Boundary Wall Construction Proposal

PROJECT NAME Pathpara


JOB LOCATION Mughalsarai, Chandauli Uttar Pradesh.
ESTIMATED ESTIMATED
START DATE 25-November-2022 FINISH DATE 30-November-2022

OWNER INFORMATION CONTRACTOR INFORMATION

OWNER CONTRACTOR
COMPANY NAME
Bali Infra Enviro Pvt.Ltd COMPANY NAME
Reetu Construction Services

OWNER MR.Chandresh Dwivedi CONTRACTOR Ajeet Shilpkar


CONTACT NAME CONTACT NAME

H.No-13/358,Sec 13 Near A-68 Seemant Nagar Kalyanpur


Arvindo Park Indra Nagar Lucknow,226022
ADDRESS ADDRESS
Lucknow .

OWNER CONTRACTOR
PHONE +91981888615 +919711308634 PHONE +918858525802 +917376772532
OWNER CONTRACTOR
N/A ajeetshilpkar07@gmail.com
EMAIL EMAIL

Term & condition


1 All the standards given are given according to the market rate, if the material cost increases, then the coded
rate will have to be increased!

2 Before starting the work, 20% advance will have to be done so that the contractor can be given ease.

3 Delay in work is inevitable due to weather or due to force Maure, which may lead to variation in the completion
date of the work.

4 If there is any kind of dispute (land or government) at the place of work, then it will be mandatory to pay the work
done by the contractor and the material cost imposed by him.

5 It is the responsibility of the client to come and check our work and quality from time to time. We refrain from any
kind of dispute after the work is over.

Final Pricing Breakdown in 10 meter boundary wall - No Of working days [4days]

Material cost - 36,250/-


Labor Cost - 10,800/-
Travel & Stay - 3,000/-
Food - 2,000/-
Extra - 1,000/-
Total Price -53,050/-
[fifty-three thousand and fifty rupees only]

final proposal rate is 5500/- per running meter !


Approx rate Costing step by step according to Draft

step *1 step *2
Layer Of PCC Approx Coasting 10mtr
First Layer Of Brick Approx Coasting 10mtr
Note -
Note -
Length : 10 - m
Mortar Ratio 1:6
width : 775 - mm Cement Price 425/-per Bag
Thickness : 150 - mm Brick price 8/- per pcs
Aggregate 65 x 10ft = 650/- course sand 75/- cubic ft -
Course sand 80 x 15 = 1200/-
Cement 02 x 430 = 860 Length : 10 - m
Half brick 250 x 4 = 2000/- Height H : 575 - mm
JCB Digging 1000 x 1hr = 1000/- Thickness : 170 - mm
Labor for
compacting 02 x 400 = 800/-
Wall Volume : 0.978 - m³
Dry Mortar : 0.272 - m³
Cement : 0.039 - m³
step *3 Sand : 0.233 - m³
Cement bags(50kg) : 1.118 - bags
Second Layer Of Brick Approx Coasting 10mtr
Note - Number of Bricks : 401.607 - bricks
Mortar Ratio 1:6 Bricks Cost : 3,212.857 - ₹
Cement Price 425/-per Bag Cement Cost : 475.138 - ₹
Brick price 8/- per pcs Sand Cost : 18.633 - ₹
course sand 75/- cubic ft -

Length : 10 - m step *4
Height H : 280 - mm
Thickness : 460 - mm Third Layer Of Brick Approx Coasting 10mtr
Note -
Wall Volume : 1.288 - m³ Mortar Ratio 1:6
Dry Mortar : 0.358 - m³ Cement Price 425/-per Bag
Cement : 0.051 - m³ Brick price 8/- per pcs
Sand : 0.307 - m³ course sand 75/- cubic ft -
Cement bags(50kg) : 1.473 - bags
Number of Bricks : 529.176 - bricks Length : 10 - m
Bricks Cost : 4,233.411 - ₹ Height H : 360 - mm
Cement Cost : 626.065 - ₹ Thickness : 600 - mm
Sand Cost : 24.552 - ₹
Wall Volume : 2.16 - m³
Dry Mortar : 0.6 - m³
Cement : 0.086 - m³
Sand : 0.515 - m³
Cement bags(50kg) : 2.47 - bags
Number of Bricks : 887.439 - bricks
Bricks Cost : 7,099.509 - ₹
Brick calculation in height
Cement Cost : 1,049.922 - ₹
7.5ft 27Radday Sand Cost : 41.173 - ₹
1ft 3.52 Radday
2ft 7 Radday 8ft 28Radday
2.5ft 9 Radday 8.5ft 30 Radday
3ft 11 Radday 9ft 32 Radday Brick calculation in length
3.5ft 12 Radday 9.5ft 34Radday
4ft 14 Radday 10ft 35Radday 4.5" Wall length 1' 1 Radda 1.45 Bricks
4.5ft 16 Radday 10.5ft 37Radday 9" Wall length 1' 1 Radda 2.90 Bricks
5ft 18 Radday 11ft 39Radday 13.5" length 1' 1 Radda 4.35 Bricks
5.5ft 19 Radday 12ft 43Radday 18" Wall length 1' 1 Radda 5.8 Bricks
6ft 21 Radday 13ft 46Radday 22.5" Wall length 1' 1 Radda 7.25 Bricks
6.5ft 23Radday 14ft 50Radday
7ft 25Radday 15ft 53Radday
step *5
step *7
Fourth Layer Of Brick Approx Coasting 10mtr Layer Of DPC Approx Coasting 10mtr
Note - Note -
Mortar Ratio 1:6 M10 - 1 : 3 : 6 1450 psi
Cement Price 425/-per Bag Cement Price 425/-per Bag
Brick price 8/- per pcs Brick price 8/- per pcs
course sand 75/- cubic ft - course sand 75/- cubic ft -
Aggregate 65/- cubic ft -
Length : 10 - m
Height H : 230 - mm Length : 10 - m
Thickness : 600 - mm Height H : 230 - mm
Thickness : 40 - mm
Wall Volume : 1.38 - m³
Dry Mortar : 0.384 - m³
Cement : 0.055 - m³
Sand : 0.329 - m³
Cement bags(50kg) : 1.578 - bags
Number of Bricks : 566.975 - bricks
Bricks Cost : 4,535.798 - ₹
Cement Cost : 670.783 - ₹
Sand Cost : 26.305 - ₹
step *9

