Professional Documents
Culture Documents
Filling Materials
Earth Fill
Sub Base Course
Base Course
Asphalt Pavement
50mm thick FDLRC
75mm thick FDLRC
100mm thick FDLRC
Curing Compound
Asphalt Sealer
Asphalt Sealant
Diamond Blade
Asphalt Concrete
Asphalt Treatment
MC-70 (Bituminous Prime Coat)
SS-1 (Bituminous Tack Coat)
Deformed Bars
Grade 40 Deformed Bar 31.60
Grade 60 Deformed Bar 32.96
Formworks Material
Formworks per m2
Columns, Beams, Walls, etc. 300.00
Footings & Grade Beams 150.00
Formworks per m. 90.00
Scaffoldings 65.00
Joint Fillers
25mm thk. Styropor 83.33
12mm thk. Styropor 41.67
Non-extruding Joint Filler (Cork type) Compressible
Backer Rod
30mmØ 7.57
28mmØ
25mmØ 5.39
20mmØ 3.67
16mmØ 2.66
12mmØ 1.26
10mmØ
Laminates "MAC/Jaefer"
0.6mm x 4' x 8' White 250.00
0.7mm x 4' x 8' Solid Colors 470.00
0.7mm x 4' x 8' Wood Grains 515.00
0.7mm x 4' x 8' Patterns 550.00
1.0mm x 4' x 8' Brushed Aluminum 2,050.00
Lumber
Narra
Yakal
Guijo
Rough Tanguile
KD Tanguile
KD Tanguile (1" x 1")
Red Lauan
CW Nails
CW Nails
Waterstops
9" x 3/16" Dumbell type w/ Centerbulb PVC Waterstops
9" x 1/4" Dumbell type w/ Centerbulb PVC Waterstops
Brass Strips
1/4" x 1/2" Brass Strip
PE Nylon Rope
10mmø PE Nylon Rope
10mmø PP Nylon Rope
Polysack Cloth
Polysack Cloth x 2.40m
Tinsmithry Works
Prepainted GI Sheet
Ga. # 24 Pre-painted long span GI Sheets Roofing
Ga. # 24 Pre-painted long span GI Sheets Ridge Rolls
Ga. # 24 Pre-painted long span GI Sheets Flashing
Ga. # 24 Pre-painted long span GI Sheets Gutter
Ga. # 26 Pre-painted long span GI Sheets Roofing
Ga. # 24 Pre-painted long span GI Sheets Ridge Rolls x 0.60m
Ga. # 24 Pre-painted long span GI Sheets Flashing x 0.90m
Ga. # 24 Pre-painted long span GI Sheets Gutter x 1.20m
Fiberglass Insulation (16.0kg/m³) w/ double sided
factory laminated alum. foil incl. chicken wire
Roof Accessories
Roof Nails
Spandek 0.40mm x 1.133mm x 2.44m Roofing (For Bunkhouse & Fencing)
Ridge Rolls 0.40mm x 0.610mm x 2.44m
Tekscrew # 3, 12.11 x 50mm
Doors & Windows
Steel Doors (By LEC Steel - Fire Rated)
Steel Flush Door (0.90 x 2.10) Fire Exit Door incl. Panic device, door closer,
lever type handle, 4 pcs. Butt hinges, lockset and acc.
Steel Flush Door (0.90 x 2.10) includes 4 pcs. Butt hinges, locksets and acc.
Steel Flush Door (1.80 x 2.10) includes 8 pcs. Butt hinges, lockset and acc.
Steel Flush Door (0.90 x 2.10) includes 4 pcs. Butt hinges, lever handle, locksets and acc.
Steel Louver Door (0.90 x 2.10) includes 4 pcs. Butt hinges, lockset and acc. & insect scree
Steel Louver Door (0.90 x 1.90)
1.00 x 2.10m Steel Flush Door SP (Using Ga.# 20 MS Panel on Ga. # 16 MS Jamb)
1.60 x 2.10m Steel Flush Door DP (Using Ga.# 20 MS Panel on Ga. # 16 MS Jamb)
1.00 x 2.10m Steel Flush Door SP with Bottom Louvers (Using Ga.# 20 MS Panel on Ga. # 16
1.60 x 2.10m Steel Flush Door DP (Using Ga.# 20 MS Panel with Honeycomb Insulation on Ga
1.60 x 2.10m Steel Flush Door DP (Using Ga.# 18 MS Louver Blades, Ga. # 18 MS Tubular Fr
Wooden Doors
Wooden Louver Door (Single Door)
Wooden Louver Door (Double Door)
0.80 x 2.10m Hollow Core Flush Door
0.90 x 2.10m Wood Panel Door
Wooden Flush Door w/ Bottom Louver
Yacal Jamb
Installation unit
unit
Glass Flooring
PVC Doors
0.90 x 2.10m PVC Door with PVC Jamb
Hardwares
Concealed Hinges
Magnetic Catches
Toyo Panic Device
Door Lockset
Door Closer
SUS Push Plate
Double Cylindrical Key Lock & Dead Bolt
Loose Pin Hinges
Spring Loaded Foot and Head Bolt
Stainless Hinges (3 ea per Door)
Cabinet Handles
Concealed Hinges
3-1/2" x 3-1/2" LPB Hinges (Brass)
(Chrome Plated)
(Stainless)
MBC Flush bolt
Flush & Head bolt (Ives B 457)
4" x 4" Toyo Butt Hinge
Painting Works
Painting (QDE)
Painting (QDE)
Painting (Epoxy Primer)
Ducco Paint
Ducco Paint
Steel Decking
0.80mm x 0.90m x LS Steel Deck 2 (80,000 psi)
Waferteks 10mm x 16mm
0.80mm x 0.955 x LS Steel Deck 2 (80,000 psi)
Welding Rod
Gabions
2.00 x 1.00 x 1.00m Gabions (Heavy galvanized) w/ 10 x 12cm opening
Waterproofing
4kg. Torch Applied Membrane
3mm Torch Applied Membrane
Capillary Type Waterproofing
Epoxy Lining
Epoxy Tank Lining (Devron 207)
Elastomeric Waterproofing
Superseal 4000 Waterproofing Membrane
Non-skid Tile
200x200x25mm Non-skid Tile 9.00
Homogenous Tile
600 x 600 x 8mm
400 x 400 x 8mm
300 x 300 x 8mm
100 x 100 x 8mm
Ceramic Tiles
100x100 Ceramic Unglazed Floor Tiles
100x200 -do-
150x150 -do-
200x200 -do-
300x300 -do-
400x400 -do-
450x450 -do-
600x600 -do-
300 x 300 Vit. Floor Tiles w/ Integral Nosing
Red Bricks
1" x 4" x 8" Red Bricks
2" x 2" x 8" Red Bricks
100 x 200 Brick Tiles
Pebbles
Beige Pebbles # 10
Beige Pebbles # 5
Black Pebbles # 10
Black Pebbles # 5
Assorted Pebbles
Mosaic Tiles
300 x 300mm Mosaic Tiles
Non-skid Tiles
200x200 Non-skid Floor Tiles (URRA)
