You are on page 1of 43

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/288773712

AC DC Railway Electrification and Protection

Conference Paper · November 2014


DOI: 10.1049/cp.2014.1439

CITATIONS READS

0 1,884

1 author:

R.D. David White


University of Birmingham
17 PUBLICATIONS   26 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Great Western Electrification View project

All content following this page was uploaded by R.D. David White on 30 December 2015.

The user has requested enhancement of the downloaded file.


AC/DC RAILWAY ELECTRIFICATION AND
PROTECTION

R D White
Chief Engineer
Technical Authority Electrical Systems Integration
Atkins United Kingdom
roger.white@atkinsglobal.com

Keyword: electrification, system voltages, feeding, return the domestic and commercial electrical supplies is that the
current, earthing. traction unit is able to change track position continuously.
This affects the characteristics and performance of the
power system and may be responsible for equipment failure
Part 1 AC 25kV 50Hz ELECTRIFICATION SUPPLY due to under voltage, overvoltage or overcurrent. If the
SYSTEM supply system is to have a high degree of security the
precise behaviour of the complete system must be known
1. High Voltage Electrical Supply and catered for in the design specification. If this is not
accomplished at the design stage then failures on the
The technical strength of all electrification schemes lies in locomotive [e.g. under voltage] or at the substation [e.g.
the fact that the prime mover is removed from the train; but Zone 3 protection trips] can cause serious operational
this is also its economic weakness. By taking power from a difficulties once the system has become live.
distribution network there is almost unlimited power
available which has been efficiently produced but the cost Electrical Supply and Railway Infeeds. Railway
of providing the fixed installations can only be justified electrification schemes draw a single-phase supply from the
where the traffic is heavy or frequency is high. national electricity HV supply system. It is inevitable
therefore that train loads of between 2-12 MW [PMCF or
The 25 kV A.C. 50 Hz electrification system has been phase angle control], will create unbalanced current within
developed specifically for railway traction purposes. The the HV 3 phase supply system, harmonic distortion and
main feature that separates this system from the voltage fluctuation to the supply system. In order to
conventional 3 phase and neutral HV distribution network minimise these effects on the HV supply authorities 3 phase
of the public supply authority is that the railway system is a networks, connections are normally made to the supply
single-phase system with one pole earthed. Even though authority network at 132/275/400 kV.
other railway administration have their own individual
electrification schemes the basic design of the systems is the Single phase transformers are connected to different phase
same. pairs of the grid supply at successive feeder stations along
the railway route, so as to provide the grid system with a
The 25kV rail network has been designed to meet the needs load that is distributed between the three phases.
of a fast, intercity, multi-track railway network carrying a
variety of trains at frequent intervals. This operation 1.1 Incoming Supply Arrangements Figure 1, 2
requires an overhead system that is inherently safe for
employees and passengers, reliable and provides a high Normally the incoming feeder circuit is supplied from the
degree of security of the supply to the traction units. This 132/275/400 kV grid networks. The level of the traction
will ensure that the electrification supply system is able to load and the availability of the grid will decide the point of
provide the required power levels to fulfil the performance connection. At the railway feeder stations two incoming
of the traction units. circuits are normally made available, both of the feeds
being capable of individually carrying the total traction load
The 25kV high voltage A.C. locomotive is a complex under normal traffic conditions, this will provide a power
element of the total A.C. power system configuration. A supply with a high degree of security. It is not sensible to
factor that makes the railway fundamentally different from provide an incoming feeder arrangement, which had a level
of security that was less than the 25kV overhead traction
system it is feeding. To increase the security of the supply 1.2 Feeder Transformers ‘Classic’ Feeding
the railway 25kV busbar are fed from independent parts of Arrangement of the Overhead Line
the H.V. network or by two H.V. busbars being fed
independently by the H.V. system. If there is a failure on 10 MVA 132 kV/25 kV fixed ratio [UK Network Rail] This
one of the supplies the fault does not interrupt the supply to transformer is normally used on suburban electrified lines.
the second railway feed [see Figure1]. The two railway The transformer is usually oil immersed and naturally
feeders could be independent or may be banked with 33 kV cooled, if an oil circulating pump and forced air cooling is
or 11 kV transformers feeding local industry or distribution installed the rating can be increased to 14 MVA.
networks.
18 MVA 132kV/25 kV variable ratio [UK Network Rail]
If there is a total loss of supply at a feeder station, supply to
the overhead railway network is transferred so that the It is necessary to adjust the transformer tap setting, to give
adjacent feeder station supplies power up to the non- the most suitable no-load voltage, this is determined by the
functioning feeder station. This new feeding arrangement characteristics of the incoming supply feeder. Once set it is
will give rise to loss of train performance due to the only necessary to adjust the tap setting if the incoming
increased voltage drop between the operational feeder power system characteristics are significantly altered. The
stations and individual locomotives. Any loss in time to the transformer is usually oil immersed naturally cooled; if oil
traction unit, due to the outage of a feeder station should be circulating pump and forced air is installed that rating can
recoverable in the next normally fed feeding section. be increased to 26.5 MVA.

Figure 1 Typical Supply Feeding Arrangement for a 25kV Electrified Railway

400 kV
Busbar Main

400kV
Busbar Reserve
Three Phase 400kV Grid Circuit

Three Phase 400kV Grid Circuit

© Copyright R D White 2006


Circuit Breaker Normally 400/25kV 400/25kV
Closed
Isolator

Switching Isolator
25kv Railway Supply
Figure 2 Typical 25kV Feeding Section Normal Feeding

Feeder Station Feeder Station


2x18MVA Intermediate 1x18MVA
Intermediate Mid Point
Track Sectioning Cabin Track Sectioning
Track Sectioning Cabin
Cabin

132/25kV Transformer

Circuit Breaker Normally Open

Circuit Breaker Normally Closed

Neutral Section Copyright Dr R D White 2002

1.3 Feeder Transformers ii. BS EN50122-1, Railway applications - fixed


‘Autotransformer’ Feeding Arrangement of the installations, Part 1: Protective provisions relating
Overhead Line to electrical safety and earthing
iii. BS EN50122-3 Railway applications - Fixed
40 to 80 MVA 400kV/50 kV installations - Electrical safety, earthing and the
Single Phase transformer impedance is typically return circuit - Part 3: Mutual Interaction of a.c.
specified to limit the maximum fault currents on the and d.c. traction systems
25-0-25kV Autotransformer Systems to 10-12 kA. This iv. BS 7671, Requirements for Electrical
level is specified due to the characteristics of the Installations. IEE Wiring Regulations Seventeenth
railway system and may be specified to prevent damage Edition, BSI, 2008.
to signalling circuits, limit the level of voltage induced v. BS EN62305 pt 1-4, Protection against Lightning,
in telecommunications cables under fault conditions, vi. BS EN50388, Railway applications — Power
and limit the touch potential to earthed parts of the supply and rolling stock — Technical criteria for
supply systems. the coordination between power
supply(substation) and rolling stock to achieve
interoperability
2. Earthing of 25kV Electrified vii. BS EN50119 Railway applications -Fixed
Railway [Figure 3]. installations -Electric traction overhead contact
lines
The 25 kV railway overhead system is a single pole viii. Guidelines for the Design Installation Testing and
distribution network with the neutral at the feeder Maintenance of Main Earthing Systems EATS 41-
station earthed. It is vital therefore that the earthing 24 1992.
arrangements of the distributed return conductor rail ix. BS 7430, Code of Practice for Earthing, BSI,
network and of the traction units conform to standard 1998.
recommendations. x. Electricity Council Engineering S 5/1.

3. UK and European Standards


i. IEC 60479-1 2005 Effects of current on human
beings and livestock.
LV Networks Network Rail Standards

xi. BS EN50310, Application of equipotential i. NR/SP/ELP/21085 Specification for the design


bonding and earthing in buildings with of earthing and bonding systems for 25kV a.c.
information technology equipment, BSI, 2006. electrified lines
xii. BS EN50310, Application of equipotential ii. PAN 0102 Earthing and Bonding for AC
bonding and earthing in buildings with Electrification Schemes applying Common
information technology equipment, BSI, 2006. Bonding
xiii. Technical Specification 41–24. Guidelines for iii. AC Traction Supplies to British Rail ER P24
the design, Installation, Testing and [1984] Electricity Association recommendation.
Maintenance of Main Earthing Systems in iv. NR/GN/ELP/00015, Signalling Power Supply
Substations, Energy Networks Association, Design
1992. v. NR/L2/TEL/30034, Radio Mast Lightning
xiv. HD637, Power Installations Exceeding 1kV a.c., Protection and Earthing System, Network Rail,
CENELEC, 1999. issue 02.
xv. IEC 60364-1, Low Voltage electrical vi. NR/SP/ELP/21106 25 kV a.c. System
installations - Part 1: Fundamental principles, Protection Calculations
assessment of general characteristics, definition, vii. NR/SP/ELP/21036 Specification for 25kV
IEC, 2005.Recommendation Booster Transformers for a.c. electrified lines
xvi. K-27, Bonding configuration and earthing inside viii. NR/SP/ELP/21078 Specification of design of
a telecommunication building, ITU-T, 1996. the Return Conductor Systems for AC
xvii. ITU-T Directive Vol II Protection of Electrified Lines
telecommunications lines against harmful effects ix. NR/SP/ELP/21074 Overhead Line Equipment
from electric power and electrified railway lines; Allocation design
Calculating induced voltage and currents in x. NR/GN/ELP/27010 Guidance for compatibility
practical cases between electric trains and electrification
xviii. ITU-T Directive Vol VI Protection of systems
telecommunications lines against harmful effects
from electric power and electrified railway lines International Standards
Danger, damage and disturbance
i. Technical Specification 41–24. Guidelines for
Group Standards the design, Installation, Testing and
Maintenance of Main Earthing Systems in
i. GM/RT/1000 Compatibility between Electric Substations, Energy Networks Association,
Trains and Electrification Systems 1992.
ii. GE/RT8023 Compatibility between Electric ii. HD637, Power Installations Exceeding 1kV a.c.,
Trains and Electrification Systems CENELEC, 1999.
iii. GL/RT1254 Electrified Lines Traction Bonding iii. IEC 60364-1, Low Voltage electrical
iv. GE/GN8600 Guidance on the Conventional Rail installations - Part 1: Fundamental principles,
Energy TSI assessment of general characteristics, definition,
IEC, 2005.
Group Standards Withdrawn 07 12 2013

v. GE/RT8016 Verification of Electrification Technical Specifications for Interoperability (TSIs)


Systems and Interactions with Other Systems
vi. GM/RT/1031 Electromagnetic Compatibility The formal definition of interoperability in the
between railway Infrastructure and Trains Interoperability Directive 2008/57/EC is "the
vii. GM/RT1042 Protection of 25 kV a.c. Overhead ability of the rail system to allow the safe and
Line Equipment from the Effects of the uninterrupted movement of trains which accomplish the
Operation of Steam Locomotives required levels of performance
viii. GL/RT1253 Mitigation of DC Stray Current
Effects i. High speed TSI ENERGY
ix. GE/RT8016 Verification of Electrification ii. Conventional TSI ENERGY
Systems and Interactions with Other Systems iii. High speed TSI RST
iv. Conventional TSI RST
Figure 3 Earthing and Bonding in AC Electrified Railways

Stage 1 & 2 Earthing and Bonding Principles


Open Route Section of an Electrified Railway

*Grid Site Earth Potential Rise: Calculations required for all


interconnections between the railway and traction return system

Grid Site Aerial Earth Wire


*Earthing Connection agreement is required with
the National Grid Operator
Feeder Station
25kV
Grid Tower

