Professional Documents
Culture Documents
Generatorprotectioncalculationssettings20080710 160323224851 PDF
Generatorprotectioncalculationssettings20080710 160323224851 PDF
Generator Protection
Sample Relay Setting Calculations
Example Generator
TIME CONSTANTS
RESISTANCES
3V0
Generator Protection – Setting Calculations
Voltage Inputs
Open Delta-Open Delta VT, secondary wired L-L Example
13.8kVLL VT Ratio = 14,440 / 120 = 120
A B C
VT Type: Line-to-Line
VNOM = 115 V
Generator Protection – Setting Calculations
13,800V
= 120
13,800/120 = 115
M-3425A
VT Type: Line-to-Line
VNOM = 115 V
Generator Protection – Setting Calculations
Voltage Inputs
3Y-3Y VT, secondary wired L-G Example
Example:
Generator rating VL-L = 13,800V VT Type: Line-to-Ground
VT Ratio = 14,400/120V = 120 VNOM = 115/√3 = 66.4 V
A
13,800 V
B
C 14,440
VT Ratio = 14,410
120V120
13,800
√3
a
b V = 115
c NOMINAL √3 =66.5 Line-to-Ground
Generator Protection – Setting Calculations
Voltage Inputs
3Y-3Y VT, secondary wired L-G (L-G to L-L selection)
Use of L-L Quantities for Phase Voltage-based elements
They will not operate for neutral shifts that can occur during
stator ground faults on high impedance grounded generators
a
SLG
Van=Vag Fault
n=g ground a
vag=0
Van= -Vng
c b
Vbn=Vbg Vbn=Vbg Vcg Vbg
n
High
Impedance c b
Ground
Vcn Vbn
Voltage Inputs
3Y-3Y VT, secondary wired L-G (L-G to L-L selection on
the relay). This selection is recommended for the
example generator.
a
b V = 115
c NOMINAL √3 =66.5 Line-to-Ground
Current Inputs
Determine primary current at rated power
¾ Ipri nom = MVA*106 / √3*VLL
¾ Ipri nom = 125*106/(1.732*13800)
¾ Ipri nom = 5,230 A
Pulse Relay:
When selected, the output contacts close for the seal in
time setting then de-energize, regardless of function
status.
Latched Outputs:
This function simulates lock out relay (LOR) operation.
When selected, the output contacts remain closed until
the function(s) have dropped out and the target reset
button is pressed.
Generator Protection – Setting Calculations
Generator Protection – Setting Calculations
IS
PRIS
59N Setpoint #2 = 35 V,
5 sec. (300 cycles)
Note: Setpoints should be
coordinated with low
voltage secondary VT
fuses
0.3
Generator Protection – Setting Calculations
59N is connected to a
broken-delta VT input
on the line side of the
14,400
generator breaker for
120 V VT ungrounded system
bus protection
The system is
ungrounded when
backfed from the GSU
and the generator
disconnect switch is
open
3EO = 3 x 66.5 = 200 V
Generator Protection – Setting Calculations
46 – Negative Sequence
Nameplate
46 – Negative Sequence
Check the response of the 46 function for high-side (69 kV)
phase-to-phase faults.
Pickup 5%
46DT Alarm
Time Delay = 30 s
46IT, K=29
Generator Protection – Setting Calculations
46 – Negative Sequence
29
Generator Protection – Setting Calculations
Rctr = CT Resistance
Rw = Wiring Resistance
RR = Relay Burden = 0.5 VA @ 5A IS
= 0.02Ω
VK > VS
Setting Summary
Slope = 10%
24 – Volts/Hertz (Overfluxing)
1.40
p.u.
