Page No:
2 Feasibility Studies 6
11 Conclusion 55
12 Reference 55-58
5|Page
In this modern age of competition, Chemical Engineers need to operate a Chemical plant in
such way that it can compete in this business environment ensuring product quality.
Tasnim Chemical Complex Ltd. (TCCL) is a sister concern of MEGHNA group. In the
beginning of 21st Century, TCCL starts its journey as the first private sector Chlor-Alkali
Industry in Bangladesh. The industry is located on newtown, sonargaon,narayanganj .
Significantly related to all the hopes and expectations of the new century, TCCL has energized
the vision to open new horizon for industrial development in the country. The project site was a
20 feet deep low-lying land from the road level that has been filled and developed suitably for
TCCL plant. It has incorporated most advanced state of the art technologies, machineries and
equipments.
FEASIBILITY SURVEY
Feasibility survey is the pre-pivotal task to establish a plant profitably. Some key factors are
necessary to analyze for the feasibility survey of a plant. For Tasnim Chemical Complex
Limited, the important key factors are listed bellow:
Availability of raw materials: Raw material collection is one of the most predominant
task. TCCL collects their raw materials from our neighbour country India. Though raw
materials also available in Bangladesh it is collected from India because of higher
quality than Bangladesh & river way transportation cost makes it attractive.
Availability of labour: Expert labours are available & there accomodation is also feasible
by easy transportation cost as TCCL situated at Dhaka area.
Power: As our government can not provide electricity at low cost, So TCCL produce
their electricity as they need. They 14.5 MW power generation capacity to fulfil their
need. They use natural gas to produce electricity .
TCCL uses surface water for their utility. Water is collected from meghna river & deep
tubewel. So they can manage their necessary amount of water easily.
Transportation cost: Their transportation cost lower enough because of their industry
situated at Narayanganj. Buyer can easily collect product produced by TCCL.
Another important thing is that disposal treatment. After treatment they can easily
through it to the river. They have good treatment system for their both effuent and
disposal.
So above discussion proved that TCCL is quiet feasible both economically & environmentally.
7|Page
PROCESS DESCRIPTION
TCCL is mainly a chloro-alkali industry.Its main products are caustic Soda(NaOH), Sodium
Hypochlorite(NaOCl), Clorine Gas(Cl2), hydrogen(H2), Bleaching(Ca(OCl)Cl). TCCL uses membrane cell
technology. Sodium hydroxide is produced (along with chlorine and hydrogen) via the Chloro-
alkali process. This involves the electrolysis of an aqueous solution of sodium chloride. The
sodium hydroxide builds up at the cathode, where water is reduced to hydrogen gas and
hydroxide ion:
In the process, three products are produced. It is vital that these are not allowed to mix. Thus, a
requirement of a commercial cell for the electrolysis of brine is that it separates the three
products effectively. Electrolysis in a simple vessel (described as a ‘one-pot’ vessel) leads to
the reaction of chlorine with sodium hydroxide to give unwanted sodium hypochlorite
(NaClO), sodium chlorate (NaClO3) and oxygen by the following reactions:
Process Procedure : TCCL works on the following step by step process. The main task of this industry is to purify the
raw salt into two steps
10 | P a g e
Primary purification
secondary purification
Raw Material:
The main raw material for this project the solid salt which is further processed to produce
caustic soda.
In this plant salts are imported from the neighboring country India. Because the composition of
the salt comes from India is better from the local salt and also have less impurities than the
local salt. We can say this by testing the composition.
Composition Percentage
Ca2+ 0.227%
Mg2+ 0.049%
SO42- 0.645%
Total Iron 13.2 ppm
NaCl 95.43%
Moisture 3.649%
Salt Saturator:
For melting the solid salt, in the salt saturator there is a continuous process of pumping of
return brine solution at about 75°c from the return brine tank which is executed from the cell
and is not converted to the caustic soda.
11 | P a g e
After melting raw salt in the salt saturator the solution is passed through a plate filter to remove
the floating substance and impurities that come from the salt feeding. Then the solution is fed
to the dosing unit.
Impurities or the mud which come from the salt decompose at the bottom of the salt saturator
and decrease the efficiency of the salt saturator. For this reason after 3-4 months the salt
saturator is washed to make it clean.
Dosing:
From analysis of the raw salt the dissolved impurities are the Ca 2+ , Mg2+ ,SO42- and the mud
that can be said. To remove these impurities chemical dosing is required. BaCl 2 is used to
removed the S . C is used to remove Ca2+ and also NaOH for the Mg2+.