Substation

Public / Non-Railway
Local Structure
Earth
Traction Return Rail

Radio Antenna Telecoms Screening Conductor


Copper Signalling
External Utilities
Earth Mat
Track circuit (e.g. Water,
or Axle Telecoms. Gas)
See Note Counters
Telecoms. PSU

See Note
5&6
Signalling PSU
Conducting

5&6
Telecomms. Path Gapping
Local Sheathed Cable
Point Machine Structure
Public / Non-

Gapping

Earth
Railway

Earth

External
MV Power Cable earth

LV/MV Cable Screens

Non-Traction Earth (NTE)

~1km typical
Track
Lightning Earth Pit Structures
Conductive Fences /
Handrails / Walkways
25kV Earthing and Bonding Principles
Stations, Viaducts and Tunnels of an Electrified Railway
Viaducts Tunnels Stations

Public / Non-Railway
~1km typical Note 7 ~1km typical Note 7 Cross Bonding either
Aerial Earth Wire side of Station Structure

25kV

Reference Drawing 4
Railway Return Current Bonding Principles
Local Structure
Earth

External Utilities
Metal Pipes (e.g. Water,

See Note
Gas)

7&8
Signalling
Radio (see note 6) Telecoms Screening Conductor Metal Trays,
Antenna Cable
(see note 3) Conducting
Containment
Path Gapping
Track circuit + Catwalk
or Axle Telecoms. (see note 6)
Counters Station
MV / LV External
Telecoms. PSU Metallic
Earth Signalling PSU earth
MV Power Cable Equipment Power
Gapping
Telecomms. Supplies Power Electrical
Local
Point Machine Structure Sheathed Cable Apparatus Cable Earth
Auxiliary Comms, Gapping
Earth Substation Vids, PA, etc

See Note
See Note

7&8
7&8
Station Main Earth Bar
Two bonds
required for
redundancy

Non-Traction Earth
(see notes 1,2,3,4) Lightning
Viaduct Protection System
Structures
Lightning Earth Pit Conductive Fences / (see note 5) Station
Tunnel Handrails / Walkways
Station Earth
Structures Structures Mat
System Overhead Line
The main factor which must be considered on an Voltage [kV]
earthed electrification system is the voltage level of < 5 mins

exposed metal in relation to the general mass of the


earth. Under normal operating conditions this should 29 U max2 [29.0 kV]

be limited to 25 volts [under the European Directive U max1 [27.5 kV]


27
EN 50122-1 this has been increased to 60V], however,
under fault conditions the limit rises to 670V for U nominal [25 kV]
25
200ms.
23
Electrical Supply System Recommendation and
Standards. The supply system parameters for the 21
interface with a high voltage transmission system at the
point of common connection with the nearest 19 U min1 [19.00kV]

non-railway consumer are specified for the UK rail


U min2 [17.25kV]
system in the Publication from the Associated 17 < 10 mins
Engineering Recommendations P24.
Details of voltage limits, variations, limits of unbalance Time in Minutes
and harmonic distortion are detailed below:
Figure System Voltage Variation
4. Supply System Parameters
Additional Requirements for Network Rail: Under
4.1 A voltage variation produced by the extreme conditions, where a supply point is completely
traction load at the point of common out of service, the traction equipment must operate down
connection:- to 12.5 kV for up to 2 minutes and 14 kV for up to 10
minutes. The frequency of the supply system will
 The voltage change caused by the load changes typically remain within the range of 50 Hz +/- 1%.
with a cyclic variation of greater than two hours is
limited to no more than 3%.
 4.3 System Frequency
 The voltage change caused by load changes with
cyclic variation of less than two hours but greater The system has a nominal frequency of 50Hz with
than two minutes is limited to a step of 1.5%, or a limits specified by the electrical generating supply
ramp of 3.0% over two seconds, limits are industry. Typically nominal frequency is 50Hz with a
reduced by 25% at 132kV. variation of plus or minus 0.5Hz. Ref G5/4 Electricity
Council Recommendations.
4.2 System Voltage Variation BS EN 50163
4.4 Harmonic Distortion
Definition of operating 25kV 15kV
System voltages The maximum value of voltage distortion due to any
odd and even harmonics have been slightly increased.
Umin2 lowest non permanent 17.5kV 11.0kV
voltage duration 10min, The maximum value for Planning Levels of Total
Umin1 lowest permanent voltage 19.0kV 12.0kV Harmonic Distortion for 20kV to 400kV is 3%.
duration indefinitely,
Un nominal voltage designed 25.0kV 15.0kV Compatibility Limits have now been added to the
system value, recommendation for system voltage 66 and 132kV
Total Harmonic Distortion is 5%, and 275 & 400kV is
Umax1 highest permanent 27.5kV 17.25kV
3.5%.
voltage duration indefinitely
Umax2 highest non -permanent 29.0kV 18.0kV
voltage duration 5 min.
4.5 Electricity Supply Tariffs
Some electric traction manufactured prior to the
introduction of these limits are not compatible , yet are The tariffs for traction supplies are not specific and
authorised to run on the network. may be negotiated by the railway company which
purchase the supply. Therefore if an intercity passenger
network is responsible for the purchase of the electrical
supply, they may negotiate a price which benefits their i. Maximum Demand Charges. Maximum demand
daytime traffic in preference to a freight haulier whose charges are made by the supply authorities, and
main traffic is over night. The benefits of this type of relate to the maximum demand required by the
bargaining may well place a railway’s freight business railway electrification system at the times of the
at a disadvantage. There are a number of parameters supply authority’s systems maximum demands.
which may be taken into consideration when a tariff is This cost is necessary to provide the capacity in the
made between a supplier and a customer. generating and H.V. transmission system, which is
only required at the periods of maximum demand.
With Electricity Power Supply Industries being
privatised, the traditional way electricity is purchased ii. Distribution Charge [within the privatised
has changed. The electricity can be purchased in some power supply network]. Privatisation of the power
cases from one of many suppliers and even the railways supply network brought about separate companies,
wholly owned power generation system. The costing the suppliers of electricity, the national distribution
therefore has become more complex and may involve a network [National Grid], and the regional
number of factors. [Operation within the UK: Unlike distribution networks [Regional Electricity
the majority of industries Network Rail purchases its Companies].
electrical supply from the two generating authorities,
Powergen and National Power in England and Wales,
and Scottish Power and Hydro Electric in Scotland.] 4.7 Power Factor of a Non Sinusoidal
Power System [figure 4]
4.6 Typical Charges for a Railway may
typically include:
The supply system is not truly sinusoidal and therefore
Data Collection and Metering Cost [1%] it is necessary to address the effect of the harmonic
This covers installation and maintenance of metering distortion on the power factor of the system. The
equipment. harmonic currents that flow in the system need to be
taken into consideration when assessing the Volt-
Connection Charge 12% Amperes. The harmonic component of the supply
This includes two components parts covering: system will reduce the effective power factor of the
system below unity.
 Maintenance of the Supply Point
 Ongoing cost of the installation spread out over The tariff rates are structured to encourage consumers
the life of the site to maximise their power factor, and hence improve the
utilisation of the installed capacity. For example, a
At each supply point the authority provides the H.V. power factor of 0.8 causes an increase of 30% in VA
switchgear, 132/25 kV transformer, protection capacity compared with the unity power factor.
equipment.
The more recent traction units are designed with an
Unit Cost [Energy 82%]. The cost of energy [kW] input pulse converter that will draw power factor that is
provided by the electricity authority is related to the very near to unity. The auxiliaries of the traction unit
basic cost of fuel. To improve the base loading of the and the passenger rolling stock may cause this factor to
supply system and reduce the peak loading, the supply reduce slightly.
authority provide different rates whereby energy can be
purchased cheaper at times of minimum demand.
Definition of Power Factor.
Distribution Costs [ 5%]
The charge made to a major consumer has to cover all
three areas. The use of the national and regional Power Factor = Real Power [unit watts]
distribution networks is normally charged to the Apparent Power [unit volt-amperes]
supplier who in turn includes this portion in the total
charge made on the customer. If the Railway Company Traction Unit Power Factor: The power factor of a
receives its supply from the 275kV supply there will Phase Angle controlled traction unit will vary from 0.5
only be a charge made to the national distribution to 0.85 this has an effect on the amount of reactive
network. power measured by the supply authority. In the UK the
supply authorities have not charged directly for reactive
Charges may be based on the following: power, however if in the future this policy is changed it
would be necessary to reconsider the power factor
taken by traction units.
The power factor of a pulse converters traction unit will The problem of three phase unbalanced loads on the
normally be close to unity. This is achieved by the supply system is that other consumers connected at the
control system of the pulse converter. In reality there point of common coupling will be affected by the
will be slight variation from 0.95 to 1. negative phase sequence currents and the consequential
voltage drops. The main risk from the NPS is in the
Figure 4 Variation of Power Factor with MVA load heating effect on A.C. motors and generators.

Limits of Unbalance: IEC Standard 34.1: This states


50 that, the limit of negative phase sequence voltage that
can be applied to induction motor terminals is 2% and
that A.C. generators must be capable of operating when
40 the circuit supplied absorbs a negative phase sequence
MVA
[NPS] current of not more than 5% of positive phase
Volt sequence component.
Amperes 30

Where there is a weak supply point it is necessary to


20
monitor the level of NPS, this is achieved with an alarm
that informs the electrical control that the limit is about
to be exceeded. It is necessary then to reduce the
10 operational traction loads to ensure that the level of
NPS is maintained within the prescribed limits.

Limits of NPS and Harmonic Distortion are detailed in


0.2 0.4 0.6 0.8 1.0 Electricity Council Recommendation [G5/4], recently
implemented [2002] by the Electricity Council
Power Factor

ii. Methods Applied to Reduce Unbalance


[figure 5]
4.8 Unbalance within the National Grid
Supply
Reduction in the level of unbalance in the power
system is a costly process especially if it has to be
An A.C. traction supply is a type of disturbing load in considered retrospectively. It is not always possible to
two respects, it inherently requires a single phase predict increased levels of load, however future
supply and secondly the locomotive transformer and increases should always be considered during the
rectifier have a non linear characteristic and therefore design stages of railway electrification.
draw a rectangular current waveform from the supply
which is rich in harmonics. The worst case is usually when one of the two
transformers is out of service and hence the second
A.C. traction supplies are single phase loads, these transformer at the feeder or [the next feeder station
supplies are connected between the line to line of the with second stage emergency feeding] takes the
public supply system. It is inevitable therefore that combined railway load. Some remedies could be
unequal phase currents will be drawn through the cheaper than providing extra railway in feeds:
public system. It follows that the voltage drop between
power stations and low voltage busbar will be unequal  two transformers at a supply point to another site
on the three phases. Any 3-phase customer fed from or a standby transformer can be provided;
that busbar will have unequal phase voltages.  Changes to the connection of the traction supply
transformers should be the first consideration
It is necessary to quantify this unbalance among the when it is required to relieve a disturbance;
three phases in order to specify limits and penalties  It may be that the railway can transfer some of its
customers must be prepared to pay if such loads are load to an adjacent and stronger supply point by
used. Classical ‘phase sequence component’ provides planning to move the mid point 25kV section
this by yielding the negative phase sequence [NPS] switch nearer to the weakened supply point;
voltage vector and this quantity is a useful and  Relief can be obtained by moving one of the
meaningful measure of the unbalance produced. proposed feeder stations;
 Balancers applied to the 3 phase network are the
only other solution to reduce unbalance
conditions. It is a variable unbalanced load and it Figure 6 Overhead Line Resonance
is applied to the network at either the 25kV or
132kV, in view of the cost of the equipment
involved and complication of installing such a
system an additional supply point may be
preferred.

