You are on page 1of 22

2022

Important
Points for Site
Engineers
Collection By : Arch.Nasser "Mansoor"
Phone & Whatsapp: +93789735776
Email: nasser.abassi2017@gmail.com
‫ﻣﻮﻓﻘﯿﺖ ﻫﺮ اﻧﺠﻨﯿﺮ و داﺷﺘﻦ ﯾﮏ ﺟﺎﻣﻌﻪ ﻣﻌﯿﺎری ﻣﻬﻨﺪﺳﯽ و اﻧﺠﻨﯿﺮی آروزی ﻣﻦ اﺳﺖ‬
Civil engineering
270
IMPORTANT POINTS FOR
CIVIL ENGINEERS
Haidari

Facebook:@Eng.haidari2010 Telegram: @civil_eng_international


-
1. There are different steps involved in Building 7. LEAR COVER TO MAIN REINFORCEMENT:
construction like, a. Footings : 50 Mm
Concreting b. Raft Foundation. Top : 50 Mm
Masonry work c. Raft Foundation. Bottom/Sides : 75 Mm
Plastering work d. Strap Beam : 50 Mm
Flooring work e. Grade Slab : 20 Mm
Formwork f. Column : 40 Mm
Steel cutting and Bending g. Shear Wall : 25 Mm
2. Measure the volume of concrete. h. Beams : 25 Mm
The volume of concrete is calculated by Multiplying i. Slabs : 15 Mm
its Length, Width, and Thickness together. For j. Flat Slab : 20 Mm
Example – 1m x1m = 1 m³ of volume of concrete. k. Staircase : 15 Mm
3. Concrete cover for reinforcement is required to l. Ret. Wall : 20/ 25 Mm On Earth
protect the rebar against corrosion and to provide m. Water Retaining Structures : 20/30 Mm
resistance against fire. 8. WEIGHT OF ROD PER METER LENGTH: DIA
4. Calculate the weight of 12m long and 10mm dia at WEIGHT PER METER; (Formula=D^2/162)
the Steel on-site. a. 6mm = 0.222Kg
By multiplying the length of the steel bar with its b. 8mm = 0.395 Kg
unit weight (Unit wt. of 10mm = 0.60 kg/m) c. 10mm = 0.616 Kg
Weight of steel = 0.60x 12 = 7.2 kg d. 12mm = 0.888 Kg
5. The equation used for calculating the unit weight e. 16mm = 1.578 Kg
f. 20mm = 2.466 Kg
of the steel bar is (D²/162).
g. 25mm = 3.853 Kg
6. The size of a concrete cube is 15 cm x 15 cm x 15
h. 32mm = 6.313 Kg
cm.
i. 40mm = 9.865 Kg

Facebook:@Eng.haidari2010 Telegram: @civil_eng_international


-
9. UNITS: 12. M20 (1: 2.48: 3.55)
a. 1bag cement-50kg Cement: 320 Kg/ M 3
b. 1feet-0.3048m 20 mm Jelly: 683 Kg/ M 3
c. 1m-3.28ft 12.5 mm Jelly: 455 Kg/ M 3
d. 1sq.m-10.76sq.ft River sand: 794 Kg/ M 3
e. 1cu.m-35.28cu.ft Total water: 176 Kg/ M 3
f. 1acre-43560sq.ft Admixture: 0.7%
g. 1cent-435.6sq.ft Fresh concrete density: 2430 Kg/ M 3
h. 1hectare-2.47acre 13. M25 (1: 2.28: 3.27)
i. 1acre-100cent-4046.724sq.m Cement: 340 Kg/ M 3
j. 1ground-2400sq.ft 20 mm Jelly: 667 Kg/ M 3
k. 1unit-100cu.ft-2.83cu.m 12.5 mm Jelly: 445 Kg/ M 3
l. 1square-100sq.ft River sand: 775 Kg/ M 3
10. 1M LENGTH STEEL ROD I ITS VOLUME Total water: 185 Kg/ M 3
V= (Pi/4) x Dia x DiaX L= (3.14/4) x D x D X 1 (for Admixture: 0.6%
1m length) Density of Steel=7850 kg/ cub meter Fresh concrete density: 2414 Kg/ M 3
Weight = Volume x Density= (3.14/4) x D x D X Note: sand 775 + 2% moisture, Water185 -20.5 =
1x7850 (if D is in mm) so = ((3.14/4) x D x D X 164 Liters,
1x7850)/ (1000x1000) = Dodd/162.27 Admixture = 0.5% is 100ml
11. DESIGN MIX 14. M30 (1: 2: 2.87)
M10 (1: 3.92: 5.62) Cement: 380 Kg/ M 3
Cement: 210 Kg/ M 3 20 mm Jelly: 654 Kg/ M 3
12.5 mm Jelly: 436 Kg/ M 3
20 mm Jelly: 708 Kg/ M 3
River sand: 760 Kg/ M 3
12.5 mm Jelly: 472 Kg/ M 3
Total water: 187 Kg/ M 3
River sand: 823 Kg/ M 3
Admixture: 0.7%
Total water: 185 Kg/ M 3
Fresh concrete density: 2420 Kg/ M 3
Fresh concrete density: 2398 Kg/M 3 Note: Sand = 760 Kg with 2% moisture
(170.80+15.20)