After the dosing of these chemical the salt solution is send to the reactor for the proper mixing.
In a chloro-alkali plant mainly five different dosing are performed and these are as follows:
= 14.49 kg/hr
= 13.83 kg/hr
12 | P a g e
= 3.129 kg/hr
= 2.634 kg/hr
= 41.18 kg/hr
= 60.32 kg/hr
1. 475 kg BaCl2
2. 2000-2500 Liter H2O
3. 500 kg HCl Chemical Reaction:
BaCO3 + HCl = BaCl2 + CO2 + H2O
13 | P a g e
In this reaction ph of HCl is 3.5 to 4 where p h should be maintained at level 6.This is done by
adding 10 to 12 kg excess NaOH.
Desired concentration-0.14%
Required composition:
Required composition:
1. 500 gm floccal
2. 1000 liter H2O Chemical Reaction:
4. Sodium Sulphide(Na2SO3):
Required composition:
1. 100L Na2SO3
2. 200L H2O
14 | P a g e
Reactor:
Reactor which is used here mainly a CSTR. In this reactor the following reaction occurs:
Na2SO4 + BaCl2 → NaCl + BaSO4 ↓
After complete mixing of the brine and dosing solution a flocculent named Megna floc is added
to the solution. Then the solution is send to the clarifier for the removing the precipitate of the
solution and also increasing the turbidity of the solution.
Clarifier:
In the clarifier the mud, precipitated produced by the chemical dosing which are carried by the
saturated brine solution is precipitated in the bottom of the clarifier. From the bottom of the
clarifier the thick mud solution of the saturated brine is pumped to the decanter and mud is
separated and collected for disposal as waste product. The brine solution driven from the
clarifier is stored in clarified brine tank and then sends to anthracite filter for further removal of
flock particles.
Anthracite filter:
Filter medium of the anthracite filter is mainly the anthracite. In anthracite filter solid-solid
adsorption occurred. Three types of carbon: large, small and medium lies in the anthracite
filter. When the brine solution is passed through the fine anthracite filter medium the flock
particles cannot pass through the medium and get trapped in the anthracite medium. Then the
solution is stored in the anthracite filter tank to make the process continuous.
Candle filter:
15 | P a g e
Candle filter is a special type of filter in which the filter medium is activated carbon and the
filter coated with the alpha cellulose. This alpha cellulose blocks the micro level particles from
the brine solution. To maintain the layer of the alpha cellulose which is externally exerted in
the upper surface of the activated carbon filter 1-2 atm pressure is maintain continuously. If the
pressure drops, there will no more alpha cellulose layer upon the activated carbon filter. To
maintain the efficiency the of the filter aid, alpha cellulose is continuously added in the candle
filter. Brine solution is feed at the bottom of the filter and mud free solution is out at the top of
the filter. After filtering in the candle filter the turbidity becomes -3 or -4 and brine solution is
3 to 4 times transparent than water.
Regeneration:
The candle of the alpha cellulose is washed away by using the back flow of the air. The new
alpha cellulose is added from the pre-coat tank.
Ion Exchanger:
Multivalent ions are exchange with the Iminodiacetic acid of ion exchange resin in the ion-
exchanger. But sodium is mono-valent ion so it is not exchanged with this resin. Na ion is
replaced by Ca2+ and Mg2+. The resin used in ion-exchanger passed only Na+ and as it is a
cation exchanger so Na+ and Cl- entered into cell house. The Iminodiacetic acid formula is as
follows:
Resin can work very well till its efficiency is high or moderate. But when concentration of Ca 2+
is less than 10 ppm and concentration of Mg2+ is 2-3 ppb the bed is needed to regenerate. The
regeneration process is as follows:
Wash-1:
At first the resin bed is washed away by demineralized water at constant flow 1600 L/h and it
continue 1 hour as all ash and dust will washed.
16 | P a g e
Back wash:
Back wash is done by DM water at a flow rate of 1.6m3/h over 30 minute. DM water supplied
at the bottom of the tower and resin was circulate with the tower. Water flow is maintained at a
constant rate so that resin does not overflow. After ensuring that all brine washed away back
wash was completed.
HCl regeneration:
18% concentrated HCl is then supplied in the at 600L/h flow rate over 30 to 50 minutes. By
adding DM water at rate 1000L/h, 5% concentrated HCl made up. When the p h of HCl
becomes 1 HCl supply will stop. During HCl regeneration Na of Iminodiacetic acid was
replaced by Cl2 and the media become acidic.