Figure 5 Three Phase Balancers

4.10 Reactive Power Compensation

On A.C. railway systems the control of the catenary


voltage is important if trains are to perform to
specification without causing mal operation of
equipment or loss of performance, this can be achieved
by means of single phase compensators since the
maximum distance between substations is a major
factor which governs the voltage regulation of the
supply network.

Reactive power compensation has two principal


applications on A.C. railway electrification systems:-
4.9 Overhead Line Resonance [figure. 6,7,8]
 It enables the peak load from the supply
system to be increased and hence allowing an
Harmonic distortion to the network voltages is caused increase in the substation spacing.
by machine saturation effects and non-linear elements
such as thyristor power converters. Electricity Supply  It reduces the 3-phase unbalance caused by
authorities specify limits for total distortion which are the single-phase loading.
generally in the range 0.5 - 3%. The harmonics
produced by power converters can cause resonance of Compensation to existing railway networks may be
the power supply network due to the series/parallel applied at the start of the electrification project or be
characteristic of the overhead line, and the supply added when the load reaches a critical level. A major
transformer, this in turn can produce serious over advantage of compensation systems is that installation
voltages. The impedance of the supply system is of the equipment will produce only a minimum amount
required to be controlled with the use of damper [rc of disturbance to the flow of railway traffic on the
network] to ensure that the system impedance is such electrification system.
that potentially dangerous over voltages do not occur.
Future electrification schemes are likely to be designed
with longer traction feeding sections and also higher
substation loads. In some areas of the world where it is
not economical to provide extensions to the high
voltage networks, longer feeding sections will become
inevitable. For minimum costs and changes to the
existing high voltage network the use of compensation
networks will be necessary.

Figure7a Locomotive A.C./D.C. Waveforms

`Figure 7b A.C. Electrification System


Waveforms
Figure 8 Equivalent Circuit for A 25kV Electrification
Systems

AC 25kV Electrification System Equivalent Circuit

ESI Supply 25kV


Traction Supply
Point 50Hz
Transformer

Supply Overhead Line


Transformer
© Copyright R D White 2006

Figure 9 Classic Arrangement of the Overhead Line including Booster


Transformers and Return Conductors

Mid Point Connector Return Conductor


Booster Transformer

Grid Site Track Side Overhead line


Sub Station Feeder
Station

Steel Work Railway Fencing


Telecommunications Cables

Earthed Screening Conductor

©
Copyright R.D.White 01/04
Armour of Cables or Metal Pipes
5. 25kV Classic Feeding Arrangement These booster transformers are positioned at
approximately 3 km intervals, one booster is required
There are a total 8337km km in the UK figures 2014 for each 25 kV overhead track feed.

5.1 Electrical Supply Grid Transformers 5.4 Feeding Arrangement

The supply points for the railway electrification system 25kV single phase supplies are received from the
[25 kV] are normally provided at intervals of between supply authorities at railway feeder stations. The
40-60 km; this spacing is specified so that the overhead function of the feeder station [FS], Intermediate track
line meets the specification for voltage regulation on sectioning cabin [ITSC] and mid point track sectioning
the 25 kV system under worst case "second emergency cabin [MPTSC] are to control the distribution of the
feeding" arrangement. The electricity supply authority supply to the overhead line equipment.
normally provides incoming feeder at 132 kV, if this is
not available it is necessary to provide the supply at At the FS each incoming feeder has its own circuit
275 kV. With the supply being only single phase, the breaker on the 25 kV busbar, the two feeds can be
electricity supply authority may try to balance its load isolated with the use of the bus-section circuit breaker
by supplying feeds from a different phase at adjacent thus allowing both feeds to be independent of each
feeders. This will not eradicate all the problems other. The HV feed is then supplied to the overhead
associated with unbalanced loads, but it does help to line through the track feeder circuit breaker supplying
reduce adverse effect on the supply authority’s system. the feed for one main railway track in each direction
from the feeder station. It is necessary, therefore, to
The security of the supply to the overhead line is provide four track feeder circuit breakers for a two
paramount for the reliability and efficiency of the track railway system. This somewhat complicated
whole traction system. To achieve this level of switching arrangement does provide the operator with a
reliability it is normal for two supply points to be very versatile system under maintenance or outage
provided at each feeder station each being able to carry conditions.
the total traction load for the feeder station under
normal railway operating conditions. Mid point track-sectioning cabins [MPTSC] are
situated at the midpoint between feeder stations. The
5.2 Return Conductors function of the MPTSC is to provide electrical
separation between adjacent supply points. The
When considering a 25 kV supply system the track MPTSC also provides sectioning and track paralleling
feeding sections are only half of the total feeding for the 25 kV systems, this provides a high level of
arrangement. One of the running rails of each track security and the best feeding arrangements without the
carries the traction return current, these rails are all loss of supply. Intermediate track sectioning cabins are
bonded together and in turn bonded to each overhead positioned approximately half way between FS and
line structure thereby forming a distributed earthing MPTSC, their function provides paralleling of the
system and typically having an overall resistance to overhead line and sectioning similar to that of a
earth of less than one ohm. At the feeder station the MPTSC, except ITSC are not able to terminate a
return rails are connected to the neutral side of the feeding section.
feeder transformer.
Normal Feeding Figure 2
5.3 Booster Transformer Arrangement Under normal feeding arrangements each FS supplies
[figure. 9] the feed to a MPTSC in each direction. Further
sectioning and paralleling of the overhead line is
The return current in the distributed earthing system is provided by the ITSC situated midway between the FS
liable to cause an excessive amount of electromagnetic and the MPTSC. Under normal feeding arrangements,
induction into adjacent telecommunications circuits. therefore, it is necessary to have the bus-section
To minimise this current is constrained to return to the coupler in the FS and MPTSC ‘open’, this ensures that
feeder transformer in return conductors positioned near the feed from the FS to the MPTSC is ‘single ended’.
to the 25 kV overhead line and in such a way as to Under this configuration the 25 kV system fault level is
reduce the level of interference. The return current is limited to 6 kA, this restricts the interference and high
constrained to flow in the return conductor by booster voltages to earth in lineside track signalling and
transformers [current transformers] which have their telecommunications equipment. To cope with such
primary connected in series with the 25 kV line and high fault currents the switchgear is normally rated at
their secondary connected in series with the rail return. 12 kA. If small feeder transformers are used, it is
possible to operate them in parallel assuming that the Second Stage "Emergency Feeding" [figure. 11
phasing is common.
Second stage "emergency feeding" is when a FS has a
First Stage "Emergency Feeding" [figure 10] complete loss of supply. This could be caused by a
failure of the 132 kV feed provided by the electricity
First stage "emergency feeding" is when a single circuit supply authority, or a failure of the one or two feeder
outage occurs at a two-circuit supply point. The 25 kV transformers in the FS.
supply is maintained to the overhead line by closing the
bus-section circuit breaker. If it is necessary to It is vital that the 25 kV A.C. supply is maintained to
maintain a feeder transformer, the two incoming ensure that the railway service does not come to a
supplies may be paralleled by closing the bus-section standstill. This is achieved by isolating the faulty
breaker, this will ensure that during the changeover, as feeds/transformers, once this has been accomplished
the feeder transformer is being isolated, supply is the bus-section breakers in the FS can be opened and
maintained to both the feeding sections. the bus-section breakers in the adjacent MPTSC closed.
This will enable the supply from the two adjacent
feeder stations to feed right up to the non-supplying
feeder that has now become a MPTSC.
Figure 10 25 kV Emergency Feeding 1st Stage

Feeder Station Feeder Station


2x18MVA 1x18MVA
Intermediate Intermediate
Mid Point
Track Sectioning Cabin Track Sectioning Cabin
Track Sectioning Cabin

© Copyright R D White 2006


132/25kV Transformer

Circuit Breaker Normally Open

Circuit Breaker Normally Closed

Neutral Section

Figure 11 25 kV Emergency Feeding 2nd Stage

Feeder Station Feeder Station


2x18MVA 1x18MVA
Intermediate Intermediate
Mid Point
Track Sectioning Cabin Track Sectioning Cabin
Track Sectioning Cabin

© Copyright R D White 2006

132/25kV Transformer

Circuit Breaker Normally Open

Circuit Breaker Normally Closed

Neutral Section

Section Overlap
6. Autotransformer 25kV [figure 12] kV power transmission, yet being able to utilise the
standard 25 kV traction equipment. The
AT’s were first used for railway electrification design autotransformer works on the principle that the train is
in 1913 when the New York, New Haven and Hertford supplied between the +25kV and rail. The rail and earth
railway electrification was extended to New Haven. currents are then returned at 50kV to the adjacent
The design by Professor Scott was introduced to reduce autotransformer at either end of the section. The current
the line loss and the inductive interference on the in the traction unit [25kV] is therefore twice the current
11-0-11kV 25Hz electrification system. [Scott was also returning through the autotransformer and the auxiliary
the inventor of the Scott connected transformer] feeder cable [50kVThe operation of classic systems is
different from the autotransformer arrangements in that
The idea was then adopted by the Japanese in 1962 for the booster transformer is only energised when a train
the extension of one of their railway lines, at 25-0- is in section, whilst the autotransformer is energised
25kV system. Subsequently in 1981 SNCF adopted the whenever the supply is available in section and is
25-0-25kV for use on a section of the Paris-Lyon TGV independent of train position. In practice however most
line. This new arrangement proved so successful, that of the train current is supplied from the two adjacent
SNCF adopted it as the standard feeding arrangement autotransformers, making a power circuit where the
for each of their new TGV lines. current is supplied mainly in the catenary and auxiliary
feeder. The main advantage of the autotransformer
The railway industry in Europe and worldwide has system over the booster transformer system is that the
been under great commercial pressure from the airlines voltage drop in the supply system [nominally 50kV] is
industries. To compete with the airlines over 500- less, with the auto-transformer capable of supplying
1000km it has become necessary to increase the line more power with less system losses, providing there is
speed to 200-300km/hr. The rapid expansion of the a train in section.
motorway network has not been able to compete with
the growth in the road freight and passenger transport. The ideal connection for an AT System is to the
There is a requirement therefore to build high speed existing National Grid Substation with a high level of
passenger intercity lines and to upgrade existing 25 kV security of supply and high fault level. The figure 12
passenger and freight lines. shows a typical double circuit input from a 400kV
Super grid Supply Point. The primaries are connected
This necessity to increase trainload, operational speed, across two phases of the supply. The secondaries are
and the frequency of trains required the introduction of centre tapped the two poles connected to +25kV and –
a stronger and more rugged electrification distribution 25kV and the centre tap connected to rail earth.
system. Autotransformer has been introduced in a
number of countries including in Australia [Blackwater 50kV feeding arrangements of the overhead line can be
and Gregory Coal line], Chinese Railways introduced on railway networks where it is difficult to
[Datong to Qinhaungdao], Russia [Vjaz’ma to Orsha], obtain a feed from the country’s own electricity supply
Japan [Bullet Train], France [TGV Lines], Spain, network. The introduction of 50kV distribution with an
Belgium [TGV Lines], Hungarian State Railway [ Lake autotransformer feeding arrangement does enable the
Balaton] and New Zealand [North Island line]. distance between feeder stations to be increased
significantly, alleviating the problem of access to the
Currently the UK has Autotransformer systems on electricity supply network.
 HS1 (Channel Tunnel Rail Link)
 Thameslink 6.2 Electrical Supply Grid Transformers
 WCML
 Liverpool-Manchester – now in service from The substation transformers are typically 400/25kV, 40
Manchester to Newton-le-Willows – and the or 80MVA transformers with source impedance 15%
upgrade to LNE specified to limit the maximum short circuit current on
25kV systems to 12kA, this is dictated by the
Implementation on Great Western Electrification, requirement of a higher power for increased trainloads
Crossrail and HS2. and increased speeds of inter city trains.. The track
feeder circuit breakers are typically rated at 1200A and
6.1 Principle of the Autotransformer 12kA for short circuit duty. Auto-transformers are
typically rated at 10MVA and impedance 0.17+j0.92
System ohms at 50 Hz [CCITT].
Autotransformer supply schemes are increasingly used
for A.C. electrification to take advantage of the 2 x 25
6.3 Autotransformer Versus Classic
Feeding Arrangement The feeding of a four-track railway is more complex
with the four track electrified railway will normally be
The main advantage of the auto-transformer system split with two fast and 2 slow tracks, theses lines can
over the booster transformer system is that the voltage either be fed separately [2 by 2] or in parallel [4 x1].If
drop in the supply system [nominally 50kV] is less, the slow and fast lines are separated there is a
with the auto-transformer capable of supplying more requirement to install two autotransformers at each AT
power with less system losses, providing there is a train site, on the other hand if all tracks are fed in parallel
in section. only one autotransformer is required. NR are currently
utilising protection system on Great western that is
based on a rationalised mesh connected design.
6.4 Feeding Arrangement of the
Overhead Line [fig13] The overhead line is sectioned at neutral sections
located at the feeder stations and at mid points between
Single Phase transformer impedance is specified to feeder stations. First stage emergency feeding requires
limit the maximum fault currents on the 25-0-25 kV the closure of the mid-bus-section circuit breakers at
A.C. system to typically 12kA. It is the reduction in the the feeder station.
source impedance of the electrical supply and the
reduction in the overhead line impedance [the removal A complete outage at a feeder station will require the
of booster transformers], that enables the auto- closure of the mid-bus-section circuit breakers at the
transformer feeding arrangement to supply longer mid point, the opening of the bus section breakers at
feeder sections when compared with the ‘Classic’ 25 the feeder station, the section of track is then fed by the
kV 6kA system. adjacent feeder stations.