Roof Tiles
12" x 12" Roof Tiles
Vinyl Tile
300x300x3.0mm Vinyl Tiles (Local)
(Imported)
300x300x3.0mm Vinyl Tiles (Anti-static)
Vinyl Adhesive
2mm thk. Gerfloor Parasafe Vinyl by Multi-line
Vitreous Tile
600 x 600 x 6mm
400 x 400 x 6mm
300 x 300 x 6mm
200 x 200 x 6mm
100 x 100 x 6mm
Porcelain Tile
600 x 600 x 6mm
400 x 400 x 6mm
300 x 300 x 6mm
200 x 200 x 6mm
100 x 100 x 6mm
Stair Nosing
Brass 50x50x3mm 1,066.33
Brass 38x38x2mm 344.40
Stainless Steel ST-350 "Tsukitora" 1,481.48
Aluminum 40x40mm 186.96
Aluminum 30x30mm 62.32
2" ø BI Pipes
1-3/4" ø BI Pipes
3/4" ø BI Pipes
2mm x 1" x 1" BI Square Tubing
3mm x 1" x 1" BI Square Tubing
2mm x 1" x 2" BI Square Tubing
2mm x 2" x 2" BI Square Tubing
3mm x 2" x 2" BI Square Tubing
2mm x 2" x 4" BI Tubular Pipe
3mm x 2" x 4" BI Tubular Pipe
2mm x 2" x 6" BI Tubular Pipe
3mm x 2" x 6" BI Tubular Pipe
0.80 mm x 4' x 8' Aluminum Sheet
1.00 mm x 4' x 8' Aluminum Sheet
1.50 mm x 4' x 8' Aluminum Sheet
3.00 mm x 4' x 8' Aluminum Sheet
1/8" x 4' x 8' Checkered Plate
3/16" x 4' x 8' Checkered Plate
1mø x 20mm thk. x 6.00m Spiral Welded Steel Pipes ASTM A-252
0.80mø x 20mm thk. x 6.00m -do-
0.65møx 4.5mm thk. x 6.00m -do-
0.45møx 4.5mm thk. x 6.00m -do-
50mm x 4' x 8' MS Plates
20mm x 4' x 8' -do-
6mm x 4' x 8' MS Plates
Sprint Metaltech (Johnson Uyseco) Tel No. 432-45-99 ; 443-39-46 ; Telefax 440-07-15
Stainless Steel Ladder Rung
Spiral Stair
Seismic Gap (Floor & Wall)
Railings
Ring w/ net
1.20 x 1.80m Fiberglass Board
Specialty Works
Glass Mirror 6mm thk. Electrolytically Cu Plated
Facial Mirror including 3.0mm thk. Plywood Backing
Mounting Bracket
Type 304 Stainless Steel Angle Frame
Wood Frame
Rubber Bumper Guard at Loading Dock
Rubber Bumper Guard at Column (700mm)
Mooring Bollard
Cleats
Rubber Dock Fender 0.60 x 3.00m
Stair Nosing
Vertical Blinds
Horizontal Blinds
Dec oline Roll-up Screen
Other Works
Fountain Equipments
Neoprene Gasket
Skim Coat
Plastering Aid (Zembond)
Toilet Partition
Cornices
Solignum
Garland
A.EQUIPMENTS:
B.MANPOWER:
Foreman
Leadman
Timekeeper
Carpenter
Mason
Steelman
Laborer
Floater
Mixer Operator
Painter
Welder
Tinsmith
HE Operator
Driver
Screeder Operator
Plumber
Genset Operator
AS OF J U N E 2016
SMALL
SCOPE OF WORKS SCALE
III. DRYWORKS
A. WALLS
a. Double drywall using 12mm thk. Gypsum board & 6mm thk. Ficem
board on metal frames w/ 3 pcf insulation incl. application of putty &
sanding -
- Framing -
- Boarding (2 sides) -
- Jointing (2 sides) -
- Insulation -
b. Double drywall using 6mm thk. Ficem on metal frames w/ 3 pcf
insulation incl. application of putty & sanding -
c. Double drywall using 6mm thk. Ficem board on metal frames including
application of putty & sanding -
d. Double drywall using 12mm thk. Gypsum board on metal frames
including application of putty & sanding -
e. Pipe Cladding using 6mm thk. Ficem board on metal frames
including application of putty & sanding -
f. Beam Cladding using 6mm thk. Ficem board or 12mm thk. Gypsum
board on metal frames incl. application of putty & putty -
g. Single wall using 12mm thk. Gypsum board on metal frames
including application of putty & sanding -
h. Drop wall using 12mm thk. Gypsum board on metal frames -
including application of putty & sanding -
i. Installation of 19mm thk. x 100mm KDT Wood Base -
j. Installation of 19mm thk. x 75mm KDT Peripheral Wood Bo -
k. Installation of Glasswall Partition -
l. Installation of Sealant -
B. CEILING
a. 12mm thk. Gypsum board on metal frames including application of
putty and sanding of joints -
(Note : Additional cost for ceiling more than 4.00m in height)
- Framing -
- Boarding -
- Jointing -
b. 10mm thk. Gypsum board Curve ceiling on metal frames including
application of putty and sanding of joints -
c. 10mm thk. Ficem board ceiling eaves on metal frames including
application of putty and sanding of joints -
d. Installation of 19mm thk. x 19mm KDT Wood Peripheral Reveal
including Sanding -
e. Installation of 50mm thk. x 50mm KDT Wood Peripheral Reveal
including Sanding -
f. Fab. & Inst. of 600 x 600mm Gypsum or Ficem Board Manh -
g. Acoustic Board Ceiling on Alum. T-runners
- Framing -
- Board -
h. Stop Beads -
i. Shadow Lines -
j. Bulk Heads ( Note : Additional cost if more than 4.00m height)
- By Area -
- By LM -
k. Fascia Board 12mm thk. Ficem Board -
l. Covelight -
m. 12mm thk. Gypsum Curtain Cove -
n. Access Manhole
- Fabrication -
- Installation -
Forming of Opening
Forming of Groove
X. Miscellaneous Concreting
a. Lintel Beams -
b. Stiffener Columns -
c. Zocalo -
d. Concrete Counter -
e. Concrete Curbs -
f. Concrete Curbs & Gutter -
XI. Others
a. Installation of Thermoshield Insulating Mortar
i. 25mm thk. -
ii. 50mm thk. -
b. Installation of Toli Vinyl Sheet (2.0mm x 1.82m x 20.00m.)