Wash-2:
To remove the acidic media again DM water supplied at a flow rate 1600L/h over 1 hour.
Consequently all Cl2 will replace by H+ ion of water.
NaOH regeneration:
Now 32% NaOH passed through the bed at a rate 200L/h with DM water of rate 1400L/h over
40 to 50 minutes. As a result COOH of iminodiacitic acid will converted to COONa and resin
regeneration will completed.
Wash-3:
Again the bed will washed away by DM water at a flow rate of 1600L/h over 1 hour to
maintain the ph 10. If ph 10 is obtained water supply should stopped.
Brine filler:
17 | P a g e
Now the resin bed will fill up by 30% NaCl at 1.8m3/h flow rate over 1 hour.
Brine feed:
At last feed brine is feed in the ion-exchange column as the bed is fully regenerated and ready
to use with 100% efficiency.
Cell House:
Membrane technology is the unique Single Element, which comprises an anode half shell, a
cathode half shell and an individual sealing system with external flanges. The Single Elements
are suspended in a frame and are pressed against each other by a clamping device to form a
"Bipolar stack”. Each Single
Element can be replaced quickly and easily. The elements are assembled in the Electrolyzer
workshop, where tightness tests are also carried out.
18 | P a g e
DIAGRAMS
Material Balance
Material balance for production 30% NaOH from 28% NaoH on the basis of 50 ton
production per day.
Basis: 200 MT
24 | P a g e
=208.33 k mol / hr
hr 1 k mol
=8333.2 kg / hr
So equivalent amount of NaCl is needed for production of equivalent Caustic Soda (NaOH).
We could write
= 300 g/L
= 5.12 kmol/m3
= 220 g/l
208.33 kmol m3
hr 1.379 kmol
= 151.073 m 3/hr
= 773.49 kmol/hr
= 30939.6 kg/hr
= 568.03 kmol/ hr
= 22721.2 kg/hr
Production of Chlorine
= 104.165 kmol/hr
= 4166.5 kg/hr
NaOHin :
27 | P a g e
m3 1 kg Solution 40 kg NaOH
= 8.989 k mol / m3
NaOHout :
m3 1 kg solution 40 kg NaoH
= 10.608 – 8.988
= 128.5 m3/hr
NaoHin NaoHout
= 1363.28 k mol / hr
= 54531.2 kg / hr
H2Oin H2Oout
=33262.56 kg/hr
=1847.92 k mol/hr
= 38171.84 kg/hr
= 2120.66 k mol/h
29 | P a g e
= ½ × 1363.28 k mol / hr
= 681.64 k mol/h
= 1363.28 kg/hr
= 12084.8 kg/hr
12084.8 kg 100
hr 95.43
=12663.523 kg/hr
H2 681.64 1363.28
Energy Balance
ΔĤin ΔHout
31 | P a g e
ΔĤNaCl = ΔHf + ∫ Cp dT
25
kJ
= (-411+ 0) mol
kJ
= -411 mol
kJ mol
ΔĤNaCl = -411 mol * 544640 hr
kJ
= -223847040 hr
ΔĤNaCl = ΔHf + ∫ Cp dT
25
kJ
= (-411 + 0) mol
kJ
= -411 mol
kJ mol
ΔHNaCl = -411 mol * 336310 hr
kJ
= -138223410 hr
ΔĤin ΔHout
60
ΔĤin = ΔHf + ∫ Cp dT
25
60
= -285.84 +∫ 75.4 dT
25
= -285.84 + [75.4 T]
= -285.84 + 75.4(60-25)
= -285.84 + 2639
kJ
= 2353.14 mol
kJ mol
ΔH(H2Oin) = 2353.14 mol * 4130190 h
kJ
= 9718915297 hr
ΔĤH2O = ΔHf + ∫ Cp dT
25
85
= -285.84 + ∫ 75.4 T
25
kJ
= -285.84 + 75.4[85-25] mol
kJ
= (-285.84 + 4524) mol
kJ
= 4238.16 mol
kJ mol kJ
ΔHH2O = 4238.16 mol *4130190 hr = 17504406050 hr
ΔHin ΔHout
ΔĤ(NaOHin) = ΔHf + ∫ Cp dT
25
kJ
= (-469.4 + 0) mol
kJ
= -469.4 mol
kJ mol
ΔH(NaOHin) = -469.4 mol * 1257680 hr
kJ
= -590354992 hr
ΔĤNaOH = ΔHf + ∫ Cp dT
25
kJ
= (-469.9 + 0) mol
kJ
= -469.9 mol
kJ mol
ΔHNaOH = -469.9 mol * 1466100 hr
kJ
= -688920390 hr
ΔĤ(Cl2out) = ΔHf + ∫ Cp dT
25
(33.60 + 1.367*10-2 T-1.607*10-5 T2 +6.473*10-9 T3)dT
=0+
kJ
= 2058 mol
kJ mol
ΔHCl2 = 2058 mol * 104165 hr
kJ
= 214371570 hr
Energy balance for H2:
85
ΔĤH2 = ΔHf + ∫ Cp dT
25
34 | P a g e
85
= 0 + ∫ Cp dT
25
kJ
= 1731.3 mol
kJ mol
ΔHH2 = 1731.3 mol * 733050 hr
kJ
= 1269129465 hr
Total ΔHin = ΔHNaCl + ΔHH2O + ΔHNaOH
kJ kJ kJ
= -223847040 hr +9718915297 hr -590354992 hr
kJ
= 8904713265 hr
H2 - 1269129465 kj/hr
Cost Estimation
