Professional Documents
Culture Documents
AC DC Railway Electrification and Protection PDF
AC DC Railway Electrification and Protection PDF
net/publication/288773712
CITATIONS READS
0 1,884
1 author:
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by R.D. David White on 30 December 2015.
R D White
Chief Engineer
Technical Authority Electrical Systems Integration
Atkins United Kingdom
roger.white@atkinsglobal.com
Keyword: electrification, system voltages, feeding, return the domestic and commercial electrical supplies is that the
current, earthing. traction unit is able to change track position continuously.
This affects the characteristics and performance of the
power system and may be responsible for equipment failure
Part 1 AC 25kV 50Hz ELECTRIFICATION SUPPLY due to under voltage, overvoltage or overcurrent. If the
SYSTEM supply system is to have a high degree of security the
precise behaviour of the complete system must be known
1. High Voltage Electrical Supply and catered for in the design specification. If this is not
accomplished at the design stage then failures on the
The technical strength of all electrification schemes lies in locomotive [e.g. under voltage] or at the substation [e.g.
the fact that the prime mover is removed from the train; but Zone 3 protection trips] can cause serious operational
this is also its economic weakness. By taking power from a difficulties once the system has become live.
distribution network there is almost unlimited power
available which has been efficiently produced but the cost Electrical Supply and Railway Infeeds. Railway
of providing the fixed installations can only be justified electrification schemes draw a single-phase supply from the
where the traffic is heavy or frequency is high. national electricity HV supply system. It is inevitable
therefore that train loads of between 2-12 MW [PMCF or
The 25 kV A.C. 50 Hz electrification system has been phase angle control], will create unbalanced current within
developed specifically for railway traction purposes. The the HV 3 phase supply system, harmonic distortion and
main feature that separates this system from the voltage fluctuation to the supply system. In order to
conventional 3 phase and neutral HV distribution network minimise these effects on the HV supply authorities 3 phase
of the public supply authority is that the railway system is a networks, connections are normally made to the supply
single-phase system with one pole earthed. Even though authority network at 132/275/400 kV.
other railway administration have their own individual
electrification schemes the basic design of the systems is the Single phase transformers are connected to different phase
same. pairs of the grid supply at successive feeder stations along
the railway route, so as to provide the grid system with a
The 25kV rail network has been designed to meet the needs load that is distributed between the three phases.
of a fast, intercity, multi-track railway network carrying a
variety of trains at frequent intervals. This operation 1.1 Incoming Supply Arrangements Figure 1, 2
requires an overhead system that is inherently safe for
employees and passengers, reliable and provides a high Normally the incoming feeder circuit is supplied from the
degree of security of the supply to the traction units. This 132/275/400 kV grid networks. The level of the traction
will ensure that the electrification supply system is able to load and the availability of the grid will decide the point of
provide the required power levels to fulfil the performance connection. At the railway feeder stations two incoming
of the traction units. circuits are normally made available, both of the feeds
being capable of individually carrying the total traction load
The 25kV high voltage A.C. locomotive is a complex under normal traffic conditions, this will provide a power
element of the total A.C. power system configuration. A supply with a high degree of security. It is not sensible to
factor that makes the railway fundamentally different from provide an incoming feeder arrangement, which had a level
of security that was less than the 25kV overhead traction
system it is feeding. To increase the security of the supply 1.2 Feeder Transformers ‘Classic’ Feeding
the railway 25kV busbar are fed from independent parts of Arrangement of the Overhead Line
the H.V. network or by two H.V. busbars being fed
independently by the H.V. system. If there is a failure on 10 MVA 132 kV/25 kV fixed ratio [UK Network Rail] This
one of the supplies the fault does not interrupt the supply to transformer is normally used on suburban electrified lines.
the second railway feed [see Figure1]. The two railway The transformer is usually oil immersed and naturally
feeders could be independent or may be banked with 33 kV cooled, if an oil circulating pump and forced air cooling is
or 11 kV transformers feeding local industry or distribution installed the rating can be increased to 14 MVA.
networks.