c. Installation of Vinyl Tiles (3.0mm x 300 x 300mm)
d. Installation of Vinyl Tiles (3.0mm x 450 x 450mm)
e. Installation of Maxwood Vinyl Planks (3.0mm x 150 x 900mm)
f. Installation of Carpet Tiles (6.5mm x 500 x 500mm) -
g. Installation of Rubber Tiles (500 x 500mm) -
h. Inst. Of Pre-Engineered Wood Flooring -
i. Inst. Of Underlying Foam -
j. Application of Levelling Compound
c. Installation of Vinyl Tiles Anti Static / Conductive
c. Installation of 100mm Coveformer ( Antistatic / Conductice )
V. REINFORCING BARS
Subcon to supply Rebar Cutter & Rebar Bender
A. Footing & Tie Beams 4.55
B. Columns & Pedestal 5.00
C. Floor beams 5.25
D. Floor slab 5.90
E. Shearwalls 5.00
F. Slab on fill 6.50
G. Lavatory counter 8.60
H. Roof Beams 5.90
I. Gutter & Parapet 6.10
J. Wall footings 7.90
K. Stair 6.10
L. Lintel beams & Stiff.columns 10.50
M. Parapet 6.10
N. Dentils (including welding) 6.45
O. Waffles 6.45
P. Tie wires 6.00
Q. Welded Wire Mesh 50.00
R. Hauling of Rebars
a. If Construction Start from Third Floor -
b. If Construction Start from Fourth Floor -
c. Loading & Unloading to Trucks -
S. Subcon Rebars (incl. supply of Tie Wires) -
T. Equipments (Rebar Cutter & Rebar Bender) -
A. Fabrication 35.00
B. Installation 20.00
C. Bending of MS Plates
A. Excavation
a. Ordinary Soil
* Bulk 300.00
* Manual 500.00
b. Adobe 750.00
c. Dewatering (By Administration)
B. Backfilling 200.00
C. Levelling 65.00
D. Excavation of Ftg. Tie Beam & Wall Footings 450.00
E. Compaction 65.00
F. Basecoarse 225.00
G. Soil Poisoning 30.00
H. Polyethelene sheets 25.00
I. PVC Waterstop, Bentonite Strips 35.00
J. Chipping
a. From 0.01-0.10 30.00
b. From 0.11-0.20 60.00
K. Pouring/Concreting
a. Floor beams, Slab & columns
i. Pumpcrete 200.00
ii. Jobmix 750.00
iii. Ready mix 485.00
b. Columns-(Job mix) 750.00
c. Wall footings (Job mix) 750.00
d. Shearwall / Retaining Walls
i. Pumpcrete 225.00
ii. Ready Mix 500.00
iii. Job mix 750.00
e. Roof beams, Gutter & Parapet
i. Pumpcrete 300.00
ii. Job mix 750.00
iii. Ready mix 600.00
f. Footings, Pedestals & Tie Beams
i. Pumpcrete
* Volume < 200.00 cu.m. -
* Volume = 200-300 ; 300-400 ; 400 & above cu.m. 175.00
ii. Ready mix
* Using Buggy 375.00
* Direct Pouring
* Volume < 200.00 cu.m. -
* Volume = 200-300 ; 300-400 ; 400 & above cu.m. 135.00
iii. Job mix 700.00
g. Dentils (All levels)
i. Pumpcrete 250.00
ii. Job mix 850.00
h. Slab on Fill/Pavement
i. Job mix 485.00
ii. Ready mix
* Using Buggy 350.00
* Direct Pouring 200.00
iii. Pumpcrete 225.00
i. Curbs & Gutter
i. Ready mix 450.00
ii. Job mix 700.00
j. Lintel Beams, Stiff. Columns & counters 850.00
k. Stair
i. Pumpcrete 250.00
ii. Job mix 700.00
l. Cistern, Septic Tank, etc.