Table 5.1: Typical percentages of fixed-capital investment values for direct and indirect cost
Direct costs
Purchased equipment 18-43%
Purchased equipment installation 5-10%
Instrumentation & controls (installed) 4-12%
Piping (installed) 3-15%
Electrical system (installed) 3-10%
Buildings (including services) 3-16%
Yard improvements 3-6%
Service facilities (installed) 7-25%
Land 2-5%
Indirect costs
Engineering & supervision 3-17%
Construction expenses 3-20%
Legal expenses 2-5%
Contractor’s fee 1-4%
Contingency 3-17%
Table 5.2 : Summary of purchased equipment cost for the Caustic Soda plant
36 | P a g e
Total 3,45,52,487
Subtotal: 1,825,000
Fixed charges
Depreciation 3% 150,000
Taxes(property) 1% 50,000
Financing (interest) 2% 100,000
Insurance 2% 100,000
Rent 3% 150,000
Subtotal 550,000
Manufacturing cost = Total of variable production cost + Total of fixed charges + Total
of plant overhead costs
38 | P a g e
Total= 1825000+55000+725000
Total= 3,100,000
Administrative expenses
Executive salaries 7% 350,000
Clerical wages 1% 50,000
Engineering 4% 200,000
Legal costs 1% 50,000
Office maintenance 1% 50,000
Communications 2% 100,000
Subtotal: 800,000
Distribution and
marketing expenses
Sales offices 3% 150000
Sales personnel expenses 2% 100000
Shipping 3% 150000
Advertising 6% 300000
Technical sales service 1% 50000
Subtotal: 750,000
Research and
7% 350000
development (R&D)
= 1900000 TK
= 3100000 + 1900000
= 50,00000 TK
SAFETY
Industrial Safety:
Industrial safety is the term consists of some precautionary measures that are
observed by people at the time of performing a job inside the factory with the help
of some machine or equipment design in such manner that can check the accident to
be happened with ultimate view to achieve the possible higher productivity.
Importance of Safety:
The ultimate aim of safety is the complete prevention of personal injury, loss of
life and destruction of properties. Effective plant safety and fire protection are
essential for every phase of operation and maintenance of equipment &
machines. Calculated risks must be reduced as far as possible. Equipment &
individual items must be examined time to time for normal service and also
emergency demands. Some major principles and practice of plant safety are
40 | P a g e
mentioned below. For safe plant operation, detailed safety instructions must
always be established. All buildings, workshops, installation, machinery and
equipment must be furnished and maintains so as to protect the workers against
accidents and professional diseases. The instructions issued by the plant
management for safe operation and for the conduct of personnel must be
followed strictly.
Responsibility of safety:
The safety is of a preventive nature; the aim is to stop the risks and
unsatisfactory conditions and their incorporation into better working
conditions. This requires contributions from and above all, co-operation
between both employees and employer.
The Bangladesh government established a general safety rule for industry called
“Safety in the Factory Rules, 1979”. Every industrial personnel is to observe the
following general safety rules:
• Use appropriate personal protective apparel and equipment for the operation.
• Use alert to unsafe conditions and reactions. Call attention to hazards so the corrections can
be made immediately.
• Know the location of emergency equipment in your area. Read and become familiar with
emergency response procedures.
• Avoid destructing or startling any co-worker in the laboratory. Practical jokes or any
horseplay cannot be tolerated at any time in the laboratory.