18 MVA 132kV/25 kV variable ratio [UK Network Rail]
If there is a total loss of supply at a feeder station, supply to
the overhead railway network is transferred so that the It is necessary to adjust the transformer tap setting, to give
adjacent feeder station supplies power up to the non- the most suitable no-load voltage, this is determined by the
functioning feeder station. This new feeding arrangement characteristics of the incoming supply feeder. Once set it is
will give rise to loss of train performance due to the only necessary to adjust the tap setting if the incoming
increased voltage drop between the operational feeder power system characteristics are significantly altered. The
stations and individual locomotives. Any loss in time to the transformer is usually oil immersed naturally cooled; if oil
traction unit, due to the outage of a feeder station should be circulating pump and forced air is installed that rating can
recoverable in the next normally fed feeding section. be increased to 26.5 MVA.
400 kV
Busbar Main
400kV
Busbar Reserve
Three Phase 400kV Grid Circuit
Switching Isolator
25kv Railway Supply
Figure 2 Typical 25kV Feeding Section Normal Feeding
132/25kV Transformer
Substation
Public / Non-Railway
Local Structure
Earth
Traction Return Rail
See Note
5&6
Signalling PSU
Conducting
5&6
Telecomms. Path Gapping
Local Sheathed Cable
Point Machine Structure
Public / Non-
Gapping
Earth
Railway
Earth
External
MV Power Cable earth
~1km typical
Track
Lightning Earth Pit Structures
Conductive Fences /
Handrails / Walkways
25kV Earthing and Bonding Principles
Stations, Viaducts and Tunnels of an Electrified Railway
Viaducts Tunnels Stations
Public / Non-Railway
~1km typical Note 7 ~1km typical Note 7 Cross Bonding either
Aerial Earth Wire side of Station Structure
25kV
Reference Drawing 4
Railway Return Current Bonding Principles
Local Structure
Earth
External Utilities
Metal Pipes (e.g. Water,
See Note
Gas)
7&8
Signalling
Radio (see note 6) Telecoms Screening Conductor Metal Trays,
Antenna Cable
(see note 3) Conducting
Containment
Path Gapping
Track circuit + Catwalk
or Axle Telecoms. (see note 6)
Counters Station
MV / LV External
Telecoms. PSU Metallic
Earth Signalling PSU earth
MV Power Cable Equipment Power
Gapping
Telecomms. Supplies Power Electrical
Local
Point Machine Structure Sheathed Cable Apparatus Cable Earth
Auxiliary Comms, Gapping
Earth Substation Vids, PA, etc
See Note
See Note
7&8
7&8
Station Main Earth Bar
Two bonds
required for
redundancy
Non-Traction Earth
(see notes 1,2,3,4) Lightning
Viaduct Protection System
Structures
Lightning Earth Pit Conductive Fences / (see note 5) Station
Tunnel Handrails / Walkways
Station Earth
Structures Structures Mat
System Overhead Line
The main factor which must be considered on an Voltage [kV]
earthed electrification system is the voltage level of < 5 mins
©
Copyright R.D.White 01/04
Armour of Cables or Metal Pipes
5. 25kV Classic Feeding Arrangement These booster transformers are positioned at
approximately 3 km intervals, one booster is required
There are a total 8337km km in the UK figures 2014 for each 25 kV overhead track feed.
The supply points for the railway electrification system 25kV single phase supplies are received from the
[25 kV] are normally provided at intervals of between supply authorities at railway feeder stations. The
40-60 km; this spacing is specified so that the overhead function of the feeder station [FS], Intermediate track
line meets the specification for voltage regulation on sectioning cabin [ITSC] and mid point track sectioning
the 25 kV system under worst case "second emergency cabin [MPTSC] are to control the distribution of the
feeding" arrangement. The electricity supply authority supply to the overhead line equipment.
normally provides incoming feeder at 132 kV, if this is
not available it is necessary to provide the supply at At the FS each incoming feeder has its own circuit
275 kV. With the supply being only single phase, the breaker on the 25 kV busbar, the two feeds can be
electricity supply authority may try to balance its load isolated with the use of the bus-section circuit breaker
by supplying feeds from a different phase at adjacent thus allowing both feeds to be independent of each
feeders. This will not eradicate all the problems other. The HV feed is then supplied to the overhead
associated with unbalanced loads, but it does help to line through the track feeder circuit breaker supplying
reduce adverse effect on the supply authority’s system. the feed for one main railway track in each direction
from the feeder station. It is necessary, therefore, to
The security of the supply to the overhead line is provide four track feeder circuit breakers for a two
paramount for the reliability and efficiency of the track railway system. This somewhat complicated
whole traction system. To achieve this level of switching arrangement does provide the operator with a
reliability it is normal for two supply points to be very versatile system under maintenance or outage
provided at each feeder station each being able to carry conditions.