Facebook:@Eng.haidari2010 Telegram: @civil_eng_international


-
15. M35 (1: 1.79: 2.57)
18. M50 (1: 1.44: 2.23)
Cement: 410 Kg/ M 3
Cement: 450 Kg/ M 3
20 mm Jelly: 632 Kg/ M 3
20 mm Jelly: 590 Kg/ M 3
12.5 mm Jelly: 421 Kg/ M 3
12.5 mm Jelly: 483 Kg/ M 3
River sand: 735 Kg/ M 3
River sand: 689 Kg/ M 3 + Bulk age 12%
Total water: 200 Kg/ M 3
Water Cement ratio: 0.36 (188 Kg)
Admixture: 0.7%
Admixture: 1.20%3
Fresh concrete density: 2400 Kg/ M 3
Micro silica: 30 Kg
Note: sand = 735 + 2%, Water = 200- 14.7 = 185.30,
Super flow 6.7% of cement
Admixture = 0.7%
19. 1 cubic meter contains 500 bricks
16. M40 (1: 1.67: 2.39)
The Standard size of the 1st class brick is 190mm
Cement: 430 Kg/ M 3
20 mm Jelly: 618 Kg/ M 3 x 90mm x 90mm and motor joint should be 10mm
12.5 mm Jelly: 412 Kg/ M 3 thick So brick with motor=200 x 100 x 100.Volume
River sand: 718 Kg/ M 3 of 1st class brick = 0.19 x 0.09 X 0.09 = 0.001539
Water Cement ratio: 0.43 cu.m Volume of 1st class brick with motor =0.2 x
Admixture: 0.7% 0.1 x 0.1=0.002 cu.m
Note: Sand = 718 + Bulk age 1% No. on bricks per 1cu.m= 1/volume of1st class brick
17. M45 (1: 1.58: 2.26) with mortar =1/0.002 = 500 no’s of bricks
Cement: 450 Kg/ M 3 20. STANDARD CONVERSION FACTORS
20 mm Jelly: 626 Kg/ M 3 Inch = 25.4 Millimeter
12.5 mm Jelly: 417 Kg/ M 3
Foot = 0.3048 Meter
River sand: 727 Kg/ M 3 + Bulk age 1%
Yard = 0.9144 Meter
Water Cement ratio: 0.43
Mile = 1.6093 Kilometer
Admixture: 0.7%
Acre = 0.4047 Hectare
Pound = 0.4536 Kilogram
Degree Fahrenheit X 5/9 – 32 = Degree Celsius

Facebook:@Eng.haidari2010 Telegram: @civil_eng_international


-
Millimeter= 0.0394 Inch 30. One Acre = 43560 Sq. ft.
Meter = 3.2808foot 31. the Full Form of UTM = Universal Testing
Meter = 1.0936yard Machine
A Rope Having Length 100cm.You Can Form Any 32. Expire of Cement is after 3 month.
Shape Using This Rope (Example: Triangle, 33. One square meter = 10.76 Sq. ft
Rectangle, Etc.,). Which Shape Will Covers 34. Unit weight of 25 mm Steel Bars is 3.85 kg/m.
Maximum Area 35. One Hectare =2.47 Acres.
1 Newton = O.101971 Kg 36. One Gallon = 3.78 Liters
1 Mm2 = 0.01 Cm2 37. One kilo newton is equal to 101.97 KG
1 Cm2 = 100 Mm2 38. One Tonne is equal to 1000 KG
1 Mm2 = 20 N 39. Maximum Free fall of concrete allowed is 1.5 m.
100 Mm2 = 2000n 40. Minimum Bars in Circular Column Should be 6 Nos
1 Cm2 = 2000n 41. The Full Form of AAC is Autoclaved Aerated
2000 N = 203.942 Kg Concrete.
So 20 N/ Mm2 = 203.942 Kg / Cm2 42. The Full Form of NDT is Non – Destructive Test.
21. the Unit weight of 12 mm Steel Bars is 0.89 kg/m 43. The Full Form of JCB is Joseph Cyril Bamford.
22. Density of Steel is 7850 kg/m³. 44. The Plate Load Test is conducted to determine
23. In Fe – 415 Steel Grade, 415 indicates the the bearing capacity of Soil.
Tensile Strength of Steel. 45. The Ring and ball test is conducted on
24. The Volume of 50 kg bag of cement is 0.035 m³. construction material Bitumen.
25. In Residential Building, Average Value of Stair 46. Minimum hook length as per IS Code is 75 mm.
Width is 900 mm. 47. The extra length in Bent up bars is 0.45.
26. The Slope of Stair should not Exceed 40º. 48. The Least Count of Dumpy is 5mm.
27. Minimum diameter of steel in Column is 12 mm. 49. The Full of EGL is Existing ground level.
28. Standard Size of Brick is 19 cm x 9 cm x 9 cm. 50. A First Class Brick Should Absorb Water More
29. Unit Weight of RCC is 2500 kg/ m³. than 20 %.