• Access to exits, emergency equipment, controls and such must never be blocked. Stairways
and hallways must not be used as storage areas even temporarily.
Safety Sign:
For the concern of the company’s personnel safety, different safety signs are used such as:
• Prohibition Sign
Example: No smoking, Pedestrians prohibited, No drinking water etc.
• Warning Sign
Example: Risk of electrical shock, Laser beam, Risk of explosion, Risk of fire, Toxic hazard.
• Mandatory Sign
42 | P a g e
Example: Eye protection, Hand, head and foot protection, Hearing and respiratory
protection etc.
Safety equipments: The following equipments are used for safety consideration
PLANT LAYOUT
The laying out of a plant is still an art rather than a science. Plant Layout is the
physical arrangement of equipment and facilities within a Plant. The Plant Layout
can be indicated on a floor plan showing the distances between different features of
the plant. Optimizing the Layout of a Plant can improve productivity, safety and
quality of Products. Unnecessary efforts of materials handling can be avoided when
the Plant Layout is optimized. It involves the placing of equipment so that the
following are minimized:
All of these goals cannot be met. For example, to reduce potential losses in case of
fire, the plant should be spread out, but this would also result in higher pumping
costs, and might increase manpower needs. The engineer must decide within the
guidelines set by his company which of the aforementioned items are most
important.
The first thing that should be done is to determine the direction of the prevailing
wind. This can be done by consulting Weather Bureau records. In Bangladesh the
prevailing winds are often from the north to south in the summer. Wind direction
will determine the general location of many things. All equipment that may spill
flammable materials should be located on the downwind side. Then if a spill occurs
the prevailing winds are not apt to carry any vapors over the plant, where they could
be ignited by an open flame or a hot surface.
For a similar reason the powerhouse, boilers, water pumping, and air supply
facilities should be located 250 ft (75 m) from the rest of the plant, and on the
upwind side. This is to minimize the possibility that these facilities will be damaged
in case of a major spill. This is especially important for the first two items, where
there are usually open flames.
Every precaution should be taken to prevent the disruption of utilities, since this
could mean the failure of pumps, agitators, and instrumentation. For this reason, it
may also be wise to separate the boilers and furnaces from the other utilities. Then,
should the fired equipment explode, the other utilities will not be damaged.
Other facilities that are generally placed upwind of operating units are plant offices,
mechanical shops, and central laboratories. All of these involve a number of people
who need to be protected. Also shops and laboratories frequently produce sparks
and flames that would ignite flammable gases. Laboratories that are used primarily
for quality control are sometimes located in the production area.
46 | P a g e
A list of items that should be placed downwind of the processing facilities is given below
Items That Should Be Located Upwind of the Plant
Plant offices
Central laboratories
Office building
Cafeteria
Storehouse
Medical building
Change house
Fire station
Boiler house
Electrical powerhouse
Electrical Substation
Cooling tower
Air compressors
Parking lot
Fired heaters
47 | P a g e
Tank farms and warehouses that contain nonhazardous, nonflammable, and non
explosive materials should be located upwind of the plant. Those that do not fit this
category should not be located downwind of the plant, where they could be damaged
and possibly destroyed by a major spill in the processing area. Nor should they be
located upwind of the plant where, if they spilled some of their contents, the
processing area might be damaged. They should be located at least 250 ft (75m) to
the side of any processing area.2 Some authorities suggest this should be 500 ft.
The same reasoning applies to hazardous shipping and receiving areas.
Sometimes storage tanks are located on a hill, in order to allow the gravity
feeding of tank cars. Care must be taken under these circumstances to see that any
slop over cannot flow into the processing, utilities, or service areas in case of a
tank fire.
Spacing of Items
The OSHA has standards for hazardous materials that give the minimum distances
between containers and the distance between these items and the property line,
public roads, and buildings. These depend on the characteristics of the material, the
type and size of the container, whether the tank is above ground or buried, and what
type of protection is provided. Specific details are provided for compressed gas
equipment containing acetylene-air, hydrogen-oxygen, and nitrous oxide, as well as
liquefied petroleum gases. They also prohibit the storage and location of vessels
containing flammable and combustible materials inside buildings, unless special
precautions are taken.