the total traction load for the feeder station under
normal railway operating conditions. Mid point track-sectioning cabins [MPTSC] are
situated at the midpoint between feeder stations. The
5.2 Return Conductors function of the MPTSC is to provide electrical
separation between adjacent supply points. The
When considering a 25 kV supply system the track MPTSC also provides sectioning and track paralleling
feeding sections are only half of the total feeding for the 25 kV systems, this provides a high level of
arrangement. One of the running rails of each track security and the best feeding arrangements without the
carries the traction return current, these rails are all loss of supply. Intermediate track sectioning cabins are
bonded together and in turn bonded to each overhead positioned approximately half way between FS and
line structure thereby forming a distributed earthing MPTSC, their function provides paralleling of the
system and typically having an overall resistance to overhead line and sectioning similar to that of a
earth of less than one ohm. At the feeder station the MPTSC, except ITSC are not able to terminate a
return rails are connected to the neutral side of the feeding section.
feeder transformer.
Normal Feeding Figure 2
5.3 Booster Transformer Arrangement Under normal feeding arrangements each FS supplies
[figure. 9] the feed to a MPTSC in each direction. Further
sectioning and paralleling of the overhead line is
The return current in the distributed earthing system is provided by the ITSC situated midway between the FS
liable to cause an excessive amount of electromagnetic and the MPTSC. Under normal feeding arrangements,
induction into adjacent telecommunications circuits. therefore, it is necessary to have the bus-section
To minimise this current is constrained to return to the coupler in the FS and MPTSC ‘open’, this ensures that
feeder transformer in return conductors positioned near the feed from the FS to the MPTSC is ‘single ended’.
to the 25 kV overhead line and in such a way as to Under this configuration the 25 kV system fault level is
reduce the level of interference. The return current is limited to 6 kA, this restricts the interference and high
constrained to flow in the return conductor by booster voltages to earth in lineside track signalling and
transformers [current transformers] which have their telecommunications equipment. To cope with such
primary connected in series with the 25 kV line and high fault currents the switchgear is normally rated at
their secondary connected in series with the rail return. 12 kA. If small feeder transformers are used, it is
possible to operate them in parallel assuming that the Second Stage "Emergency Feeding" [figure. 11
phasing is common.
Second stage "emergency feeding" is when a FS has a
First Stage "Emergency Feeding" [figure 10] complete loss of supply. This could be caused by a
failure of the 132 kV feed provided by the electricity
First stage "emergency feeding" is when a single circuit supply authority, or a failure of the one or two feeder
outage occurs at a two-circuit supply point. The 25 kV transformers in the FS.
supply is maintained to the overhead line by closing the
bus-section circuit breaker. If it is necessary to It is vital that the 25 kV A.C. supply is maintained to
maintain a feeder transformer, the two incoming ensure that the railway service does not come to a
supplies may be paralleled by closing the bus-section standstill. This is achieved by isolating the faulty
breaker, this will ensure that during the changeover, as feeds/transformers, once this has been accomplished
the feeder transformer is being isolated, supply is the bus-section breakers in the FS can be opened and
maintained to both the feeding sections. the bus-section breakers in the adjacent MPTSC closed.
This will enable the supply from the two adjacent
feeder stations to feed right up to the non-supplying
feeder that has now become a MPTSC.