Facebook:@Eng.haidari2010 Telegram: @civil_eng_international


-
g. Construction Scheduling & Monitoring

51. Number of Bricks used in 1 Cubic meter of 61. the potential risk factors for workers on the
Brickwork is 500 Nos. construction site are:
52. The Normal Consistency of Portland cement is 25 a. Following are the risk factors for workers,
%. for not following the safety protocols:
53. The Expansion in Portland cement is tested by b. Risk to fall from height
Soundness Test. c. Failure Scaffold and Trench
54. According to IS Code, Full Strength of Concrete d. Change of Electric shock and arc blast
is achieved after 28 Days. e. Motion injuries
55. the Volume of 1 bag of cement is 0.035 m³ 62. Hybrid Foundation: Hybrid Foundation is used to
56. Minimum Grade of Concrete Used for RCC is M – reduce the amount of settlement in high rise
20. building, which contains both soils supported mat
57. Cement Expire is After 3 month. and piles.
58. The Full Form of DPR is Detailed Project Report. 63. The different ways of demolition are: Demolition
59. The initial and final setting time for cement is is commonly done through Hydro-demolition,
initial: Less than 30 min and 600 min. Dismantling and Pressure Bursting.
60. the Responsibilities of a Construction Manager in 64. Floating Slab Foundation: Type of mat foundation
the project are: having the hollow mat formed by the grid of thick
a. Responsibilities of a Construction Manager reinforced concrete walls between two thick
in the project reinforced concrete slabs is termed as Floating
b. Supervising the construction Site. Slab Foundation.
c. Estimate the proper cost of the project 65. Flashing: Joints in a building can be sealed and
d. Purchasing the materials required for protected from water penetration through
construction before work begins. extended construction called as Flashing. It can
e. Purchasing the materials required for be installed at the walls and parapets.
construction before work begins.
f. Analyzing the proposals.

Facebook:@Eng.haidari2010 Telegram: @civil_eng_international


-
66. different types of roof systems are : d. Accessory buildings
a. Following are the types of roof system, e. Drainage
b. Slate or Stone roofs f. Retaining wall
c. Wood shingle roofs g. Compaction of fill material
d. Metal roofing systems h. Caulking at opening
67. the phase inspections done by local authority i. Pavement edging
while construction are : j. Protection against moisture penetration
a. Various inspections during the construction k. Design of dwelling structure
includes, 69. the Order of Change request is :
b. Inspection of Site Change order request is a written document given
c. First or pre-construction Inspection by the owner, requesting an adjustment to the
d. Inspection of Foundation before placing of contract sum or an extension of the contract
concrete time. It can be issued by the architect or owners
e. Framing inspection representative.
f. Insulation inspection is done after 70. The components covered within Construction Cost
insulation are: Materials required, labor expense, equipment
g. Lastly, the final inspection is done after and services, contractor’s overhead, and profit
the completion of the construction are covered under the estimated construction
68. the some of the Inspections, done after the cost while compensation or salary paid to the
completion of construction are : architect, consultant, or engineers, cost of the
a. Listed are some of the checking or land, and other costs that is owner’s
inspection is done on the exterior side of responsibility is not covered in it.
the construction is, 71. Distribution bars of slabs should not be more
b. Storm sewer system than 1/8 of slab thickness and should not be less
c. Safety provision (terraces, porches, than 8mm.
areaways)