Processing Area
48 | P a g e
There are two ways of laying out a processing area. The grouped layout places all
similar pieces of equipment adjacent. This provides for ease of operation and
switching from one unit to another. For instance, if there are 10 batch reactors,
these would all be placed in the same general area, and could be watched by a
minimum of operators; if they were spread out over a wide area, more operators
might be needed. This type of scheme is best for large plants. The flow line layout
uses the train or line system, which locates all the equipment in the order in which
it occurs on the flow sheet. This minimizes the length of transfer lines and,
therefore, reduces the energy needed to transport materials. This system is used
extensively in the pharmaceutical industry, where each batch of a drug that is
produced must be kept separate from all other batches. In other industries it is used
mainly for small-volume products. Often, instead of using the grouped or flow line
layout exclusively, a combination that best suits the specific situation is used.
Elevation
If there is no special reason for elevating equipment, it should be placed on the
ground level. The superstructure to support an elevated piece of equipment is
expensive. It can also be a hazard should there be an earthquake, fire, or explosion.
Then it might collapse and destroy the equipment it is supporting as well as that
nearby. Some pieces of equipment will be elevated to simplify the plant operations.
An example of this is the gravity feed of reactors from elevated tanks. This
eliminates the need for some materials-handling equipment. Other pieces may have
to be elevated to enable the system to operate. A steam jet ejector with an inter
condenser that is used to produce a vacuum must be located above a 34 ft (10 m)
barometric leg. Condensate receivers and holding tanks frequently must be located
high enough to provide an adequate net positive suction head (NPSH) for the pump
below. For many pumps an NPSH of at least 14 ft (4.2 m)
Hz0 is desirable. Others can operate when the NPSH is only 6 ft (2 m) H2O.
The third reason for elevating equipment is safety. In making explosive materials,
such as TNT, the reactor is located above a large tank of water. Then if the mixture
in the reactor gets too hot and is in danger of exploding, a quick-opening valve
below the reactor is opened and the whole batch is dumped into the water. An
emergency water tank may need to be elevated so that, in case of a power failure,
cooling water to the plant will continue to flow, and there will be water available
should a tire occur. Sometimes this tank is located on a nearby hill. An elevation
49 | P a g e
plan should be drawn to scale showing the vertical relationships of all elevated
equipment. These drawings, as well as the plot plan, are usually sketched by the
engineer and then redrawn to scale by a draftsman.
Maintenance
Maintenance costs are very large in the chemical industry. In some cases the cost of
maintenance exceeds the company’s profit.
Construction and Building
Proper placing of equipment can result in large savings during the construction of the
plant. For instance, large columns that are field-erected should be located at one end
of the site so that they can be built, welded, and tested without interfering with the
construction of the rest of the plant.
Buildings
Included with the layout of the plant is the decision as to what types of buildings
are to be constructed, and the size of each. When laying out buildings, a standard
size bay (area in which there is no structural supports) is 20 ft x 20 ft (6m x 6m).
Under normal conditions a 20 ft (6 m) span does not need any center supports. The
extension of the bay in one direction can be done inexpensively. This only
increases the amount of steel in the long girders, and requires stronger supports.
Lavatories, change rooms, cafeterias, and medical facilities are all located inside
buildings. The minimum size of these facilities is dictated by OSHA. It depends on
the number of men employed. Research laboratories and office buildings are
usually not included in the preliminary cost estimate. However, if they are
contemplated their location should be indicated on the plot plan.
Processing Buildings
Quality control laboratories are a necessary part of any plant, and must be included
in all cost estimates. Adequate space must be provided in them for performing all
tests, and for cleaning and storing laboratory sampling and testing containers. The
processing units of most large chemical plants today are not located inside
buildings. This is true as far north as Michigan. The only equipment enclosed in
buildings is that which must be protected from the weather, or batch equipment that
requires constant attention from operators. Much of the batch equipment used
today does not fit this category. It is highly automated and does not need to be
enclosed. When buildings are used, the ceilings generally vary from 14 to 20 ft (4
50 | P a g e
to 6 m). Space must be allowed above process vessels for piping and for access to
valves. One rule of thumb is to make the floorto-
floor heights 8- 10 ft (approximately 3m) higher than the sides of a dished-head
vertical tank.6 Packaging equipment generally must be in an enclosed building, and
is often located at one end of the warehouse. If the material being packaged is
hazardous, either this operation will be performed in a separate building, or a
firewall will separate it from any processing or storage areas
Warehouse:
The engineer must decide whether warehouses should be at ground level or at dock
level. The latter facilitates loading trains and trucks, but costs 1520% more than
one placed on the ground. It is usually difficult to justify the added expense of a
dock-high warehouse. To size the amount of space needed for a warehouse, it must
be determined how much is to be stored in what size containers. The container
sizes that will be used are obtained from the scope. Liquids are generally stored in
bulk containers. No more than a week’s supply of liquid stored in drums should be
planned. Solids, on the other hand, are frequently stored in smaller containers or in
a pile on the ground.
