Price:
Cement 235 /bag
Sand 850 cu. m.
Gravel 800 cu. m.
Reinforcement 378 6m long
Tie Wire 70 /kg
Price:
Cement 250 /bag
Sand 850 cu. m.
Gravel 800 cu. m.
Reinforcement 420 6m long
Tie Wire 70 /kg
Lateral Ties 170 6m long
Wall Footing
Class Bill of Materials Cost of Estiamte
Cement: 10.0 bags Wall Footing Cost: 4506.8
Depth 0.6 m Sand: 0.5 cu. m.
Width 0.3 m Gravel: 1.1 cu. m.
Length of Wall 6m Main Reinforcement: 3.0 lghts
# of Reinf. 3 pcs Tie Wie: 0.3 kg
Spacing Of Lat. Ties 0.4 m Lateral Ties: 3 lghts
Price:
Cement 235 /bag
Sand 450 cu. m.
Gravel 750 cu. m.
Reinforcement 260 6m long
Tie Wire 70 /kg
Lateral Ties 100 6m long
Price:
Cement 255 /bag
Sand 1200 cu. m.
Gravel 1500 cu. m.
Reinforcement 170 6m long
Tie Wire 70 /kg
Price:
CHB 20 pcs
Cement 250 bags
Sand 800 cu. m.
Reinforcement 170 lghts
Tie Wire 70 kg
Price:
Hardi Senepa 110 /lgth
Self drilling tile screw 550 /box
f Materials Cost of Estiamte
lgths Gypsum Cost: 41767.3
pcs
lgths
lgths
lgths
pcs
boxes
boxes
sheets
Price:
Cement 250 /bag
Sand 850 /cu. m.
Price:
Tile 700 /piece
Cement 250 /bag
Joint Filler 55 /kg
Paint Bill of Materials
Area to be Painted 240 sq. m. Primer: 10 /gal
No. of Coats 240 sq. m. Top Coat: 2304 /gal
Concrete Neutralizer: 2 /gal
Price: Flat Latex: 12 /gal
Primer 700 /gal
Top Coat 500 /gal
Concrete Neutralizer 200 /gal
Flat Latex 700 /gal
Cost of Estiamte
Finish Cost: 52878.0
Cost of Estiamte
Finish Cost: 382840
Cost of Estiamte
Finish Cost: 1169300
Column Bill of Materials
Length of Column 7m lumber: 5897.9 bd. ft.
# of Column 15 pcs
Lumber size cm
Price:
lumber 25 /bd. ft.
Price:
lumber 30 /bd. ft.
Price:
lumber 16 /bd. ft.
plywood 600 /sheet
Cost of Estiamte
Finish Cost: 147446.3
Cost of Estiamte
Finish Cost: 73710.0
Cost of Estiamte
Finish Cost: 62080.0
TOTAL: 283236.3