Column Footing Bill of Materials Cost of Estiamte

Class Cement: 198.0 bags Col. Footing Cost: 125946.6


Sand: 11.0 cu. m.
Thickness cm Gravel 21.9 cu. m.
Area 2.25 sq. m. Main Reinforcement: 137.0 lghts
# of Footing 39 pcs Tie Wire: 10.8 kg

Length of Reinf. 1.5 m


# of Bars along its L 7 pcs
# of Bars along its W 7 pcs

Price:
Cement 235 /bag
Sand 850 cu. m.
Gravel 800 cu. m.
Reinforcement 378 6m long
Tie Wire 70 /kg

Column Bill of Materials Cost of Estiamte


Class Cement: 36.0 bags Column Cost: 32207.0
Sand: 2.0 cu. m.
Length of Column 11 m Gravel: 4.0 cu. m.
# of Column 4 pcs Main Reinforcement: 32.0 lghts
Size of Column cm Tie Wire: 12.8 kg
Lateral Ties: 53.0 lghts
Total Length of Reinf. 6m
# of Reinf. 8 pcs
# of Lateral Ties 53 pcs
Length per Lateral Ties 1.5 m
Price:
Cement 250 /bag
Sand 850 cu. m.
Gravel 800 cu. m.
Reinforcement 378 6m long
Tie Wire 75 /kg
Lateral Ties 100 6m long

Beam & Girder


Class Bill of Materials Cost of Estiamte
Cement: 237.6 bags Beam/Girder Cost: 151188.9
Length of Beam 10 m Sand: 13.2 cu. m.
# of Beam 22 pcs Gravel 26.4 cu. m.
Size of Beam cm Main Reinforcement: 132.0 lghts
Tie Wire: 134.5 kg
Total Length of Reinf. 6m Lateral Ties: 148.5 lghts
# of Reinf. 6 pcs
# of Lateral Ties 135 pcs
Length per Lateral Ties 0.3 m

Price:
Cement 250 /bag
Sand 850 cu. m.
Gravel 800 cu. m.
Reinforcement 420 6m long
Tie Wire 70 /kg
Lateral Ties 170 6m long

Wall Footing
Class Bill of Materials Cost of Estiamte
Cement: 10.0 bags Wall Footing Cost: 4506.8
Depth 0.6 m Sand: 0.5 cu. m.
Width 0.3 m Gravel: 1.1 cu. m.
Length of Wall 6m Main Reinforcement: 3.0 lghts
# of Reinf. 3 pcs Tie Wie: 0.3 kg
Spacing Of Lat. Ties 0.4 m Lateral Ties: 3 lghts

Price:
Cement 235 /bag
Sand 450 cu. m.
Gravel 750 cu. m.
Reinforcement 260 6m long
Tie Wire 70 /kg
Lateral Ties 100 6m long

Slab Bill of Materials Cost of Estiamte


Class Cement: 144.0 bags Slab Cost: 75781.60
Sand: 8.0 cu. m.
Thickness cm Gravel: 16.0 cu. m.
Area 80 sq. m. Main Reinforcement: 158.2 lghts
Tie Wire: 15.1 kg
Type of Reinforcement way
Bar Spacing cm

Price:
Cement 255 /bag
Sand 1200 cu. m.
Gravel 1500 cu. m.
Reinforcement 170 6m long
Tie Wire 70 /kg

Wall Bill of Materials Cost of Estiamte


Class CHB: 625.0 pcs Wall Cost: 91816.0
Cement: 77.0 bags
CHB Size cm Sand: 5.0 cu. m.
Main Reinforcement: 312.0 lghts
Area: 50 sq. m. Tie Wire: 43.0 kg

Ver. Reinf. Spacing: cm


Hor. Reinf. Spacing: Layer

Price:
CHB 20 pcs
Cement 250 bags
Sand 800 cu. m.
Reinforcement 170 lghts
Tie Wire 70 kg