Control Rooms
The control center(s) and the electrical switching room are always located in an
enclosed building. It is important that both of these services be maintained so that
the plant can be shut down in an orderly manner in the case of an emergency.
Therefore these buildings must be built so that should an external explosion occur
the room will not collapse and destroy the control center and switching center. To
avoid this, either the structure must have 3-4 ft (l-l.2 m) thick walls, or the roof
must be supported independently of the walls. The Humble Oil and Refining Co.
has specified that the building withstand a 400 psf (2,000 kg / m2) external
explosive force. To keep any flammable or explosive vapors from entering the
building, it is frequently slightly pressurized. This prevents the possibility of an
internal explosion.
Chapter 5
HAZOP Analysis
51 | P a g e
node at once) and "too small and simple" (many trivial and repetitive nodes, each of
which has to be reviewed independently and documented).
HAZOP
Table No:- 01
Parameter/Guid More Less None Reverse As well Part of Other then
e Word as
Flow Corrosion Undesired
of PVC. ion can be
High No No No High mixed
with
brine.
Pressure Ion GPL will
High No No No High exchanger be
resin will reduced.
destroiate.
Temperature Low PVC Explosion.
No No No Low installation
will
destroiate.
Level No Corrosion Brine can
High No No High of pipeline not pass
properly.
Time Too Too Operating GPL will
long No No No long cost will be
be high. reduced.
Table no:- 02
Ref./Paramete Deviation Cause Consequenc Safeguards Action
r e
Brine can Corrosion, Flow can be Manually flow
Flow High Flow pass damage of controlled by can be
53 | P a g e
Braine Section
1.Flow
2. Temperature
54 | P a g e
1. High Flow
2. Low Temperature
1. Damage of pipeline
2. Corrosion, explosion can’t occur
1. Manually control
2. Manually control
Stage is complete
Fig:- Flow diagram for the HAZOP analysis of section or stage of an operation
Conclusion:
The Textiles and Dyeing sector in Bangladesh are playing the major role in the economy. It is a
booming sector of Bangladesh and it require a huge amount of chemicals including Sodium
hydroxide. The total requirement of caustic soda per Annual about 80,000 ton. And ASM
Chemical Industries Limited produces 20,000 ton per annum. So there is a good opportunity to
set up this kind of Industry since it is the only industry in private sector.
55 | P a g e
It is one of the modern factory in Bangladesh which is operated by DCS system which is used
only in four industries in Bangladesh including it. It is equipped with latest technology,
machineries and facilities. This factory maintains an effective administration, securities and
good labour management. So every year this factory fulfils the estimate production capacity.
From this I have received a good concept on the latest technology of chemical process in this
selective field. Besides that I can mentioned some machineries like Clarifier, Evaporator,
Boiler, Ion Exchange column which I have only the theoretical knowledge before.
In this report, I have tried my best to cover up all aspects of this plant including process
chemistry and operation, utilities, environmental pollution, safety aspects, economics etc.
Finally, the visit was an event of great success and sufficient significance from the both
academic and professional view point. I hope the concerning authority will realize the prime
importance of such type of industrial visit will take adequate steps to make it more effective in
the years to come.
List of References
1. Shreve RN. Chemical process industries, 3rdedition. New York: McGraw hill Book
Company, 1967.
2. Othmer Kirk, encyclopedia of chemical technology, vol. 21. New York: John Wiley & Sons,
2004.
3. Kern DQ. Process Heat Transfer. New Delhi: McGraw Hill Companies, 2004.
6. Plant Design and Economics for Chemical Engineers (Fifth Edition). By Max S. Pters, Klaus
D. Timmerhaus, Ronald E. West; University of Colorado.
56 | P a g e
7. Perry's Chemical Engineering Handbook (7 ed.). (D. W. Green, & J. O. Maloney, Eds.)
McGraw Hill Companies Inc.
8. J.M. Smith and H.C Van Ness. Introduction to Chemical Engineering Thermodynamics
.Third Edition. International Student Edition.
9. Samuel Strelzoff, 1981.Tecnology and Manufacture of Ammonia. A Wiley_Interscience
Publication.
10. J.M Thomas and W.J Thomas. 1967. Introduction to the principles of Heterogeneous
Catalysis .Academic Press, London & New York.