Figure 10 25 kV Emergency Feeding 1st Stage
Neutral Section
132/25kV Transformer
Neutral Section
Section Overlap
6. Autotransformer 25kV [figure 12] kV power transmission, yet being able to utilise the
standard 25 kV traction equipment. The
AT’s were first used for railway electrification design autotransformer works on the principle that the train is
in 1913 when the New York, New Haven and Hertford supplied between the +25kV and rail. The rail and earth
railway electrification was extended to New Haven. currents are then returned at 50kV to the adjacent
The design by Professor Scott was introduced to reduce autotransformer at either end of the section. The current
the line loss and the inductive interference on the in the traction unit [25kV] is therefore twice the current
11-0-11kV 25Hz electrification system. [Scott was also returning through the autotransformer and the auxiliary
the inventor of the Scott connected transformer] feeder cable [50kVThe operation of classic systems is
different from the autotransformer arrangements in that
The idea was then adopted by the Japanese in 1962 for the booster transformer is only energised when a train
the extension of one of their railway lines, at 25-0- is in section, whilst the autotransformer is energised
25kV system. Subsequently in 1981 SNCF adopted the whenever the supply is available in section and is
25-0-25kV for use on a section of the Paris-Lyon TGV independent of train position. In practice however most
line. This new arrangement proved so successful, that of the train current is supplied from the two adjacent
SNCF adopted it as the standard feeding arrangement autotransformers, making a power circuit where the
for each of their new TGV lines. current is supplied mainly in the catenary and auxiliary
feeder. The main advantage of the autotransformer
The railway industry in Europe and worldwide has system over the booster transformer system is that the
been under great commercial pressure from the airlines voltage drop in the supply system [nominally 50kV] is
industries. To compete with the airlines over 500- less, with the auto-transformer capable of supplying
1000km it has become necessary to increase the line more power with less system losses, providing there is
speed to 200-300km/hr. The rapid expansion of the a train in section.
motorway network has not been able to compete with
the growth in the road freight and passenger transport. The ideal connection for an AT System is to the
There is a requirement therefore to build high speed existing National Grid Substation with a high level of
passenger intercity lines and to upgrade existing 25 kV security of supply and high fault level. The figure 12
passenger and freight lines. shows a typical double circuit input from a 400kV
Super grid Supply Point. The primaries are connected
This necessity to increase trainload, operational speed, across two phases of the supply. The secondaries are
and the frequency of trains required the introduction of centre tapped the two poles connected to +25kV and –
a stronger and more rugged electrification distribution 25kV and the centre tap connected to rail earth.
system. Autotransformer has been introduced in a
number of countries including in Australia [Blackwater 50kV feeding arrangements of the overhead line can be
and Gregory Coal line], Chinese Railways introduced on railway networks where it is difficult to
[Datong to Qinhaungdao], Russia [Vjaz’ma to Orsha], obtain a feed from the country’s own electricity supply
Japan [Bullet Train], France [TGV Lines], Spain, network. The introduction of 50kV distribution with an
Belgium [TGV Lines], Hungarian State Railway [ Lake autotransformer feeding arrangement does enable the
Balaton] and New Zealand [North Island line]. distance between feeder stations to be increased
significantly, alleviating the problem of access to the
Currently the UK has Autotransformer systems on electricity supply network.
HS1 (Channel Tunnel Rail Link)
Thameslink 6.2 Electrical Supply Grid Transformers
WCML
Liverpool-Manchester – now in service from The substation transformers are typically 400/25kV, 40
Manchester to Newton-le-Willows – and the or 80MVA transformers with source impedance 15%
upgrade to LNE specified to limit the maximum short circuit current on
25kV systems to 12kA, this is dictated by the
Implementation on Great Western Electrification, requirement of a higher power for increased trainloads
Crossrail and HS2. and increased speeds of inter city trains.. The track
feeder circuit breakers are typically rated at 1200A and
6.1 Principle of the Autotransformer 12kA for short circuit duty. Auto-transformers are
typically rated at 10MVA and impedance 0.17+j0.92
System ohms at 50 Hz [CCITT].
Autotransformer supply schemes are increasingly used
for A.C. electrification to take advantage of the 2 x 25
6.3 Autotransformer Versus Classic
Feeding Arrangement The feeding of a four-track railway is more complex
with the four track electrified railway will normally be
The main advantage of the auto-transformer system split with two fast and 2 slow tracks, theses lines can
over the booster transformer system is that the voltage either be fed separately [2 by 2] or in parallel [4 x1].If
drop in the supply system [nominally 50kV] is less, the slow and fast lines are separated there is a
with the auto-transformer capable of supplying more requirement to install two autotransformers at each AT
power with less system losses, providing there is a train site, on the other hand if all tracks are fed in parallel
in section. only one autotransformer is required. NR are currently
utilising protection system on Great western that is
based on a rationalised mesh connected design.
