Bridge T Beam
Bridge T Beam
1. DESIGN DATA
A B C D
3. CALCULATION OF MOMENT
1.75
P1 = 10.503 t
P1 P1 P2 = 0.050 t
q1 q1 = 0.662 t/m
q2 = 0.440 t/m
B C
2.00
1.44
0.280 0.280
A B C D
Section 0 1 2 3 4 5
H (cm) 20 20 20 20 20 20
b (cm) 100 100 100 100 100 100
d' (cm) 2 2 2 2 2 2
h = H - d' (cm) 18 18 18 18 18 18
n 21 21 21 21 21 21
sa 1400 1400 1400 1400 1400 1400
Ca =h/((n.M)/(b.sa))^0.5 max 3.554 3.822 3.719 3.822 3.554
d 0.400 0.400 0.400 0.400 0.400 0.400
100nw (table of n value) 0.000 4.091 2.191 2.632 2.191 4.091
As =wbh 3.507 1.878 2.256 1.878 3.507
Use steel bar
D (mm) 12 12 12 12 12
units (nos) 5.0 5.0 5.0 5.0 5.0
Distance of bar 20.0 20.0 20.0 20.0 20.0
A (cm²) 5.655 5.655 5.655 5.655 5.655
Result OK ! OK ! OK ! OK ! OK !
A. MIDLE BEAM
2.60
0.20
0.80
0.30 1.25
0.1
0.35
1. LOADING ANALYSIS
523.61
523.23 392.57
261.90 D Diagram
261.52 130.86
0.19
-0.19
-130.86 -261.52
-261.90
-392.57 -523.23
37.400 37.40 37.40 37.40 -523.61 ton
0.00 0.00
M Diagram
17125.29
17125.29
29363.87 29363.87
36701.20 39151.83 36701.20
A L= 299.20 B
74.80
ME = Pa . Y + Pd . F
= 474.504 + 13014.076
= 13488.580 t m
ha = 1.86 m
Ha = P (ha + 2.00) ;P= 100 kg 1.45
= 386 kg/m 5.20
RA = RB = 1/2 * V1 * L
= 37.150 t
Ma = RA * 1/2 L - 1/8 * V1 * L²
= 2778.795 t m
2.60
0.20
0.30 0.80
1.25 1.45
0.1
0.35
Y = S(A.Y)/SA = 49.15 cm
Zr = Y + 125
= 174.15 cm = 1.742 m.
Distribution load :
Dd = 0.5 x D ; lb = distance of beam = 2.00 m
= 1.100 t/m
Line load
Pa = 0.5 x P ; lb = distance of beam = 2.00 m
= 6.000 t
2. MAXIMUM MOMENT
PERMANENT LOADING
Total moment = MD + ME
= 39151.828 + 13488.580 A B
= 52640.408 t m
1/2 L 1/2 L
TEMPORARY LOADING
Mps = Md + Ml + Ma + Mr
= 39151.828 + 13488.580 + 2778.795 + 29.181
= 55448.385 t m
3. SHEARING FORCE
Dead Load
RA = RB = 523.615 ton
Live Load
a). Load D
Pa = 6.344 t Pa = 6.344 t
Dd = 1.163 t/m
A 299.20 B
DA = Pa.Y + Pd * F
= 180.329 ton
Permanent load
Total D = 523.615 + 180.329 = 703.943 ton
Temporary load
Total D = 523.615 + 180.329 + 37.150 = 741.093 ton
4. CALCULATION MOMENT ON SECTION MAIN BEAM
1 2 3 4
A 74.80 74.80 74.80 74.80 B
299.20
37.40 37.40 37.40 37.40
LOADING ANALYSIS
1 523.61 37.400 3.494 19583.185 2443.354 0.389 37.400 0.000 14.541 0.000 17125.289
2 523.61 74.800 3.494 39166.369 9773.416 0.389 74.800 0.000 29.082 0.000 29363.871
3 523.61 112.200 3.494 58749.554 21990.186 0.389 112.200 37.400 43.623 14.541 36701.203
4 523.61 149.600 3.494 78332.738 39093.663 0.389 149.600 74.800 58.164 29.082 39151.828
X L-X
Y = (L - X) . X/L
X L-X
RA = RB = 37.150 t
V1 = 0.248 t/m
Max = RA . X - 1/2 . V1 . X²
1 2 3 4 d' ho
H h
Section units 1 2 3 4
SHEARING STRESS
1 f32
2 f32
7 f32
7 f32
0.5 x P
0.5*R[-10]C[1]
0
0
0
2*R[-1]C
3*R[-2]C
0
BRIDGE LENGTH - SAMBUNGAN VERTIKAL sisi kanan - kiri
BRIDGE LENGTH - SAMBUNGAN VERTIKAL sisi kanan - kiri
LEBAR JEMBATAN - SIDEWALK - BAHU JALAN
0
L=
2
#VALUE!
0
3 3 3 3
25 25 25 25
5 7 11 13
12
h
Kunjungi ilmubeton.com
mari sharing tekniksipil
dan memajukan konstruksi indon
Gratis https://www.ilmubeton.com/2018/06/kumpulan-gamb
video dari sponsor https://www.ilmubeton.com/2018/06/paket-lengkap-vide
n.com
onstruksi indonesia
on.com/2018/06/kumpulan-gambar-rencana-rumah-cad-dalam.html
.com/2018/06/paket-lengkap-video-tutorial-software_25.html