The most commonly used AT system in use is two The auxiliary feeder conductors [-25kV] act as the
track high speed railway, using a two track mesh return path to the feeder station at 50kV, which reduces
feeding arrangement with AT’s spaced at typically 5 the level of the supply current and acts to suppress the
km. The feeding arrangement is such that when a fault railway magnetic fields and subsequent induced
occurs on either feed, both feeds are disconnected. voltages into lineside conductors.
With the feeds electrically isolated the track feeder
circuit breakers are closed. The feed with the fault will
immediately open, the circuit can then be isolated
leaving the remaining circuits operational.
Figure 12 25-0-25 kV Electrification Autotransformer

Grid Substation
Double Winding Transformer
Secondary 2x25 kV 25 kV Current

50kV Current
400, 275 kV
50Hz

Autotransformer Catenary and Contact wire Autotransformer


2x 25kV 25kV Catenary and Contact wire 2 x 25kV
25kV
50kV

25kV Return EarthedBonded


ReturnEarthed Running Rails
BondedRunning

25 kVkV
-25 Auxiliary
Return Feeder Wire
Conductor

© RDWhite3/99
© RDWhite 01.04

Autotransformer Feeder Station Autotransformers at Autotransformer Midpoint Section


5 to 10 km spacing

Auxiliary Return
Auxiliary Feeders
Return Feeders

Four-track railway feeding


arrangement in parallel

Neutral Section
Feeder Transformer

Circuit Breaker Insulated Overlap


Normally Closed © Copyright
© CopyrightRR.D.White
D White 2006
Circuit breaker normally open

Figure 13 Typical 25-0-25kV Four Track Autotransformer Feeding Arrangement


7. Neutral Sections and Section Static Clearance: Static clearances being defined as
Insulators the clearance between any part of the energised
overhead line and a fixed earth structure.
Many neutral sections in the UK utilise section
insulators, glass fibre rods are used, the rod is vacuum Passing Clearance:
impregnated with silicon rubber, ceramic beads are Passing clearances being defined as the clearance
then threaded onto the glass fibre rod, silicon rubber is between (a) any part of the energised overhead line and
then inserted between the ceramic beads to provide a fixed earth structure as a train passes through the
flexibility. Ceramic beads are used because of the section or (b) earthed part of the traction vehicle and
insulating properties thereby providing the isolation at any part of the energised overhead line.
not only neutral sections but also section insulators.
This type of insulator is used because the design is such Electrical Clearance on UK Network
that its dynamic performance is similar to that of the
length of contact wire which it replaces. This specification required a total headroom above the
kinematic load gauge of 680 mm. In 1962 the British
Arthur Flury Section Insulators Railway Network revised the clearances following tests
and service experience:-
The development of polytetraflourethylene (PTFE) and
glass fibre an insulating materials enabled the design of 200 mm static clearances
neutral sections to be drastically changed. They now 150 mm passing clearances
consist of fibreglass with a ptfe sleeve over which are
threaded alternate beads of hydrated aluminia and These reduced clearances along with new resistant
PTFE. The hydrated aluminia provides a hard wearing supports for overhead line equipment beneath over
surface to the passage of the pantograph and the PTFE bridges and in tunnels, has enabled the minimum
provides the required flexibility. headroom to be reduced to 175 mm thus considerably
reducing the cost of obtaining electrification
clearances. Where there is insufficient headroom to
allow normal catenary/contact wire arrangement, i.e. at
over bridges or tunnels, the research and development
work has shown that good current collection could be
achieved by two contact wires supported side by side.
This design also prevents damage to the catenary wire
[aluminium] with bird strikes in tunnels etc.

In 1974, there was a continued investigation into the


possible reduction of electrical clearances. It was found
that surge levels and 50 Hz voltage withstand were
governed by the electrical field stress between the end
fitting on the support arm for the contact wire and the
roof of the over bridge or tunnel. It was then shown that
redesign of this end fitting into semi-circular shape
thereby evenly distributing the electrical stress, enable
the surge and 50 Hz voltage withstand levels to remain
the same whilst reducing the overall clearance. This
development has enabled the clearance to be specially
reduced to

95 mm static clearance
8. Electrical Clearances 70 mm passing clearance

The electrical clearances for overhead electrified The passing clearance from the contact wire to the
railways were originally based on the UIC Kinematic load gauge was also reduced to 125 mm.
recommendation for 25 kV 50 Hz systems were defined The specially reduced clearances are adopted in cases
as follows ( reference BSEN 50119) :- of exceptional difficulty or where great expense would
be incurred in creating greater headroom. It was also
270 mm static clearances necessary to add an additional 25 mm for increased
150 mm passing clearances uplift of the contact wire at speeds above 60 km. hr-1.
Enhanced Normal Reduced Special
Reduced

25kV AC Static electrical 600 mm or 599 – 270 mm 269 – 200 mm 199 – 150 mm
electrified clearance greater
lines

Passing 600 mm or 200 mm or 199 – 150 mm 149 – 125 mm


electrical greater greater
clearance

1500V DC Static electrical 500 mm or 499 – 150 mm 100 mm N/A


electrified lines clearance greater

Passing 500 mm or 100 mm or 99 – 80 mm N/A


electrical greater greater
clearance

Fixed Bridge 200 passing


arm and 270 static

circumstances and to perform an open-close-open


9. 25kV Distribution and Supply sequence [auto-reclose] on a fault in others.
Protection Equipment Figure 15
The successful achievement of these duties relies upon
the availability of good mechanical design to meet the
Protection of electrical equipment is two fold, firstly it demands of opening and closing the circuit breaker
limits the damage to plant caused by faults or excessive contacts, and good electrical design to ensure that the
overloads and any consequential damage that may circuit breaker can satisfy the electrical stress.
arise, it also provides protection for personnel who are
working on or in the vicinity of the power system. During the opening and closing sequence an electric arc
occurs between the contacts of the circuit breaker, and
Protection in most cases cannot prevent faults from advantage is taken of this discharge to assist in the
occurring but can limit their effects. Protection is able circuit-interruption process. For instance, in an A.C.
to prevent overloads, which would exceed the design network, the arc is tolerated in a controlled manner
ratings of the supply network and is able to prevent until a natural current zero of the waveform occurs
interference with or damage to other utilities, either by when the discharge is rapidly quenched to limit the
induced currents corrupting communications or by reaction of the system to the interruption.
stray return currents corroding steel structures, water
and gas mains. The Vacuum Circuit Breaker Figure 15 The first
research into vacuum circuit breakers was carried out
between 1926 and 1931 at the California Institute of
Circuit Breakers. Technology. Although a number of laboratory models
were produced, the technology at that time was
The purpose of a circuit breaker is to ensure the inadequate to produce practical consistent devices;
unimpeded flow of current in a network under normal consequently the work was abandoned.
operating conditions, and to interrupt the flow of
excessive current in a faulty network. It may also be A revival of interest in this type of breaker by the
required to interrupt load current under some General Electric Company [USA] and ERA [UK] led
to the development of viable power devices having
characteristics far superior to existing forms of circuit
breakers.

Figure 14a Vacuum Circuit Breaker Spring


Actuator

Originally VCBs were developed with spring actuators,


VCBs have now been developed with innovative
permanent magnetic actuator. This facilitates a drastic
reduction in the number of parts, thus high reliability
and sturdiness. An electronic controller with sensors
monitors all the functions of the circuit-breaker and its
own functional reliability. This new technology
provides the optimum solution for extremely high
number of switching operations including freedom
from maintenance as a standard feature.

1 Lever shaft 5 Plunger


2 Proximity sensors 6 Opening coil
3 Closing coil 7 Emergency manual opening
4 Permanent magnet
Figure 14b Section of the operating mechanism and
pole part of the circuit breaker

( ref. E. Dullni, H. Fink, C.Reuber A VACUUM CIRCUIT-


BREAKER WITH PERMANENT MAGNETIC ACTUATOR AND
ELECTRONIC CONTROL)

Figure 15 Classic 25kV Protection Arrangement


SF6 Circuit Breakers
The SF6 circuit breaker uses the ability of the
colourless, odourless, tasteless, non-toxic, chemically
stable gas as a quenching medium.

The outstanding characteristic of the SF6 was its


chemical inertness under normal conditions.
Realisation that it also possesses compressive and
thermal absorption properties, which are sufficiently
different from those of other interrupter media such as
oil and air, makes it possible to utilise it in an
interrupter environment. These characteristics have led
to the development of the puffer, suction self
pressurising and rotary arc interrupters.

However SF6 is classed as a “Greenhouse Gas” and is


therefore subject to the Greenhouse Gas Regulations
2009. This has made it now undesirable for new
installations on Network Rail, both in terms of record-
keeping and training of staff.
10. Disturbances due to 25kV AC Electrification System

HV Supply
i. Unbalance of the 3 phase supply, RFI from the Distribution System
ii. Harmonics three phase supply, i. Current collection mechanism.
iii. 400kV earth faults ii. Operation with multiple contact wires.
iv. Rise of earth potentials iii. HV switching of the power system
iv. Resonance of the power system at MHz
25 kV Distribution System v. Excessive voltage stress across insulators
i. Charging of the overhead line at 1st resonant vi. Disturbances on the overhead line
frequency
ii. Switching on the a.c. power RFI from the Traction Unit
iii. Changes with the feeding arrangement, i. Transients due to raising the traction unit
iv. Degraded modes: outages of the feeder pantograph
stations; outages of booster transformers ii. Interaction of power system contacts earthing,
v. Magnetic fields wheel rail, rail to rail
vi. Line resonance effects iii. Operation of multiple pantographs
vii. 25kV earth faults iv. Switching of thyristors and semiconductors.
viii. Induced voltages into line-side cables
ix. Neutral sections RFI from the Track Circuits
x. Radio Frequency Interference. i. Track circuit current producing arcing poor
wheel to rail,
Traction Unit Disturbances ii. High voltage impulse track circuit
i. Inrush effects of the traction transformer,
ii. Characteristic disturbance switching, overlap
effect
iii. Production of 25kV system resonant
frequencies
iv. Radio Frequency Interference
v. Disturbance to signalling track circuits
vi. Return current systems
vii. Return currents and earth currents to third
parties.