i. Pumpcrete 250.00
ii. Job mix 1,050.00
m. Floor Slabs
i. Placing of Concrete -
ii. Straight to Finish -
L. Cutting of Prestress Concrete Piles 850.00
M. Trimming of Mechanically Excavated Soil 250.00
N. Cutting of Concrete using Concrete Saw 125.00
O. Cutting of Concrete Sheet Piles 550.00
P. Cutting of Bored Piles
a. 0.60 to 1.00 mø 5,000.00
b. 1.20 to 1.80 mø 7,500.00
Q. Steel Deck Installation 100.00
A. Concrete
a. By Equipment 4,000.00
b. Manual (using Jackhammer) -
c. Hauling & Disposal of Debris -
B. CHB Walls 85.00
C. Corr. G.I. Sheets 60.00
D. Asbestos Roofing 75.00
E. Steel Roof Framing 100.00
F. Wooden Roof Framing 75.00
G. Wooden Floor Framing 70.00
H. Steel Windows 60.00
I. Doors 75.00
J. Double Wall Partition 50.00
K. Ceiling 50.00
L. Gutter & Flashing 35.00
M. Chipping of Floor topping 100.00
N. Cabinets,counters & shelves 75.00
O. Chipping of tiles 150.00
P. Scraping of vinyl tiles 50.00
Q. Wood parquet 60.00
R. Chipping of Synthetic Finish 50.00
S. Alum. Framed Glass 75.00
T. Blasting of Footings (by Dynamite) -
U. Blasting of Walls (by Dynamite) -
V. Cutting of Concrete -
W. Electrical
X. Plumbing
A. Latex Paint
a. Exterior -
Up to 36 Stories -
b. Interior -
c. Dulux Masonry Paint -
B. Silicon Water Repellant
a. With Conc. Neutralizer -
C. Automotive Paint
a. By Area (Metal Doors) -
b. By LM (Metal door jambs & 2"dia.GI Pipe Railing) -
c. By LM (1/2" Square Bars) -
D. Flat Wall Enamel (Alkyd Type)
a. By Area (Plywood Ceiling & HCF Doors) -
b. By LM (Kd Tang.baseboard & Stair Railing) -
E. Quick dry enamel
a. Steel Doors or Metal Surfaces -
b. Steel Windows (One side only) -
c. Trusses -
d. Trusses -
e. 2"dia. GI Pipes -
f. 1/2" Square Bars -
F. Polyurethane Paint
a. By Area -
b. By LM -
c. Natural (Wood Parquet) -
d. With Bleach (Natural Color) -
e. With Stain & Bleach -
G. Varnishing
a. Narra (Bleach)
i. By Area (Narra Plywood Partition) -
ii. By LM (Narra Stair Handrails) -
b. Ordinary Wood
i. Lattice -
ii. Doors
Flush Door -
Panel Door -
iii. Jambs -
iv. Baseboards -
v. Inside Cabinets -
H. Duco Paint
a. By Area (Cabinets & HCF Doors) -
b. By LM (Jambs, Mouldings & Stair Handrails)
i. 10" -
ii. 7" -
iii. 3" -
I. Spraytex
a. Concrete Ceiling -
b. Plywood ceiling -
J. Epoxy Paint
a. Metal Surfaces -
b. Trusses -
c. Trusses -
d. Trusses (Epoxy Primer) -
e. Tank
Inside -
Outside -
f. Tower -
g. Floor & Walls (Ordinary) -
h. Industrial Flooring -
K. Semi-Duco (Sprayed QDE)
a. By Area -
b. By LM -
L. Xyladecor
a. By Area -
M. Reflectorized Paint
a. Pedestrian Traffic Paint -
b. Wall (Zebra Type) -
c. By Lm (4" or 6") -
d. Parking No.(Signage) -
e. Tank Signage -
N. Satin Finish -
O. Thompson Water Seal
a. On Floors -
b. On Walls -
P. Acrytex
a. Gloss -
b. Semi-gloss -
c. Plain -
d. By LM -
Q. Textured
a. Gloss & Semi-gloss -
b. Textured Acrytex or Text-a crete w/ ordinary latex paint top -
For areas less than 0.30m -
c. Textured Acrytex or Text-a crete w/ ordinary acrytex or
text-a crete paint top coat -
For areas less than 0.30m -
R. Oil Finish on Cabinets
a. By Area -
b. By LM -
c. Handrubbed w/ penetrating stain -
d. Lacquer Stained (Semi-gloss) -
(Flat) -
S. Others
a. Tilecoat (Davies) -
b. Polomix (Dutch Boy) -
-
c. Sulatone (Boysen) -
d. Plexibond -
e. Gypsum Board Paint (excluding taping) -
f. Fiber Cement Paint -
g. Revarnish (Wash-over) -
h. Revarnish (Change Color) -
i. Roof Paint (New) -
j. Roof Paint (Repainting) -
k. Repainting (Latex) -
l. Repainting (Enamel) -
m. Low Cost Housing
i. Latex -
ii. Enamel -
iii. QDE (including primer) -
n. Multipleck w/ Deck Tape -
o. Granitone -
Textured Granitone w/ Colorless Protective Gloss Coating -
Simulated Textured Granite like Paint Fin. W/ Polyurethane Top Coat
Finish w/ Std. Manufacturer's Groove -
p. Liquid Tile Textured by Davies -
q. Mal Pherson by Davies -
r. Zinc Chromate (2 coats primer for steel trusses) -
s. Zinc Epoxy -
t. Turco Rustproofing -
u. Multifleck -
v. Stonetek -
w. Floor Epoxy Coating -
XI. FABRICATED MATERIALS (Materials & Sashworks)
XIII. OTHERS
K. Testing of Materials
i. Testing of Rebars (Length = 1.00m) (3 pcs. / 5,000 kgs.) -
ii. Testing of CHB (3 pcs. / 1,000 pcs.)
* 4" Chb -
** 6" Chb -
iii. Concrete Cylinder (Compression Test) (6 pcs. / 50.00 m -
iv. Soil Test
* Modified -
** Standard -
*** Field Density Test -
L. Precast Concrete -
-
NOTES :
All tools,equipments,scaffolding installation,accessories,hauling & other miscellaneous
shall be shouldered by the sub-contractors.
Hauling costs are included in above unit costs up to fourth floor if it will be done
starting to ground floor,however if works started from third or fourth floor,
additional hauling cost will be given to the subcontractors.
For High Rise Building, Hauling shall be done by Tower Crane but with the help of Subcon lab
(Painting) All lineal meters shall be computed once,(ex.Z-bar & sq.bar=total length=lm)
New unit costs are based on a minimum salary of P491.00/day
New unit costs are based if material is within the periphery of the building,if not
make an additional hauling costs to be computed by PE.
All items not included in above items of work shall be the responsibility of the Project
Engineer to compute and award to the contractors.
Formworks Unit Costs are based on Conventional Forms to be used,when scaffold use is
lumber add an additional of P15.00 per sq.m. of beams,slabs,Shearwall or RC Walls.
All unit costs are based on the standard construction procedures,any actual works that
deviates on standard shall be the responsibility of the PE concerned.
Differentiating Small to Medium and Large Scale construction shall be the responsibility
of the Project Job Captain involved.
CONSUMABLES:
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^^^^^^^^^^^^^^^^^^
Nails =
Total bft. =
Total bft. =
STRUCTURAL WORKS:
D.M.=Total materials + 7% consumables
D.L.=30% of D.M. (For Roof Framing)
40% of D.M. (For Others)
D.C.=D.M.+D.L.
Indirect Cost:
Contingencies=7.5% of D.M.
Overhead/Supervision=5% of D.C.
Profit=10% of D.C.