Layer Of copping Approx Coasting 10mtr


step *8 Note -
M10 - 1 : 3 : 6 1450 psi
Third Layer Of Brick Approx Coasting 10mtr Cement Price 425/-per Bag
Note - Brick price 8/- per pcs
Mortar Ratio 1:6 course sand 75/- cubic ft -
Cement Price 425/-per Bag Aggregate 65/- cubic ft -
Brick price 8/- per pcs
course sand 75/- cubic ft - Length : 10 - m
Height H : 230 - mm
Length : 10 - m Thickness : 40 - mm
Height H : 1225 - mm
Thickness : 230 - mm

Wall Volume : 2.818 - m³ step *10


Dry Mortar : 0.783 - m³
Cement : 0.112 - m³ Layer Of Plaster Approx Coasting 10mtr
Sand : 0.671 - m³
Cement bags(50kg) : 3.222 - bags
Number of Bricks : 1,157.573 - bricks Note -
Bricks Cost : 9,260.587 - ₹ Cement Price 425/-per Bag
Cement Cost : 1,369.516 - ₹ course sand 75/- cubic ft -
Sand Cost : 53.707 - ₹ Length : 10 - mtr
Height H : 610 mm
Thickness : 15 mm
Both Side

Description Quantity Unit Price Amount

First Grade brick (Lal Peti) 2000 ₹8.00 ₹16,000.00

course Sand (mauram) in ft 130 ₹80.00 ₹10,400.00

Ultra Tech OPC 11 ₹430.00 ₹4,730.00

River Sand in ft 10 ₹12.00 ₹120.00


Aggregate ft 50 ₹70.00 ₹3500.00
miscellaneous cost 0 ₹1500.00 ₹1500.00
Total Material Cost in 10 mtr 36,250.00
Note :- The amount offered is only standard, it can be
less or more according to the market rate and cost!
Labour & mason Costing With Ideal Working hours n Area !

Particular of Item Qty per day Skilled Labour Un-Skilled Labour Excavation
In Ordinary Soil 200Cft/5.66M3 1 Mazdoor Excavation In Hard Soil 1
Mazdoor
BB Work in Cement Mortar in Foundation and Plinth 100Cft/2.83M3 I Mason 2 Mazdoor BB work in
Super Structure 70Cft/2m3 I Mason 2 Mazdoor
Plastering 200Sft/20M2 I Mason 2 Mazdoor Pointing 300Sft/
28M3 I Mason 2 Mazdoor Floor Topping 100Sft/2.83M3 I
Mason 2 Mazdoor PCC I Mason 2 Mazdoor
Filling/Campacting of Earth under Floor 300Cft 1 Mazdoor Sand
Cushion Under floor 300Cft 1 Mazdoor
Brick Ballast under floor 300Cft 1 Mazdoor DPC I
Mason 1 Mazdoor
Brick laid by Mason 1000 Nos I Mason 2 Mazdoor
Brick laid by Mason in foundation 1350 Nos I Mason 2 Mazdoor

Description Quantity Time / Day Unit Price Amount

JCB for digging 1 1 ₹1,000.00 ₹1,000.00

labor for compaction 1 1 ₹450.00 ₹450.00

labor for lifting bricks 1 1 ₹450.00 ₹450.00

mason for brick work 3 2 ₹750.00 ₹2,250.00

labor for mortar lifting 4 2 ₹450.00 ₹1,800.00

Labor for aggregation 3 3 ₹450.00 ₹1,350.00

Mason for aggregation 3 3 ₹750.00 ₹2,250.00

miscellaneous cost 0 0 ₹1,000.00 ₹1,000.00

Total Material Cost in 10 mtr 10,800.00


Note :- The amount given is only standard, it
It may be more or less depending on the city or rural area.