6.4 Feeding Arrangement of the
Overhead Line [fig13] The overhead line is sectioned at neutral sections
located at the feeder stations and at mid points between
Single Phase transformer impedance is specified to feeder stations. First stage emergency feeding requires
limit the maximum fault currents on the 25-0-25 kV the closure of the mid-bus-section circuit breakers at
A.C. system to typically 12kA. It is the reduction in the the feeder station.
source impedance of the electrical supply and the
reduction in the overhead line impedance [the removal A complete outage at a feeder station will require the
of booster transformers], that enables the auto- closure of the mid-bus-section circuit breakers at the
transformer feeding arrangement to supply longer mid point, the opening of the bus section breakers at
feeder sections when compared with the ‘Classic’ 25 the feeder station, the section of track is then fed by the
kV 6kA system. adjacent feeder stations.
The most commonly used AT system in use is two The auxiliary feeder conductors [-25kV] act as the
track high speed railway, using a two track mesh return path to the feeder station at 50kV, which reduces
feeding arrangement with AT’s spaced at typically 5 the level of the supply current and acts to suppress the
km. The feeding arrangement is such that when a fault railway magnetic fields and subsequent induced
occurs on either feed, both feeds are disconnected. voltages into lineside conductors.
With the feeds electrically isolated the track feeder
circuit breakers are closed. The feed with the fault will
immediately open, the circuit can then be isolated
leaving the remaining circuits operational.
Figure 12 25-0-25 kV Electrification Autotransformer
Grid Substation
Double Winding Transformer
Secondary 2x25 kV 25 kV Current
50kV Current
400, 275 kV
50Hz
25 kVkV
-25 Auxiliary
Return Feeder Wire
Conductor
© RDWhite3/99
© RDWhite 01.04
Auxiliary Return
Auxiliary Feeders
Return Feeders
Neutral Section
Feeder Transformer
95 mm static clearance
8. Electrical Clearances 70 mm passing clearance
The electrical clearances for overhead electrified The passing clearance from the contact wire to the
railways were originally based on the UIC Kinematic load gauge was also reduced to 125 mm.
recommendation for 25 kV 50 Hz systems were defined The specially reduced clearances are adopted in cases
as follows ( reference BSEN 50119) :- of exceptional difficulty or where great expense would
be incurred in creating greater headroom. It was also
270 mm static clearances necessary to add an additional 25 mm for increased
150 mm passing clearances uplift of the contact wire at speeds above 60 km. hr-1.
Enhanced Normal Reduced Special
Reduced
25kV AC Static electrical 600 mm or 599 – 270 mm 269 – 200 mm 199 – 150 mm
electrified clearance greater
lines
HV Supply
i. Unbalance of the 3 phase supply, RFI from the Distribution System
ii. Harmonics three phase supply, i. Current collection mechanism.
iii. 400kV earth faults ii. Operation with multiple contact wires.
iv. Rise of earth potentials iii. HV switching of the power system
iv. Resonance of the power system at MHz
25 kV Distribution System v. Excessive voltage stress across insulators
i. Charging of the overhead line at 1st resonant vi. Disturbances on the overhead line
frequency
ii. Switching on the a.c. power RFI from the Traction Unit
iii. Changes with the feeding arrangement, i. Transients due to raising the traction unit
iv. Degraded modes: outages of the feeder pantograph
stations; outages of booster transformers ii. Interaction of power system contacts earthing,
v. Magnetic fields wheel rail, rail to rail
vi. Line resonance effects iii. Operation of multiple pantographs
vii. 25kV earth faults iv. Switching of thyristors and semiconductors.
viii. Induced voltages into line-side cables
ix. Neutral sections RFI from the Track Circuits
x. Radio Frequency Interference. i. Track circuit current producing arcing poor
wheel to rail,
Traction Unit Disturbances ii. High voltage impulse track circuit
i. Inrush effects of the traction transformer,
ii. Characteristic disturbance switching, overlap
effect
iii. Production of 25kV system resonant
frequencies
iv. Radio Frequency Interference
v. Disturbance to signalling track circuits
vi. Return current systems
vii. Return currents and earth currents to third
parties.