Facebook:@Eng.haidari2010 Telegram: @civil_eng_international


-
83. The binding wire needed in steel reinforcement is
72. Maintain the maximum thickness of slab which is
8 kg per MT.
125mm.
84. As per IS code, 3 samples should be taken for
73. The PH value of the water should not be less than
core cutting tests for every 100m2 in Soil filling.
6.
85. Electrical conduits shall not run in the column.
74. Maximum diameter of the bars used for lapping
86. Earthwork excavation for basement above 3m
should be 36mm. Bars with more than the
should be stepped form.
mentioned diameter should not be allowed.
87. Backfilling of any kind should be compacted 95%
75. Maximum chair spacing is always 1m and a
of dry density at the optimum moisture content.
minimum diameter that is used for these bars is
They should be in layers not more than 200mm
12mm.
for filling above structure and 300mm for no
76. Longitudinal reinforcement need not be less than
structure.
0.8% of the gross area of cross section nor
88. F soling is specified the soling stones shall be laid
should it be more than 6% of the same.
at 45° to 60° inclination, not in a vertical way with
77. The main bars used in the slabs should not be less
interstices filled with sand.
than 8mm in case HYSD bars are used and 10mm
89. Cement should be stored in dry places. It will be
when plain bars are used.
placed on a raised platform say about 200mm
78. The minimum diameter that is used for dowels
above floor level and 300mm away from walls.
bars is 12mm.
90. Bags to be stacked till 10 bags high in a manner
79. The maximum standard of free fall of concrete is
that it is protected from moisture and
1.50m.
contamination.
80. The comprehensive strength of bricks is 3.5
91. Fresh concrete samples should be taken and at
N/mm2
least a set of 6 cubes of 150mm shall be prepared
81. Absorption of water by bricks should not be more
and cured. 3 cubes each at 7 days and 28 days
than 15%.
shall be tested for comprehensive strength. Test
82. Lapping should not be employed for bars with
results must be given to engineering for approval.
diameters greater than 36mm.
When the results are unsatisfactory necessary
rectification measures need to be taken.

Facebook:@Eng.haidari2010 Telegram: @civil_eng_international


-
92. Set of cube test need to be done for each 30 cum 103. The maximum freefall of concrete that is allowed is
of concrete / each level of casting / each batch 1.50m.
of cement.
93. Water that is used for mixing and curing should 104. Water absorption of bricks should not be more
be clean and free from oils, alkali, salts, sugar and than 15 percent.
organic materials or other deleterious 105. Ph value of the water should not be less than 6.
substances. PH. shall be generally between 6 and
8. 106. Bricks Compressive Strength is 3.5N/mm2.
94. Maximum chair spacing is 1.00m or 1 number per 1
107. Binding wire in steel is required is 8kg per MT.
m2.
95. For the diameter, more than 36mm lapping is not 108. 3 samples should be taken for the core cutting test
allowed for the bars. for every 100m2.
96. A minimum of 12mm diameter bars of chairs is to
109. 36mm is the maximum diameter of the bars used
use on-site.
for lapping. Bars having more than this diameter are not
97. For dowels steel of 12mm diameter should be
allowed.
used.
98. Longitudinal reinforcement not more than 6% of 110. Maximum chair spacing is 1m and the minimum
gross C/S and not less than 0.8 percent of C/S. diameter used for these bars is 12mm.
99. The minimum vertical bars for the Square column
111. Minimum diameter used for dowels bars is 12mm.
is 4no’s and 6no’s for the Circular Column.
112. Longitudinal reinforcement should not be less than
100. Main bars in the Slab shall not be less than 8mm
0.8% of gross area of cross section and not be more
(HYSD) or 10mm (plain Bars) and the distribution
than 6% of the same.
bars not less than 8mm and not more than 1/8 of the
slab. 113. Minimum number of bars used for square columns is
4 and that of a circle is 6.
101. Dimension Tolerance of a cube is +2mm.
114. The main bars used in the slabs should not be less
102. The minimum thickness of a slab is 125mm.
than 8mm when HYSD bars are used and 10mm when
plain bars are used.
Facebook:@Eng.haidari2010 Telegram: @civil_eng_international
-
115. The distribution bars in slabs should not less than 126. Floating slab foundation: A floating concrete
8mm and not more than 1/8 of slab thickness. foundation is a type of mat foundation that consists of
the hollow mat formed by a grid of thick reinforced
116. Minimum thickness of slab is 125mm.
concrete walls between two thick reinforced concrete
117. Maximum free fall of concrete is allowed to 1.50m. slabs is called as a floating concrete foundation.

118. Lap slices not be employed for bars greater than 36 127. The Unit weight of 12 mm Steel Bars is 0.89 kg/m.
mm.
128. 1: 1.5: 3 is the mix ratio for M – 20 Grade of
119. PH value of the water should not be less than 6. concrete.

120. Compressive strength of Bricks is 3.5 N/mm2. 129. The size of a concrete cube is 15 cm x 15 cm x 15
cm.
121. Water absorption of bricks should not be more than
15 %. 130. (D²/162) is the general equation used to calculate

122. Binding wire required in steel reinforcement is 8 kg unit weight of steel bar.

per MT. 131. Calculate the weight of 12m long and 10mm dia.
123. As per IS code, 3 samples should be taken for core steel bar on-site
cutting test for every 100m2in soil filling. Here, we can multiply the length of the steel bar by its

124. The curb and also state the height of the low curb unit weight (unit wt. of 10mm = 0.60 kg/m)

are: A curb is defined as a structure that can separate Therefore, Weight of steel = 0.60x 12 = 7.2 kg.
pavement and median, pavement and shoulder, pavement
132. Concrete Cover is provided to reinforcement, the
and footpath. The height of the low curb is restricted
function of the cover is to protect the reinforcement
to 100mm only
bars against corrosion and to provide ultimately provide
125. The density of steel used in construction is 7850 resistance against fire.
kg/m³.