ACTUAL PRODUCTIONS
A. Formworks
Crew: 1 Leadman
1 Carpenter
1 Laborer
Production :
a. Columns
b. Footing Tie Beams & Pile Ca
c. Floor Beams
d. Floor Slabs
e. Roof Beams
f. Gutter & Parapet
g. Shearwalls
h. Stairs
i. Lintel Beams & Stiff. Columns
B. Rebars
Crew: 1 Steelman
Production : For 8 hrs. Operation
a. Columns & Pedestals
b. Footing Tie Beams & Pile Ca
c. Floor Beams
d. Floor Slabs
e. Roof Beams
f. Gutter & Parapet
g. Shearwalls
h. Stairs
i. Lintel Beams & Stiff. Columns
j. Slab on fill
C. Laying of CHB
Crew : 4.00
4.00
Production : 30.00
D. Boracay Finish
Crew : 4.00
4.00
Production : 15.00
30.00
E. Plastering
Crew : 4.00
4.00
Production : 30.00
45.00
F. Floor Topping
Crew : 4.00
4.00
Production : 35.00
G. Black Pebbles
Crew : 4.00
4.00
Production : 17.50
30.00
H. Glazed Tiles
Crew : 4.00
4.00
Production : 30.00
N. Vinyl Tiles
Crew : 2.00
1.00
Production : 45.00
O. Tinsmithry Works
Crew : 2.00
1.00
Production : 20.00
Installation = 10.00-20.00sq.m./d
P. Painting Works
Crew : 4.00
4.00
Production : 60.00
85.00
Q. Ceiling Installation
Crew : 2.00
2.00
Production : 15.00
12.50
Crew: 2 carpenters
Production = 6.50 sq.m./day (w/o
5.00 sq.m./day (w/ ceiling
R. Structural Steel
Fabrication :
Crew : 2.00
1.00
Production : 100.00
Manual Erection :
Crew : 1.00
2.00
Production : 150.00
S. Condeck
Installation
Crew : 4.00
2.00
Production : 150.00
OTHER INFORMATIONS :
FORMWORKS P
A-FRAMES P
217.00 bag
bag
bag 40kg/bag
bag 50kg/bag
100.00 kg.
300.00 bag
225.00 bag
200.00 bag
205.00 gal.
950.00 bag
185.00 bag
250.00 m3
520.00 m3
550.00 m3
m2
m2
m2
kg. 1.30
kg. 1.32
"Remington"
55.00 kg.
50.00 kg.
50.00 kg.
50.00 kg.
m2
m2
m2
m2
25.00 pc.
15.00 pc.
45.00 pc.
40.00 pc.
100.00 m2
120.00 m2
150.00 m2
1,130.00 pc.
1,550.00 1,610.00 pc.
550.00 pc.
900.00 pc.
400.00 pc.
500.00 pc.
350.00 pc.
65.00 bdft.
54.00 bdft.
3.50 lft.
12.00 bdft.
"Kutang Bato"
50.00 65.00 kg.
kg.
m2
m2
m2
m2
m2
m2
m2
72.51 m2 1.80m x 6.00m. 620.00
122.81 m2 1.80m x 6.00m. 1,050.00
m2
m2
m2
m2
m. "Boral"
m. "Boral"
m. "Boral"
m. "Boral"
82.00 pc.
m.
m. "Moldex PE Pipe"
m2
m2 7,020.00
18.13 m2 6,240.00
m2 6,240.00
kg.
kg.
45.00 kg.
kg.
kg.
kg.
kg.
545.00 liter
liter
kg.
kg.
kg.
kg.
475.00 bag
3,000.00 bag
148.00 bag 25 kg/bag
263.50 bag 25 kg/bag
kg.
kg.
kg.
kg.
pail 28kg/pail (1kg per 5lm-150mmwide
kg.
liter
liter
gal 4kg/gal.
set 36kg/set
gal 5kg/gal
ctg. 300ml/ctg.
ctg. 300ml/ctg.
ctg. 300ml/ctg.
ctg. 300ml/ctg.
ctg. 600ml/ctg.
kg.
kg.
kg.
kg.
70,000.00 drum 200 liters/drum
kg.
980.00 bag
kg. 11.5kg/m2-25mm thk.
850.00 bag
350.00 m2
1,000.00 bag
900.00 bag
2,000.00 drum
1,500.00 gal.
1,500.00 gal.
m2
m2
1,500.00 sheet 1/2"x3'x10'
2,500.00 sheet 3/4"x3'x10'
3,000.00 sheet 1"x3'x10'
85.00 sheet
125.00 sheet
704.00 sheet
1,056.00 sheet
2,100.00 sheet
7.50 m.
m.
m.
m.
2.65 m.
m.
m.
"Specseal"
575.00 ssg.
385.00 ssg.
250.00 ssg.
660.00 liter 1,650.00/pack (2.50 liters)
240.00 ssg.
350.00 tube 600 ml/tube
"Gyproc" "BPB"
275.00 board
board
board
280.00 310.00 board
495.00 board
465.00 board
board
board
board
board
board
board
900.00 board
board
board
"Flexboard"
285.00 board
335.00 700.00 board
450.00 750.00 board
720.00 845.00 board
1,025.00 board
1,980.00 board
2,250.00 2,700.00 board
pc.
pc.
pc.
"PETRONNE"
pc.
350.00 pc.
387.50 pc.
387.50 pc.
387.50 pc.
387.50 pc.
pc.
337.50 pc.
400.00 pc.
180.00 pc.
390.00 m2 50.00
620.00 m2 110.00
1,050.00 m2 150.00
340.00 m2 110.00
36.00 pc.
450.00 m2 35.00
800.00 pc.
board
board
board
board
board
board
board
board
board
board
board
board
board
board
board
board
board
board
"JAEFER"
240.00 pc. CMT/Exelcon 20
80.00 pc. - do - 20
40.00 pc. - do - 20
200.00 pc. - do - 20
20.00 lft.
"JAEFER"
pc.
pc.
pc.
9.00 pc.
pc.
pc.
pc.
pc.
13.90 pc.
m.
pc.
pc.
pc.
pc.
pc.
pc.
pc.
pc.
pc.
pc.
pc.
22.00 pc.
22.00 pc.
55.00 pc.
pc.
pc.
pc.
4.55 pc.
pc.
pc.
pc.
pc.
0.88 pc.
0.95 pc.
1.44 pc.
1.60 pc.
1.88 pc.
2.00 pc.
2.50 pc.
3.75 pc.
0.75 pc.
0.90 pc.
0.30 pc.
0.78 pc.
0.78 pc.
pc.
pc.
pc.
pc.
pc.
2.62 m.
20.34 m.
2.62 m.
0.65 m.
50.00 pc.
300.00 pc. 0.37
2.00 lft.
1,770.00 pail 110.625
6.00 pc.
860.00 pail 28kg/pail (1kg per 5lm-150mmwide
board
board
board
board
board
board
board
board
board
board
bd.ft.
bd.ft.
bd.ft.
45.00 bd.ft.