Disturbance to Signalling Track Circuits


i. Ground voltages
ii. Immunity Concerns from traction return
current
iii. The immunity concerns are related to the
connection of 25kV systems to 132, 275 &
400 kV power supply networks. The interface
may produce high rise of earth potentials, and
interference due to lightning strike.
Part 2 DC RAILWAY ELECTRIFICATION 2.1 D.C. Conductor Rail Systems 600V and
SUPPLY SYSTEM 750V

1. Introduction With the lower D.C. systems voltages, it is usual to


have the traction power feeding arrangement at either
Railway electrification has in the past been dominated track level [light rail heavy metro systems] or via an
by overhead contact wire and D.C. third/ fourth overhead line [street running trams].
conductor rail electrification systems. The historical
reasons for this have been the success of the D.C. Third rail system is usually cheaper for surface lines’
traction motor and the necessity of a D.C. supply. insulation problems, the system voltage is 600/750 V
Mercury arc rectifiers were originally used to provide on the third rail [UK Network Rail, Singapore MRT]
rectification at substations with the D.C. power being
transmitted to the traction equipment by the conductor In fourth rail system [UK LUL] the positive conductor
rail or overhead wire. Success in producing mercury is at a potential of +400 V and the negative or fourth
arc rectifiers capable of being operated on board the rail at -230 V, this is a 630 V system. Underground
railway vehicle enabled railway A.C. electrification systems use a fourth rail to carry the return current to
system to become a reality in the 1950/60's. minimise stray traction leakage currents. Without the
fourth rail these leakage currents would cause corrosion
2. DC Traction System Voltages of buried water and gas pipes by electrolytic action.
The centre earth system minimises the voltage of
The conductor rail or overhead power supply is system voltage to earth, thereby reducing the risk of
designed to operate within specified voltage limits and injury to electric shock.
it is necessary that the traction unit is capable of
handling the voltage provided. The traction motors and With side contact system of ground collection the
control gear are required to be adequately insulated to conductor rail is fully shrouded by guard boarding
the maximum operating voltage of the supply network. except where the collector shoes makes contact.
Traction motors for D.C. systems are normally wound Underneath contact system has been used in the
for 600/750 V and connected permanently in parallel Docklands light rail, and Singapore MRT systems. This
for 600/750 V D.C. supplies, or connected in series requires the conductor rail to be mounted on insulated
parallel pairs for 1500 V D.C. operation. On 3000 V brackets and obviously is more costly than the third rail
D.C. supplies the traction motors are normally wound top contact system. In adverse weather conditions,
for 1500V operation and connected two in series on however much better current collection was obtained.
full voltage and as a result they are larger in diameter This system, like the side contact system, uses the
and more difficult to install under the low floors of running rails for the return current.
multiple unit stock. The establishment of D.C. supply
voltages have traditionally been chosen to meet the A further factor with third rail systems is that the return
needs of the D.C. traction motor control. current has to be carried by the running rails that may
also be required for automatic signalling. This
In the past the main advantage of the D.C. supply increases the signalling costs since some means has to
system compared to the A.C. supply system is that a be found of discriminating between the traction
less complex traction control system is required, currents and the signalling currents.
however with the advent of high power GTO's [gate
turn off thyristors], IGBT [insulated gate bipolar In bad weather the build up of ice and snow on the
transistors] and the microprocessor, 3 phase drives are conductor rails is a serious hazard and may be
becoming more common on both A.C. and D.C. sufficiently severe to cause the service to be withdrawn
electrification systems. With the advent of 3 phase as the collector shoes are unable to make contact with
drives the D.C. voltage is not a design requirement for the rails. In the third rail system the leakage currents
the traction engineer, due to the ability of the traction may be so increased that they cause an almost sustained
input converter to set the D.C. link voltage to the fault on the system and greatly reduce the efficiency.
inverter drive. It is likely therefore with new schemes
using three phase drives that other voltages could be 2.2 D.C. Overhead Contact Systems
used. 750/1500/3000 VD.C.

The use of electric power for traction purposes


naturally involves the transmission of power over
considerable distances; obviously this can best be
achieved by the use of a high voltage. When the
contact system is placed overhead, the voltage can be network. With light rail/supertram applications it is
increased and the danger to personnel is greatly usually only necessary to provide the supply at a couple
reduced. A greater substation spacing is possible, of points and therefore it can be obtained directly from
together with an improved system efficiency due to the the electricity supply utility.
copper losses being reduced [e.g. if the voltage is
doubled then for a given power the current is halved The A.C. switchboard, will have in addition to the
and hence the copper losses are reduced to one incoming breakers, local supply breakers and feeder
quarter]. breakers to other substations. The local supply
breakers provide the supply to traction
2.3 750V D.C. Overhead Metro/LRV transformer-rectifier units, and auxiliary step down
systems transformers, which are required in the immediate
vicinity.
It was in 1987 that the first low floor tram network
opened in Grenoble with a fleet of 20 TSF-2 trams 3.2 The Positioning of Supply Points.
supplied by GEC Alstom. Today the tram design
announced anywhere in the world is virtually certain to The number of feed points to the railway network will
be low floor vehicle. For new high platform light rail depend upon the size of the electrification system and
networks, production of high floor LRV continues. the capacity required at any particular point. On urban
mass transit systems EHV supplies may not be
3. DC HV Supply System [figure 23] available and space for substations and feeders are
difficult to obtain and expensive. It is sometimes
High Voltage Distribution System One of the main necessary therefore to provide the supply from local
drawbacks when using D.C. traction systems is the fact HV feeders 33/66kV supplies. This is convenient from
that electrical energy is universally generated by the supply authority viewpoint and provides a high
electricity supply authorities in the form of alternating degree of supply integrity, however it does raise two
current. It is therefore necessary in most instances for problems, voltage regulation and voltage harmonics.
the railway authority to provide its own high voltage
A.C. distribution network linking the lineside A typical breaker supply arrangement is given in
substations as well it own rectifier plant. This does Figure23 where one circuit breaker is connected to
have the effect of increasing the capital expenditure each side of the Bus Coupler Breaker which feeds step
when D.C. systems are compared to A.C. systems. down transformers [33kV/11kV] and the 11 kV
switchboard, these circuit breakers are equipped with
Substations are spaced at regular intervals; this usually the protections relays to protect the step down
results in the operation of a high voltage A.C. transformer.
distribution network linking the lineside substations as
well as the maintenance of the D.C. overhead system. The 11kV distribution network is provided throughout
Obviously this increases the capital expenditure when this system where all the passenger stations have 11kV
the various systems are compared. switchboards. At each station the 11kV is transformed
in the passenger stations typically to 415V 3 phase for
domestic supplies. To provide a high level of security
3.1 The High Voltage [HV] and Extra High
of these supplies duplication is provided at each
Voltage [EHV] Electrical Supply System. location.
The HV A.C. incoming supplies from a National Grid
or Distribution Network Operators [DNO], or Railway
Generators provide the feed for the D.C. traction power
substations. The local supplies for stations, tunnel-
cooling fans, auxiliary circuits including batteries,
chargers and uninterruptible power supplies [UPS] for
computers and signalling circuits, are provided by the
REC.

The electrical supply is fed to the railway at typically


132kV, 66kV or 33kV and the electrical power is then
on larger systems distributed through a separate A.C.
network at a medium voltage of 33kV, 22kV or 11kV
by the railway/metro. This supply is used to provide
traction power at regular intervals around the railway
Figure 23a Typical Feeding Arrangement 1500V D.C. Electrification System ( Heavy Metro)

Distribution Network
Operator

HV Busbar

AC Breaker

11 kV Busbar

AC Breaker Railway AC Breaker


11kV Ring
owned
Rectifier
Substation Rectifier
Substation

Rectifier DC
Rectifier DC
Breaker 1500V DC Busbar 1500V DC Busbar Breaker

Sectioning
Power Transformer
Point Circuit Breaker Normally Open

Rectifier Unit
© Copyright R D White 2006
Isolator Normally Open

Insulated Overlap

Figure 23b Typical Feeding Arrangement 750V D.C. Electrification System (Tram)

33/11kV Supply 33/11kV Supply

Power Transformer

Feeder Station Circuit Breaker Normally Closed

Rectifier Unit

Isolator Normally Open


Insulated Overlap or
Sectioning Gap

I/2 I/2

I/4
I/4

I/4 I/4
3.3 Positions of the Lineside Traction Sub- 4. Substation Electrical performance
Stations Specification [figure 24 and 25]
A detailed analysis is needed to establish the correct The detailed electrical performance of the substation
positions of sub-stations on the railway system, a has to be designed into the system at the outset, it is
simple mathematical approach has been included at the dependent upon the traction load specified by the
end of this paper. Having established the working operating business, and the level of supply redundancy
voltage 600V, 750V, 1500V or 3000V the exact required. Provision for future extension of the system,
position of the substation has to be decided. This the increase in train loads, and the change of type of
decision is made on the technical performance of the vehicles to be operated must also be considered.
power system, however it is also necessary to take into
account other factors which will determine the final In the design of a traction substation it is necessary to
choice, availability of land, position of junctions and take into consideration the following aspects:-
crossovers, the provision of road access up to the main
door of the building in order to facilitate the transport  The power factor of the converter unit and the
of spare items of plant and any necessary maintenance supply transformer on the supply network
test equipment.  Traction supply and converter arrangements
 The production of harmonics in the input A.C.
The most economic distance between substation is ( BS supply current, and the distortion to the input
EN 50388 (High Traction Power Classic ): supply voltage.

 600V D.C. is 2-3km Design specification for Greenwich Traction Substation


 750 V D.C. 3km, [Jubilee Line Extension]
 1500V D.C. is 2 - 8km
 3000V D.C. is 7.5- 12.5km  Rated capacity 2400kW
 Rated D.C. traction voltage 600VDC
 Rated D.C. traction current 4000A
The distribution voltage for D.C. overhead Metro and  Short circuit protection 40 kA 0.25 sec
Mainline systems is typically 1500V, 3000V, and  Transformer 22kV/415V
therefore requires less isolation and clearance than for  Rated Capacity 2½ MVA
A.C. electrification. The mechanical strength of the  Short circuit protection 40 kA 0.25 Sec
overhead line conductor becomes the main factor in
overhead design making the conductor sizes not
dissimilar between 1500 V D.C. and 25 kV A.C. Where
the power requirements exceed the capability of the
overhead catenary it is necessary to include parallel
feeds along the overhead masts. Connections are made
at regular intervals to the catenary to ensure good
current sharing.