•
1.35
•
1.30
1.25
1.20
1.15
•
1.10
1.05
1.00
0 200 400 600 800 1000 1200 1400 1600 1800 2000
time
24 – Volts/Hertz (Overfluxing)
10000
Inverse Time Element Generator V/Hz Capability
Pickup = 110% V/Hz Protection Curve (Inverse)
Curve #2 V/Hz Protection Curve (Definite time)
1000 K= 4.9
100
Alarm Settings:
Definite Element #2
Pickup = 106% Definite time element #1
Time Delay = 3 sec Pickup = 135%
10
Time Delay = 4 sec
0.1
100 105 110 115 120 125 130 135 140 145
24 – Volts/Hertz (Overfluxing)
Generator Protection – Setting Calculations
X2 = 16.4 %
Values shown above are from
generator test sheet
X1SYS = 6.25%
X2
All reactances on generator base (125 MVA)
= 16004/RC = 16004/1600 = 10 A
46
Generator Protection – Setting Calculations
X”d XT
Egen
Xt 10
Vgen = 100% = 100% = 39%
X "d + X t 15.6 + 10
I fault 12.75
MPU = = = 6.67
I pickupVgen (%) 4.9(0.39)
Generator Protection – Setting Calculations
MPU = 6.67
Generator Protection – Setting Calculations
• Pickup = 4.9 A
• Definite Time Curve
• Time Dial = 4.5
• Voltage Restraint
Generator Protection – Setting Calculations
Assumptions:
E gen 100
I MinFault = = = 0.46 pu
Xd + Xt 206.8 + 10
The fault appears farther than the actual location due to infeed.
Generator Protection – Setting Calculations
21 Phase Distance
The 21 function should be set to provide system backup protection.
To 5559 line 96
line 86 To PP4
3976 3975
line 87
To sub 47
125 MVA base 3977 3974
10%
line 97
GEN
69 KV
4,000 foot cable 3978 3973 To sub PP4
3972
21
line 94
To line 83 To PP4
21 Phase Distance
Typical 69 kV cable impedance: (0.2 + j0.37)% per mile
= (0.2 + j0.37) x 4000 = (0.152 + j0.28)% @100 MVA
5280
21 Zone-1 Settings:
GEN
(0.19 + j0.35)%
69 KV
4,000 foot cable
21
Generator Protection – Setting Calculations
21 Zone-1 Settings:
21 Zone-2 Settings:
Zone-2 will be set to look up to the substation bus.
21 Zone-2 Settings:
Setting Summary for 21-2
• Diameter = 2.73 Ω
• Time delay = 1.0 sec (60 cycles). This should cover
backup clearing for fault on transmission (69 KV)
system. Most lines have a dual primary.
• Angle of maximum torque: 85°
• 60FL supervised
Generator Protection – Setting Calculations
Z1 Z2 at RPFA should
2.7 Ω not exceed 150 to 200
1.6 Ω 85o
Z2 reach at % of generator rating
RPFA 1.64 (31.8o)
0 R
In our example Zone-2 reach at RPFA should not exceed 50% to 66.66% of
1.0 pu impedance (200% to 150% load).
Breaker Failure-50BF
When the relay (or another device) send a trip signal to open the
breaker and current continues to flow OR the breaker contact
continues to indicate closed, the upstream breaker is tripped.
Generator Protection – Setting Calculations
¾ Set the breaker failure time longer than the maximum clearing time
of the breaker plus the margin.
¾ Initiate 50BF with all relays that can trip the generator breaker.
¾ Use programmable inputs to initiate the breaker failure for all other
relays that trip the generator breaker.
