Professional Documents
Culture Documents
Setting (50/51)
Calculate setting of IDMT over Current Relay for following Feeder and CT
Detail
Feeder Detail: Feeder Load Current 384 Amp, Feeder Fault current Min11KA and
Max 22KA.
CT Detail: CT installed on feeder is 600/1 Amp. Relay Error 7.5%, CT Error 10.0%,
CT over shoot 0.05 Sec, CT interrupting Time is 0.17 Sec and Safety is 0.33 Sec.
IDMT Relay Detail:
IDMT Relay Low Current setting: Over Load Current setting is 125%, Plug
setting of Relay is 0.8 Amp and Time Delay (TMS) is 0.125 Sec, Relay Curve is
selected as Normal Inverse Type.
IDMT Relay High Current setting :Plug setting of Relay is 2.5 Amp and Time
Delay (TMS) is 0.100 Sec, Relay Curve is selected as Normal Inverse Type
Relay Setting of IDMT and Instantaneous over current and earth fault Relay
RELAY IDENTIFICATION:
87-Differential relay
IDMT stands for Inverse Definite Minimum Time relay
SETTING METHODS:
51 & 51N
51 and 51N are both inverse time relay and used to detect phase fault and earth fault
respectively. There setting methods are same but the only difference is that pick up of
51 is higher than that of 51N.
The following parameters are required to calculate the settings of 51 and 51N.
1. PICK UP: this is the value of current through relay for which the relay picks up.
2. PSM (Plug Setting Multiplier): this is the ratio of fault current through relay
coil and pick up current. (it is relays inherent property)
3. TSM (Time Setting Multiplier): it is the ratio of required relay operating time
and actual relay operating time.
Basically if the TSM=1 then the relay operating time is very high, that’s why a
fraction given as TSM to decrease the relay operating time as per requirement or to
co-ordinate with the up and downstream feeders.
Sample calculation:
Pick Up Calculation:
The single diagram shows a very simple and typical line, through which 90A current
is flowing, a CT of rating 120/5A is connected via which the 51 and 51N relays are
connected.
Let say, the relay 51 will pick up for 120% of full load current.
=4.5 A
Now remember one thing, that some relay manufacturers make their relay pick up
range in the following manner, say 0.5-10 * CT sec. That means the CT secondary
will be multiplied within the relay program. So here multiplication with CT secondary
will not be applicable.
=1.2 * 90/120=0.9
Relay will display the following setting- 0.9 * CT sec (In) (In general In is
referred as the relay rated current, which is in general same as the CT secondary
current. That is CT secondary and Relay rated current shall be same. However there
is exception for earth fault relay, which is beyond scope of this article)
So, it is strictly required to read the relay catalogue and know the setting range.
Method of calculating pick up of 51N is same as mentioned above, but the pick-up is
considered as 5-10% of full load current, if the feeder is being fed from a transformer
which has NGR then pick-up may be considered as 5-10% of NGR rating.
Suppose a transformer has an NGR of 400A for 10 sec i.e. limiting earth fault current
upto 400 A. with NCT having ratio of 200/1A.
Here also see the relay catalogue to know if the CT sec is required to be multiplied or
it will be multiplied internally.
Following the above mentioned process pick up of inverse time over current and earth
fault relay is calculated.
However for earth fault protection is better to select minimum available pick up to
ensure maximum sensitivity.
PSM calculation:
=41.66/4.5
=9.26
There are several types of IDMT relay characteristics available now, according to the
characteristics the relay operating time are the determined. The formulas are as
follows:
So settings are –
2. TMS=0.24
Phase fault
1. B/c and i/c of mcc: 80% of the busbar rating or 120% of the connected load (take
the available data).
2. Upstream relay of sl no. 1 ( i.e. O/g of pcc): Select pick up higher than selected for
sl no. 1
3. B/c and i/c of pcc: 120% of transformer full load current.
4. At the h.v side of the transformer (51 which is back up of the downstream or lv side
51 relay): 130% of transformer hv side full load current.
Ground fault
1. B/c and i/ of mcc: 15-30% of busbar rating.
2. Upstream relay (o/g of pcc):30% of bus bar rating
3. B/c and i/c of pcc: 20% of transformer full load current.
For 51n always use minimum available setting, that will ensure maximum percentage
of protection.
TIME GAP
TRY TO MAINTAIN TIME GAP OF 0.25 SEC BETWEEN RELAYS.
50 & 50N
These can be used as definite time relay or instantaneous relay.
For relay 50 connected at H.V side of the transformer: For such connection the
pickup shall be more than the inrush current of the transformer. Otherwise the relay
will trip during transformer starting.
If the 50 relay is connected with motor feeder for motor protection then pickup will be
higher than the starting current of the motor.
Time delay may be or may not be given depending upon the requirement of
instantaneous or time delayed operation.
50N setting method is also same, but use minimum pick up setting, generally 5-10%
of NGR rating can be used. If NGR is not there then the same % of FLC can be used,
but try to use minimum pick up setting for the relay to ensure maximum percentage of
protection.