65.00 bd.ft.
3.50 lft.
bd.ft.
45.00 kg.
340.00 m.
380.00 m.
165.00 lm.
22.00 m. 9.17
45.00 lft.
415.00 m2 114.80
170.00 m. 110.00
170.00 m. 110.00
255.00 m. 110.00
350.00 m2 35.00
190.00 m. 110.00
285.00 m. 110.00
380.00 m. 110.00
140.00 m2 66.00
25.00 m2 -
85.00 kg.
316.00 pc. 39.50 /lft.
236.84 pc. 29.61 /lft.
0.83 pc.
Materials Installation
set 6,720.00 2,100.00
7,500.00 set
7,950.00 set
12,000.00 set
7,000.00 set
11,000.00 set
7,472.00 set
7,817.00 set
90.00 bdft.
3,500.00 m2
7,500.00 m2
4,000.00 set
100.00 pc.
25.00 pc.
6,500.00 set
4,500.00 set
3,500.00 set
1,200.00 set
1,200.00 set
700.00 pair
650.00 set
295.00 pc.
65.00 pc.
75.00 pc.
65.00 pc.
130.00 pc.
350.00 pc.
2,500.00 set
1,000.00 set
450.00 pc.
180.00 m2
120.00 m.
85.00 m2
450.00 m2
250.00 m.
50.00 liter
47.50 liter
85.00 liter
1,800.00 pc.
456.00 m2
370.00 m2
370.00 m2
900.00 m2
423.00 m2
400.00 m2
350.00 m2
pc.
pc.
pc.
pc.
4.00 pc.
10.50 pc.
10.50 pc.
14.50 pc.
35.00 pc.
150.00 pc.
175.00 pc.
250.00 pc.
105.00 pc.
3.50 pc.
10.50 pc.
12.50 pc.
14.50 pc.
17.50 pc.
35.00 pc.
150.00 pc.
175.00 pc.
250.00 pc.
25.00 pc.
4.00 pc.
5,000.00 m2
2,500.00 m2
120.00 pc.
210.00 pc.
300.00 pc.
60.00 can
40.00 can
1,000.00 m2
1,200.00 m2
4.00 pc.
4.00 pc.
13.00 pc.
90.00 can
90.00 can
45.00 can
45.00 can
50.00 can
45.00 pc.
12.50 pc.
25.00 pc.
75.00 pc.
32.00 pc.
60.00 pc.
52.50 pc.
450.00 gal.
550.00 m2
m. Luzon Foundry Code #110
m.
m.
m.
m.
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
180.00 m2
494.44 m2
611.11 m2
666.67 m2
110.00 m2
2,150.00 pc.
1,250.00 pc.
850.00 pc.
1,000.00 pc.
850.00 pc.
510.00 pc.
650.00 pc. 9.58 kgs.
1,000.00 pc. 14.36 kgs.
475.00 pc. 7.18 kgs.
1,250.00 pc. 19.15 kgs.
2,000.00 pc. 28.73 kgs.
1,850.00 pc. 28.73 kgs.
3,000.00 pc. 43.09 kgs.
3,200.00 pc. 38.31 kgs.
4,000.00 pc. 57.46 kgs.
1,200.00 pc. 18.69 kgs.
1,500.00 pc. 23.36 kgs.
2,400.00 pc. 35.04 kgs.
4,800.00 pc. 70.07 kgs.
3,500.00 pc. 74.16 kgs.
4,500.00 pc. 111.24 kgs.
179.56 pc.
90,000.00 pc.
72,900.00 pc.
13,020.00 pc.
9,000.00 pc.
52,554.33 pc.
21,021.73 pc.
6,674.40 pc.
350.00 pc.
450.00 pc.
25.00 pc.
elefax 440-07-15
1,200.00 pc.
30,000.00 set
4,000.00 m.
2,500.00-5,000.00 m. (From Bacolod City Hall)
4,500.00 sq.m.
100.00 m.
175.00 ft2
200.00 ft2
75.00 ft2
50.00 ft2
2,500.00 pc.
1,500.00 pc.
1,000.00 m.
500.00 set
45,000.00 unit
250.00 pc.
1,250.00 pc.
150.00 pc.
115.00 pc.
15.00 pc.
7.50 pc.
50.00 pc.
30.00 pc.
65.00 pc.
10.00 pc.
800.00 pc.
150.00 pc.
350.00 m3
35.00 m2 15.00
3,500.00 m2
2,000.00 m2
150.00 no.
250.00 m.
273.42 m.
10,000.00 unit
1,500.00 unit
65,000.00 pc.
45,000.00 pc.
175,000.00 pc.
170,000.00 set
8,500.00 m. Stainless Steel (Hammerhead)
6,500.00 m. Fiberglass
160.00 m2
4,300.00 m2
950.00 gal.
250.00 m.
590.00 m.
105.00 ft2
45.00 ft2
260.00 ft2 Less 30% (As of April 2008) Add 12% VAT
100,000.00 set
750,000.00 set
1.50 kg.
37,500.00 van 20 footer Container Van
250.00 m.
510.00 m.
1,070.00 pc.
28,750.00 pc.
27,200.00 pc.
450.00 bag
288.00 gal.
4,850.00 m2
65.00 bft.
3,000.00 pc.
110.00 m.
1,800.00 - 2,400.00 m2 (Including Installation)
13,000.00 m3
850.00 m2
525.00 gal.
250.00 pc.
115.00 m2
25.00 m2
45.00 m2
23.00 lft.
30.00 lft.
450.00 m2
32.00 pc.
100.00 pc.
36.00 pc.
14.00 pc.
450.00 pc.
35,000.00 roll 972.22 /sq.m.
75.00 pc.
1,800.00 roll
980.00 bag
2,600.00 pail
180.00 m2
150.00 m2
7,500.00 m2
120.00 m2 3 kg./sq.m.
140.00 m2 4 kg./sq.m.
165.00 m2 5 kg./sq.m.
2,700.00 roll
2.50 lm.
2,500.00 gal.
1,000.00 pc.
7,000.00 pc.
RENTALS
2,500.00 /hr.
1,250.00 /hr.
850.00 /hr.
750.00 /hr.
650.00 /hr.
500.00 /hr.
900.00 /hr.
500.00 /hr.
250.00 /hr.
125.00 /hr.
100.00 /hr.
150.00 /hr.
100.00 /hr.
2,000.00 /hr.
150.00 /hr.
75.00 /hr.