Facebook:@Eng.haidari2010 Telegram: @civil_eng_international


-
133. Measure the volume of concrete it is a simple task 137. The Critical Path Method (C.P.M) are: Critical Path
of multiplying its Length, Width, and Thickness together. Method is a strategy and method which uses the symbolic
For Example – 2m x 2m x 2m = 8 m³ of the volume of diagram to represent the respective tasks and activities
concrete. involved in the construction.

134. Different steps involved in building construction: 138. The void ratio: Void ratio is the ratio of the volume
Major steps involved in Building construction like, of voids to volume of solids.

a. Concreting 139. The tests used for checking brick quality are:
b. Masonry work
Absorption test, Hardness Test, Shape & size test,
c. Plastering work
crushing strength test, soundness test, etc. are
d. Flooring work
performed to determine the brick quality. For example,
e. Formwork
in the water absorption test, brick is dipped in
f. Steel cutting and Bending
freshwater for 16 hours in water. And depending on the
135. 995 mm is the maximum value of the throw of a weight of brick its class is decided such as if the weight
switch for a broad gauge track. of brick after dipping in water doesn’t exceed 20% it can
be considered as a first-class brick if below 22.5% it can
136. Specific Gravity of Cement be Determine are:
be considered as second class brick, and so on.
The composition of cement is itself in powder form.
140. In Indian railways, the minimum formation width in
Hence it is not easy to measure its specific gravity.
embankment for a single line of board gauge is 6.1m.
Ultimately knowing its specific gravity is not particularly
useful. 141. The Purpose of the Gap in the Road on the Bridge:
The purpose of the gap in the road is to allow road
Finding a conclusion to a solution is that the more useful
expansion and contraction caused due to temperature
question is “What is the typical density of concrete?”
changes, without damaging or deformation the road.
And according to the rule of thumb, its answer is that
the normally cured concrete has a density of about 150
pounds per cubic foot.

Facebook:@Eng.haidari2010 Telegram: @civil_eng_international


-
142. The Materials Used in Building a Gravity Dam: Activities focus on identifying defects in the actual
Compacted earth and concrete are used depending on the products produced.
dam type. Many gravity dams could be constructed of
148. The major types of reinforcements used in
compacted earth. While high dams are generally made out
prestressing are:
of concrete. The spillway is a necessary requirement for
dams. Spalling Reinforcement: The Spalling stress adjured
leads to stress behind the loaded area of the anchor
143. Anchors used to check to creep of concrete.
blocks. Which results into the breaking off of the
144. Cement soundness: It is the property of cement that surface concrete.
ensures that the cement does not go through any
Equilibrium reinforcements: In this type several
unwanted expansion or experience any change in volume
anchorages exist where the prestressing loads are
once it has been set. Cement soundness is a necessary
applied in a sequential manner.
process to help cement get rid of any possibilities of the
mortar or concrete from getting expanded. Bursting Reinforcements: Various stresses occurs in case
of the stress concave trajectories towards the line of
145. Flat bearing: is a highly effective process for
action of load. In order to reduce such stresses, here the
repairing concrete walls or damaged surfaces.
reinforcement in the form of bursting is required.
146. The length of each fish plate is 457.2mm.
149. The portion of a brick cut across the width is called
147. QA & QC BAT.

Quality Assurance (QA): Set of activities to make sure 150. Uses of Groynes are:
quality in the processes by which works are done is
a. Stop the longshore drift.
termed as Quality Assurance (QA). It is the process of
b. Slow down erosion.
managing for quality.
151. The functions of columns in a building are:
Quality Control (QC): Quality Control can be defined as a
set of activities that ensure quality in work. This Support structural load and transfer it through beams to
the foundation.

Facebook:@Eng.haidari2010 Telegram: @civil_eng_international


-
152. The recommended standards of tamping rod used in 157. Reason for concrete being weak in tension are:
cube filling for cube test are: According to the IS code
a. Concrete is a combination of materials like
2386, a 16 mm steel rod with rounded edge is
several aggregate types, cement, pozzolana,
recommended specifications.
water, air, etc. which are stick together with a
153. The range for the bearing capacity of granite is cement paste. The zone called the “interface
around in between 30 to 35 kg/cm2. zone” is the weakest link in the structure. During
compression, that interface is the only to
154. The recommended slump for the column is 75 to 125
transfer compressive stresses from aggregate to
mm
aggregate. Which does not require exceptional
155. Grouting: Grout is a fluid form of concrete that is strength.
used to fill the voids and this method is nothing but b. While the scenario under tension is not the same.
grouting. The aggregates in tension are trying to pull away
from each other and the bond is what holds it
156. The major difficulties faced during pumping
concrete works are: tightly. Since it is significantly weaker than the
aggregates, it is what results in failure.
a. The force needs to overcome the friction between
158. Bursting Reinforcement is: Tensile stresses induced
concrete and the pumping pipes along with the
during prestressing operation are called as bursting
weight of concrete and the pressure head.
b. Segregation and Bleeding are the major problems reinforcement and it is maximum where the stress
trajectories are concave towards the line of action of the
associated with pumping.
c. Aggregate selection is important in this process to load.

reduce errors in work.