Generator Protection – Setting Calculations
Setting Summary
¾ 50BF Pickup = 1 A
1.00
MVA = kV2 ( Rc )
Z Rv
ImpedanceLocus
1.0pu During Loss of Field Zone 1
Impedance Locus
Zone1
1.1Xd During Loss of Field
Xd
Zone2
-X
Scheme 1 Scheme 2
Generator Protection – Setting Calculations
40 – Loss of Field
Generator Ratings (Primary):
Rated (base) MVA = 125
Rated (base) Phase-PhaseVoltage (VB): 13.8 kV
Rated (base) Current (IB) = MVA x 103/(√3 VB) = 5,230 A
Xd = 2.068 pu
X' = 0.245 pu
d
Zone-1 Settings
Diameter: 1.0 pu = 1.0 x 20.3 = 20.3 ohms
Zone-2 Settings
Diameter: X = 2.068 x 20.3 = 42.0 ohms
d
40 – Loss of Field
0 R
X’d = 2.5 Ω
2
Zone 1
1.0 p.u. = 20.3 Ω
Xd = 42.0 Ω
Zone 2
-X
Generator Protection – Setting Calculations
Generator Characteristics
20
Overexcited
Reactive Power into the Generator
Underexcited
-20
MEL GCC
-40
SSSL
MEL
GCC
-60
Q(Mvar)_)
SSSL
-80
-10
Zone 2 Zone 1
-20
-30
-40
-50
Generator Protection – Setting Calculations
Overexcited
Real Power into the System P (MW)
0
0 20 40 60 80 100 120 140
-20 Underexcited
GCC
MEL
Reactive Power into the Generator
SSSL
-40
MEL
GCC
-60 SSSL
Zone 2
-80
-100
Q (Mvar)_
-120 Zone 1
-140
Generator Protection – Setting Calculations
Zone-2 Settings
Diameter = 1.1 Xd + XT + Xsys
= 1.1 x 42+2.03+1.27 = 49.5 Ohms
Off-set = XT+Xsys = 2.03 + 1.27 = 3.3 ohms
Angle of Directional Element: -13o
Undervoltage Supervision:
Undervoltage Pickup = 80% of nominal voltage
= 0.8 x 115 = 92 V
Time Delay with undervoltage = 60 cycles.
Generator Protection – Setting Calculations
R
0
-30 -20 -10 0 10 20 30
Zone 2
Zone 1
MEL -10
GCC
SSSL
-20
Dir Element
X -30
0 10
-10
-40
-50
Generator Protection – Setting Calculations
Overexcited
Reactive Power into the Generator
Underexcited
-20
MEL GCC
Zone 2
-40
SSSL
MEL
GCC
-60
Q(Mvar)_)
SSSL
Zone1
-80
Generator Protection – Setting Calculations
78 – Out-of-Step
Generator and transformer test sheet data, and system
information:
X′d =24.5%
XT = 10% on generator base
XSYS = 6.25% on generator base
78 – Out-of-Step
Out-of-Step (78)
jX
XSYS
1.5 XT = 3 ohms
XT 1.5 XT
0 R
T N S
GEN 120o swing locus
(Xd' )
'
2 Xd = 10 ohms
d
2.4 ohms
Generator Protection – Setting Calculations
78 – Out-of-Step
Generator Protection – Setting Calculations
81 Frequency Protection
81 Frequency Protection
81 Frequency Protection
Generator limits: IEC 60034-3: 2005
This IEC standard specifies that the generator is required to
deliver rated power at the power factor over the ranges of +/- 5%
in voltage and +/-2% in frequency.
Operation beyond these limits must be restricted both in time
and extent of abnormal frequency.
81 Frequency Protection
Setting Summary:
81-1 : Pickup: 60.6 Hz
Time Delay: 10 sec
(may be set to alarm)
81-2: Pickup: 59.4 Hz
Time Delay: 60 sec
81-3: Pickup: 58.4 Hz
Time Delay: 10 sec
81-4: Pickup: 57.4 Hz
Time Delay: 1 sec
Generator Protection – Setting Calculations
Field Insulation
Real-Time Monitoring
Generator Protection – Setting Calculations
Initial Conditions:
Brush Lift Detection (64B) > Field breaker closed
> Relay energized
> Generator and excitation
system
must be ground free (resistance
field-ground >100Kohms)
Brush Voltage
Generator Protection – Setting Calculations
300
600
0.5