350.00 /hr.
1,500.00 /hr.
1,250.00 /hr.
750.00 /hr.
500,000.00 /unit
273,240.00 /unit
268,400.00 unit
66,000.00 unit
16,500.00 unit
34,700.00 unit
25,360.00 unit
20,000.00 pc.
12,200.00 pc.
2,700.00 pc.
1,400,000.00 unit
100,000.00 /mo.
980,000.00 unit
1,200,000.00 unit
450,000.00 unit
7,300,000.00 unit
BUYING
500,000.00 /unit
273,240.00 /unit
268,400.00 unit
66,000.00 unit
16,500.00 unit
34,700.00 unit
25,360.00 unit
20,000.00 pc.
12,200.00 pc.
2,700.00 pc.
1,400,000.00 unit
980,000.00 unit
1,200,000.00 unit
450,000.00 unit
7,300,000.00 unit
DAILY RATES
750.00 /day
650.00 /day
550.00 /day
550.00 /day
550.00 /day
550.00 /day
456.00 /day
485.00 /day
475.00 /day
600.00 /day
650.00 /day
650.00 /day
750.00 /day
650.00 /day
485.00 /day
550.00 /day
550.00 /day
481.00 491.00
MEDIUM LARGE
SCALE SCALE UNITS
50.00 - lm.
185.00 - sq.m.
135.00 pc.
160.00 pc.
plus 15.00 plus 15.00
Installation Stripping
Big Scale
200.00 100.00 sq.m.
195.00 100.00 sq.m.
190.00 100.00 sq.m.
195.00 100.00 sq.m.
190.00 100.00 sq.m.
225.00 100.00 sq.m.
215.00 100.00 sq.m.
200.00 100.00 sq.m.
215.00 100.00 sq.m.
195.00 100.00 sq.m.
195.00 100.00 sq.m. Materials
285.00 - sq.m. 320.00
300.00
90.00 - sq.m.
265.00 - sq.m.
350.00 - set
250.00 - set
175.00 - set
600.00 - set
175.00 - set
175.00 - set
175.00 - set
175.00 - set
175.00 - set
100.00 - lm.
12.50 - pc.
30.00 - pc.
30.00 - pc.
250.00 - sq.m.
12.50 - sq.m.
450.00 - sq.m.
140.00 - sq.m.
120.00 - sq.m.
130.00 - sq.m.
60.00 - sq.m.
400.00 - sq.m.
350.00 - sq.m.
350.00 - sq.m.
350.00 - sq.m.
350.00 - sq.m.
200.00 - sq.m.
200.00 - sq.m.
135.00 - lm.
40.00 - lm.
40.00 - lm.
1,350.00 - sq.m.
55.00 - lm.
335.00 - sq.m.
135.00 - sq.m.
100.00 - sq.m.
100.00 - sq.m.
335.00 - sq.m.
315.00 - sq.m.
80.00 - lm.
80.00 - lm.
160.00 - pc.
200.00 - sq.m.
55.00 - sq.m.
50.00 - lm.
85.00 - lm.
250.00 - sq.m.
160.00 - lm.
135.00 - lm.
165.00 - pc.
165.00 - lm.
165.00 - unit
85.00 - unit
260.00 - sq.m.
45.00 - sq.m.
285.00 - sq.m.
55.00 - sq.m.
325.00 - sq.m.
75.00 - sq.m.
340.00 - sq.m.
85.00 - sq.m.
360.00 - sq.m.
105.00 - sq.m.
220.00 200.00 sq.m.
225.00 215.00 sq.m.
750.00 - sq.m.
700.00 - sq.m.
1,875.00 - sq.m.
1,750.00 - sq.m.
1,750.00 - sq.m.
1,650.00 - sq.m.
1,650.00 - sq.m.
1,500.00 - sq.m.
225.00 - lm.
550.00 - lm.
450.00 - lm.
100.00 - lm.
150.00 - sq.m.
85.00 - cu.m.
125.00 - sq.m.
125.00 - sq.m.
125.00 - sq.m.
450.00 - sq.m.
225.00 - sq.m.
375.00 - sq.m.
200.00 - sq.m.
225.00 - sq.m.
85.00 - sq.m.
225.00 - sq.m.
550.00 - sq.m.
850.00 - sq.m.
450.00 - sq.m.
750.00 - sq.m.
375.00 - sq.m.
510.00 - sq.m.
325.00 - sq.m.
600.00 lm.
415.00 lm.
250.00 - lm.
265.00 - lm.
165.00 - lm.
485.00 - lm.
190.00 - lm.
250.00 - lm.
165.00 - sq.m.
285.00 - sq.m.
120.00 sq.m.
5.00 pc.
15.00 pc.
15.00 sq.m.
100.00 - sq.m.
120.00 - sq.m.
290.00 - sq.m.
10.00 - sq.m.
40.00 - sq.m.
220.00 sq.m.
280.00 lm.
4.00 3.75 kg.
4.50 4.00 kg.
4.75 4.25 kg.
4.85 4.50 kg.
4.70 4.25 kg.
5.90 5.25 kg.
7.90 7.00 kg.
5.00 4.50 kg.
5.65 5.00 kg.
6.75 6.25 kg.
5.25 4.50 kg.
9.00 8.00 kg.
5.65 5.25 kg.
5.65 5.25 kg.
5.65 5.25 kg.
6.00 6.00 kg.
45.00 40.00 sq.m.
0.50 - kg.
0.60 - kg.
0.50 - kg.
- 4.85 kg.
0.50 - kg.
200.00 - cu.m.
150.00 100.00 cu.m.
150.00 - cu.m.
125.00 100.00 cu.m.
650.00 550.00 cu.m.
100.00 - cu.m.
150.00 - sq.m.
750.00 600.00 pp
200.00 175.00 sq.m.
100.00 85.00 lm.
500.00 350.00 pp
4,000.00 3,000.00 pp
6,000.00 4,500.00 pp
85.00 65.00 sq.m.
+ 15% Outside MM
180.00 - sq.m.
200.00 - sq.m.
180.00 - sq.m.
200.00 - sq.m.
135.00 - sq.m.
500.00 - sq.m.
280.00 - lm.
125.00 - lm.
170.00 - sq.m.
125.00 - lm.
280.00 - sq.m.
150.00 - sq.m.
150.00 - sq.m.
85.00 - lm.
125.00 - lm.
65.00 - lm.
500.00 - sq.m.
280.00 - lm.