Distribution Network
Operator
HV Busbar
AC Breaker
11 kV Busbar
Rectifier DC
Rectifier DC
Breaker 1500V DC Busbar 1500V DC Busbar Breaker
Sectioning
Power Transformer
Point Circuit Breaker Normally Open
Rectifier Unit
© Copyright R D White 2006
Isolator Normally Open
Insulated Overlap
Figure 23b Typical Feeding Arrangement 750V D.C. Electrification System (Tram)
Power Transformer
Rectifier Unit
I/2 I/2
I/4
I/4
I/4 I/4
3.3 Positions of the Lineside Traction Sub- 4. Substation Electrical performance
Stations Specification [figure 24 and 25]
A detailed analysis is needed to establish the correct The detailed electrical performance of the substation
positions of sub-stations on the railway system, a has to be designed into the system at the outset, it is
simple mathematical approach has been included at the dependent upon the traction load specified by the
end of this paper. Having established the working operating business, and the level of supply redundancy
voltage 600V, 750V, 1500V or 3000V the exact required. Provision for future extension of the system,
position of the substation has to be decided. This the increase in train loads, and the change of type of
decision is made on the technical performance of the vehicles to be operated must also be considered.
power system, however it is also necessary to take into
account other factors which will determine the final In the design of a traction substation it is necessary to
choice, availability of land, position of junctions and take into consideration the following aspects:-
crossovers, the provision of road access up to the main
door of the building in order to facilitate the transport The power factor of the converter unit and the
of spare items of plant and any necessary maintenance supply transformer on the supply network
test equipment. Traction supply and converter arrangements
The production of harmonics in the input A.C.
The most economic distance between substation is ( BS supply current, and the distortion to the input
EN 50388 (High Traction Power Classic ): supply voltage.
50Hz 3 Phase
Line to Line
Vdc 12 Pulse
20
mS
Figure 24 Transformer Rectifier Unit and Third Rail Connection
4.3 The Traction Supply Transformer and Harmonics Produced in the Conductor or Catenary
Rectifier Arrangements. supply. The D.C. output voltage waveform produces a
ripple that is related to the pulse number of the
The pulse characteristic of the supply system is converter. This will therefore produce harmonics in the
primarily defined by the transformer winding and load current waveform that are typically related to
converter arrangement. A number of simple 300Hz, 600Hz, 900Hz etc. depending on the rectifier
arrangements of the transformer windings may be pulse number.
chosen with a 3 phase A.C. supply system to provide 6
or 12 pulse D.C. output voltage. Other ripple 5. Feeding Arrangement of the Third
frequencies may be achieved using two converters and Rail or Overhead Line
windings, which are phase displaced or wound in an
alternative star/delta configuration. With normal feeding arrangement the substations are
connected in parallel onto the traction conductor or
A 12 pulse rectifier therefore can be obtained by overhead supply. There is a D.C. circuit breaker at each
connecting two separately fed phase displaced, 6 pulse end of the feeding section to provide protection under
systems in series or parallel. On the other hand a fault conditions. Each substation feeds from a common
similar result can be obtained by using a 3 phase D.C. busbar through D.C. circuit breakers in both
winding transformer with one star and one delta directions, the feed is separated by a bypass isolator,
connected secondary winding. The arrangement will this is normally open and closed only when it is
provide the necessary 30o displacement of the supply to necessary to bypass the substation.
provide a twelve pulse ripple when the respective
bridges are connected in series or parallel. Normal Feeding Arrangement: This is where all of the
feeder D.C. circuit breakers are in service providing
Harmonics Produced in the Supply Network. The double end feeding of the section of traction supply.
rectifier works by switching the load current from one The isolator at each substation is normally open
phase to the next, this process is called 'commutation'. providing an isolated feeding section of traction supply,
If the transformer has leakage reactance the line current and ease of protection of the feeding section.
cannot switch instantaneously due to the effect of the
leakage reactance, this process is called 'overlap'. Tee feeding Arrangement: This is implemented at a
During the overlap period all devices are conducting in substation when a D.C. feeder circuit breaker at one
the outgoing and incoming arms of the rectifier. This end of the feeding section is open. The ‘tee’ feeding
will produce a short circuit on the input and the output arrangement is achieved by closing the bypass isolator
to the rectifier. allowing the remaining D.C. circuit breaker at the
substation to feed the traction supply in both directions.