Facebook:@Eng.haidari2010 Telegram: @civil_eng_international


-
159. Steps in Concreting are as given below: b. It should feel smooth when rubbed between
fingers. If the hand is inserted in heap cement
a. Batching of Concrete
or its bags, it should feel cool.
b. Mixing.
c. When a pinch of cement is thrown in Water then
c. Transportation of Concrete
cement should float for some time before it
d. Compaction of Concrete
sinks.
e. Curing
d. Cement should be lump-free when checked by
160. The Water-Cement Ratio: Ratio of weight of water putting the hand in the mixture.
to the weight of cement used in a concrete mix. A lower
163. Honeycomb in concrete: Air Pocket is another name
constant ensure higher strength and durability but is
for honeycomb in concrete which is usually formed during
difficult to mix i.e. low workability of Concrete Mix.
concrete casting.
Admixtures are added to deal with workability.
164. Bearing capacity of soil: The bearing capacity of soil
161. Types of cement
is the ability of soil to withstand the load imposed by the
Various types of cement which are used for quality Foundation.
construction are listed below: Portland Pozzolana Cement
165. The minimum recommended weight of fine aggregate
(PPC), Low Heat Portland Cement, Colored Portland
for sieve analysis as per ASTM C136 is 300 g.
Cement, Hydrophobic cement, Ordinary Portland Cement
(OPC), White Portland Cement (WPC), Rapid Hardening 166. The duration of the minimum curing concrete period:
Cement, Portland Slag Cement, Sulphate resisting As per IS 456 – 2000 recommendations the curing period
Portland Cement, White Portland Cement (WPC), etc. of concrete must be at least 7 days in case of OPC
(Ordinary Portland Cement), and at least 10 days for the
162. Tests necessary for the quality check of cement
concrete with added mineral admixtures. It is also
are:
mandatory for OPC exposed to dry and hot weather
a. On looking, Cement should have a grey color with conditions to have at least a 10-day curing period.
a light greenish shade.

Facebook:@Eng.haidari2010 Telegram: @civil_eng_international


-
167. The Retaining wall is the wall constructed to resist 173. The ideal size of the living room ranging from small
the pressure of an earth filling. to large are:

168. The process called for covering the concrete placed a. Very small size living room= 7 x 10 feet
on the exposed top of an external wall is called coping. b. Small living room= 10x 13 feet (for two 2 seater
sofa)
169. Plastic bitumen is the best-suited bitumen used is
c. Medium living room= 12×18 feet (for 3 Seater
for filling cracks in masonry structures.
sofa)
170. The terms bending moment (BM) & Shear force (SF) d. Large living room= 15×20 feet (for 4 seater or 5
are: seater sofa)

A bending moment is a reaction that tends to bend the 174. Types of Roofs are as listed below:
element when an external for resist shear force is a
a. Gull wind roof
major objective than its ability to resist an axial force.
b. Mansard roof
The axial force acts parallel to the longitudinal axis.
c. Bell cast roof
171. Grunting: Grunting is a kind of process in which a mix d. Sawtooth roof
of cement & sand is in the proportion of 1:3 is shouted on e. Monitor roof, etc.
a concrete surface with the use of a cement gun under f. Half hipped roof
the pressure of 2 to 3 kg/cm2. It is a process with high g. Dutch gable roof
effectiveness maintained for repairing concrete walls or h. Skillion roof
damaged surfaces. i. Gambrel roof

172. Maximum temperature that is allowable for fresh 175. The standard height of the roof can be one or two
concrete used according to the ASTM is 32oC. stories tall. If you do not need to make the roof taller
and yet you won’t make it look bigger from outside, you
can use a mansard roof containing multiple floors. Pitch is
adjusted so as to give a bigger look.