400.00 - sq.m.
500.00 - sq.m.
500.00 - sq.m.
500.00 - sq.m.
275.00 - lm.
500.00 - sq.m.
500.00 - sq.m.
525.00 - sq.m.
280.00 - lm.
280.00 - lm.
400.00 - sq.m.
500.00 - sq.m.
280.00 - lm.
225.00 - lm.
125.00 - lm.
400.00 - sq.m.
400.00 - sq.m.
500.00 - sq.m.
500.00 - sq.m.
280.00 - lm.
0.50 - kgs.
700.00 - sq.m.
600.00 - sq.m.
700.00 - sq.m.
600.00 - sq.m.
600.00 - sq.m.
400.00 - sq.m.
250.00 - lm.
400.00 - sq.m.
450.00 - sq.m.
350.00 - sq.m.
125.00 - lm.
100.00 - no.
125.00 - letter
350.00 - sq.m.
350.00 - sq.m.
200.00 - sq.m.
400.00 - sq.m.
400.00 - sq.m.
350.00 - sq.m.
185.00 - lm.
450.00 - sq.m.
450.00 - sq.m.
200.00 - lm.
450.00 - sq.m.
200.00 - lm.
450.00 - sq.m.
250.00 - lm.
500.00 - sq.m.
400.00 - sq.m.
375.00 - sq.m.
500.00 - sq.m.
700.00 - sq.m.
250.00 - lm.
700.00 - sq.m.
500.00 - sq.m.
180.00 - sq.m.
180.00 - sq.m.
180.00 - sq.m.
450.00 - sq.m.
150.00 - sq.m.
180.00 - sq.m.
150.00 - sq.m.
150.00 - sq.m.
150.00 - sq.m.
150.00 - sq.m.
100.00 - sq.m.
850.00 - sq.m.
1,750.00 - sq.m.
750.00 - sq.m.
2,750.00 - sq.m.
700.00 - sq.m.
625.00 - sq.m.
150.00 - sq.m.
700.00 - sq.m.
35.00 - sq.m.
875.00 - sq.m.
1,000.00 - sq.m.
450.00 - sq.m.
110.00 - bd.ft.
100.00 - bd.ft.
3,100.00 - set
3,400.00 - set
3,300.00 - set
3,700.00 - set
4,600.00 - set
4,400.00 - set
750.00 - set
9,000.00 - set
15,000.00 - set
1,500.00 - set
2,000.00 - set
4,000.00 - set
175.00 - sq.ft. Labor = P 10.00 - 15.00/sq.ft.
185.00 - sq.ft.
75.00 - sq.ft.
125.00 - sq.ft.
225.00 - sq.ft.
50.00 - kgs. Materials
40.00 30.00 kgs. Fabrication & Installation
375.00 - cu.m.
325.00 - cu.m.
350.00 - cu.m.
450.00 - cu.m.
1,500.00 /hole
75.00 - lm.
125.00 - lm.
300.00 - shot
175.00 - lft.
280.00 - sq.ft.
450.00 - joint
2,250.00 - truss
200.00 - lft.
350.00 - sq.ft.
250.00 - pc.
280.00 - pc.
280.00 - pc.
250.00 - pc.
2,500.00 - hole
2,500.00 - hole
500.00 - hole
25,000.00 - cu.m.
3,500.00 - sq.m.
350.00 - sq.m.
300.00 - sq.m.
135.00 - sq.m.
3,000.00 - lm.
5,500.00 - pp Driving
350.00 - lm.
2,500.00 - pp
r miscellaneous
total length=lm)
of the Project
he responsibility
^^^^^^^^^^^^^^^^^
BF
------------------------ = No. of kegs.
40 X 45
Vt x 192
------------------------ (For Ftb, Lintel beams & Stiff.columns)
2.40
Vt x 192
------------------------ (for all other structures)
1.60
Wt
Wires #16 = ---------------------- (For Big Scale Projects)
65x45
Wt
Wires #16 = ---------------------- (For Medium Scale Projects)
60x45
Wt
Wires #16 = ---------------------- (For Small Scale Projects)
50x45
Fabrication (Built-up I-Beam)
Production = 5 to 8 tons/day (12 welders)
Erection (Floor Framing)
Production = 8 to 12 tons / day
Installation
Steel Lumber
3.00 4.00
ng Tie Beams & Pile Caps 4.00 4.50
2.50 6.00
2.50 7.00
2.00 4.00
r & Parapet 2.00 3.00
3.00 3.50
3.50
Beams & Stiff. Columns 5.00
ES P 25.00-40.00 / SQ.M.
/lm.
19.09 /lft.
13.41 /lft.
/lft.
/lft.
/lft.
/lft.
/m
/m
/m2
365.62 /kg.
332.38 /kg.
354.54 /kg.
345.68 /kg.
365.62 /kg.
354.54 /kg.
101.30 /kg.
111.40 /kg.
175.41 /kg.
87.65 /kg. 4,513.89 /sq.m.
87.20 /kg. 3,368.06 /sq.m.
87.65 /kg. 2,256.94 /sq.m.
118.48 /kg. 583.33 /sq.m.
108.29 /kg. 399.31 /sq.m.
93.75 /lm.
67.87 /kg.
69.61 /kg.
66.13 /kg.
65.26 /kg.
69.61 /kg.
64.39 /kg.
69.61 /kg.
83.54 /kg.
69.61 /kg.
64.22 /kg.
64.22 /kg.
68.50 /kg.
68.50 /kg.
47.20 /kg.
40.45 /kg.
(Bostik)
1.02
y for 2 days + P10,000.00/pp x 8 = P 280,000.00
al no. of BP
al no. of BP (Ultrasonic)
rs/day = 12/5 = 2.40 sq.m./day
LABOR
UNIT
COST
sq.m./day 251.50
sq.m./day 223.56
sq.m./day 167.67
sq.m./day 143.71
sq.m./day 251.50
sq.m./day 335.33
sq.m./day 287.43
sq.m./day 287.43
sq.m./day 201.20
/sq.m.
/sq.m.
/lm.
/sq.m.
/lm.
/sq.m.
/sq.m.
/lm.
/sq.m.
/sq.m.
/sq.m.
/sq.m.
/lm.
/lm.
/sq.m.
/lft.
/sq.m.
/lm.
/sq.m.w/o Ceiling Truss
/sq.m.w/ Ceiling Truss
./day/installer
/kg.
/kg.
/kg.
/sq.m.