Site Acceptance Test Report Date : 28-01-18

Contractor’s Name: SEPCO III Customer: NGSA

Name Of Substation: AL ZULFI 9064-380/132/33KV BSP Contract No: 4400006712


ENERGY METER Page 1 of 5
Panel/Bay No:SST1 Equip. No.: Dwg. Ref.:CA-808637 Record No.:

A. General Data and Information

MAKE Landis+Gyr CT RATIO 800/1A


MODEL E650 PT RATIO 33/0.120KV
ACCURACY CLASS 0.2S HZ 60 HZ
SERIAL NO. 51301874

B. Function Test

NO FUNCTIONS
1 Physical /Visual Inspection.
2 Electrical check.
3 Metering Minimum Current
4 Current Measurement
5 Voltage Measurement
6 POWER(MW-MVAR) Measurement
7 Accuracy Test
8 Maximum Demand

1. Mechanical Check and Visual Inspection

Item Description Remark


1 Inspect for physical damage and defects. DONE

2 All connection check according to the wiring diagram. DONE

3 Verify tightness for external wiring. DONE

2. Electrical Checks:

Date :
TESTING ENGINEER SEC- CSD - Engineer

Signature: ___________________ Signature: ________________


Name : A. SALMAN FAREES Name :ENGR.FAYAZ AHMED
Site Acceptance Test Report Date : 28-01-18

Contractor’s Name: SEPCO III Customer: NGSA

Name Of Substation: AL ZULFI 9064-380/132/33KV BSP Contract No: 4400006712


ENERGY METER Page 2 of 5
Panel/Bay No:SST1 Equip. No.: Dwg. Ref.:CA-808637 Record No.:

Item Description Remark


1 Wiring check as per Ref (approved) Drawing DONE

2 Auxiliary power supply checked for rating and polarity DONE

3 Test Switch checked for correct function DONE

3. Metering

- CREEP TEST

APPLIED VOLTAGE APPLIED CURRENT REMARKS


69.28 0.0 A No Increment In Energy Values
69.28 0.1A Minimum current value.

4- CURRENT MEASUREMENTS:

Current (KA) measurement Current (KA) measurement


3 ph Secondary Expected Actual
Current injected (A)
A B C A B C

0.00 0.00 0.00 0.00 0 0 0

0.25 0.2 0.2 0.2 0.2 0.2 0.2

0.50 0.4 0.4 0.4 0.4 0.4 0.4

1.00 0.8 0.8 0.8 0.8 0.8 0.8

5- Voltage Measurements:

Date :
TESTING ENGINEER SEC- CSD - Engineer

Signature: ___________________ Signature: ________________


Name : A. SALMAN FAREES Name :ENGR.FAYAZ AHMED
Site Acceptance Test Report Date : 28-01-18

Contractor’s Name: SEPCO III Customer: NGSA

Name Of Substation: AL ZULFI 9064-380/132/33KV BSP Contract No: 4400006712


ENERGY METER Page 3 of 5
Panel/Bay No:SST1 Equip. No.: Dwg. Ref.:CA-808637 Record No.:

3Ph Phase Voltage (KV) meas. Phase Voltage (KV) meas


Secondary Expected Actual
Voltage applied
(V) PH-N VA VB VC VA VB VC

0.00 0.00 0.00 0.00 0.3 0.3 0.3

34.64 9.5 9.5 9.5 9.5 9.5 9.5

51.96 14.2 14.2 14.2 14.2 14.2 14.2

69.28 19.05 19.05 19.05 19 19 19

6- Power & Energy Measurements:

3 ph
3 Ph Phase Power factor MW meas. MVAR meas.
current
Voltage Angle
injected
applied (V) set @ Exp Actual Exp Actual Exp Actual
(A)

69.28 1.00 0.0 1 0.99 45.7248 45.7374 0 0

1.00 45 0.707 0.70 32.327 32.3410 32.327 32.3410


69.28
1.00 90 0 0 0 0 45.7248 45.7374
69.28
1.00 180 -1 -0.99 -45.7248 -45.7374 0 0
69.28
1.00 270 0 0 0 0 -45.7248 -45.7391
69.28
1.00 315 0.707 0.70 32.327 32.3427 -32.327 -32.3401
69.28

7. Accuracy Test:

Accuracy Test of Meter (Active Energy).