Facebook:@Eng.haidari2010 Telegram: @civil_eng_international


-
176. Common problems faced by architecture are: 179. The skills required for a good architect are:

a. The client would sometimes not be able to know a. Conceptual understanding related to designing
what they want that is when the architect will face models.
problems in designing the structure. b. Basic knowledge of computer and architectural
b. When budget is limited software programs.
c. When the requirement of the customer is custom c. Various Engineering abilities.
design at standard design cost d. General and Business aptitude.
d. When an architect is provided with less space to e. Knowledge about 3D model Designs.
work
180. 1/8 on the architect ruler is a scale that converts
177. Wooden Shingles: Slats or sheets rectangular in 1/8 inch onto the drawing to 1 foot. Its representation
shapes that are nailed to the exterior surface are called will be a drawing with a scale of 1/8”= 1 foot.
wooden shingles. The shingling method is a traditional
181. Structural Frame or Systems are:
weatherproofing method for building.
Beams and columns form load-bearing assembly on a
178. the most helpful and best engineering Apps are:
foundation called Structural frames. However, the
a. Sketchbook columns and beams are mostly fabricated off-site and
b. Photoshop Express can be assembled on site.
c. Flipboard
182. Demising wall: Demising wall act as a boundary that
d. Evernote
separates your land or house from neighbor’s house or
e. STEEL
property.
f. Dropbox
g. Houzz The Significance of the labor and material payment bond
h. AutoCAD Ws is if the contractor fails to pay for all labor, materials,
i. Magic Plan equipment’s or services in accordance with the contract,
he or she will guarantee payment to the owner under this
bond. Hence it is a bond between the owner and the main
contractor

Facebook:@Eng.haidari2010 Telegram: @civil_eng_international


-
183. (CPM) is a strategy along with the method of 193. In steel dowels, a rod minimum of 12 mm diameter
representing the respective tasks and activities to be should be used.
involved in the construction with respect to a symbolic
194. Steel Char maximum spacing is 1.00 m (or) 1 No per
diagram.
1m2.
184. The binding wire required in steel reinforcement is
195. lapping in reinforcement is not allowed for the bars
8 kg per Metric ton.
having diameters more than 36 mm.
185. The minimum Compressive strength of Bricks is 3.5
196. Normal concrete temperature allowed during
N / mm2.
placement is 10 to 32 degree centigrade or 50 to 90
186. PH value of the water used should not be less than degree F.
6.
197. The maximum height during pouring or free fall of
187. Water absorption of bricks is limited to not more concrete is restricted to 1.5 to 2 meters to avoid
than 15 %. segregation of concrete.

188. Lap splices shall not be used for bars larger than 36 198. Curing period for concrete is minimum 7 days and
mm. maximum of 14 days at temperature of 50.

189. The freefall of concrete is allowed a maximum of 199. Typical vibrator used for concrete has a head
1.50m in height. diameter of 30, 50, and 80 mm. The frequency of
vibration is 140-200 hz.
190. The minimum bars used for a square column are 4
No’s and 6 No’s for the circular column. 200. Normal types of vibrators for concrete are: needle
vibrator – surface vibrator – screed vibrator – external
191. Longitudinal reinforcement should not less than 0.8%
vibrator or formwork vibrator and table vibrator.
and more than 6% of gross C/S.
201. Some common methods of concrete curing are wet
192. Steel Chairs minimum of 12 mm diameter bars to be
covering, water spraying, sheet covering, soaked hessian
used.
cloth, electrical curing, and membrane curing.

Facebook:@Eng.haidari2010 Telegram: @civil_eng_international


-
202. Slump of concrete is measured by slump cone test. 213. The grey color of cement is due to tetra calcium
alumina ferrite.
203. Workability of concrete is measured by slump cone
test or compaction factor test. 214. MATERIAL CALCULATION:

204. Three types of slump are collapse, shear, and true CEMENT IN BAGS
slump.
a. PCC 1:5:10 1440/5*0.45 129.60Kg 2.59
205. Typical range of concrete slump in wet condition is b. PCC 1:4:8(M 7.5) 1440/4*0.45 162.00Kg 3.24
150 to 175 mm. c. PCC 1:2:4(M 15) 1440/2*0.45 324.00Kg 6.48
d. PCC 1:3:6(M 10) 1440/3*0.45 216.00Kg 4.32
206. Normal standard concrete has compressive strength
e. RCC 1:2:4(M 15) 144/2*0.45 324.00Kg 6.48
in the range of 2500 to 4000 psi or 17 to 28 Mpa.
f. RCC 1:1.5:3(M 20) 1440/1.5*0.45 32.00Kg 8.64
207. Compressive strength is tested by crushing g. RCC 1:1:2(M 25) 370.00Kg 7.40
concrete cylinders in the UTM machine h. RCC M 30 410.00Kg 8.20

208. Size of concrete sample for compressive strength i. RCC M35 445.00Kg 8.90
j. RCC M40 480.00Kg 9.60
cylinder is 150 mm diameter and 300 mm height.
215. Height of building = 3.15m.
209. Rebound hammer test is used for non-destructive
testing of concrete. 216. Height of parapet wall should be 1m.

210. Normal aggregates sizes used in concrete is in range 217. Height of window = 2.1m.
of 9.5 mm to 37.5 mm.
218. Minimum thickness of slab = 125mm.
211. Specific gravity of cement is around 3.15
219. Minimum thickness of lintel = 15cm.
212. 4 basic compounds of cement are called brogues
220. Thickness of DPC = 2.5cm.
compounds they are tricalcium silicate, dicalcium silicate,
tricalcium aluminate, tetra-calcium alumina-ferrite. 221. Maximum diameter of the bars used for lapping is
36mm. Bars having more than this diameter are not
allowed.