10. G.C Bond.1962 Catalysis by Metals .Academic Press, London and New York.
11. Chris A. Clausen and Guy Mattson, 1978.Principles of Industrial Chemistry, A-Wiley Inter-
science Publication.
12. I.P Mukhlenova. 1982. Calculation in Chemical Technological Processes. Khimiya,
Leningrad.
13. Occupational Health and Safety Manual. (2004, October 12). Retrieved June 13, 2013, from
Department of Transportation and Works, New Foundland, Canada:
http://www.tw.gov.nl.ca/publications/ohs.pdf
14. Technical Information and Safe Handling Guide for Methanol. (2006, September).
Retrieved November 10, 2012, from http://www.methanol.org/Health-And-Safety/Safety-
Resources/Health---Safety/Methanex-TISH-Guide.aspx
15. Fire and Life Safety Compliance Guide. (2009, March). Retrieved June 14, 2013, from
University of Medicine and Dentistry, New Jersey:
http://www.umdnj.edu/eohssweb/publications/firecomplianceguide.pdf
16. How to Interpret Piping and Instrumentation Diagrams. (2010, August 24). Retrieved May
22, 2012, from http://chenected.aiche.org/series/interpret-piping-instrumentation-diagrams
17. Chang, J. I., & Lin, C.-C. (n.d.). A study of storage tank accidents. Journal of Loss
Prevention in the Process Industries, 2006(19), 51-59.
18. Chemical Engineering Plant Cost Index (averaged over year). (n.d.). Retrieved June 18,
2013, from Norwegian University of Science and Technology:
http://www.nt.ntnu.no/users//magnehi/cepci_2011_py.pdf.
57 | P a g e
19. Dynalene MS-1 Technical Data Sheet. (n.d.). Retrieved July 23, 2013, from
http://www.dynalene.com/v/vspfiles/templates/210/datasheets/Dynalene_MS-
1_Technical_Data_Sheet.pdf
20. Fluids- Latent Heat of Evaporation. (n.d.). Retrieved July 12, 2013, from The Engineering
Toolbox: http://www.engineeringtoolbox.com/fluids-evaporation-latent-heat-d_147.html
21. Gowariker, V. (2009). The Fertilizer Encyclopedia. John Wiley & Sons.
22. Holloway, M. D., Nwaoha, C., & Onyewuenyi, O. A. (Eds.). (2012). Process Plant
Equipment- Operation, Control, and Reliability. Hoboken, New Jersey: John Wiley & Sons Inc.
23. Latent Heat of Melting of some common materials. (n.d.). Retrieved July 12, 2013, from
The Engineering Toolbox: http://www.engineeringtoolbox.com/latent-heat-melting-solids-
d_96.html
24. Liquids and Fluids- Specific Heats. (n.d.). Retrieved July 14, 2013, from Engineering
Toolbox: http://www.engineeringtoolbox.com/specific-heat-fluids-d_151.html
25. List of safety precautions for shutdown activities of chemical plants. (n.d.). Retrieved June
18, 2013, from Chemical Plant Safety: http://www.chemicalplantsafety.net/safety-tips/list-of-
safety-precautions-for-shutdown-activities-of-chemical-plants/
26. Lloyd, L. (2011). Handbook of Industrial Catalysts - Fundamental and Applied Catalysis. In
Chapter 2 The First Catalysts. Springer .
27. Chemical Safety Handbook. (2002). Retrieved June 16, 2013, from Southern States
Chemical: http://www.sschemical.com/wp-content/uploads/SAFETY1.pdf
28. Riegel, E., & Kent, J. (2003). Riegel's Handbook of Industrial Chemistry. Springer.
29. Sinnott, R. K. (1999). Coulson & Richardson's Chemical Engineering Volume 6 (Chemical
Engineering Design) (3 ed.). Butterworth-Heinemann.
30. Sinnott, R. K. (1999). Coulson & Richardson's Chemical Engineering Volume 6 (Chemical
Engineering Design) (3 ed., Vol. 6). Butterworth-Heinemann.
31. A.I. Basaroff, J.Prakt.Chem.2 (1870) no.1,283.
32. P.J.C. Kaasenbrood, H.A.G. Chermin, paper presented to The Fertilizer Society of London,
1st Dec., 1977.
58 | P a g e
35. 2001 Jonckers Stamicarbon 2001/0041813, Process for the preparation of urea.
36. 1980 Zardi Snamprogetti CA 1069932 A1 Method for the condensation of carbamate in
urea synthesis installations.