The input supply voltage waveform and the output D.C.
waveform will therefore be interrupted producing a Single End Feeding Arrangement: Single end feeding
notch in the voltage waveform and oscillation due to arrangement on double end fed sections is a temporary
the RLC characteristic of the supply system. This has feeding arrangement following the loss of the feed from
the effect of distorting the A.C. supply waveform at the a track feeder D.C. circuit breaker. This mode of
point of common coupling. feeding is normally only temporary and if the feed
cannot be restored within a reasonable period of time it
The input current to the rectifier produces a stepped is normal that the traction supply reverts to ‘tee’
waveform due to the switching strategy of the rectifier feeding.
converter. The rectifier input line currents that are
associated with a 12 pulse bridge rectifier can be shown Bypass Feeding arrangement: This occurs when there is
by the Fourier Transform to be 11th, 13th, 23rd, 25th a loss of supply at the substation or the failure of the
with a less amount from the 5th, 7th, 17th, 19th. feeder D.C. circuit breakers in both directions, under
this condition the associated isolator is closed. The
Harmonic distortion levels are specified by the UK traction supply is provided from the feeder D.C. circuit
Electricity Council Recommendation G5/4 lays down breakers at the adjacent substations. In the case of
the limits of harmonic current that may be generated single end fed sections, it is necessary to close only the
back in the supply network. As a result of design appropriate bypass isolator.
predictions it is possible to decide whether 6 pulse, 12
pulse or 24 pulse will meet the supply authority’s Loss of supply from Transformer Rectifier Units: The
regulations. In urban areas with systems supplied at supply system is designed with more than one
transformer rectifier unit at a location. The traction UKs Southern was the first train operator in the country
supply is normally designed to operate with one to introduce regenerative braking on the third rail DC
transformer rectifier unit out of service at any location. network. Southern’s sister company, Southeastern
If the complete substation is lost, the substation should introduced its first regenerative train
operate as a track paralleling hut. in the next few days.
Until now, energy released by trains during braking has The supply system parameters for the interface with a
been wasted in heating the braking resistors on the high voltage transmission system at the point of
train. common connection with the nearest non-railway
consumer are specified in the Publication from the Rail Insulation ( BSEN 50122-2)
Associated Engineering Recommendations G5/4
The railway normally uses the train wheels and running
System Voltage Variation: provisional European rails as the traction current return path to the DC
regulation EN 50163 [Supply Voltage of Traction substation, (except fourth rail systems). Where the rails
Systems], existing UK regulations GM/RC 1502. are not insulated from the sleepers, the earth return is
considerably more complex since the current may flow
System Voltage Variation: European regulation EN out of the rails and return at some other point (stray
50163 [Supply Voltage of Traction Systems], existing current). Most modern rail systems use high insulated
UK regulations [P 7/2, P8, P13/1,P16] rails to prevent the current from leaving the rails and
corroding metallic structures
*Future D.C. traction systems for tramways and local
railways should conform with system nominal voltage A very important aim when designing a DC electrified
of 750,1500,3000V railway is to control return DC traction current and
+In case of regenerative braking a voltage of 800 may avoid passing these currents through the reinforcement
be admissible of concrete structures, and in particular highly stressed
^In case of regenerative braking a voltage of 1000 may concrete structures to avoid causing damage to the
be admissible reinforcement through electrolytic corrosion.
8. Return Current Systems BSEN 50122-2 Criteria for Protection of Rails The
Running Rail is normally insulated from the sleeper /
The railway normally uses the train wheels and running concrete pad by the use of insulation pads placed under
rails as the traction current return path to the D.C. the rails with an insulation value in line with the
substation, [except fourth rail systems ]. The rails are European Standard EN 50122-2. (Table 1 Page 6; No
not insulated from the sleepers, structures on which added rail insulation 0.5 S/km for open formation and
they are fixed. The earth return is considerably more 2.5 S/km for closed formation). This level can be
complex than is at first perceived since the current that improved with the application of track insulation
flows out of the rails and returns at some other point, it mounting pads or polymeric insulation. This value of
is referred to as stray current. insulation however will reduce over time, due to
degradation of the track insulation. For closed
There are typically five earthing strategies in the way formation, improved levels of insulation can be
that the negative at the substation is connected to the achieved where the rail is to be embedded in the road.
running rails and these are detailed below: Note Design Limits should 10 times better than this.
