FINANCIAL PROPOSAL
Date: 01-12-2016
Cost Breakdown of Stair Rettrofitting:
Sl Item Unit Q'ty Rate Total Amount Remarks
1 Chemical Bolt NOS 6.00 11715.00 70290.00
2 New Steel Column NOS 2.00 129591.00 259182.00
3 Stair Retrofitting Work JOB 1.00 88560.00 88560.00
Amount required for stair retrofitting 418032.00
Cost Breakdown of Shed Retrofitting:
4 I-Beam Retrofitting JOB 1.00 440166.00 440166.00
5 Wire Bracing JOB 1.00 32614.00 32614.00
6 Column Replacing JOB 1.00 80982.00 80982.00
Amount required for shed retrofitting 553762.00
Total= ৳ 971,794.00
In Word:
Mode of Payment:
1 50% of the quoted rate should be given along with the work order.
2 20% of the quoted rate should be given after completion of the Item 01,02,03 & 06.
3 10% of the quoted rate should be given after completion of the Item 04.
4 10% of the quoted rate should be given after completion of the Item 05.
5 Rest of the 10% of the quoted rate should be given after final checking of the consultant.
Scope of Work:
1 All work will be done as per the initial submitted structural drawing. (See The Attachment)
2 Any further modification will be charged separately as per the current market rate.
Zakaria Mahmud