The 3000 V system is applied almost entirely to the


main line system in order to maximise substation
spacing, with 750 V and 1500 V D.C. supplies
predominantly chosen for urban mass transit or light
rail systems.
Factors Influencing Substation Spacing:

 Maximum Permissible Voltage Drop


 System loading
 Track layout and return system
 Conductor Cross Section
 Circuit Breaker Tripping Current
 Control of Stray Current
Transformer Secondary 12 Pulse Switch Gear Overhead Line or Third Rail
Windings Converter and Busbars
Phase Displaced

50Hz 3 Phase
Line to Line

Vdc 12 Pulse

Return Running Rails


750V
1500
V dc
12 Pulse
Rectifier

20
mS
Figure 24 Transformer Rectifier Unit and Third Rail Connection

Figure 25 Performance of Substation Transformer Rectifier Unit


Reference EN50163 [Table 1,]

Table 1 600* 750 1500 3000


Definition of operating D.C. System Voltages
lowest non permanent voltage, 400 500 1000 2000
lowest permanent voltage, 400 500 * 1000 2000
nominal voltage designed system value, 600 750 1500 3000
highest permanent voltage duration indefinitely 720 900 1800 3600
highest non permanent voltage duration 5 min. 800 1000 1950 3900
UK Special Condition 400*

4.1 The D.C. Voltage Regulation.


represented as a source e.m.f., supply reactance and
The regulation of the substation is a vital characteristic supply resistance per phase.
of the D.C. electrification system. If the regulation is
too steep then the train will not have sufficient volts to
maintain train timetables. Raising the voltage at the
substation will provide a higher voltage on the load but [t] = Vm sin [t + ] source emf
may produce excessive voltages on no load conditions.
A lower regulation is achieved by reducing the the A.C. current which flows can be calculated as
impedance of the supply transformer, this however will
increase the short circuit fault current which will i = Vm [sin[t +  -] - [e -[R/L]t sin [ - ]]
require a higher rating for the circuit breakers and Z
converters. The optimum design is therefore a where Z = [X2 + R2]
compromise between regulation of the substation and L = supply and line inductance
the level of short circuit fault current. X = supply and line reactance
R = supply and line resistance
Advanced transformer designs using coupled-  = point in the cycle at which the short
secondary this allows low regulation over the normal circuit occurred
load range and yet limit the short circuit current. This  = tan-1 [L/R]
is achieved by using secondary windings which are = angular velocity of the supply rad/sec
coupled to achieve the correct short circuit current to
regulation relationship.
This analysis can be used to establish the instantaneous
DC Short Circuit Fault Current. The D.C. short fault current obtained from faults remote from the
circuit level is an important design characteristic of the substation itself, provided that a value of line
power supply system. The fault level must be of such a inductance and resistance can be established.
level that it does not interfere with normal train
operation. The level must be of such a level that the The value of the D.C. fault current can be achieved by
short circuit rating of the rectifier devices is not adding each of secondary line currents point by point
exceeded. The short circuit rating of the rectifier during the D.C. short circuit. With a 6-pulse system
devices is specified by the surge rating of the device this will include the inverse of the line currents shown.
The D.C. fault current obtained will be the typical fault
under a fault condition. It is also necessary to ensure current.
that the transformer windings are adequately braced
against stress brought about by short circuit forces. 4.2 Power Factor of the Transformer
Finally, the D.C. track circuit breakers must be capable Rectifier Unit.
of successfully interrupting any short circuit.
The overall power factor of the rectifier unit and the
A short circuit at the output of the rectifier terminals traction supply transformer are normally specified to be
applies a balanced three phase short circuit to the A.C. better than 0.9 p.u. [including distortion factor]
system, normal circuit theory can be applied to
establish the fault current which flows. The secondary
circuit of the transformer and rectifier can be
Power Factor = Irms [fundamental] x cos ] 33/66/132 kV it is normal to use 12 or 24 pulse
Irms [total] rectifiers to ensure compliance with G5/3.

4.3 The Traction Supply Transformer and Harmonics Produced in the Conductor or Catenary
Rectifier Arrangements. supply. The D.C. output voltage waveform produces a
ripple that is related to the pulse number of the
The pulse characteristic of the supply system is converter. This will therefore produce harmonics in the
primarily defined by the transformer winding and load current waveform that are typically related to
converter arrangement. A number of simple 300Hz, 600Hz, 900Hz etc. depending on the rectifier
arrangements of the transformer windings may be pulse number.
chosen with a 3 phase A.C. supply system to provide 6
or 12 pulse D.C. output voltage. Other ripple 5. Feeding Arrangement of the Third
frequencies may be achieved using two converters and Rail or Overhead Line
windings, which are phase displaced or wound in an
alternative star/delta configuration. With normal feeding arrangement the substations are
connected in parallel onto the traction conductor or
A 12 pulse rectifier therefore can be obtained by overhead supply. There is a D.C. circuit breaker at each
connecting two separately fed phase displaced, 6 pulse end of the feeding section to provide protection under
systems in series or parallel. On the other hand a fault conditions. Each substation feeds from a common
similar result can be obtained by using a 3 phase D.C. busbar through D.C. circuit breakers in both
winding transformer with one star and one delta directions, the feed is separated by a bypass isolator,
connected secondary winding. The arrangement will this is normally open and closed only when it is
provide the necessary 30o displacement of the supply to necessary to bypass the substation.
provide a twelve pulse ripple when the respective
bridges are connected in series or parallel. Normal Feeding Arrangement: This is where all of the
feeder D.C. circuit breakers are in service providing
Harmonics Produced in the Supply Network. The double end feeding of the section of traction supply.
rectifier works by switching the load current from one The isolator at each substation is normally open
phase to the next, this process is called 'commutation'. providing an isolated feeding section of traction supply,
If the transformer has leakage reactance the line current and ease of protection of the feeding section.
cannot switch instantaneously due to the effect of the
leakage reactance, this process is called 'overlap'. Tee feeding Arrangement: This is implemented at a
During the overlap period all devices are conducting in substation when a D.C. feeder circuit breaker at one
the outgoing and incoming arms of the rectifier. This end of the feeding section is open. The ‘tee’ feeding
will produce a short circuit on the input and the output arrangement is achieved by closing the bypass isolator
to the rectifier. allowing the remaining D.C. circuit breaker at the
substation to feed the traction supply in both directions.
The input supply voltage waveform and the output D.C.
waveform will therefore be interrupted producing a Single End Feeding Arrangement: Single end feeding
notch in the voltage waveform and oscillation due to arrangement on double end fed sections is a temporary
the RLC characteristic of the supply system. This has feeding arrangement following the loss of the feed from
the effect of distorting the A.C. supply waveform at the a track feeder D.C. circuit breaker. This mode of
point of common coupling. feeding is normally only temporary and if the feed
cannot be restored within a reasonable period of time it
The input current to the rectifier produces a stepped is normal that the traction supply reverts to ‘tee’
waveform due to the switching strategy of the rectifier feeding.
converter. The rectifier input line currents that are
associated with a 12 pulse bridge rectifier can be shown Bypass Feeding arrangement: This occurs when there is
by the Fourier Transform to be 11th, 13th, 23rd, 25th a loss of supply at the substation or the failure of the
with a less amount from the 5th, 7th, 17th, 19th. feeder D.C. circuit breakers in both directions, under
this condition the associated isolator is closed. The
Harmonic distortion levels are specified by the UK traction supply is provided from the feeder D.C. circuit
Electricity Council Recommendation G5/4 lays down breakers at the adjacent substations. In the case of
the limits of harmonic current that may be generated single end fed sections, it is necessary to close only the
back in the supply network. As a result of design appropriate bypass isolator.
predictions it is possible to decide whether 6 pulse, 12
pulse or 24 pulse will meet the supply authority’s Loss of supply from Transformer Rectifier Units: The
regulations. In urban areas with systems supplied at supply system is designed with more than one
transformer rectifier unit at a location. The traction UKs Southern was the first train operator in the country
supply is normally designed to operate with one to introduce regenerative braking on the third rail DC
transformer rectifier unit out of service at any location. network. Southern’s sister company, Southeastern
If the complete substation is lost, the substation should introduced its first regenerative train
operate as a track paralleling hut. in the next few days.

6. Regeneration After almost two years of planning and testing, the


Southern three-car Class 377(328) Electrostar trains are
Regeneration of the Traction Units now returning electricity back into the rail system when
it brakes, allowing other trains using the same section
AC drives have become very popular and proved to be of track to draw on that energy for power.
very robust when compared to D.C. motors. They are
also able to give a better acceleration; the braking is
greatly improved along with the high regenerative 6.1 Technical Merits of Regenerative
braking rates. The regenerate operation enables the System
energy consumption to be minimised and brake
maintenance to be reduced. Although there are fewer  Reduction of heat produced in underground metro
substations and the conductor cross section is reduced, systems;
the limit of the size of the third rail tends to be set by  Elimination of brake resistors;
mechanical considerations rather than electrical  Reduction of brake dust in tunnels;
problems.  Reduction of maintenance in tunnels;
 Improved efficiency of the Railway Network; and
The development of 3 phase induction drives has reduction in energy costs.
introduced higher power drives and the ability of
regenerative braking energy back into the supply
system. Three phase induction motors are attractive due
6.2 Disadvantages of Regenerative Systems
to the elimination of the D.C. commutator. This
 More capital investment in traction and supply
reduces the chance of mechanical breakdown and
equipment.
eliminates the need for maintenance. The induction
motor is able to develop more torque due to the control  More harmonics in the medium voltage supply.
system, the motor design and the fact that there is  Intelligent protection system on the supply and
increased space on the rotor. Size for size the induction traction equipment able to discriminate with
is more powerful than the equivalent D.C. motor, regenerating units.
consequently it has a higher power to weight and power
to volume ratio. The capital cost of introducing inverter 7. UK Standards
drives on traction equipment is close to D.C. drives,
therefore A.C. drives are financially viable and able to Earthing
produce a more superior performance.
BS 7430:1991 Code of practice for earthing
Currently there are a number of applications where BS 7671 Regulation for Electrical Installations
energy is being regenerated by traction units, with the BS 7361: Part 1:1991Cathodic protection Part 1 Code
energy [allowing for receptivity] being returned to the of practice for land and marine applications.
D.C. electrification network. This energy is then BS EN62305 Code of practice for protection of
utilised by other trains on the same network. structures against lightening.
BS EN50122-1 Railway applications fixed
Regenerative braking, returning energy to the supply installations, protective provisions relating to
system has been common place since the 1980 electrical safety and earthing.
including MTRC Hong Kong, MRT Singapore, 750V BS EN50122-2 Railway applications fixed installations
and Tram Systems. , protective provision against the effects of
stray currents caused by dc traction systems .
Ref Southern Press Release No. 125 02 May 2008
Southern is first to introduce third rail regenerative Electrical Supply System Recommendation and
braking Standards

Until now, energy released by trains during braking has The supply system parameters for the interface with a
been wasted in heating the braking resistors on the high voltage transmission system at the point of
train. common connection with the nearest non-railway
consumer are specified in the Publication from the Rail Insulation ( BSEN 50122-2)
Associated Engineering Recommendations G5/4
The railway normally uses the train wheels and running
System Voltage Variation: provisional European rails as the traction current return path to the DC
regulation EN 50163 [Supply Voltage of Traction substation, (except fourth rail systems). Where the rails
Systems], existing UK regulations GM/RC 1502. are not insulated from the sleepers, the earth return is
considerably more complex since the current may flow
System Voltage Variation: European regulation EN out of the rails and return at some other point (stray
50163 [Supply Voltage of Traction Systems], existing current). Most modern rail systems use high insulated
UK regulations [P 7/2, P8, P13/1,P16] rails to prevent the current from leaving the rails and
corroding metallic structures
*Future D.C. traction systems for tramways and local
railways should conform with system nominal voltage A very important aim when designing a DC electrified
of 750,1500,3000V railway is to control return DC traction current and
+In case of regenerative braking a voltage of 800 may avoid passing these currents through the reinforcement
be admissible of concrete structures, and in particular highly stressed
^In case of regenerative braking a voltage of 1000 may concrete structures to avoid causing damage to the
be admissible reinforcement through electrolytic corrosion.