Fourth Rail Systems: The level of insulation is determined not only by the
the problem relating to leakage currents is overcome by installation but the maintenance of the track bed. Every
the insulation of the fourth rail [London Underground effort should be made to minimise the risk of ballast
UK] coming into contact with the rails, since ballast,
especially when wet will reduce the insulation value of
Traction Return Current Systems the rails to earth.
Floating System with Rail to earth shorting Hazards Associated with Rail Potentials
devices, Over Voltage Protection Device Lantau The track is insulated from ground to minimise leakage.
and Airport Railways Hong Kong and Dubai Introducing insulation means that voltages between the
Metro, Sydney Metro. rails and ground will occur. These voltages are a
Floating System with Rail to earth detection and potential hazard to passengers and railway staff when
main tripping of the main circuit breakers, coming into contact with rail or anything connected to it
Singapore MRT. and the ground. Reduction of rail touch voltages can be
Other Floating Earth Systems [Croydon Tram achieved by clamping the rail to ground if a dangerous
UK, Hong Kong LRT, Edinburgh Tram ] voltage is reached and resetting as soon as possible
Rail System partially floating not intentionally afterwards. It is necessary to have quick detection of the
earthed [Network Rail UK] high voltage and then activate a "clamp", by a thyristor
Drainage Diode earth, Hong Kong MTRC, device, GTO device or contactor, to short out the
Sheffield Tram, voltage.
Floating & Diode Interfaces MTRC, DLR MML (
Manchester), LUAS ( Dublin Light Rail) Diode Earthed System (Figure 28)
Floating Fourth Rail London Underground
This arrangement includes a diode at the traction
substation which is connected to the substation local
earth. The inclusion of the diode will cause the rail
potentials to be either at zero (diode is conducting) or
above zero if the diode is reverse biased.
Telecoms PSU
Telecoms.
Cable
REC
Supply
DC
Voltage Track circuit
NGC SignallingPSU
Substation
Tunnel
Structure © R D White 2004
Rebars
Copper
Earth Mat Station
Metallic
Structures
Figure 26 Earthing and Bonding on D.C. Railway
Tunnel Requirements of
Lining Draft Earthing
Telecoms PSU
Standard
Telecoms.
Cable
DNO DC SignallingPSU
Local Track
RECS Structures
Station
Apparatus
© R D White 2004
Rebars
Copper
Earth Mat Station
Metallic
Structures
Figure 27 Earthing and Bonding on DC Electrified Railways (LUL)
Figure 28 and 29 Diode Earth and Floating Negative Rail Return Systems
Traction Current
Catenary
Substation Rectifier
DC System Voltage
Diode Earth
Vrail
Vrail
Distance
9. Stray Current Traction Return This European Standard applies to all new lines,
extensions and to all major revisions to existing
The railway authority is responsible for any damaged lines for the following electric traction systems:
or corrosion to other companies’ equipment due to
effects of stray or leakage currents from the railway. Running Rail Insulation
With new railway electrification projects this has to be
addressed during the design period, to minimise any The Running Rail is normally insulated from the
modifications that may be required in operation of the sleeper / concrete pad by the use of single and double
railway. insulation pads placed under the rails with an insulation
value in line with the European Standard EN 50122-2.
CENELEC European Standards [Table 1 Page 6; No added rail insulation 0.5 S/km for
open formation and 2.5 S/km for closed formation].
CENELEC European Standard EN50122-2 Part 2 This level can be improved with the application of
‘Protection against the effects of stray current caused track insulation mounting pads or polymeric insulation.
by D.C. Traction Systems indicates that in Light Rail This value of insulation however will reduce over time
systems the stray current will be minimised if the return due to degradation of the track insulation.
conductor system is allowed to float, and if the negative
busbars are deliberately not connected to earth or to a For closed formation, improved levels of insulation can
stray current conductor via diodes. be achieved where the rail is to be embedded in the
The total stray current at a particular location is road. The level of insulation is determined not only by
dependent on the design of the infrastructure and in the installation but the maintenance of the track bed.
particular whether this includes slab or ballasted track. Every effort should be made to minimise the risk of
ballast from coming into contact with the rails, since
CENELEC European Standard EN 50122-3:2010 as of ballast, especially when wet will reduce the insulation
01st October 2010 Railway applications - Fixed value of the rails to earth.
installations - Electrical safety, earthing and the return
circuit - Part 3: Mutual Interaction of a.c. and d.c.
traction systems.