Facebook:@Eng.haidari2010 Telegram: @civil_eng_international


-
222. Minimum diameter of bars used in slab = 8mm. 237. Final setting time of cement = 10hrs = 600 minutes.

223. Minimum diameter of bars used in column = 12mm. 238. PH value of the water should not be less than 6.

224. Minimum number of bars used in square or 239. Riser of staircase = 150mm to 200mm.
rectangular column = 4 bars.
240. Tread of staircase = 250mm to 300mm.
225. Minimum number of bars used in circular column = 6
241. Angle of staircase = 25° to 40°.
bars.
242. Tensile or Flexural strength of concrete = 0.7√fck.
226. Maximum diameter of bars used in slab = 1/8 ×
thickness of slab. 243. Modulus of elasticity of concrete = [Ec=5000√fck].

227. Maximum chair spacing = 1m. 244. Young's modulus of steel = [Es=2×10^5 N/mm2].

228. Chairs minimum of 12 mm diameter bars to be used. 245. F.O.S for steel = 1.15.

230. Minimum diameter used for dowels bars is 12mm. 246. F.O.S for concrete = 1.5.

231. Longitudinal reinforcement should not be less than 247. Standard size of brick = 190mm×90mm×90 mm =
0.8% and not be more than 6% of gross area of cross 19cm×9cm×9cm.
section. 248. A good brick clay contains 20 to 30% of alumina, 50
232. Binding wire required in steel reinforcement is 8kg to 60% of silica and the remaining constituents are Lime,
per MT. Magnesia, Sodium, Potassium, Manganese and iron oxide.

233. Weight of 1 cement bag = 50kg. 249. Colour of good brick is deep red, cherry or copper
Coloured.
234. 1 bag of cement = 1.25 cubic feet = 0.0347 cubic
meter. 250. Compressive strength of bricks is 3.5 N/mm2.

235. No. of cement bags in 1m^3 = 28.8 bags. 251. Maximum water absorption of first class brick is 15%
of its dry weight
236. Initial setting time of cement = 30 minutes.

Facebook:@Eng.haidari2010 Telegram: @civil_eng_international


-
252. The excess of silica in the clay makes the brick 262. When concrete is to be laid under water, Quick
brittle and weak. setting cement is used.

253. Process of manufacturing of bricks consists of 263. Maximum free fall of concrete allowed to 1.50m.
Preparation of brick clay, Moulding bricks, Drying of
264. Test on Fresh Concrete
bricks and Burning of bricks.
a. Slump Test - Workability.
254. Moulding of bricks may be hand moulding or machine
b. Compacting Factor.
moulding.
c. Vee-Bee Test.
255. The burning of dry bricks is done either in clamp or
265. Test on Hardened Concrete
in a kiln.
a. Rebound (Schmidt) Hammer Test.
256. The ingredients of ordinary cements are Lime,
b. Ultrasonic Pulse Velocity Test.
Silica, Alumina, Calcium sulphates, Iron oxide, Magnesia,
Sulphur & Alkali's. 266. CONCRETE GRADE

257. Ordinary Portland cement consists of 62 to 67% of M5 = 1: 5: 10


Lime. M7.5 = 1: 4: 8
258. The initial setting time of ordinary Portland cement M10 = 1: 3: 6
should not be less than 30 minutes.
M15 = 1: 2: 4
259. The final setting time of ordinary Portland cement
should not be more than 10 hours. M20 = 1: 1.5: 3

260. Initial and Final setting time of cement is M25 = 1: 1: 2


determined by Vicat's apparatus. M30 & above grade based on Design Mix
261. The normal consistency of Portland cement is about
25%.

Facebook:@Eng.haidari2010 Telegram: @civil_eng_international


-
267. Specific gravity of Cement, Bricks Sand m. Organizational skills
n. Problem-solving skills.
a. Cement – 3.16 g/cm3
b. Bricks – 2g/cm3 270. The main bars used in the slabs should not be less
c. Sand – 2.65 g/cm3 than 8mm when HYSD bars are used and 10mm when plain
bars are used.
d. Standard size of brick – 19cm X 9Cm X 4Cm.

268. Unit weight of PPC, RCC, STEEL

a. PCC – 24 KN/m3,
b. RCC – 25 KN/m3,
c. Steel – 7850 kg/m3

269. Important point of civil engineering basics on


project management on construction sites

a. Scheduling
b. Cost control
c. Risk management
d. Contract management
e. Critical thinking
f. Project Recovery
g. Task management
h. Quality management
i. Meetings management
j. Leadership
k. Decision Making
l. Negotiation

Facebook:@Eng.haidari2010 Telegram: @civil_eng_international


-

You might also like