8. Return Current Systems BSEN 50122-2 Criteria for Protection of Rails The
Running Rail is normally insulated from the sleeper /
The railway normally uses the train wheels and running concrete pad by the use of insulation pads placed under
rails as the traction current return path to the D.C. the rails with an insulation value in line with the
substation, [except fourth rail systems ]. The rails are European Standard EN 50122-2. (Table 1 Page 6; No
not insulated from the sleepers, structures on which added rail insulation 0.5 S/km for open formation and
they are fixed. The earth return is considerably more 2.5 S/km for closed formation). This level can be
complex than is at first perceived since the current that improved with the application of track insulation
flows out of the rails and returns at some other point, it mounting pads or polymeric insulation. This value of
is referred to as stray current. insulation however will reduce over time, due to
degradation of the track insulation. For closed
There are typically five earthing strategies in the way formation, improved levels of insulation can be
that the negative at the substation is connected to the achieved where the rail is to be embedded in the road.
running rails and these are detailed below: Note Design Limits should 10 times better than this.

Fourth Rail Systems: The level of insulation is determined not only by the
the problem relating to leakage currents is overcome by installation but the maintenance of the track bed. Every
the insulation of the fourth rail [London Underground effort should be made to minimise the risk of ballast
UK] coming into contact with the rails, since ballast,
especially when wet will reduce the insulation value of
Traction Return Current Systems the rails to earth.

 Floating System with Rail to earth shorting Hazards Associated with Rail Potentials
devices, Over Voltage Protection Device Lantau The track is insulated from ground to minimise leakage.
and Airport Railways Hong Kong and Dubai Introducing insulation means that voltages between the
Metro, Sydney Metro. rails and ground will occur. These voltages are a
 Floating System with Rail to earth detection and potential hazard to passengers and railway staff when
main tripping of the main circuit breakers, coming into contact with rail or anything connected to it
Singapore MRT. and the ground. Reduction of rail touch voltages can be
 Other Floating Earth Systems [Croydon Tram achieved by clamping the rail to ground if a dangerous
UK, Hong Kong LRT, Edinburgh Tram ] voltage is reached and resetting as soon as possible
 Rail System partially floating not intentionally afterwards. It is necessary to have quick detection of the
earthed [Network Rail UK] high voltage and then activate a "clamp", by a thyristor
 Drainage Diode earth, Hong Kong MTRC, device, GTO device or contactor, to short out the
Sheffield Tram, voltage.
 Floating & Diode Interfaces MTRC, DLR MML (
Manchester), LUAS ( Dublin Light Rail) Diode Earthed System (Figure 28)
 Floating Fourth Rail London Underground
This arrangement includes a diode at the traction
substation which is connected to the substation local
earth. The inclusion of the diode will cause the rail
potentials to be either at zero (diode is conducting) or
above zero if the diode is reverse biased.

Characteristics of the diode earth system:


 Stray current is minimal where there is no rail
leakage
 Where there is rail leakage the diode returns this
to the substation
 The diode acts as a unidirectional connection to
remote earth
 Diode conducts with negative rail potentials (
typically at substations and regenerating trains)

There are particular difficulties in operating a diode


earthed system in conjunction with regenerative trains,
which may produce negative rail potentials and hence
encourage diode conduction.

Floating Negative Return Current System (figure


29)
In this arrangement there is no intentional connection
between the traction substation negative and the
substation earth. The effect is to produce a system that
floats about the remote earth potentials.
Earth Wire

Telecoms PSU

Telecoms.
Cable
REC
Supply

DC
Voltage Track circuit

NGC SignallingPSU

Substation

Local Track Structures


RECS
Station
Apparatus

Tunnel
Structure © R D White 2004
Rebars

Copper
Earth Mat Station
Metallic
Structures
Figure 26 Earthing and Bonding on D.C. Railway
Tunnel Requirements of
Lining Draft Earthing
Telecoms PSU
Standard

Telecoms.
Cable

Track circuit Air main

DNO DC SignallingPSU

Substation Voltage Lead Sheathed


Signal Cables

Sub Station Main Earth Bar Station Main Earth Bar

Local Track
RECS Structures

Station
Apparatus

© R D White 2004
Rebars

Copper
Earth Mat Station
Metallic
Structures
Figure 27 Earthing and Bonding on DC Electrified Railways (LUL)
Figure 28 and 29 Diode Earth and Floating Negative Rail Return Systems

Traction Current
Catenary

Substation Rectifier
DC System Voltage

Traction Return Current

Main Earth bar


Vrail Vrail Vrail

Diode Earth

Vrail

Traction Current Catenary

Substation DC System Voltage


Rectifier

Traction Return Current


Main Earth bar

Vrail Vrail Vrail

Vrail

Distance
9. Stray Current Traction Return This European Standard applies to all new lines,
extensions and to all major revisions to existing
The railway authority is responsible for any damaged lines for the following electric traction systems:
or corrosion to other companies’ equipment due to
effects of stray or leakage currents from the railway. Running Rail Insulation
With new railway electrification projects this has to be
addressed during the design period, to minimise any The Running Rail is normally insulated from the
modifications that may be required in operation of the sleeper / concrete pad by the use of single and double
railway. insulation pads placed under the rails with an insulation
value in line with the European Standard EN 50122-2.
CENELEC European Standards [Table 1 Page 6; No added rail insulation 0.5 S/km for
open formation and 2.5 S/km for closed formation].
CENELEC European Standard EN50122-2 Part 2 This level can be improved with the application of
‘Protection against the effects of stray current caused track insulation mounting pads or polymeric insulation.
by D.C. Traction Systems indicates that in Light Rail This value of insulation however will reduce over time
systems the stray current will be minimised if the return due to degradation of the track insulation.
conductor system is allowed to float, and if the negative
busbars are deliberately not connected to earth or to a For closed formation, improved levels of insulation can
stray current conductor via diodes. be achieved where the rail is to be embedded in the
The total stray current at a particular location is road. The level of insulation is determined not only by
dependent on the design of the infrastructure and in the installation but the maintenance of the track bed.
particular whether this includes slab or ballasted track. Every effort should be made to minimise the risk of
ballast from coming into contact with the rails, since
CENELEC European Standard EN 50122-3:2010 as of ballast, especially when wet will reduce the insulation
01st October 2010 Railway applications - Fixed value of the rails to earth.
installations - Electrical safety, earthing and the return
circuit - Part 3: Mutual Interaction of a.c. and d.c.
traction systems.

The scope is for fixed installations, when it is


reasonably likely that hazardous voltages or currents
will arise for people or equipment, as a result of the
mutual interaction of a.c. and d.c. electric traction
systems. It also applies to all aspects of fixed
installations that are necessary to ensure electrical
safety during maintenance work within electric traction
systems.

The mutual interaction can be of any of the following


kinds:
Figure 28 Double Insulated Rail Clips
 Parallel running of a.c. and d.c. electric Floating Negative or Diode Earthed Railway
traction systems;
 Crossing of a.c. and d.c. electric traction
This normally includes a rectifier drainage panel
systems;
located at the Rectifier Substation for those assets
 Shared use of tracks, buildings or other
within close proximity, and remote rectifier cubicles for
structures;
those assets requiring protection that are remote from
 System separation sections between a.c. and
the Rectifier Substation.
d.c. electric traction systems.
A drainage system to protect Utilities and the railway
Scope is limited to basic frequency voltages and
infrastructure normally includes a drainage diode, a
currents and their superposition. This European
current limiting resistor, and surge arrestor. Where it is
Standard does not cover radiated interferences.
identified that stray current protection is required,
cables are bonded from the infrastructure to drainage
diodes mounted in cabinets at the track side or in the
Rectifier Substation.

Provision of Stray Current Control

Where monitoring indicates that there is a high level of


leakage current from the D.C. electrification system,
and therefore potential damage to metallic structures,
arrangements must be made to provide the appropriate
form of cathodic protection to railway infrastructure,
utilities and non railway property.

The only condition when the track earth may be


connected to true earth is by means of a short circuiting
device, which operates for a pre-determined short
period of time when the track potential exceeds a
specified direct contact of 60V D.C. as specified in EN
50121-1 Section 4.1.1
References 6. Seminar D.C. Traction Stray Current Control
21.10.99, IEE Railway Industry Group.
British and European Regulations:
IEE and IRSE Conference and Proceedings
1. The Railways Act 2005
2. EMC Regulations 2005 1. IRSE ASPECT 2003; Signs of the Times for Train
3. Requirements for Electrical Installations (BS Control; London.
7671) 2. IRSE ASPECT 2006; Quality of service through
4. Railway Safety Principles and Guidance – Part 2 Signalling And Communication; London.
Section B: Guidance on Stations 3. IEE Residential Railway Electrification
5. Construction (Design and Management) Infrastructure School, 2005; ISBN 0-86341-511-3.
Regulations 2007. 4. Systems’ IRSE Seminar Railway Interfaces; IEE
6. Construction (Health, Safety and Welfare) Savoy 18 November 2006.
Regulations 1996.
7. Management of Health and Safety at Work IEE and IRSE Conference Papers
Regulations
8. 1999. 1. White R. D. 2005, ‘Induced Longitudinal Voltage
9. Railways (Safety Critical Work) Regulations 1994 and screening of lineside Cables’; IEE
10. Railways (Safety Case) Regulations 1994 International Conference on Railway Engineering
11. Control Of Substances Hazardous to Health Development into the 21st Century, Miramar Hotel
(COSHH). Hong Kong.
12. Transport and Works Act, 1992 2. White R.D. 2006 November Atkins Rail
13. Electricity at Work Regulations 1989. ‘Electrification Interfaces and Electromagnetic
14. Health and Safety at Work Act 1974. Compatibility with Railway Control Systems’
15. SRA Code of Practice – Train and Station Services IRSE Seminar Railway Interfaces; IEE Savoy
for Disabled Passengers 3. White R.D., Zhang Z., Cox J., Armstrong D,
Price S, Sept 2003 ‘Induced Longitudinal Voltage
Books Publications into Lineside Cables for WCRM’ IRSE ASPECT
Signs of the Times for Train Control; London.
1. White R. D, Chapter O5, 2000, Railway 4. Lilley M ‘Signalling systems compatibility at radio
Electrification, Kemps Engineering Handbook frequencies’ IEE 6th Residential Course on
Miller Freeman pp 2473 -2489, ISBN 086382 442 Electric Traction System, Wrightsons. Chapter D4.
0. ISB 0-86341-452-4.
2. Williams T Armstrong 2000, ‘EMC for Systems 5. Hewitt M 2005, ‘Impact of Electrification systems
and Installations’ , Newnes ISBN 0-7506-4167-3. on signalling’ The IEE Second Residential Course
3. Technical Specification for Interoperability on REIS Wrightsons. Chapter D4. ISBN 0 –
relating to energy subsystems of the Trans 86341 –511 – 3.
European high speed rail system. 2002; Office of 6. T Loades, 2005 ‘Practical considerations of EMC
the Journal of the European Union. compatibility on Railtrack WCRM’ The IEE
4. Marshman C; ‘Guide to the EMC Directive’; EPA Second Residential Course on REIS Wrightsons.
Press; ISBN 0-9517362-7-2. Chapter D4. ISBN 0 – 86341 –511 – 3.
7. D Bradley 2005 ‘Compatibility between railway
Journal Publications electrical systems’ IEE Residential Railway
Electrification Infrastructure School, , ISBN 0-
86341-511-3.
1. Dr R J Hill Feb 1997 IEE Power Engineering
8. White R.D. ‘GTO and IGBT three phase traction
Journal Part 6 Electromagnetic Compatibility
inverter drives’; IEE ‘Power Electronics and
Sources and Equipment.
Variable Speed Drives’ 7th International
2. Dr R J Hill Electric Railway Traction Part 7
Conference 1998.
Electromagnetic interference in traction systems
9. White R.D. ‘Fault Currents on AC Electrified
Power Engineering Journal Dec 97; Vol 11; No 6.
Railways, Rail Potentials and Interference with
3. Carson JR ‘Wave Propagation in Overhead wires
Track Circuits; IRSE YM Conference 2000 July
with ground return’. 1926 Bell System Technical
00; ISBN 1356-1448.
Journal 5 p539-554.
10. White R.D. ‘Power Supply Design Issues for 25kV
4. Mellitt B ‘Simulation shows how choppers can
AC Electrification Systems’ Conference on
save energy’ Railway Gazette International 135(4)
Traction Power Supplies IMechE Headquarters,
p300-304 1997’.
London 22nd January 2006.
5. Dr R J Hill Power Electric Railway Traction Part
11. R D White WS Atkins Rail 1999, 'Modelling for
1-7 Traction Systems, Power Engineering Journal
EMC Studies on High Performance Railway
1997.
Systems'. AIC Electrification and Power Supply 2. Influence of Commutating Reactance on the
Conference London March 99. Design of D.C. Power Supply Converters, L. L.
12. Chew TC ‘Chopper Control Equipment for Denning GEC ALSTHOM Publication.
Singapore MRT ’ Electric Railway System for a 3. Protective Relays For Rail Transport System GEC
new Century London 1987 pp6-12, ISBN ALSTHOM Protection and Control.
085296351-3. 4. J.G.Yu “The Effect of earthing strategies on rail
13. Mellitt B, Johnston W.B., Allan J, Shao Z Y, potential and stray currents in DC transit railways”
Denley M 1989, ‘Whole System Compatibility CEGELEC Projects Ltd UK.
measurement on 50 kV New Zealand Railway’, 5. “Stray Current Design Parameters for D.C.
International Conference on Main Line Railways” Proc of the ASME/IEEE Joint Railroad
Electrification York pp 246-251, ISBN 85296384. Conference pp 19-28 1992;.
X. 6. J G Yu and C J Goodman “Computer Analysis of
touch and step voltages for D.C. Railways”., Proc.
IEE Conference on 'Main Line Railway of the third International Conference on Computer
Electrification' Publication 312: Aided Design, Manufacture and Operation in the
Railway and other Advanced Mass Transit System
IEE Conference on 'Electric Railway Systems for a Washington 1992.
New Century'. Publication 279:

1. Y.Yoshiki, T.Jinzenji, T. Kodor, H.Inokuchi


"Static Power Supply for D.C. 1500 V Transit
System" IEE Conference on 'Main Line Railway
Electrification' Publication 312.

2. J Bouley "Electrification: why not?" IEE


Conference on 'Electric Railway Systems for a
New Century' Publication 279.

3. Professor S Sone; University of Tokyo, Japan S


Ishizu; Japanese Railways, Tokyo, Japan The
International Union of Railways, France
"Reassessment of power feeding systems at
introducing regenerative trains".
4. "Contribution to energy saving in D.C. railways",
R Filliatre IEE Conference on 'Electric Railway
Systems for a New Century' Publication 279.
5. P O Barnwell, Professor B Mellitt and Dr C J
Goodman W B Johnston "Assessment of voltage
controlled substations for D.C. traction
applications" IEE Conference on 'Electric Railway
Systems for a New Century' Publication 279.
6. H Puntis, P Strubin "Determination of protection
requirements for D.C. traction systems and the
development of a solid state protection relay to
optimise current availability" IEE Conference on
'Electric Railway Systems for a New Century'.
Publication 279.
7. J E Buttery, D N Ebenezer and B P McCormick
"Electromechanical and electronic falling voltage
track impedance devices for fault detection
on D.C. track systems", IEE Conference on
'Electric Railway Systems for a New Century'
Publication 279.

Other DC Electrification Publications

1. R. J. Kemp, R. W. Sturland GEC ALSTHOM


publication 'Integrated Design of D.C. railway
systems'.
British Standards BS EN 50123-7- Railway applications. Fixed
2:2003 installations. d.c. switchgear.
BS EN 50123- Railway applications. Fixed Measurement, control and
1:1996 installations. D.C. switchgear. protection devices for specific
General use in d.c. traction systems.
BS EN 50123- Railway applications. Fixed Isolating current transducers and
1:2003 installations. D.C. switchgear. other current measuring devices
General BS EN 50123-7- Railway applications. Fixed
BS EN 50123- Railway applications. Fixed 3:1999 installations. d.c. switchgear.
2:1996 installations. d.c. switchgear. d.c. Measurement, control and
circuit breakers protection devices for specific
BS EN 50123- Railway applications. Fixed use in d.c. traction systems.
2:2003 installations. D.C. switchgear. Isolating voltage transducers and
D.C. circuit breakers other voltage measuring devices.
BS EN 50123- Railway applications. Fixed Isolating voltage transducers and
3:1996 installations. d.c. switchgear. other voltage measuring devices
Indoor d.c. disconnectors and BS EN 50123-7- Railway applications. Fixed
switch-disconnectors 3:2003 installations. d.c. switchgear.
BS EN 50123- Railway applications. Fixed Measurement, control and
3:2003 installations. D.C. switchgear. protection devices for specific
Indoor d.c. disconnectors, switch- use in d.c. traction systems.
disconnectors and earthing Isolating voltage transducers and
switches other voltage measuring devices
BS EN 50123- Railway applications. Fixed BS EN 50123- Railway applications. Fixed
4:1999 installations. d.c. switchgear. 1:1996 installations. D.C. switchgear.
Outdoor d.c. in-line switch- General
disconnectors, disconnectors and BS EN 50123- Railway applications. Fixed
d.c. earthing switches 1:2003 installations. D.C. switchgear.
BS EN 50123- Railway applications. Fixed General
4:2003 installations. D.C. switchgear. BS EN 50123- Railway applications. Fixed
Outdoor d.c. disconnectors, 2:1996 installations. d.c. switchgear. d.c.
switch-disconnectors and circuit breakers
earthing switches BS EN 50123- Railway applications. Fixed
BS EN 50123- Railway applications. Fixed 2:2003 installations. D.C. switchgear.
5:1999 installations. d.c. switchgear. D.C. circuit breakers
Surge arresters and low-voltage BS EN 50123- Railway applications. Fixed
limiters for specific use in d.c. 3:1996 installations. d.c. switchgear.
systems Indoor d.c. disconnectors and
BS EN 50123- Railway applications. Fixed switch-disconnectors
5:2003 installations. D.C. switchgear. BS EN 50123- Railway applications. Fixed
Surge arresters and low-voltage 3:2003 installations. D.C. switchgear.
limiters for specific use in d.c. Indoor d.c. disconnectors, switch-
systems disconnectors and earthing
BS EN 50123- Railway applications. Fixed switches
6:1999 installations. D.C. switchgear. BS EN 50123- Railway applications. Fixed
D.C. switchgear assemblies 4:1999 installations. d.c. switchgear.
BS EN 50123- Railway applications. Fixed Outdoor d.c. in-line switch-
6:2003 installations. D.C. switchgear. disconnectors, disconnectors and
D.C. switchgear assemblies d.c. earthing switches
BS EN 50123-7- Railway applications. Fixed BS EN 50123- Railway applications. Fixed
1:2003 installations. d.c. switchgear. 4:2003 installations. D.C. switchgear.
Measurement, control and Outdoor d.c. disconnectors,
protection devices for specific switch-disconnectors and
use in d.c. traction systems. earthing switches
Measurement, control and BS EN 50123- Railway applications. Fixed
protection devices for specific 5:1999 installations. d.c. switchgear.
use in d.c. traction systems. Surge arresters and low-voltage
Application guide limiters for specific use in d.c.
BS EN 50123-7- Railway applications. Fixed systems
2:1999 installations. d.c. switchgear. BS EN 50123- Railway applications. Fixed
Measurement, control and 5:2003 installations. D.C. switchgear.
protection devices for specific Surge arresters and low-voltage
use in d.c. traction systems. limiters for specific use in d.c.
Isolating current transducers and systems
current measuring devices. BS EN 50123- Railway applications. Fixed
Isolating current transducers and 6:1999 installations. D.C. switchgear.
other current measuring devices D.C. switchgear assemblies
BS EN 50123- Railway applications. Fixed Outdoor d.c. in-line switch-
6:2003 installations. D.C. switchgear. disconnectors, disconnectors and
D.C. switchgear assemblies d.c. earthing switches
BS EN 50123-7- Railway applications. Fixed BS EN 50123- Railway applications. Fixed
1:2003 installations. d.c. switchgear. 4:2003 installations. D.C. switchgear.
Measurement, control and Outdoor d.c. disconnectors,
protection devices for specific switch-disconnectors and
use in d.c. traction systems. earthing switches
Measurement, control and BS EN 50123- Railway applications. Fixed
protection devices for specific 5:1999 installations. d.c. switchgear.
use in d.c. traction systems. Surge arresters and low-voltage
Application guide limiters for specific use in d.c.
BS EN 50123-7- Railway applications. Fixed systems
2:1999 installations. d.c. switchgear. BS EN 50123- Railway applications. Fixed
Measurement, control and 5:2003 installations. D.C. switchgear.
protection devices for specific Surge arresters and low-voltage
use in d.c. traction systems. limiters for specific use in d.c.
Isolating current transducers and systems
current measuring devices. BS EN 50123- Railway applications. Fixed
Isolating current transducers and 6:1999 installations. D.C. switchgear.
other current measuring devices D.C. switchgear assemblies
BS EN 50123-7- Railway applications. Fixed BS EN 50123- Railway applications. Fixed
2:2003 installations. d.c. switchgear. 6:2003 installations. D.C. switchgear.
Measurement, control and D.C. switchgear assemblies
protection devices for specific BS EN 50123-7- Railway applications. Fixed
use in d.c. traction systems. 1:2003 installations. d.c. switchgear.
Isolating current transducers and Measurement, control and
other current measuring devices protection devices for specific
BS EN 50123-7- Railway applications. Fixed use in d.c. traction systems.
3:1999 installations. d.c. switchgear. Measurement, control and
Measurement, control and protection devices for specific
protection devices for specific use in d.c. traction systems.
use in d.c. traction systems. Application guide
Isolating voltage transducers and BS EN 50123-7- Railway applications. Fixed
other voltage measuring devices. 2:1999 installations. d.c. switchgear.
Isolating voltage transducers and Measurement, control and
other voltage measuring devices protection devices for specific
BS EN 50123-7- Railway applications. Fixed use in d.c. traction systems.
3:2003 installations. d.c. switchgear. Isolating current transducers and
Measurement, control and current measuring devices.
protection devices for specific Isolating current transducers and
use in d.c. traction systems. other current measuring devices
Isolating voltage transducers and BS EN 50123-7- Railway applications. Fixed
other voltage measuring devices 2:2003 installations. d.c. switchgear.
BS EN 50123- Railway applications. Fixed Measurement, control and
1:1996 installations. D.C. switchgear. protection devices for specific
General use in d.c. traction systems.
BS EN 50123- Railway applications. Fixed Isolating current transducers and
1:2003 installations. D.C. switchgear. other current measuring devices
General BS EN 50123-7- Railway applications. Fixed
BS EN 50123- Railway applications. Fixed 3:1999 installations. d.c. switchgear.
2:1996 installations. d.c. switchgear. d.c. Measurement, control and
circuit breakers protection devices for specific
BS EN 50123- Railway applications. Fixed use in d.c. traction systems.
2:2003 installations. D.C. switchgear. Isolating voltage transducers and
D.C. circuit breakers other voltage measuring devices.
BS EN 50123- Railway applications. Fixed Isolating voltage transducers and
3:1996 installations. d.c. switchgear. other voltage measuring devices
Indoor d.c. disconnectors and
switch-disconnectors IEE ETS Supply AC & DC 2014
BS EN 50123- Railway applications. Fixed
3:2003 installations. D.C. switchgear.
Indoor d.c. disconnectors, switch-
disconnectors and earthing
switches
BS EN 50123- Railway applications. Fixed
4:1999 installations. d.c. switchgear.

View publication stats

You might also like