Lintel Beam Bill of Materials Cost of Estiamte


Class Cement: 0.2 bags Wall Cost: 419.6
Sand: 0.0 cu. m.
Length of lintel beam 2m Gravel: 0.0 cu. m.
Main Reinforcement: 1.0 lghts
Price: Tie Wie: 0 kg
Cement 235 bags Lateral Ties: 2 lghts
Sand 550 cu. m.
Gravel 700 cu. m.
Reinforcement 142 lghts
Tie Wire 70 kg
Lateral Ties 100 kg
Ceiling - Gypsum Board Bill of Materials
Ceiling Area 108.4 sq. m. Wall Angle: 17.0
Perimeter 47 m Concrete Nails: 157.7
Length of Hanger 3m J Furring: 58.0
Carrying Channel: 29
Price: Single Furring: 25
Wall Angle 45 /piece W - Clip: 193
Concrete Nails 2 /pcs Rivets: 2
J Furring 130 /lgth Ficem Screw: 2
Carrying Channel 125 /lght Gypsum Board: 37
Single Furring 100 /lght
W - Clip Double 4 /pcs
Rivets 550 /box
Ficem Screw 550 /box
Gypsum Board 650 sheets

Ceiling - Vinyl Soffits Bill of Materials


Width of Eaves 1.2 m Wall Angle: 63.0
Length of Eaves 85 m Concrete Nails: 601.0
Ceiling Area 180 sq. m. J Furring: 96.0
Perimeter of Entire Ceiling 180 m Carrying Channel: 48
Length of Hanger 2m Single Furring: 27
W - Clip: 320
Price: Rivets: 4
Wall Angle 66 /piece Ficem Screw: 4
Concrete Nails 2.5 /pcs Vinyl Soffits: 95
J Furring 220 /lgth J - Channel: 50
Carrying Channel 254 /lght
Single Furring 167 /lght
W - Clip Double 6.72 /pcs
Rivets 550 /box
Ficem Screw 600 /box
Vinyl Soffits 690 /lgth
J - Channel 300 /lgth
Skirtings and Mouldings Bill of Materials
Perimeter 66 m Moulding: 28.0
Depth of Skirting 0.15 m Skirting 28.0
Moulding Nails: 560
Price: Paint: 1
Moulding 530 /lgth
Moulding Nails 2 /pc
Paint 300 /gal

Fascia Bill of Materials


Perimeter of Celing 85 m Hardi Senepa: 36.0
Length of Senepa 2.4 m Moulding Nails: 2

Price:
Hardi Senepa 110 /lgth
Self drilling tile screw 550 /box
f Materials Cost of Estiamte
lgths Gypsum Cost: 41767.3
pcs
lgths
lgths
lgths
pcs
boxes
boxes
sheets

f Materials Cost of Estiamte


lgths Vinyl Soffits Cost: 130551.9
pcs
lgths
lghts
lghts
pcs
boxes
boxes
lgths
lghts
f Materials Cost of Estiamte
lghts Skirt & Mold Cost: 16260.0
lghts
pcs
gals

f Materials Cost of Estiamte


lghts Fascia Cost: 5060.0
boxes
Plain Cement Finish Bill of Materials
Class Cement: 199.0 bags
Sand: 3.68 cu. m.
Wall Area 230 sq. m.
Plaster Thickness
Thickness of Finishing 20 mm
# of sides 2

Price:
Cement 250 /bag
Sand 850 /cu. m.

Tile Bill of Materials


Area to be Tiled 175 sq. m. Tiles: 486 pcs
Tile Width 60 cm Cement: 151 bags
Tile Length 60 cm Joint Filler: 87.5 kg

Price:
Tile 700 /piece
Cement 250 /bag
Joint Filler 55 /kg
Paint Bill of Materials
Area to be Painted 240 sq. m. Primer: 10 /gal
No. of Coats 240 sq. m. Top Coat: 2304 /gal
Concrete Neutralizer: 2 /gal
Price: Flat Latex: 12 /gal
Primer 700 /gal
Top Coat 500 /gal
Concrete Neutralizer 200 /gal
Flat Latex 700 /gal
Cost of Estiamte
Finish Cost: 52878.0

Cost of Estiamte
Finish Cost: 382840
Cost of Estiamte
Finish Cost: 1169300
Column Bill of Materials
Length of Column 7m lumber: 5897.9 bd. ft.
# of Column 15 pcs
Lumber size cm

Price:
lumber 25 /bd. ft.

Beam Bill of Materials


Length of Beam 3m lumber: 2457.0 bd. ft.
# of Beam 63 pcs
Lumber size cm

Price:
lumber 30 /bd. ft.

Flooring Bill of Materials


Area 175 sq. m. lumber: 1592.5 bd. ft.
Lumber size cm plywood: 61 sheets

Price:
lumber 16 /bd. ft.
plywood 600 /sheet
Cost of Estiamte
Finish Cost: 147446.3

Cost of Estiamte
Finish Cost: 73710.0

Cost of Estiamte
Finish Cost: 62080.0

TOTAL: 283236.3