Date :
TESTING ENGINEER SEC- CSD - Engineer

Signature: ___________________ Signature: ________________


Name : A. SALMAN FAREES Name :ENGR.FAYAZ AHMED
Site Acceptance Test Report Date : 28-01-18

Contractor’s Name: SEPCO III Customer: NGSA

Name Of Substation: AL ZULFI 9064-380/132/33KV BSP Contract No: 4400006712


ENERGY METER Page 4 of 5
Panel/Bay No:SST1 Equip. No.: Dwg. Ref.:CA-808637 Record No.:

Result Result
IEC 62053-22
Test # Test Description Import Export
Limitations
(Error %) (Error %)
1 10% In, 100%Vn UPF ± 0.2 0.0248 0.0265
2 100% In, 100%Vn UPF ± 0.2 0.0174 0.0148
3 300% In, 100%Vn UPF ± 0.2 0.0304 0.0278
4 600% In, 100%Vn UPF ± 0.2 -0.0086 -0.0112
5 10% In, 100%Vn 0.5Lag ± 0.3 0.0595 0.0648
6 100% In, 100%Vn 0.5Lag ± 0.3 0.0319 0.0300
7 300% In, 100%Vn 0.5Lag ± 0.3 0.0109 -0.0155
8 600% In, 100%Vn 0.5Lag ± 0.3 -0.0086 -0.0155
9 10% In, 100%Vn 0.8Lead ± 0.3 0.0196 0.0208
10 100% In, 100%Vn 0.8Lead ± 0.3 0.0276 0.0271
11 300% In, 100%Vn 0.8Lead ± 0.3 0.0401 0.0375
12 600% In, 100%Vn 0.8Lead ± 0.3 0.0401 0.0375

Accuracy Test of Meter (Reactive Energy).

Result Result
IEC 62053-23
Test # Test Description Import Export
Limitations
(Error %) (Error %)
1 10% In, 100%Vn UPF ± 2% 0.0235 0.0291
2 100% In, 100%Vn UPF ± 2% 0.0174 0.0174
3 300% In, 100%Vn UPF ± 2% 0.0304 0.0304
4 600% In, 100%Vn UPF ± 2% 0.0781 -0.0086
5 10% In, 100%Vn 0.5Lag ± 2% 0.0122 0.0247
6 100% In, 100%Vn 0.5Lag ± 2% 0.0138 0.0138
7 300% In, 100%Vn 0.5Lag ± 2% 0.0401 0.0401
8 600% In, 100%Vn 0.5Lag ± 2% 0.0401 0.0401
9 10% In, 100%Vn 0.8Lead ± 2% 0.0482 0.0578
10 100% In, 100%Vn 0.8Lead ± 2% 0.0319 0.0319
11 300% In, 100%Vn 0.8Lead ± 2% 0.0154 0.0154
12 600% In, 100%Vn 0.8Lead ± 2% -0.0625 -0.0105

Date :
TESTING ENGINEER SEC- CSD - Engineer

Signature: ___________________ Signature: ________________


Name : A. SALMAN FAREES Name :ENGR.FAYAZ AHMED
Site Acceptance Test Report Date : 28-01-18

Contractor’s Name: SEPCO III Customer: NGSA

Name Of Substation: AL ZULFI 9064-380/132/33KV BSP Contract No: 4400006712


ENERGY METER Page 5 of 5
Panel/Bay No:SST1 Equip. No.: Dwg. Ref.:CA-808637 Record No.:

8.Maximum Demand Test:

Phase
3 Ph Voltage 3 ph current MW meas. MVAR meas.
Angle
applied (V) injected (A)
set @ Exp Actual Exp Actual

69.28 1.00 60 22.862 22.80 39.597 39.49

Test Inst. Used :

EQ: OMICRON CMC 256+ Serial No.: RJ921T


Cal. Due: 10/05/2018

Date :
TESTING ENGINEER SEC- CSD - Engineer

Signature: ___________________ Signature: ________________


Name : A. SALMAN FAREES Name :ENGR.FAYAZ AHMED